Activity

Description

Immediate
Predecessors

A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q

Set up the project acquisition team


Write down the project requirements
Acquisition of Land and Site Development
Building Overall Plan
Construction of Buildings
Establishment of Basic Infrastructure
Getting Permissions from respective departments
Recruitment of Faculty and Staff
Expansion of Phase I to Phase II (Expand of Infrastructure)
Develop new products and services after frist phase
Testing and Feed back of products and services
Expansion of Phase II to Phase III (Expand of Infrastructure)
Develop new products and services after second phase
Testing and Feed back of products and services
Expansion of Phase III to Phase IV (Products and Services)
Testing and Feed back of products and services
Expansion of Phase IV to Phase V (Products and Services)

A
B
B
C,D
E
F
G
G,H
I
J
J,K
K,L
M
M,N
O
O,P

Estimated
Time
Accumulated
(weeks)
Weeks

1
1
4
2
50
4
4
4
20
24
4
20
50
4
30
4
30

1
2
6
8
58
62
66
70
90
114
118
138
188
192
222
226
256

Year I

Year II
Year III
Year IV
Year V

Project Evaluation Review Technique


Activity
A
B
C
D
E
F
G
H

J
K

M
N

O
P

Description
Set up the
project
acquisition team
Write down the
project
requirments
Acquisition of
Land and Site
Development

Building Overall
Paln

Construction of
Buildings
Establishment of
Basic
Infrastructure
Getting
Permissions
from respective
departments

Recruitment of
Faculty and Staff

Expansion of
Phase I to Phase
II (Expand of
Infrastructure)
Develop new
products and
services after
frist phase
Testing and
Feed back of
products and
services
Expansion of
Phase II to
Phase III
(Expand of
Infrastructure)

Develop new
products and
services after
second phase
Testing and
Feed back of
products and
services
Expansion of
Phase III to
Phase IV
(Products and
Services)
Testing and
Feed back of
products and
services
Expansion of
Phase IV to
Phase V
(Products and
Services)

AverageTime

EST

EFT

LST

LFT

Total Slack

Critical

Critical
Activity
Variance

3.00

0.00

3.00

0.00

3.00

0.00

YES

0.44

3.83

3.00

6.83

3.00

6.83

0.00

YES

0.69

6.17

6.83

13.00

6.83

13.00

0.00

YES

0.69

5.17

6.83

12.00

7.83

13.00

1.00

NO

10.17

13.00

23.17

13.00

23.17

0.00

YES

61.36

9.33

23.17

32.50

23.17

32.50

0.00

YES

7.11

3.67

32.50

36.17

32.50

36.17

0.00

YES

0.11

3.00

36.17

39.17

36.17

39.17

0.00

YES

0.11

19.50

39.17

58.67

39.17

58.67

0.00

YES

0.69

22.67

58.67

81.33

58.67

81.33

0.00

YES

0.44

3.67

81.33

85.00

81.33

85.00

0.00

YES

0.11

18.83

81.33

100.17

180.67

199.50

99.33

NO

48.33

85.00

133.33

85.00

133.33

0.00

YES

2.78

3.67

133.33

137.00

133.33

137.00

0.00

YES

0.11

29.33

137.00

166.33

137.00

166.33

0.00

YES

0.44

3.67

166.33

170.00

166.33

170.00

0.00

YES

0.11

29.50

170.00

199.50

170.00

199.50

0.00

YES

0.69

Projected time of completion

Min/Avg Project
Completion Time

199.50

Target
Time

23

Time

215.89

Project Variance

75.92

Probability

0.00%

Target
Probability

97%

Note: Time span has to read in terms of weeks