TRANSPORT PAPERS
WASHINGTON, D.C.
TP-30
MARCH 2010
TRANSPORT
SECTOR
BOARD
2010 The International Bank for Reconstruction and Development / The World Bank
1818 H Street NW
Washington, DC 20433
Telephone 202-473-1000
Internet: www.worldbank.org
This volume is a product of the staff of The World Bank. The findings, interpretations, and conclusions
expressed in this volume do not necessarily reflect the views of the Executive Directors of The World
Bank or the governments they represent.
The World Bank does not guarantee the accuracy of the data included in this work. The boundaries,
colors, denominations, and other information shown on any map in this work do not imply any
judgment on the part of The World Bank concerning the legal status of any territory or the
endorsement or acceptance of such boundaries.
Rights and Permissions
The material in this publication is copyrighted. Copying and/or transmitting portions or all of this work
without permission may be a violation of applicable law. The International Bank for Reconstruction and
Development / The World Bank encourages dissemination of its work and will normally grant
permission to reproduce portions of the work promptly.
For permission to photocopy or reprint any part of this work, please send a request with complete
information to the Copyright Clearance Center Inc., 222 Rosewood Drive, Danvers, MA 01923, USA;
telephone: 978-750-8400; fax: 978-750-4470; Internet: www.copyright.com. All other queries on
rights and licenses, including subsidiary rights, should be addressed to the Office of the Publisher, The
World Bank, 1818 H Street NW, Washington, DC 20433, USA; fax: 202-522-2422; e-mail:
pubrights@worldbank.org.
To order additional copies of this publication, please send an e-mail to the Transport Help Desk
transport@worldbank.org
CONTENTS
Overview ...............................................................................................................................11
Introduction ...........................................................................................................................17
I.
Public policies .................................................................................................................19
A.
B.
C.
D.
Tolls ........................................................................................................................24
II.
E.
F.
G.
Regulatory regime.....................................................................................................32
III.
H.
I.
References .............................................................................................................................41
Annexes ................................................................................................................................43
I.
Taking Stock Of The Federal Road Concession Program ........................................................45
II. Experience Of The Concessions Launched In 1995-1997 (1st Phase) ......................................47
III. Experience Of The Concessions Launched In 2007 (2nd Phase) ..............................................55
IV. Public Policy Issues and Options ........................................................................................65
V.
Service Levels .................................................................................................................70
Tables
Table 1. Toll road network under private concessions ..................................................................12
Annexes:
Table 2.1. First phase concessions under ANTT supervision ..........................................................47
Table 2.2. Number of investment program updates since contract signing ......................................51
Table 2.3. Tariff evolutions under the first phase of concessions ...................................................52
Table 2.4. Simulation of financial returns on NovaDutra concession ...............................................53
Table 3.1. Breakdown of 2nd phase concession costs ....................................................................55
Table 3.2. Results of the tendering of the second phase of concessions..........................................60
Table 3.3. Comparison of cost structure of 1st and 2nd phases concessions at constant prices ...........62
Table 3.4. Detailed Comparison of 1st and 2nd Phase Cost Structures and Tariffs on of 1st and 2nd
Phase Cost Structures and Tariffs ......................................................................................63
Table 5.1. Service Level Criteria................................................................................................73
Figures
Figure 1. Road investments by level of government 2000-2006 ....................................................17
Figure 2. Country risk (EBMI+) 1998-2008 ................................................................................20
Figure 3. Average base toll rates under various concession programs (R cent/km) ..........................24
Figure 4. Highest toll for a heavy vehicle as multiple of base toll ...................................................25
Figure 5. Tariff evolution under the first round of federal concessions until 2008 .............................28
Annexes:
Figure 2.1. Road investments by level of government 2000-2006 .................................................49
Figure 2.2. Dutra higway, traffic forecast by concesssionarie vs. realized .......................................50
Figure 2.3. Evolution of main Brazilian financing rates 1996-2007 .................................................51
Figure 2.4. Compared evolution of the consumer index and the tariff inflator (Dutra road) ...............56
Figure 2.5. Tariff evolutions under the first phase of federal concessions until 2008 ........................56
Boxes
Box 1. Santiago - Valparaiso - Vina del Mar Toll Road .................... Error! Bookmark not defined.21
Box 2. China's Experience with Expressway Network Development ................................................37
Annexes:
Box 1.1. Selected lessons from the Brazilian federal concession programs......................................46
Box 3.1. Regulation mechanism: The economic and financial equilibrium principle ..........................56
Box 3.2. History of the preparation of the second phase of concessions .........................................58
Box 3.3. Poor Design, a Hurried Pace, and Financial Disaster: Renegotiation in Mexico's Highway
Program .........................................................................................................................61
Box 4.1. France's regional motorway networks ...........................................................................67
ACKNOWLEDGEMENTS
This study was undertaken at the initiative of Jose-Luis Irigoyen, Sector Manager of the Transport unit
of the Latin America and Caribbean Region of the World Bank. The authors of the report are Adrien
Vron, Transport Specialist, and Jacques Cellier, Consultant. The authors benefited from the guidance
of Aymeric Meyer, Task-manager responsible for the interurban road transport portfolio of the World
Bank in Brazil.
Assistance from the government of Brazil, especially the Ministry of Transport and the Land Transport
Regulation Authority (Agencia Nacional de Transporte Terrestres ANTT), is gratefully acknowledged.
ANTT notably provided key access to information related to the ongoing road concessions in Brazil and
the paper was enriched by constructive advice from ANTT senior management and executives.
This paper also benefited from comments and advice from several peer reviewers including Tomas
Serebrisky, Jordan Schwartz and Francesco Totaro, as well as Aurelio Menendez, Jose Guilherme Reis
and Yasuhiko Matsuda, and Debbie Wetzel.
During a technical workshop held in Brasilia in December 2009, a draft of this paper was presented to
the main stakeholders in Brazil for discussion. At the Federal level, this workshop gathered
representatives from the Ministries of Finance and Transport, the ANTT and the National Transport
Infrastructure Department (Departamento Nacional de Infra-estrututa de Transporte DNIT).
Representatives from the States of Minas Gerais, Rio Grande do Sul and Bahia also participated in the
workshop. Finally, representatives from the private sector were also present.
FOREWORD
With globalization and the constant reorganization of production and distribution chains, logistics have
become a key determinant of inter-regional trade and international competitiveness. While the
Brazilian overall economy has shown impressive improvement over the past decade, the countrys
economic growth remains hampered by high logistics costs, which still represent about 15 to 18
percent of GDP. This is well above those of China and India and nearly twice the 9 percent average
cost in OECD countries.
High logistics costs stem in part from the way the transport sector is organized, a situation largely
inherited from the past marked by years of low investment in transport infrastructure and a focus on
the roads subsector. As a result, logistics nowadays heavily rely on the costly road transport mode,
which carries some 60 percent of goods and 95 percent of passengers. Ironically, given the scarce
resources allocated to the sector, the road infrastructure itself has remained in an overall poor
condition until very recently, further contributing to the high cost of transport. Various initiatives have
been undertaken since 2000 to improve the management of the sector, including institutional and
policy reforms; a renewed long-term transport planning exercise; increased participation of the private
sector through concessions and performance-based contracts; release of budget constraints notably
since 2005; and the implementation of large multi-year investment programs.
Despite these efforts, further improvements in the management of the transport sector remain
essential to contribute to reduce logistics costs in Brazil and foster increased economic growth. In
2007-2008, the World Bank initiated an Analytical Advisory Activity (AAA) which takes stock of the
progress to-date in the management of the sector and focus on investigating ways to further improve
the efficiency of public expenditures in the sector. A number of activities have been undertaken under
this AAA, including technical assistance and original research into the functioning of the transport
sector, resulting in the following studies: Brazils Experience with Performance-based Contracts in
Road Rehabilitation and Maintenance; Private Participation in the Road Sector in Brazil; and An
Appraisal Framework for Transport Investments.
The present paper, Private Participation in the Road Sector in Brazil: Recent Evolution and Next Steps,
investigates and details Brazils successful experience with public-private partnerships (PPPs) for the
management of the road infrastructure and explores approaches for future improvements in Brazils
PPP program. It is our hope that this paper will contribute to the vibrant discussion among Brazils
policymakers, advisors, financiers and private sector partners on how best to reduce the cost of
logistics, increase trade and bolster economic opportunity for all Brazilians.
Laura Tuck
Sector Director
Sustainable Development Department
Latin America and the Caribbean Region
The World Bank
Makhtar Diop
Director
Brazil - Country Management Unit
Latin America and the Caribbean Region
The World Bank
ABSTRACT
Today, Brazil has the second longest highway network under private concessions in the world. This
paper analyzes Brazils experience under the two first phases of the federal road concession program,
and highlights some of the programs strengths and areas for further development. 1 Despite the
unfolding world financial and economic crisis, the potential for further private participation in the
sector appears very good. This paper essentially argues that it may be time for Brazil to revamp its
current models for private participation in the sector, which may soon reach their limit in terms of
being able to meet efficiently the needs of a growing economy. In summary, Brazil could: (i) diversify
its toll road model to allow for more innovative public-private partnership 2 structures, (ii) update its
toll regulatory and contractual framework to overcome some of the design problems that have led to
relatively inefficient tolling, (iii) consolidate the institutional framework for road concessions to give a
stabilized basis for further developments, (iv) develop a policy framework adapted to the current
Brazilian environment, taking into account the need to ensure harmonized levels of service and tolls
across the country, and (v) adapt the sector financing framework to the rising capacity of private
markets.
1
The paper does not cover performance-based public contracts (the so-called CREMA contracts), which were
reviewed under a separate paper entitled Performance Based Contracts in the Road Sector, Brazil experience.
2
The term public private partnership in this report refers to any type of partnership between the public sector
and a private firm, and is not limited to the definition in Law 11.079 of 2004 (Law of PPPs).
OVERVIEW
1.
Toll roads concessioning has not followed a straightforward path in Brazil. After the emergence
of the concession model in 1993, a quick expansion followed. The program then paused during ten
years, until 2007-2008 where a new expansion phase of the sector was initiated both by the Federal
and State levels of government. In 2008 toll roads covered about 12,000 km, an extension that could
potentially double in the medium run if the governments plans materialize. Most of the main roads in
Brazil would then be operated as private concessions which, in turn, lead to good road performance,
something vital to the economy. This paper aims at contributing to the ensuing policy discussion this
situation would generate. It presents a limited evaluation of the experience to date under the federal
road network concession program, which represents about a third of the Brazilian tolled network. The
paper argues that while the program has essentially met its goals, its implementation revealed a
series of weaknesses in the concession model, set in place in the 1990s and basically used until today.
To get the best of private participation in the sector, Brazil would need to create or revise its sector
policies and tools, as well as the institutional, regulatory and financing frameworks.
GOOD DEVELOPMENT PROSPECTS FOR THE SECTOR
2.
Inexistent in 1990, the Brazilian highway network managed under concession contracts covers
today more than 12,000 km, only second in length to Chinas road network under concession. 3 The
private sector has achieved the goals of the program - consistently delivering quality services to the
users. Rate of deadly accidents was halved in ten years on tolled routes 4 while it has overall slightly
increased on the federal network over the same period. In 2007, 22 of the 23 best quality roads in
Brazil were tolled highways. 5 The private sector invested R$ 1.2 billion per year between 2002 and
2006, about 12 percent of total investment in the sector during the same period, a period marked by a
severe fiscal adjustment which constrained public spending. 6 As a consequence, while the quality of
the rest of the network severely worsened between 1998 and 2006, tolled highways maintained an
adequate level of service. 7
3.
Fifteen years after the beginning of the first concessions, the regulatory models put in place
initially were maintained and consolidated, notably at the Federal level and in the Sao Paulo State. The
initial period proved painful. In several states, governments repeatedly attempted to unilaterally cut
tariffs or even undertake expropriation. Many juridical remedies were initiated by civil society, leading
sometimes to the cancellation of concessions or the impossibility to operate toll plaza. However, the
frequency of such events strongly decreased in the last five years, and economic-financial terms for
the concessionaire were upheld by the courts. Particularly, management of the first round of the
federal government program (about 1,480 km) by the now-extinct DNER between 1995 and 2002 and
currently by the Land Transport Regulatory Agency (ANTT) proved strong, with no contract being
substantially renegotiated: the many revisions mostly increases or adjustments to much too detailed
initial investment programs were realized within the contractual framework that had been set up
initially. 8 Regulatory governance appeared reasonable, with ANTTs performance in line with the
Brazilian infrastructure regulators average, and substantially higher than comparable Asian peers. 9
3
A partial survey made in 2005 by the Chinese National Audit Office, identified a toll road network of 133,100 km,
25 percent of which was managed through concessions (usually under state-owned companies). Chinese National
Audit Office (2005).
4
Sernam (2007)
5
CNT (2007)
6
ABCR (2006)
7
CNT (2003) and World Bank (2005)
8
Large contract restructuring occurred in several state programs such as in Parana or Rio Grande do Sul one
concession had to be transferred to the federal level. In general terms, renegotiation occurs when the original
contract and financial impact of a concession contract is significantly altered and such changes were not the result
of contingencies spelled out in the contract. Cf. Guasch (2004).
9
See in particular Correa & Al. (2006)
11
12
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
12,361 km
1,482 km
2,601 km
3,470 km
1,759 km
2,495 km
506 km
8,536 km
~ 6,000 km
8,444 km
3,378 km
5,654 km
> 31,200 km
Private
investments as %
of total sector
investments
12% (2000-2006)
14.5% (2007)
~ 10% (19952004)
Source: Sernam (2007), ABCR (2006), IBTTA website, ASECAP (2007), World Bank (2007), French Ministry of
Sustainable Development (2008), Chinese National Audit Office and World Bank calculations.
4.
With an end to the heavy investments phase, the concession companies under the first phase
of concessions began, and continue today, to generate an increasing amount of revenues. This led to a
consolidation of the sector as several groups (CCR, OHL, Ecorodovias, TPI, Bertin-Equipav) actively
sought expansion fields, either through secondary market purchases or new projects, some
successfully raising capital through stock exchange listing.
5.
Stable regulatory practices, balanced contracts, numerous players, availability of capital at
relatively low cost, and predictable cash-flows, all contribute to increasing competition, and to
reducing the costs and tolls that regulatory agencies seek to obtain. As a result, tolls obtained in late
2007 through the auctions of a second phase of federal concessions (about 2,600 km) were low if
compared globally about R$ 2c/km, ten times below European levels, and five times below the
existing rates in Brazil. Similar competition levels 11 would be expected from further developments, if
the long-term impacts of the 2008 financial crisis on the Brazilian macroeconomic environment
remained limited. 12
RATIONALE FOR REFORM: MAIN MESSAGES
6.
Brazil will have to further tap into private capital to address its infrastructure needs.
The need for Brazil to increase its investments to improve its economic and social performance is well
documented. 13 The Brazilian infrastructure stock remains low compared to comparable countries such
as Mexico and Chile, especially in the transport sector. 14 Close to two decades of below necessary
levels of investment led to precarious road surface conditions and congestion, while over-reliance of
the economy on the road mode exacerbated negative impacts. Faster country development will keep
pushing up household equipment rates as well as trade, leading transport demand growth to exceed
economic expansion rates in the medium run. To ensure that the transport sector can act as a lever
for economic growth instead of as a bottleneck, federal investment would need to be fulfilled; current
needs were evaluated at about R$ 16.5 billion per year by the 2007 National Logistic and Transport
10
State of Sao Paulo auctioned an additional 1,763 km of highways in November 2008, to be quickly implemented.
In average 7 to 14 bids have been received under the 2007 round of concessions
12
Concessions bid in November 2008 by the State of Sao Paulo appear a sign that the appetite of the private
sector had remained unharmed, as discounts from 6 to 55 percent were obtained on the administrations maximum
price.
13
See for instance World Bank (2007).
14
World Economic Forum 2007. Brazil ranked behind Chile and Mexico in terms of infrastructure and second to last
in the road sector.
11
Overview
13
Plan (PNLT) twice the current budgets and eight times the budgets prevailing five years ago.
Bridging the gap will require, among others, a heavy mobilization of toll roads financing. Recognizing
this, the federal administration announced plans to proceed soon with two additional phases of
concessions, for an additional 4,700 km of highways. Parallel developments are planned or under way
in the States of Sao Paulo (1,763 km) and Minas Gerais (up to 7,000 km). Overall, the extension of
the privately managed network could quickly double, making a large contribution to economic
development, if the framework for private participation proves strong enough.
7.
Private participation models in use are not optimal in the current road sector
environment. The current concession model in use was created in the 1990s, in a very different
macroeconomic context which led to limiting the scope of private involvement. In the 1990s, fiscal
constrains pushed the public sector to try to find ways to reduce public expenditures including
maintenance of assets. The public resources for private concessions were impractical under the 1995
Concession Law, which also introduced a series of detailed prescriptions predetermining many
contractual clauses. High capital costs led to concessions which mainly focused on operation and
maintenance of existing road itineraries, including many urban segments. Low development of new
technologies in the 1990s led to inefficient and open toll systems 15 in which many users can use
segments of the highway without paying tolls. Accordingly, tolls are currently paid by a portion of all
users and these toll revenues finance mainly administrative expenditures: 80 percent of revenues of
the first phase concession and two thirds of revenues from the second phase concession are used to
finance road administration, basic operating expenses, toll collection, remuneration of capital or taxes,
and only 2040 percent to road works (mainly rehabilitation) or road services.
8.
Today the sectors environment offers quite a different picture: budget allocations to the
sector are at a fifteen year high, private markets offer low-cost alternatives, inexpensive tolling
technologies are widely available, and traffic demand justifies investments in construction works not
just maintenance. However, concession models in use have been only marginally adjusted. The
government strategy to avoid concessions with heavy investments to, inter alia, keep toll levels low
should notably be questioned. This strains taxpayers and reduces the level of efficiency of public
expenditures. Indeed, among financing instruments, tolling is probably more pro-poor than public
taxes which are relatively regressive in Brazil. New ways to conciliate high investment needs with
affordable tolls, however, could be implemented through established instruments outlined in the Law
of 2004 public-private partnerships 16 (PPP), in which a less rigid legal framework opens the way for
public financial contributions as well as longer contract horizons; however, such a model has not yet
been successfully applied in the sector, with possibly the exception of the state PPP for the MG-050.
9.
Weaknesses in the initial design and approach to regulation in the first phase federal
concessions has led to high tolls relative to the level of services provided today. Even though
no major restructuring occurred, the experience of the first phase of federal road concessions is not
clear cut. In the past 13 years (out of 25 year contracts), frequent investment program modifications
took place, leading to sizeable increases which were compensated under DNER management by hefty
tariff increases of an average 40 percent, up to 124 percent. Thanks to efforts of the ANTT, which took
over the management in 2002, tariffs were since contained in real terms, but initial increases could
not be reverted. Furthermore, contract regulation has suffered from being fully anchored in the initial
commercial proposals of the concessionaire: unit costs, financial rates or traffic forecasts offered at
the bidding time have to be used by the ANTT without market-based updates throughout the
concession. Initial conditions are therefore preserved during 25 years, preventing users from
benefiting from productivity gains or reduced capital costs. While significant upside possibilities were
clearly necessary in the 1990s to attract private capital, and could only materialize over the life of the
concession, a certain degree of flexibility could nevertheless have been introduced in the contracts to
account for the evolving environment. The inertia appears to be responsible for up to 75 percent of
the five fold difference between the older concessions and the current tolls on federal highways.
Detailed regulatory data show that 2008 costs for toll computation are much higher for the old
15
Users are charged a flat-rate toll which is not determined by the distance traveled or number of exits passed. It
is possible to exit the toll road before the toll plaza, use other streets to bypass it, and then re-enter the highway
on the other side of the toll plaza and therefore use the toll road without paying.
16
As several other countries, Brazil differentiates concessions, id est private investments which are fully financed
by tolls and are regulated by a 1995 concession law, from public private partnerships, which can also be financed
by tolls but necessarily incorporate public contributions and are regulated by the 2004 PPP law.
14
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
concessions than for the new ones: twice for financial costs and four times for physical and
administration expenditures.
10.
Highly competitive auction for the second phase of federal concessions might require
a shift in regulation. The success of the government in delivering in 2007 a record-fast 17 and highly
competitive tendering (7 to 13 offers per concession) for the second phase of federal concessions
might yield a mixed outcome in the long-term. The auction process, based on the lowest toll offered,
secured very low tolls, up to 65 percent discounts from base government forecasts. While this is good
news for the users, this could put at risk the concessions and might ultimately prove costly to the
taxpayer. Unlikely low returns to capital or extremely high traffic forecasts apparently expected by the
concessionaires might be symptomatic of low-balling strategies. The materialization of less optimistic
traffic levels more in line with the governments initial forecasts for instance could then put at risk
financial viability. The way ANTT regulates these contracts will likely require adaptation to the new
context: low returns on capital upheld by rules built into the contracts might de facto provide
incentives to concessionaires of the second phase to gradually solicit reductions in their investment
programs.
11.
The institutional framework could be consolidated to ensure a healthy long-term
development of the program. Interventions by many actors without clear distribution of
responsibilities and frequent evolution of practices compounded by a lack of consensus on the
principles for private involvement, a difficult fiscal situation, and a risky environment for the private
sector, were some of the reasons which generated a 10 year delay in the second phase of
concessions. This program was originally planned for 1997 but was only implemented in 2007 as
responsibility for program management and approval was disputed, political uncertainties on the exact
scope of the desired private participation created interruptions, and the technical documentation
underpinning the second phase was repeatedly evaluated as incomplete. More recently: (i) in 2007, a
pilot PPP project (BR 116-324) initially prepared by the Ministry of Planning was transferred to the
ANTT, and (ii) in 2008, Casa Civil requested the Brazilian National Development Bank (BNDES) to
prepare a new phase of concessions. The inter-ministerial Council for Integration of Transport Policies
(CONIT), mandated by the 2001 transport restructuring law but only created in 2008, could prove a
good instrument for stabilizing practices and approving the key sector policies.
12.
Tolling principles in use do not contribute to an efficient tariff policy. Current tolling
principles generate important economic inefficiencies and inequities, with regard to the difference in
tolls between regions and between itineraries, the repartition of concession costs between long and
short distance users, as well as between vehicle types. In the absence of an overarching policy
approach, tolls have been set as outputs of the tendering process, on a project by project approach.
This resulted in a high level of disparity, locked in for 25 years, as tolls were based on surface
conditions, financial costs, and competition levels that prevailed at bid time. Given the implicit target
of full cost recovery, tolls differ strongly from marginal costs. Moreover, this logic appears relatively
regressive: while the most highly trafficked highways can generate low tariffs, the roads with less
transit or in poorer regions are de facto excluded from being candidates for concessions. Differences
between full and marginal costs also distort competition between itineraries in areas where several
alternatives are available: in the State of Sao Paulo, kilometric costs on highways vary by a 1 to 6
range, without obvious differences in the service to the user. The open toll system itself is a source of
inequity that reduces social acceptability of tolling. For a user living close to a new toll plaza, the
introduction of a concession can generate an uncompensated loss; on the other hand, many users
transiting in between plazas do not pay tolls. As a result, the costs of the concessions might actually
be borne by only a fraction of users, mostly the long-haul traffic, as urban traffic remains in great
proportion toll-free. An inefficient tolling structure, uncommon by world standards, penalizes further
the most efficient trucks, and consequently, internal trade.
13.
BNDES role in the sector could be reviewed to increase space for private
participation. Reflecting the good position of the Brazilian economy until 2008, private capital
markets have been increasingly active in the toll road sector, taking a larger share of toll sector
finance, through the granting of debentures for refinancing projects and developing a secondary
equity market. However, despite this greater availability of private financing, most initial concession
debt financing has so far been realized through the BNDES. The institution espouses two implicit
17
4 months between request for bids and contract award and 2 additional months to contract signature.
Overview
15
mandates in the road sector: (i) provide finance where the private markets cannot offer sufficiently
favorable terms, and (ii) reduce financial costs to enhance affordability of tariffs, through subsidized
rates. However, those mandates could be reconsidered in light of the new sector environment. If the
long-term impacts of the financial crisis of 2008 on the sector remained limited, the rapid increase of
national infrastructure investments could push requests for BNDES funds beyond the institutions
financing capacity. BNDES would increasingly have to turn down requests and, naturally, result in a
smaller share of total sector financing. 18 Moreover, international experience converges to say that
subsidized financing is ill-suited to achieve an affordability policy goal.
STRATEGY FOR REFORM: POLICY RECOMMENDATIONS
14.
Diversify the tolling instruments. To reap more benefits from private participation in the
sector, Brazil could rethink its instruments. Private participation could be oriented towards greenfield
highways, parallel to existing roads, at maximum capacity or incorporated into major duplication
works. If needed, higher tolls would then be more socially acceptable if alternative itineraries existed.
In parallel, progressing towards adjusting user contributions in line with their effective use of the
network, through closed-system highways for instance, would make tolling more equitable as well as
increase the scope of resources available. Instead of working on a project by project basis, strong
revenue-generating capacity of some segments could be used either to finance the development of
concession highway networks through corporate-finance schemes, or to finance the maintenance of
local networks as contemplated in the State of Sao Paulo. Brazil could create a cross-subsidy
mechanism to develop PPPs in poorer regions, for example through a pooling of tolls. Such an
instrument for regional development policy should be transparent, competitive and based on a careful
analysis of the viability of new concessions. Dilution of traffic risks could also reduce costs, for
instance through adoption of a pilot program to use corporate finance instead of only project
finance, 19 or through the development of specific financial instruments. When necessary and to ensure
a market appetite for riskier concessions, the public sector could implement new intervention tools,
such as traffic guarantees or direct payments, while maintaining strong monitoring of possible
contingent liabilities. Many of these evolutions could be realized within the PPP framework.
15.
Update the toll road regulatory and contractual framework. Current contract and
tendering practices could be revised in new concessions to take into account the experience of the two
first phases. Revising the current concession award criteria to reduce the risk of low-balling appears to
be a priority. 20 A larger transfer of the construction risk to the private sector appears to be positive as
it enables the concessionaire to optimize its road maintenance program, allowing lower long-term
costs, as seen in the second phase bid results. However, additional iterations appear to be necessary,
for example, through better definitions of rules for asset condition at contract end. This note suggests
additional iterations for the allocation of traffic and financial risks, as well as revisions or clarifications
on penalty, termination and amortization rules. Some measures could be implemented by the ANTT
within the current legal framework while others might require legal adaptations. Measures targeted at
promoting a more business-oriented behavior from the concessionaire, through user discount
programs or commercial enterprising of the roadway, might be part of the latter adaptation required.
16.
Furthermore, to better control and harmonize price escalation, this note suggests attempting
to reduce the frequency of investment program revisions probably to a five year occurrence, except
for substantial modifications. This may be achieved by relying less on the initial commercial proposals
for toll revisions and rate updates, and more on increasing incentives to concessionaires to match
investments with effective demand. Regulation setting could increasingly take into account real
commercial prices, financial costs or competitors productivity gains, bringing the sector closer to a
traditional price-cap utility regulation scheme and further from a pure contract based regulation. It
should be underlined that any evolution must maintain the delicate balance between incentives.
Modifications ought to be introduced with caution and consultation and probably only for new
contracts as the clarity and stability of regulation bring sizeable long-term gains by themselves.
18
19
20
16
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
17.
Consolidate the institutional framework for road concessions. The government could
consider: (a) clearly defining the respective responsibilities of the central and transport ministries,
ANTT, and BNDES in developing and implementing the PPP program; (b) undertaking the formulation
of the policies discussed in section 1 of this report for consideration and decision by the CONIT, in
accordance with the process established under the recent Presidential Decree no. 6.550 of August 27,
2008; (c) streamlining the review process for PPPs, delegating the formal approval of future
concessions from the National Privatization Council (CND) to the CONIT; (d) authorizing the Ministry of
Transport (MT) and providing the necessary resources and incentives to recruit and train professional
staff and managers to gradually develop a group of competent and motivated staff in the areas of
transport policies, planning and program monitoring and evaluation; (e) through MT and the CONIT,
and in close cooperation with the Forum of State Secretaries of Transport, formulating a
comprehensive and viable strategy for decentralizing the management of the road network, and
seeking congress approval of an agreed proposal for a new PNV law; and (f) facilitating the
recruitment and retention of qualified staff by the regulatory agencies, including ANTT, and ensuring
that agency directors and managers are selected on the basis of technical and managerial
competency, and independent from political and private interests.
18.
Develop a policy framework adapted to the new environment. The Ministry of
Transport, with technical support from ANTT and the National Transport Infrastructure Department
(DNIT), could formulate clear policies regarding guaranteed service levels to road users on the federal
network. They could provide the necessary guidelines in order to have consistent concessionaire or
contractor obligations and performance standards. Service levels related to road surface and capacity
may be differentiated on the basis of two-lane highway versus dual carriageway, and depending on
whether they are tolled or not. The objective of a policy for a parallel toll would be to define efficient
and equitable toll rates, as consistent as possible across the network, and coherent with the service
levels offered. Another objective would be to specify how affordability for poorer users and in the less
developed regions can be ensured. Such policies would be supported by road user opinion surveys
which would assess user preferences and willingness to pay for such services levels. Regarding tolling
technology, the Ministry of Transport could promote an exchange program with the participation of
concessionaires in order to establish a strategy to develop efficient and equitable tolling systems.
19.
Advantages could be considerable if these policies were coordinated with state governments to
ensure consistent pricing signals and development of an efficient truck fleet configuration.
Strengthening cooperation with the Forum of the Secretaries of Transport might lead to an effective
coordination mechanism, as with the European Conference of Ministers of Transport. A general
framework to harmonize tolls could be established, paralleling the Eurovignette Directive which defines
general principles at the EU level for setting tolls for heavy vehicles.
20.
Adapt financing sources to the evolution in the capital markets. Rather than decrease
the number of projects in which it is involved, BNDES could increase its leverage, through reduced cofinancing ratios and/or riskier instruments, such as subordinate debt. BNDES would then act as a
catalyst, with the objective to make financially feasible a larger number of projects, and develop new
private markets. BNDES financing would become essentially additional, in order to generate
maximum efficiencies. This could be a good opportunity to rethink the structure and objectives of the
Federal PPP guarantee fund, established in 2004 and yet to be implemented, with the purpose of
exploring new financial markets and in the country context considering Brazils investment grade
obtained in 2008. Re-centering BNDES financing role would not imply disregarding affordability for
poorer users. Yet, this issue could be treated more effectively with specific instruments which would
target specific user groups.
INTRODUCTION
1.
In 1995, amidst a severe fiscal crisis, the Brazilian government launched a federal toll road
concession program, targeted at ensuring the quality of the main road corridors in a time when public
money had become scarce. The states followed suit, and the size of the highway network managed
under private concessions at the federal and state levels expanded quickly to reach 9,700 km by the
end of the 1990s. With relatively stable levels of investments, road quality under private management
was adequate even during the fiscal crisis, enabling improved road safety and reduced transport costs,
while the rest of the network degraded up until 2006.
Figure 1. Road investments by level of government 2000-2006
9
8
7
Billion Reais
6
5
4
3
2
1
0
2002
2003
2004
2005
Federation
States
2006
Municipalities
2.
Public acceptance of concessions remained limited during a long time. Local opposition to toll
existing itineraries was often relayed in the political or judicial spheres, and at times led to the
restructuring of several projects pressed by creeping expropriation threats. However, in most cases,
administrations and tribunals reaffirmed the contracts validity and maintained their initial economicfinancial equilibriums. In 2007, despite initial affordability concerns, the federal government launched
a new phase of concessions (2,600 km). Several modifications to the tendering and contractual
frameworks were designed to allow for stronger competition and greater devolution of operational
management to the private sector. The competitive process resulted in extremely high discounts, with
tolls around R$0.02-0.03/km, five times below tolls on existing comparable highways, and amongst
the lowest globally.
3.
Currently, both federal and several state-level governments are preparing for new concession
and PPP programs in the road sector in order to bridge the so-called Brazilian infrastructure gap. The
federal administration announced plans to proceed with two additional phases of concessions in 2009,
for an additional 4,700 km of highways. Parallel developments are expected in the States of Sao Paulo
(1,760 km) and potentially Minas Gerais (estimates 7,000 km). If macroeconomic conditions following
the financial crisis of 2008 returned to previous observed levels, 21 the extension of the privately
managed network could quickly double. Contrary to past trends, where private and public investments
were considered as mutually exclusive, governments have simultaneously launched concessions as
well as large public investments programs, such as in the federal governments Growth Acceleration
Plan (PAC).
21
17
18
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
4.
Experience from the first 13 years of the federal road concession program, on which this note
is centred, is rich in relevant lessons (See annex I) and raises important questions such as: (i) Are the
tolls of the first phase of concessions bringing value for money to the users? (ii) What caused a 10year delay in launching the second phase of concessions? (iii) Will the second phase concessions be
financially viable? (iv) Should the current concession model focused on rehabilitation and operation
remain unchanged for future concessions?
5.
This note reviews the main determinants of the Brazilian road concession model in light of the
experience gained from the first two phases of federal concessions (see Annex II and III for a review
of the two phases). It offers recommendations on the policies and tools as well as the institutional,
regulatory and financing frameworks.
I.
PUBLIC POLICIES
6.
This section is a review of key public policy options for concessions and public-private
partnerships in roads, 22 in light of Brazils and other countries experiences. The following issues are
included: (A) scope of private participation; (B) scope of public participation; (C) service levels; and
(D) tolls and tariffs.
10.
private concessions where traffic is sufficient to generate enough revenues to cover all project
expenditures
public-private partnerships where some form of public participation is needed, in addition to
tolls, to cover all project expenditures
administrative concessions where tolling is not justified or practical, and public payments
would be made to the private operator on the basis of specified outputs and/or service levels.
11.
New construction (greenfield) projects and major duplication projects might become
feasible as PPPs, in light of what transpired between 2004-2008. This period was characterized by the
countrys stable macro-economic framework, low perceived risk, and much reduced cost of capital
(see graph 23), together with a dynamic economy growing annually 35 percent in the medium run, a
dynamic export sector, and increasing demand for transport and motorization rate (automobile fleet
expanded at 7 percent/year since 2003 24). Such a model would effectively resolve the above
mentioned service level and traffic safety problems of the open toll system through controlled
22
As several other countries, Brazil differentiates concessions, id est private investments which are fully financed
by tolls and are regulated by a 1995 concession law (9,074), from public private partnerships, which can also be
financed by tolls but necessarily incorporate public contributions and are regulated by the 2004 PPP law (11,079).
23
Brazil has showed also a good resilience to the financial crisis, with the country risk (EMBI+) jumping only from
250 point to 400-450 points in the first quarter of 2009, while Latin America and other emerging country indexes
reached spreads around and above 700 points.
24
Fenabrave (2007)
19
20
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
accesses and better geometric and safety standards. Tolling at exits would be both efficient, due to
the small number of accesses, and equitable, since payments are directly proportional to the distance
travelled. Good candidate projects could parallel existing highways operating at or close to capacity,
with a high proportion of urbanized or semi-urbanized segments. While the impacts of the 2008
financial crisis on the country and sector might delay some of the most ambitious plans, the long-term
rationale of the greenfield option appears strong.
Figure 2. Country risk (EBMI+) 1998-2008
2500
2000
1500
1000
500
0
01/02/2002
EMBI+ spread
01/02/2004
12/30/2005
12/31/2007
Source: Bloomberg
12.
Road network concessions or PPPs may also be viable instruments. By conceding a
network of various roads with different traffic volumes and characteristics, traffic risk may be
somewhat reduced. In addition, capital investments can be more easily scheduled, which makes it
easier to secure resources for financing of subsequent rounds of investments, even in periods of global
financial strain. This advantage is even more important in the case of greenfield projects, where
financing for the construction of a subsequent segment can be guaranteed by the revenues from
segments already in operation. France has developed an extensive network of motorways with
minimal public budget outlays on this basis (see Annex V).
13.
Cross-subsidies. Using operating surpluses on existing tolled roads to finance the
construction of new road segments is a common practice internationally. Since 1972, Japan has
pooled toll resources, on the basis that: (i) traffic generated by the construction of new sections of the
network benefit existing concessions, (ii) some sections could be insufficiently viable by themselves
while are important at the network level, (iii) it fosters toll uniformity and the creation of linkages
between user services and tolls, (iv) it reduces the need for public investments, and (v) as some
regions had benefitted earlier than others from high capacity road development, it may be acceptable
to use those revenues to finance the construction of other sections. Similarly, until the 2000s France
followed an approach whereby the construction of new sections was awarded to existing
concessionaries, which then benefitted from extensions to the concession duration. 25 Brazil, for which
road network development needs are high, particularly in the poorer regions, could set up a crosssubsidizing mechanism, as an instrument of its regional development policy. International experience
shows that the mechanism should be explicit, ensure competition between constructors, and be
grounded in a careful project analysis.
25
This approach ended in 2001 as it was perceived that it did not ensure explicit competition between contractors
for the award of new concessions.
Public policies
21
Basic policy options in road projects requiring public support to attract private investors are:
15.
Traffic risk is a key determinant of the attractiveness of a toll road concession. The risk is
lower for an existing road with a history of traffic conditions, and usually higher for a new toll road
(greenfield project). Projects requiring significant capital investment during the early years may need
the public sector to mitigate or even assume the traffic risk.
16.
There are various forms of traffic or revenue guarantees whereby the government or a public
entity is obligated to compensate the operator when actual traffic volumes are below certain predefined thresholds. Conversely, in the event of higher than expected traffic growth, the contract can
obligate the operator to share surplus revenues with the state. The Chile program is a successful
example of such revenue guarantees. Yet since revenue guarantees were optional and coupled with an
obligation to share surplus revenues with the state, many bidders actually turned down the optional
guarantee, and concessionaires are currently keeping substantial surplus revenues. Since such
guarantees would result in contingent liabilities for the government, which are difficult to predict and
to budget for, Chile developed and implemented an innovative form of minimum revenue guarantee
mechanism whereby the term of the concession is adjusted so as to reach the contractual present
value of toll revenues specified in the contract, as resulted from the tender. The mechanism is
implemented for the Santiago Valparaiso Vina del Mar toll road (Box 1).
17.
Some governments have preferred to assume the traffic risk entirely considering that the
concessionaire, having practically no influence on traffic, is not better placed than the public sector to
assume traffic risk. In those cases, payments are made directly to the private operator.
18.
Direct payments to private operators are a widely-used method to fund privately-operated
roads, whether tolled or not. Payments can be designed as a supplement to toll revenues or as a
subsidy during initial construction needed to make the project financially viable. Payments can also
cover all the costs of the concession, when toll revenues are recovered by the public sector, or when
there are no tolls. In this latter case, the public sector assumes the traffic risk entirely. These
availability payments are subject to the concessionaire making available certain assets in specified
conditions, and can also be linked to service level and performance indicators.
19.
Norways PPP road program is one example of such model, where tolls collected by a public
company are used to make availability payments to the operator subject to compliance with outputbased specifications. The United Kingdoms PPP road program is an example of availability payments
for no-toll road concessions. After abandoning shadow tolls, the United Kingdom has moved to a
system of direct payments made from the public budget to the private operator, linked to asset
availability and quality specifications, maintenance performance, and, on recent transactions, service
levels specified through average traffic speeds.
Box 1. Santiago Valparaiso Vina del Mar Toll Road
The project included large upfront investments and complex works such as tunnels and viaducts, and the traffic
risk was considered substantial. In order to mitigate the traffic risk, a minimum guaranteed revenue mechanism
was proposed to bidders, which were free to accept it or not. The mechanism consisted of guaranteeing the bidders
that the total actual concession revenues (expressed in present value, with one of two options of a fixed or a
variable discount rate) would reach the total target concession revenues of their bid, which was the contract award
criterion. The term of the concession would be adjusted, up to a maximum of 25 years, in order to reach the
contractual total target concession revenues.
The bidding process included first a review of a technical proposal, with detailed and specific requirements,
including investment budget, operation and maintenance plan, a tolling system plan, and regarding designs, the
bidders were free to accept the governments engineering designs or to propose a design alternative. Only the
commercial proposals of the bidders who had their technical proposals accepted were open. The lowest total target
concession revenue bidder was awarded the contract and obligated to constitute a special purpose company with
equity of at least 30 percent of project costs.
22
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
20.
Shadow tolls are payments made by the conceding agency to the operator on the basis of
actual traffic volumes and agreed toll rates. Traffic risk is not efficiently shared since low traffic risk is
on the private operator and high-traffic risk is assumed by the government. Justification for shadow
tolls, which were first introduced in the United Kingdom, was based on public benefits derived from
the use of the road. But shadow tolls are not efficient since they do not charge users for the actual
cost of road use as with explicit tolls, and therefore the efficient demand management role of an
explicit toll is lost.
21.
Portugal and Spain have used both real and shadow tolls to finance greenfield projects and
existing highways. But governments payment obligations under these contracts have increased so
much that many concessions had or will have to be converted to user-paid tolls.
22.
In order to address the above issues and opportunities, the Ministry of Transport (MT) could,
with the new framework of the PPP law, formulate policies for public and private participation in roads.
Such policies are essential to provide guidance to ANTT and DNIT in developing and implementing
their own programs in a coherent manner, and to ensure the efficiency, equity, and sustainability of
the programs.
C. Service levels
23.
Concessionaires obligations under road concession contracts in Brazil are specified through
the so-called PER (Programa de Exploracao da Rodovia) which includes:
24.
The specified work programs and timetables have proved to be inadequate when traffic
differed substantially from original projections (as generally occurs) and where urban
sprawl has required unforeseen investments, especially since contracts have built-in
incentives for new works. Such problems have resulted in numerous contract
renegotiations which generally benefited concessionaires;
Performance standards are defined by project engineers, case by case, in the absence of a
coherent policy based on user preferences; and
Capacity-related service level obligations are specified through US-based parameters
which are neither applicable to Brazils conditions nor enforceable.
25.
This section focuses on the major service level issues which could be effectively resolved
through appropriate public policy and related regulations or norms from ANTT and/or DNIT,
specifically: (i) road surface; (ii) pavement structure, and (iii) road capacity
26.
Road surface related concessionaire obligations are specified by performance standards
based on the following main parameters: (i) longitudinal roughness; (ii) ruts (transversal
deformations); (iii) cracks; (iv) IGG, indice de gravidade global, a composite index combining the
frequency and severity of various surface defects (abandoned in the recent phase 2 of the program);
(v) skid resistance; and (vi) absence of potholes, debris, and so on.
27.
Performance standards are defined by the engineers responsible for the specific projects or
programs, without clear guidelines or consideration of road user preferences. As a result, some
specifications are not consistent across the network and some may not be realistic. For example,
longitudinal roughness (IRI) requirements may range from 2.5 to 3.5 mm/m among similar highways.
An IRI of 2.5 mm/m is neither realistic, particularly when one considers contractors capacity for
surface finishing, nor justified, particularly on a two-lane highway.
28.
Pavement structures are not a major concern of road users, but they represent state-owned
assets which are temporarily transferred to a private operator, and which must be effectively
preserved so that they are returned at no loss to the state at contract end or any prior termination
Public policies
23
date. The structural capacity of pavements is also an important determinant of future road surface
condition.
29.
Concession contracts under the first phase of the Federal Road Concession Program define
minimum pavement structures through specific structural works at explicit future dates. There are
problems with such rigid specifications: (i) actual traffic rarely follows original forecasts, therefore the
specified works may no longer be justified at the time they are due; (ii) specifying technical solutions
does not allow for technological improvements over time and can therefore be inefficient; and (iii)
concessionaires can often demonstrate that they have better technical solutions than the ones
specified in the contracts. These issues have led to many contracts renegotiations which have
benefited concessionaires. There is no experience yet on this issue with recent contracts under the
Programs second phase, but the obligations of a (five-year) minimum remaining pavement lifetime at
the end of the concession seem both too vague and insufficient. The example of France, where the
administration and the concessionaire agree on a program of rehabilitation five years before the
contractual end might be a good strategy to consider.
30.
The contracts also specify maximum values for pavement deflexions. Deflexions can be a good
indicator of localized structural problems, but they are very sensitive to temperature and humidity,
and therefore they might not be an effective indicator of the structural capacity of an entire road
segment.
31.
The structural capacity of pavements could be more effectively specified through minimum
structural numbers for traffic-homogeneous sections. Contract specifications could also clearly define
the methodology, including structural coefficients of key materials and relevant relations, in order to
permit the requirement of enforceability for such obligations. Work programs currently specified as
obligations under the PER would become only indicative and feasible work programs, to be used as a
reference by bidders in structuring their bids. Bidders would be allowed to propose alternative
solutions provided they meet the specified structural numbers. The works timetable could be adjusted
in line with actual traffic on the basis of the specified relationship between structural numbers and
volume of traffic.
32.
Road capacity related concessionaire obligations are specified through (1) pre-defined
capacity works to be carried out in accordance with a timetable, independent of actual traffic, and/or
through (2) service level standards derived from the US Highway Capacity Manual (HCM).
33.
The pre-defined capacity works have to be revised and/or postponed where and when traffic
does not follow projections, which has generally been the case, resulting in contract renegotiations.
Service level could not be effectively monitored and enforced since it is based upon parameters which
are not easily measurable. In addition, these parameters, which were defined in the United States,
where road user behaviour and highway characteristics are quite different, are not applicable to
Brazils conditions without some substantial adjustments (see Annex VI for further details).
34.
The service levels could first be defined on the basis of clear and measurable indicators, for
example average travel speeds on two-lane highways and average vehicle densities per lane on multilane highways. They could then be monitored together with traffic volumes and various highway
composition characteristics, in order to develop reliable relationships between traffic and service levels
applicable to Brazilian roads and conditions. After such reliable relationships are developed,
concessionaire obligations regarding capacity works could be more easily specified through traffic
volumes.
35.
The Ministry of Transport, with technical support from ANTT and DNIT, could therefore
formulate a clear policy regarding guaranteed service levels provided to road users. Road surface and
capacity related service levels could be differentiated between two-lane and dual carriageway, and
whether they are tolled on not. Such service levels would be supported by road user opinion surveys
to assess user preferences and willingness to pay for such service levels (section D). Such policies
would provide the necessary guidelines to ANTT and DNIT to guarantee adequate and coherent
services levels across the network through consistent concessionaire or contractor obligations and
performance standards.
24
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
D. Tolls
36.
The Concession law restricted concession contract award criteria to the lowest user tariff or to
the highest concession award value (the user tariff being specified), or to a combination of lowest
tariff and highest award value. Since federal concessions were awarded to bidders offering the lowest
base toll rate, the first phase contracts, awarded at a time of high capital costs and limited
competition by Brazilian construction companies, resulted in substantially higher toll rates than those
recently awarded under the second phase, with a much reduced cost of capital and greater
competition from foreign bidders. Sao Paulo State initial concessions included more upfront capital
investments and were awarded to bidders offering the highest award concession value, therefore the
pre-determined toll rates were even higher.
37.
With subsequent rate adjustments, phase 1 federal concession rates are now close to the
rates of the Sao Paulo, Mexico or Chile concessions, which had larger initial investment obligations
(see graph below, at mid-2008 exchange rates).
Figure 3. Average base toll rates under various concession programs (R cent/km)
20
18
16
14
12
10
8
6
4
2
nc
e
Fr
a
in
Sp
a
Ch
in
a
Po
rtu
ga
l
ly
ex
ic
o
M
Ita
k
pe
a
Ch
ile
of
f-
lo
Pa
u
av
e
de
Ja
ne
iro
Ri
o
Sa
o
.1
Fe
d
de
do
ra
n
Ri
o
st
w
Su
l
an
a
Pa
r
SA
e
av
w
nd
.2
Fe
d
rg
en
tin
a
Source: ANTT, ABCR, IBTTA, World Bank (1999), private concession companies websites and authors'
calculations
38.
The disparity between toll rates also resulted from the widely differing road conditions at
bidding. Since toll rates offered under a competitive bidding process reflect the costs of required initial
rehabilitation and upgrading works, rates can be quite different among road segments. Justifying
differences on rates by claiming different user benefits is weak when taking the long term perspective
of achieving equity. Users of different road segments with similar service levels will, for the duration of
the concessions, pay substantially different tolls which reflect the road conditions segments at the
time of concession award rather than the current service levels or the cost of road use.
39.
Toll rates are also affected by decisions on contract specifications, including the designs of
capital works and the concessionaires obligations for service levels. These designs and specifications
are prepared by road agency engineers who generally do not consult with road users nor are the
specifications discussed during the formal public consultation process. They reflect the engineers road
service ideals rather than those which users would want or prefer.
Public policies
25
40.
The toll rate structure is another issue. In particular, toll rates for trucks and buses are
derived directly from the base toll rate for cars by a multiplier equal to the number of axles. As a
result, the toll rate for a six-axle truck is six times the toll rate for a passenger car and three times the
toll rate for a two-axle truck. Moreover, toll rate structure worldwide rarely exceeds a factor of 4
between larger trucks and passenger cars, and it is generally below 3 (see graph hereafter). The
economic rationale for such a structure is weak on efficiency or equity grounds.
41.
Efficient toll rates, leaving aside the issue of taxes paid by road users, would be determined by
the long term marginal costs of road use of the various categories of vehicles. An equitable cost
recovery policy may then allocate fixed costs, independent of traffic, equally to the various types of
vehicles. Such a pricing policy would substantially reduce differences between toll rates of the larger,
more efficient (six and seven-axle) trucks, and the smaller, less efficient (two and three axle) trucks.
A toll rate analysis done during the preparation of the feasibility study for the BR-116 / BR-324
segments in Bahia led to similar conclusions.
Figure 4. Highest toll for a heavy vehicle as multiple of base toll
7.0
6.0
5.0
4.0
3.0
2.0
1.0
0.0
Japan
(intercity)
Indonesia
Japan
(urban)
China
Italy
Thailand
Hungary
France
Chile
Philippines
Spain
USA (New
Jersey
Turnpike)
Brazil
Source: ANTT, Quinet, Trujillo & Estache (2000) and selected concessionaires websites
42.
Toll collection systems on open toll road concessions consist of toll plazas located on the
main roadway (accesses to the road are too numerous to be controlled). In order to maintain an
acceptable service level on the roadway (since most users have to stop at the toll gate for payment),
and to keep system efficiency (a ratio of toll revenues net of collection costs over gross revenues)
sufficiently high to justify tolling, toll plazas must be located at some distances, generally between 30
and 100 km in inter-urban areas. As a result, since all users of a given vehicle category passing
through a toll plaza pay the same toll, independently of the distance driven on that road, the actual
toll rate per kilometer of road use can vary widely, making such tolling systems quite inequitable. In
order to avoid the problem with numerous short distance daily trips in urban areas, toll plazas have
been located away from urban areas. But since concessionaires are generally also responsible for the
urban sections of the highway, long distance traffic is de facto subsidizing urban traffic. These equity
issues could, in principle, be substantially tackled through modern, in motion, toll collection
technology.
43.
Toll affordability is a problem for many users: according to a survey contracted by the
ANTT, about 80 percent of users consider toll rates too high or much too high. This is due in part to
the inequity of the open tolling system: while most local users do not have to pay tolls, some may
have to pay a full rate for relatively little road use where no alternative route is available. The
discontent of user groups, particularly truckers, reflects the other facet of this imbalance: those
26
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
travelling mostly long-distance are subsidizing short-distance traffic. The concessionaire could be
obligated to address such issues by providing special discount rates for local users. Toll structure can
also be used to reduce the rates for local buses and motorbikes, attempting to target more directly
lower income population. The disparity of toll rates between short-distance and long-distance users, in
part as a result of the older concession model (Federal and Sao Paulo State) on the one side and the
new concessions on the other, may be more difficult to resolve. It raises the issue of sustainability of
such disparate toll systems overtime, particularly in a period of rapidly increasing fuel prices.
44.
The Ministry of Transport could formulate a toll policy which addresses the above-mentioned
issues. An important objective would be to define efficient and equitable toll rates, as consistent as
possible across the network and coherent with the service levels offered. Toll rates could, in particular,
be differentiated between two-lane and dual carriageways. Such a policy should be developed based
on the results of a road user survey which would attempt to identify user preferences regarding
service levels and willingness to pay for such services. Regarding tolling technology, the Ministry of
Transport could promote an exchange program, with the participation of concessionaires, to develop
efficient and equitable tolling systems.
II.
45.
The federal government succeeded in developing a functioning set of bidding and contract
principles as well as regulation mechanisms, resulting most notably in the high competition that took
place during the tendering of the second phase of concessions, as well as in record speed. However,
there is room to further consolidate and improve this framework without compromising those results.
This review in this section provides key options for designing contract clauses of the tender process
and for regulations, in light of Brazils and other countries experiences. The following issues are
reviewed: (i) risk allocation; (ii) contract and tender design issues; (iii) regulation issues.
46.
Both tender process and contract design are described by the Concession law 8987 of 1995
and the PPP law of 2004. The Concession law prohibits public participation, restricts tariff policy to one
single (base) tariff and a pre-determined tariff structure, impedes termination rules efficiently
protecting investors, and largely does not promote the generation of complementary revenues. The
PPP law offers more flexibility on some of these points, but it is a priori limited to projects that would
require public financing. As the administration usually opts to define prior to tender which law would
apply to the projects, and given the governments preference for contract structures that do not
mobilize public money over long periods, so far no road projects have been tendered with the PPP law
at the federal level. On the contrary, the government preferred to undertake the required heavy works
through a classic concession tendering process, such as on the Florianopolis-Curitiba axis. Some of the
following suggestions are likely to imply legal adaptations or flexible jurisprudence. Ultimately, from
the sectors perspective, the inclusion of the concession law under the wider umbrella of the PPP law
might be beneficial.
E. Risk allocation
47.
Risk allocation in concessions was improved by the ANTT in the second phase of concessions,
with more risks transferred to the actors who were best capable of managing them.
48.
Construction risk was largely borne by the users in the first phase concessions, as
modifications in the effective volume and input prices impacted tariffs. This led to frequent investment
program revisions of the concessions (PER) and, at least while the contracts were managed by the
DNER, to a higher tariff escalation than observed in the cost of traditional public works contracts (see
graph below). To increase concessionaires responsibility in the second phase of concessions, the ANTT
separated works into two categories: (i) non-mandatory works that must be realized to comply with
the contracts performance targets and are within the full technical and financial responsibility of the
concessionaire, and (ii) mandatory (improvement) works such as third lanes, whose timing is defined
by the ANTT and whose costs are based on kilometric prices defined in the initial commercial
proposition. This arrangement appears much more satisfactory in terms of risk allocation, as
concessionaires have strong incentives to optimize their productivity. 26 Similar experience in France
showed how a company, Cofiroute, could reduce its initial costs by gradually adapting pavement
thickness to traffic levels, a move that had not been anticipated by the regulator. 27 This is likely to
reduce the need for frequent investment program revisions. However, enforcing performance
standards and introducing additional investments might become problematic if a disconnection
between costs, initial prices and rates of returns on investments appear with time.
26
In case of greenfield projects, several risks might appear out of reach for the concessionaire: (i) geologic risks
for major tunnels, (ii) land acquisition and expropriation risk.
27
See Bousquet & Fayard (2001)
27
28
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
Figure 5. Tariff evolution under the first round of federal concessions until 2008
200%
185%
150%
124%
Ponte
100%
Novadutra
Concer
CRT
50%
36%
26%
Concepa
28%
24%
13%
10%
11%
1% 1%
1%
16%
8%
0%
-4%-6%
-9%
-16%
-50%
Base escalation in
real terms
-6%
Revisions led by
DNER
Revisions led by
ANTT
-9%
49.
Important shortcomings of the contracts stem from the fact that contract revisions are
financially neutral for the federal and local governments, while users have little or no influence over
the decision-making processes. Particularly, any modification of the investment program is to be paid
by the users, without public financing, even though it was ordered at a government entitys discretion
the ANTT. Typically, this leads municipalities to solicit the ANTT to incorporate into contracts
additional local improvement works (parallel lanes, footbridges) for which costs would be borne by
long-distance users, with ANTT remaining without clear guidelines or oversight on investment
selection. Contracts of the second phase of concessions introduce a new possibility for the
governments to finance additional works on the road under concession possibly with different
contractors and a competitive process, as the concession law currently prohibits any monetary
transfer to the concessionaire. Within this contractual framework, it could be up to the ANTT and the
MT to establish the norms that would define when and how this new process should be chosen, and
when it would be justified to ask the users for additional contributions. Consulting with users
associations or associating them in the processes would bring increased transparency and good
governance to the system.
50.
Traffic risk is completely transferred to the concessionaire in the current framework: the
public sector does not provide guarantees and tariff evolutions are always computed by the
concessionaire on the basis of traffic forecasts realized before concession contract signing. This
traditional allocation of risk sets a good discipline for the public filtering white elephants, and the
private side reducing risks of low balling. However, in a context of quickly evolving oil prices, ANTT
could seek to reduce concession risks (and hence financial costs) by partly exonerating
concessionaires from a risk they by large cannot control. As mentioned previously, this could be
realized through a concession design that extends or shortens concession terms in case of traffic
evolutions. Additional efficiency gains would be ensured by the optimization of the investment
program in function of observed traffic, for instance by specifying the timing of investments through
actual traffic volume or service levels thresholds. This would prevent the construction of capacity
works when traffic and revenues are much below forecasts. This last possibility has appeared in the
new contracts for the second phase of concession; ANTT is able to modify scheduling as a function of
traffic but remains to be regulated or further incorporated in contract design.
28
The total tariff evolution in real terms for Concepa (185 percent) correspond largely then to the start of the
concession, through an updated monetary tariff package between 1994 and 1997 (around 45 percent) and another
given the first revision of the Basic Toll (around 93 percent).
29
51.
Financial risks are also fully transferred to the concessionaires. This common setting for road
concessions is actually a specificity of the sector as regulatory trends for utilities opt for a long-term
balance of rates of returns on investments with capital costs. As the history of the first phase of
concessions shows, a fall in financing rates offers sizeable windfall benefits to the sponsors (estimated
at about 20 percent of toll rates) that are not transferred to the users. This risk is partly asymmetric,
as an increase in financing rates gives incentive to the concessionaire to reduce its losses by
postponing or sizing down new investments. It is only partly manageable by the private partner: while
good financial management brings some gains, market fundamentals such as country risk are by large
out of reach for a private player. In new contracts, carefully designed clauses reducing financial risk
transfers would probably ultimately benefit the users. To avoid changing the initial balance of the
contracts or changing tolls faster than private partners can adjust their financing conditions, several
paths can be chosen: (i) sharing refinancing benefits when they occur, or (ii) revising regularly (for
instance maintaining constant during the first two years and then every five years) the discount rate
used for analyzing tariff revisions and adjustments by maintaining a given spread with some base
rate 29 instead of maintaining constant the original global rate of return. Such a mechanism could align
users interest with the concessionaires for concessions having more than 20 year duration.
29
In this formula, the equilibrium of the contract would no longer be based on the internal rate of return as stated
by the concessionaire, but on the sum of the discounted cash-flows over the length of the concession, with a nonuniform discount rate.
30
See Estache & Rus (2000)
31
Route T5 Temuco-Rio Bueno, in A. Gomez-Lobo & S. Hijinosa (1999).
30
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
54.
An alternative concession award criterion to consider would be concession duration. True,
previous experience in the first round of concessions in Mexico was actually very negative, but this
was due to a basic flaw at conception: as concessionaires were allowed to set both toll rates and
concession length, they elected short durations combined with very high fees, which proved
unrealistic. Many unviable concessions had thus to be fully renegotiated. Such a design can be easily
improved, by setting a mandatory toll rate, or by defining an acceptable toll range. An advanced
design based on the lower present value of revenues is being used in Chile (see Box 1). In this last
framework, the candidates place an offer on the discounted sum of revenues over the length of the
concession that they expect to receive, the toll rate being set independently. During the concession,
the concession length is adjusted to compensate for the observed traffic levels. With necessary
adaptations, this formulation brings several benefits, including a reduction of traffic risk on the
concessionaire, revision rules that do not necessarily impact toll levels, and a less controversial
computation of transfers in case of an early termination of contract.
55.
Penalty rules affect the incentives of the concessionaire to guarantee good availability of the
services under the contract, both in terms of timeliness and quality level. The current framework for
the first and second phases of concessions is based on a range of administrative sanctions and
penalties. This reliance on a sanction/fines regime as the sole instrument for giving incentives for
quality can be inefficient as it introduces during the duration of the contract an exceptional judicial
process that can be both lengthy and contentious. Fully implementing this would require: (i) a strict
contractual definition of performance levels and the processes to measure them as well as (ii) a good
monitoring system from the ANTT with possibility of independent appeal. However, experience has
been relatively mixed: while processes to measure performance lack the necessary contractual
detail, 32 the government was not able to maintain adequate capacity to monitor regularly all the
performance items set in the first phase of concessions.
56.
To overcome such shortcomings, bonus systems or performance payment systems have often
been designed to complement a sanction regime. For instance, in Spain, the new concession
framework allows extending the concession by up to a year in cases of good performance. In Italy or
France, good performance as measured by the regulator or by surveys is rewarded by a faster toll
escalation. In a similar line, a performance framework was proposed by the ANTT for the concession of
the BR116-324 system; under those conditions, toll escalation would be reduced if the concessionaire
does not reach all its performance targets.
57.
Termination rules, as an essential component of risk allocation, 33 are not sufficiently defined
in the current contracts. Exact compensations are to be determined in the courts and the exact risk
allocation remains unclear. In concession contracts, two termination rules hold the highest
importance: (i) the compensation due in case of a public preference to terminate the contract, and (ii)
the compensation due in case of low performance or incapacity of the concessionaire. As for (i), it is
important to ensure that the debt providers and the holders of other obligations contracted by the
concessionaire can be fully compensated, and that the sponsors can recover their costs and probably a
reasonable return on their investment. This can be achieved either by aligning the compensation in
case of termination by the administration with a discounted sum of revenues for the concessionaire or
with a combination of discounted revenues and the assumption of contractual obligations by the
administration. As for (ii), it is important to set the rules to reduce risks of low balling by the
concessionaire without increasing excessively risk borne by the debt providers further from what is
necessary for them to realize a thorough due diligence process, especially if there is no
prequalification process. This can ensure better management of the concession and also reduce
possible bias in the tendering process which presumably had pushed construction companies to
overstate construction costs as well as traffic forecasts. International trends in this matter are either
to use the book value of goods or a discounted sum of cash-flows as a basis for the compensation and
then impose penalties. While the use of a discounted sum of cash-flows adds fairness in the tendering
process and in concession management, those advantages should be balanced with the increased risks
on the debt providers. Capping ex ante the discount rate as well as using real data for estimating
costs, book values and future cash-flows, are essential elements of those computations. Whatever the
32
For instance, in the second phase of concessions, it is not specified whether the roughness index should be
computed as an average over the concession or over limited coherent segments, nor at what time of the year
should the deflexion index be computed.
33
See for instance a general discussion of the topic in World Bank (1998)
31
framework used, allowing step-in rights for the debt holders before incapacitating the concessionaire
brings additional security and lower private debt costs. Lower present value auction processes (see
Box 1) bring easy termination payments calculation rules transfer is roughly equal to the present
value of the revenues not yet collected less relevant operations and maintenance costs.
58.
Amortization rules are another determinant of concession profitability and toll rates. Current
rules impose: (i) a linear profile, but with different depreciation periods as a function of typical
investments; and (ii) a total depreciation by concession end. This translates generally into relatively
low levels of depreciation at concession start and high levels at the end, which tends to increase rates
at the beginning of concession and lower them at the end. The government could explore alternative
profiles with faster depreciation rates that might reduce initial capital contribution and lower financing
costs. As part of the PAC, the government authorized fast depreciation schedules for selected types of
investments. ANTT could assess the virtual impact of this potential measure on the recent road
concessions.
59.
Similarly, current amortization rules prevent the concessions direct assets (the road itself) to
hold a book value for the concessionaire at the end of the concession, and consequently cannot be the
object of a compensation at concession end. While this position is justified for pure asset operation
and maintenance concessions, it is not when the contracts involve the construction of an infrastructure
whose life-length is longer than concession horizon (for example, civil works for road duplication or
urban ring, tunnels, bridges). This might hinder the development of concessions incorporating heavy
infrastructure works, and especially greenfield projects. In addition, it largely impedes any sizeable
investment to be introduced in the last years of a concession: impact on tolls would be
disproportionate as investments would need to be recovered by concession end. To overcome those
issues, it might be interesting for the government to explore both longer concession lives as well as
the possibility of using residual values. 34
60.
Business-oriented behavior of the concessionaire can contribute to reduce base tolls and
optimize the use of the road. In a common framework, the concessionaire is allowed to introduce toll
discounts programs such as passes, either to attract the categories of users that are more likely to be
sensitive to the toll levels, or to orient the users towards the most efficient toll collection systems. This
flexibility is particularly useful for the concessionaire to adjust downwards for lower than expected
traffic for some categories of users. Further flexibility can be given by regulating on the basis of
average tariffs by category of vehicles instead of simply on head tariffs. 35 Coupled with incentives built
in the concession contract, it can offer the concessionaire an additional flexibility to postpone
congestion, such as through the creation of tariff variations in function of the time of the day. In
metropolitan areas, benefits would be expressed in reduction of the overall costs of transport and
delays of expansion investments. Also, flexibility could be used to raise additional initial capital
through the sale of long-term passes during construction period, constituting some user-based quasiequity, reducing the amount of capital to be raised. Cost of the passes would be equal to the
discounted sum of future tolls expected from the user. While the contracts for the concessions of the
second phase have opened the possibility for discount programs at the discretion of the companies,
ANTT guidance or incentives might be necessary for the concessionaires to make full use of those new
possibilities.
61.
Another important factor is how much the concessionaire can benefit from the commercial
exploration of the roadway. Efficient regulations can both provide incentive for the development of
services and contribute to reducing the toll rates. Current Brazilian legislation imposes that additional
revenues shall be used to limit toll levels. While this appears as a reasonable goal, regulation restricts
de facto the development of those services and sources of revenues. As per contract definition,
additional revenues are to be taken into account during the yearly contract revision to limit tariff
progression, leaving only the concessionaire with the possibility to keep a fixed 15 percent share of
revenues to balance its investment costs. With little benefits to expect, incentives for developing
value-added services are low while incentives for dissimulation of profits are high. As a consequence,
the overall level of additional revenues is limited to about 2 percent of toll revenues, to be compared
34
The project for a bridge of the Messina Straight was considering such an arrangement.
In this case, the concessionaires have flexibility to reduce tolls (for various user classes or depending on time of
day or week) below a contractual ceiling.
35
32
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
with 14 percent for the major Italian concession company Autostrade. 36 In its last version, the
concession law specified that additional revenues should be taken into account in toll revisions to
reduce toll rates. This probably gives little room to introduce new contractual arrangements that would
provide the right incentives to the concessionaires while allowing the users to reap part of the
benefits. To develop a framework that would allow for the development of this industry while
preserving the users interests, the government could investigate introducing international experience
and involve all stakeholders in a specific dialogue.
62.
Dispute settlement mechanisms are particularly deficient in Brazil. On the efficiency of its
dispute settlement mechanism, the World Economic Forum in 2007 ranked the country to the
penultimate position in Latin America, just ahead of Venezuela. This is not a problem of lacking of
framework: the first phase of concessions contracts integrated clauses for the use of two conciliatory
commissions (technical and financial) as well as an arbitration tribunal according to the Brazilian law.
However, experience showed that those processes were not used, as decisions could not be binding
and did not rule out appeals in non-technical courts. Consequently, dispute settlement processes for
federal concessions have been either informal or judicial. Reflecting this, second phase concession
contracts did not include any clause on dispute settlement. For most cases, the credibility enjoyed by
the most established regulators, such as ANTT or ARTESP in the State of Sao Paulo, makes the current
framework sufficient. Nevertheless, to further strengthen the concession framework it may be useful
to include some mechanism for potential substantial disputes, which could have negative long-term
consequences for the sector. Innovations could be tested, such as introducing independent expert
panels. 37 Though, without binding power, a likely outcome given Brazilian reliance on judicial
processes, their value-added would not be significant.
G. Regulatory regime
63.
Toll evolution rules are contractually based on the maintenance of the economic and
financial equilibrium of the concession, through: (i) a revision triggered when a risk not assumed by
the private sector materializes, such as a modification of the investment program; (ii) a readjustment
based on a predetermined price variation index.
64.
The economic and financial equilibrium of the contract is the base of the current
concession agreements. This concept was translated into a set of operational rules that define how
evolutions of the duties of the concessionaire should impact its revenues. While the candidates bid on
a unique toll rate, they attach to their proposal a financial model (in real terms) containing their own
traffic forecasts and investment schedule. This financial model, and especially the implied rate of
return on capital (without considering the financial structure of the concession) over 25 years, become
the base of the contract regulation. To reestablish the rate of return of the concession to its initial
level when an event occurs which has risks supported by the public (for example, modifications of
required investments or of direct taxes, and so on), the events impact on costs and revenues is
inserted into the model, holding the other parameters at the level initially set by the concessionaire
(including traffic and unit costs) and allowing the tariff to shift.
65.
This formulation introduces, in a transparent way, the necessary flexibility a long-term
contract concession should hold. However, it presents some drawbacks in its current form and could
be adjusted. Because revisions are based on commercial prices and traffic forecasts set before
concession start, they cannot account for long-term evolutions of productivity, traffic, and financing
costs. As such, the alignment of the incentives of the concessionaire and the needs of the users
cannot be maintained in the long-run, creating situations where the concessionaire has incentives to
overinvest or, on the contrary, slash investments. Concessions of the first and second phase probably
exhibit such discrepancy but with opposite incentives (see Part II). Moreover, while tendering is based
on a single tariff level, different combinations of costs, revenue forecasts and rate of returns
requirements can justify the same tariff. Classically, a candidate has incentives to over-estimate those
costs of investments where he expects additional demands and under-estimate those where a contract
36
Half of Autostrades complementary revenues are generated by service areas royalties, advertising and
telecommunications revenues, and for the other half by improved payment systems. Autostrade (2006)
37
PPIAF (2006)
33
prevents any revision. Bidders do not have full incentives to reveal their true characteristics to the
agency. This situation is aggravated in cases of low competition.
66.
A positive adjustment would be to introduce elements of the concession environment in its
continued regulation instead of basing it on the initial commercial proposition. One path that may be
explored involves revisions based on observed real traffic and current commercial cost estimates while
linking returns to prevailing financing conditions averaged over a sizeable time period. The increased
transaction costs implied by traffic forecasts and detailed cost impacts would suggest limiting this
procedure to sizeable or multi-annual revisions. To ensure that the initial traffic risk sharing is
preserved, traffic adjustments should only have a marginal impact, for instance limiting traffic volume
influence to the computation of the marginal impact of additional investment requirements or specific
kinds of capacity-related investments. The design of the BR/116-324 project follows this direction, as
a procedure was introduced to assess the marginal effect of selected events (including additional
investment requirements) based on actual traffic and market prices.
67.
Experience from the first phase of concessions shows also that investment revisions have been
extremely frequent, about 1 to 1.5 per year. This is partly due to the overly detailed initial investment
program which contains detailed quantitative values of all road works, and as a result is an integral
part throughout the lifetime of those contracts. Administration uses those concession contracts in a
similar way as in a traditional public works contract, with prices maintained for a 25 year period and
payments realized by users. As for public contracts, repetitive bargaining processes and asymmetry of
information weaken the position of the administration and are likely only to benefit the
concessionaire. 38 For those contracts, ANTT could try to further reduce the frequency of revisions, for
instance limiting investment revisions strictly to five year periods, as alluded to in the second phase of
concessions.
68.
Toll adjustment rules bring together the objectives of (i) reducing concession risks through
indexation of toll rates with cost indexes; (ii) sharing the toll burden between different cohorts of
users; (iii) providing incentives to the concessionaire to realize productivity gains in its operation of
the road. In this light, experience from the first phase of concession has been mixed, as it appears
that important productivity gains were not shared with the users. An international review reveals that
there is neither consensus nor good literature to ascertain the most adaptable formulas, and that rules
are usually set on a case by case basis. Escalation has been based on GDP per capita in the United
States, on a mix of inflation and exchange rates in Peru, on input price inflation in the first phase of
concessions, and on the consumer price index in the second phase in Brazil. In Italy, escalation is
based on inflation minus price-cap, with the differential between inflation and escalation a function
of expected productivity gains and observed service levels. In France, escalation is limited to 70
percent of inflation, but the economic conditions of the concession are periodically estimated and
productivity gains are required.
69.
From a microeconomic point of view, tariffs increasing faster than inflation during the
concession life can be justified on the basis of rising short-term marginal congestion costs. The
economic literature favors the use of long-term marginal costs instead, which adjustment is not
necessarily in line with inflation. 39 From a macroeconomic point of view, fully indexing public utility
prices with inflation can prove negative. During high inflation periods, price indexation can feed
inflation spirals while reducing the purchasing power of those consumers whose salary adjusts on a
delayed basis. As for regulating utilities, it may be preferable to define a regime based on a
combination of inflation and sector productivity gains.
70.
For future concessions, several paths of reform could be cautiously explored, always trying to
maintain an appropriate balance of incentives for the concessionaire, at contract tendering as well as
during implementation. The following proposition could be evaluated by the ANTT:
revisions of the investment program on a five year term, based on real traffic and costs. The first
revision occurring after the end of the initial rehabilitation and upgrading program,
38
39
34
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
using historic nominal costs of capital (as observed or computed) in the financial monitoring
spreadsheet used for tariff updates. An NPV calculation with different discount rates for different
dates would replace the currently used IRR calculation. 40
forecast future maintenance and operation costs based on a mix of inflation and a productivity
index, computed for instance, as a function of productivity gains observed in other concessions,
thereby introducing a process close to a yardstick regulation. Expected productivity gains could be
set on a five year term.
71.
Implementing these principles would imply adjusting the current regulatory models used by
the ANTT. As a test of the robustness of the new framework for future concessions, ANTT could
estimate their virtual impact on the existing first and second phase concessions.
72.
Additional regulation rules could also be introduced: (a) to limit concessionaires incentives
to excessively increase the initially set investment program, and hence the tariffs; a cap on the real
tariff increase over the concession could be set, in line with the legal requirements for traditional
public works (25 percent). This would partly determine when additional investments on the concession
should be procured independently; (b) revenue sharing clauses could also be introduced. Caps on
traffic levels could be set and when triggered would imply either a reduction of tolls or a transfer of
part of the additional revenues to the public. Experience shows that such clauses are preferable to
pure profit sharing clauses which suffer from their complexity, 41 (c) automatic toll adjustment during
high inflation rate periods could be authorized. Current rules dictate waiting until the annual tariff
readjustment, which would be severe with double digit inflation rates. For instance, in some
concessions, Chile allows the concessionaires to adjust tolls in cases when the inflation index changes
by more than 15 percent since the last toll revision.
40
Variable discount rates are commonly used to value bonds, using a yield curve. Calculation would be based on an
extension of the classic discount formula. For example, if r1 is the interest rate in year 1, and r2 is the interest rate
in year 2, then the present value in year 0 of I2 income in year 2 is I2/(1+r1)(1+r2).
41
A. Gomes-Lobo & S.Hinojosa (2000).
III.
H. Institutional Issues
73.
The institutional framework is still considered inadequate to effectively prepare and
implement programs of public private partnerships in roads, and more generally in transport. The
main institutional issues and organizational weaknesses are in the areas of policy formulation,
planning, regulation and supervision, which were discussed in the preceding sections. They are mostly
within the jurisdiction of the Ministry of Transport, but some lie outside. These weaknesses are
responsible to a large extent for the lack of progress with concessions and other public private
partnerships in the sector, lack of investments, and the resulting inadequate condition of large
portions of the road network.
74.
The organizational structure of the transport administration is mainly the result of the
sector restructuring law enacted in 2001 and a subsequent Presidential decree enacted in 2003. The
law, enacted several years after the first road concessions and the privatization of the railways,
delineated a new institutional framework consistent with the trend towards more private involvement
in the sector, and in large part with international experience. It led to the establishment of two
regulatory agencies, ANTT and ANTAQ, for regulating and supervising concessions and other forms of
public private partnerships in the land transport and water transport sub-sectors (though the
Executives proposal to the Congress was for only one transport agency); to the extinction of DNER
and the creation of DNIT, for executing public sector programs; and to the extinction of GEIPOT, which
was the policy formulation and planning arm of the Ministry.
75.
The original text of the law also aimed at strengthening the sector policy formulation and
planning functions through an organizational restructuring of the Ministry of Transport itself and
through the creation of an inter-ministerial Council for Integration of Transport Policies (CONIT). But a
Presidential veto on a number of articles of the Law relevant to the organizational restructuring of MT,
which were conflicting with a broader restructuring undertaken by the new administration, and a
subsequent Presidential decree enacted in 2003, resulted in unclear areas of competences and
responsibilities between the Ministry and its agencies. In particular, the restructuring law was clearly
attributing concession planning and procurement functions (Planos de Outorgas) to the agencies, while
the Presidential decree attributed the same functions to a newly-created Departamento de Outorgas in
the Ministry. A broader debate on the competences of the regulatory agencies versus the central
administration emerged at that time and is still ongoing.
76.
The institutional capacity of the Ministry of Transport needs to be strengthened. Prior
to restructuring, MT was relying largely on GEIPOTs staff for policy formulation and planning. After its
extinction, GEIPOT staff either transferred to the regulatory agencies or retired. The Ministry is still
clearly under-staffed, and its capacity for overall policy formulation, planning and M&E could be
improved. As a result, no real progress was made in these areas, with the notable exception of the
recently-completed National Logistics and Transport Plan.
77.
The PPP institutional framework which resulted from the PPP law, includes an interministerial PPP Committee (Comite Gestor de Parcerias Publico-Privadas Federais), responsible for
approving all federal PPPs, and a PPP unit, established within the Planning Ministry, responsible for
preparing pilot PPP projects and for supporting the preparation of such projects by sector ministries or
agencies. In addition, all privatization transactions, including road concessions, must be approved by
an inter-ministerial Privatization Council, the CND (Conselho Nacional de Desestatizacao). This
approval process could be cumbersome and results in substantial delays. In order to facilitate the
process, the government could consider transferring the responsibility for approving roads, and
possibly other transport, concession and other PPP programs and projects, to the CONIT once it
becomes operational (see recommendations below).
78.
The international experience with central PPP units has been mixed. 42 In general, the
relative success of central PPP units is based on a diagnosis of the relative weaknesses of
42
35
36
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
governments in undertaking PPPs that the unit is designed to address specifically. Generally, those
with executive power tend to be more effective than those that are purely advisory. Ineffective
governments tend to have ineffective PPP units. Without high-level political support for the PPP
program, a PPP unit will most likely fail. In Brazil, the PPP unit in 2006 prepared a pilot road
transaction, the BR-116/BR-324 in the State of Bahia. Substantial efforts were made to directly
involve all relevant sectors in the process, including MT and ANTT, through formal task forces and ad
hoc consultations. But the preparation process remained perceived as being led solely by the PPP unit
without high level political support or buy-in from the entities in charge of projects. Project
preparation ultimately stalled among disagreements from sector entities on various elements of the
proposed project design. Over the years the PPP unit gradually lost its relevance as a governmentlevel coordination effort was engaged under the leadership of the Casa Civil.
79.
The role of BNDES in the sector is important, not only in terms of financing (see Section B
hereafter), but also in helping structure concessions. BNDES, acting as technical secretariat of the
CND, coordinated the privatization of the railways in the 1990s. More recently, BNDES participated in
the preparation of the above-mentioned pilot PPP in Bahia (awarded as a concession), and is now
actively involved in the preparation of a new phase of federal road concessions. BNDESs contributions
are essential, particularly in the areas of financial analysis and structuring of projects.
80.
The Supreme Federal Tribunal (TCU) has been playing an increasingly large role in the
sector, in its thorough review of the bidding documents for new concession programs and its close
monitoring of the regulation of the existing contracts. TCU role became gradually more technical with,
for example, thorough discussions with ANTT for the second phase of concessions centered on the
forecasted costs (for example pavement thickness) and financing parameters (cost of capital) used in
order to determine the maximum tariff values of the auctions. Both BNDES and TCU bring significant
added-value at the technical level, but it should be ensured that discussions and decisions on key
policy and regulatory issues remain with the sector administration.
81.
The policy formulation, planning and monitoring and evaluation functions are,
according to the law, responsibilities of the Ministries of Transport and the CONIT. The original law
mandated the creation, within MT, of three Secretariats, including a Planning Secretariat, which would
have assumed the planning functions of the extinct GEIPOT and would have served as a technical
secretariat for the CONIT. But with the veto and subsequent Presidential decree, only two Secretariats
were created within MT: the Secretariat for National Transport Policy (Secretariat de Politica Nacional
de Transportes), responsible for policy formulation and planning, and the Secretariat for Transport
Program Management (Secretariat de Gestao dos Programas de Transportes), responsible for the
supervision, monitoring and evaluation of public programs.
82.
In order to consolidate this institutional framework, the government could consider to: (a)
clearly define the responsibilities of the central and transport ministries, ANTT, and BNDES in
developing and implementing PPP programs; (b) formulate, through MT, transport policies and plans,
including the set of policies discussed in Section I of this report, and prepare for the decisions to be
submitted to the CONIT, in accordance with the recent Presidential Decree no. 6.550 of August 27,
2008; (c) streamline the review process for PPPs at the central level, delegating the formal approval of
future concessions from the National Privatization Council (CND) to the CONIT; (d) authorize MT, and
provide the necessary resources and incentives, to recruit and train professional staff and managers to
gradually develop a group of competent and motivated staff in the areas of transport policies, planning
and program monitoring and evaluation; (e) through MT and the CONIT, and in cooperation with the
Forum of State Secretaries of Transport, formulate a comprehensive and viable strategy for the
decentralization of the management of the road network, and seek congressional approval for a
proposed agreement of a new PNV (Plano Nacional de Viacao) law; and (f) facilitate the recruitment
and retention of qualified staff by the regulatory agencies, including ANTT, and ensure that agency
directors and managers are selected on the basis of technical and managerial competence, and
independent of political and private interests.
83.
The decentralization of the management of the road network, besides an increased
participation of the private sector through PPPs, also requires transferring federal highways which are
not of national interest to the jurisdictions of the states, and delegating to state administrations the
management of those federal highways which could be more efficiently managed by such
decentralized administrations. In spite of many attempts by the federal administration over the last 15
years, the decentralization process has not made much progress. The law of the PNV of 1973, which
37
identifies all the transport infrastructures which are in the federal jurisdiction, and which consequently
can be allocated with funds from the federal budget, is a major legal impediment for the proposed
transfers of jurisdictions. Several proposed revisions of the law to enable such transfers have stalled in
the Congress, due to lack of cooperation between the federal government and the states.
84.
The government could, through MT and the CONIT, and in cooperation with the Forum of State
Secretaries of Transport, formulate a comprehensive and viable strategy for the decentralization of the
management of the road network, which would be in the interests of the federation and the states.
Such agreed strategy could then be formalized through a revised proposal for a new PNV law, which
could be more easily approved by the congress if previously endorsed by state administrations. The
Ministry of Transport, through its Secretariat for Transport Program Management, could then be made
responsible for implementing the decentralization strategy, and for reporting progress to the CONIT.
85.
Further, under such an agreed decentralization strategy, MT and State Secretariats of
Transport could cooperate to first plan and then implement an efficient network of interstate toll
roads, in a coordinated way. Chinas experience with coordinated planning and decentralized
construction of a network of over 40,000 km of toll expressways over 15 years is particularly
interesting (Box 2 below).
Box 2. Chinas Experience with Expressway Network Development
From 1990 to 2005, during the period of the 8th, 9th and 10th Five-Year Plans, China completed over 40,000 km
of tolled expressways, which now constitute the National Expressway Network (NEN). This was achieved by
investing over US$40 billion per year in roads, with about one third of that amount allocated to the NEN.
Many factors contributed to the rapid development of the NEN, but five key factors stand out:
- A clear long-term development plan committed through five-year programs, jointly prepared by the national and
provincial governments;
- The simultaneous implementation efforts by Chinas provinces and mega-municipalities;
- The pooling of national and provincial government resources, through their own funds and domestic and foreign
debt, and some private sector finance through various concession schemes;
- The greenfield characteristics of most expressway projects, allowing implementation with limited interference with
existing networks; and
- The availability of a large pool of qualified construction firms and design engineers drawn from former major state
owned enterprises to meet the unprecedented demand.
Chinas expressway network has been planned through the interaction of entities at the central and provincial
levels, following an approach that emphasized the objective of connecting all major cities to one another. At the
national level, the Ministry of Communications Planning Department started designing the plan, with inputs from
other line agencies, research institutes, and the Provincial Communications Departments (PCDs). The PCDs, having
participated in the overall definition of the corridors, then define the detailed alignments and designs within the
respective provincial boundaries.
Implementation of the planned expressways is the responsibility of the 27 PCDs and the traffic bureaus for the four
mega cities (Beijing, Chongqing, Shanghai, and Tianjin). The provinces typically finance 6690 percent of the
capital cost, through their own budgets and debt. MOC sets policies, standards and provides investment support
towards the construction cost. Once the expressways are opened, they are managed by the PCDs through an
operating company or other authorized entities. The private sector provides finance on a limited scale through
different types of concession schemes.
The key lessons learned for consideration in the next phases of the expressway expansion program are: (i) focus
on improved demand estimation methodologies, including the impact of higher or lower toll rates on demand; and,
(ii) emphasis on the analysis of a set of alternative options, including not only different alignments but also the
possibilities of phased construction. The latter might be particularly important where demand estimates show a
relatively long ramp-up period of low traffic volumes, and must take into account the adequate analysis of the
costs of the alternative technical options. In all, these methodological approaches call for a rigorous life-cycle
analysis of alternative alignments and phased options, taking into account levels of traffic demand that would vary
depending on toll levels and competing parallel routes.
Source: World Bank (2007)
86.
The regulation and supervision functions are clearly within the responsibilities of ANTT
where user tolls are collected. For toll-free roads, the regulation and supervision of the so-called
38
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
administrative concessions are expected to be with DNIT (although this assumption has not yet been
tested) or with state road administrations if the management of such roads is delegated.
87.
The ANTT has, since its creation, gradually strengthened its capacity for regulating and
supervising concessions and other forms of public private partnerships. ANTT was initially staffed with
experienced personnel transferred from public entities that had been eliminated such as RFFSA and
GEIPOT, and short-term contracted staff. Significant numbers of young staff have more recently been
recruited on a permanent basis but they require intensive training to become operational. Substantial
progress was made in establishing regulations, and systems of accounts and information for the
regulation and supervision of the roads and rail concession contracts and permissions and
authorizations for bus companies, some with assistance under Bank loans and PPIAF grants. Also,
efforts were made to ensure transparency in the agencys decisions. But accounting and other
information is not yet sufficiently analyzed to produce and effectively use reliable benchmarks. The
ANTT successfully managed the preparation, bidding and contracting process for the second phase of
federal road concessions.
88.
In order to address the regulatory and supervision issues discussed in section II, ANTT could
further strengthen its accounting and information systems, make better use of this information, and
develop reliable benchmarks for costing works and services. Consultations with road users could be
broadened through more systematic opinion surveys. In order to effectively contribute to the
development of a new PPP model, consistent with the public policies to be formulated by MT as
discussed in Section I, ANTT will need to build on its experience with regulating and supervision the
old concessions and incorporate international experience. For these purposes, ANTT would have to
continue building a stable group of competent, well-trained and motivated professional staff. The
government could facilitate this process by revising the salary structures for regulatory staff to enable
the recruitment and retention of as qualified professionals as those in the private sector. Finally, to
further strengthen governance, the government could ensure that agency directors and managers are
consistently selected on the basis of their technical and managerial competences, and are independent
from political and private interests.
I.
Financing issues
89.
Sources of capital expanded favorably for the sector in the past ten years. At the launch of
the first phase of concessions in 1995, equity was provided exclusively by construction companies,
and debt by the Brazilian development bank (BNDES) at subsidized rates and the multinational
agencies (IADB, IFC). Such financing proved adequate to support the birth of the sector, as the
favorable debt financing conditions (long maturities, grace period, weak covenants) offered by the
development banks allowed the sponsors to achieve high gearing (ratio 30/70) and profitability levels.
With the expansion of the Brazilian capital markets, and the more favorable financing conditions, the
picture changed, and emerging concessionaire groups (CCR, TPI, Ecorodovias, CRT) growingly
refinanced early loans as well as acquisitions on the basis of debentures and/or public listing.
90.
BNDES infrastructure credit lines remain very attractive for the sector. The institution has
held two key and distinct mandates in the road sector: to provide finance where the private markets
cannot offer favorable terms, and to reduce financial costs to enhance affordability of tariffs, through
longer terms and subsidized rates. Clearly, BNDES offers very favorable loan conditions: (i) long-term
loans (initially 8 and now 10 years in practice with a grace period of 2 years), (ii) that can finance up
to 70 percent of initial investment expenditures (initially 60 percent), (iii) at subsidized variable rates
(TJLP: 6.25 percent in early 2008) increased by limited credit spreads (total 1 percent for more secure
ones to 4.8 percent for most risky ones, recently reduced by 50 base points as part of the PAC). As a
comparison, the Brazilian interbank short-term refinancing rate (CDI/Selic) was set at 12.25 percent
base points in early 2008, and a AAA debenture sold on average 100 points above that is to say 600
points above BNDES levels. BNDES competitive advantage comes notably from having access to
special funding sources, with low government-mandated long-term return requirements, such as the
Workers Support Fund (FAP). This is not a unique feature of the sector: subsidized directed lending in
Brazil, mostly channeled by the BNDES, accounted in 2006 for about one third of total long-term
39
lending, for a total fiscal cost estimated at 1 percent of GDP. 43 Rationale for this policy has been based
historically on the lack of capacity of the private market to address the special sectors needs.
91.
Multinational financing lost part of the competitive advantage it was holding in the sector
ten years ago: large offer of BNDES financing reduces the possibility to finance initial physical
investments and currency mismatch with revenues reducing the attraction of dollar labeled loans for
refinancing. As an important exception, the different framework of the tender in the Sao Paulo State
partly rules out BNDES financing, as auction is based on important initial monetary payments from the
sponsor to the conceding authority. As a result, for the recent auction of part of the Sao Paulo Road
Ring, CCR firm has been considering contracting an IADB US$950 million loan (A/B structure) to
finance its promised R$2 billion transfer to the State. However, traditional investment loans have
generally stalled, with the last private-sector deals with IADB and IFC closing in the end of the 1990s,
and several concessionaires (Ecovias, CCR) refinancing in advance loans from multinationals through
large debenture. Since then, investments from IFC have been more leveraged, destined to finance
private equity investment in major companies (AG construction group).
92.
Local financial markets have effectively been taking a growing share of the road concession
financing. Generally speaking, the amount of primary issuance (mostly bonds and stocks) on the
Brazilian market multiplied four times between 2002 and 2006. In a direct reflection, all
concessionaire groups (about two thirds of the existing concession portfolio in number and a much
larger share in traffic and revenues) have now refinanced themselves through variable-rate
debentures, mostly based on the CDI or the consumer index (IGP-M). The debt structure of the CCR,
the largest Latin American toll concession company, was in 2006 made of 55 percent local debentures,
BNDES financing representing only about a quarter of the liabilities. Shareholders capital structure is
progressively evolving too, with a reduction of the participation of construction companies44 and the
public listing of part of the CCR and TPI groups.
93.
However, this activity of local markets has so far been concentrated on toll road refinancing,
while bond emission or private bank borrowing at concession start remained very limited. Results of
the second phase of concessions show that all concessionaires preferentially considered borrowing
from the BNDES to finance initial capital expenditure. Though, at an aggregate level, high demand for
BNDES long-term financing lines is generating a growing unmet demand, that grew from R$8.9 to
54.7 billion between 2002 and 2006. 45 Given the forecasted high rate of increase in infrastructure
investments in the coming years, it is likely that in the medium term, BNDES might not be able to
address all the financing needs of the sector. It might thus be interesting for the government to
review its direct lending policy and to consider orienting the BNDES toward taking the larger role of a
bridge for opening up under-funded sectors for institutional investors. Rather than decrease the
number of projects in which it is involved, BNDES could aim at increasing its leverage, through
reduced co-financing ratios and/or more risky instruments, such as subordinate debt. Through this,
the BNDES would act as a catalyst, with objectives to make finance-able a larger number of projects,
and develop new private markets. This would ensure that BNDES financing stays essentially
additional, for maximum efficiency.
94.
This reorientation appears also natural, in the current context, as it is unlikely that using
subsidized credit for infrastructure is an efficient anti-poverty tool. On the one hand, it is unclear
whether the opportunity cost on the BNDES managed funds were compensated by the reduction in toll
rates obtained. To generate similar toll rates, direct subsidies through the PPP framework would
probably have been more cost-effective. On the other hand, users who face affordability problems are
likely to amount only to a limited share of the transit. Rather than through undiscriminating
instruments, a more cost-effective way to ensure their access to transport services would be through
targeted programs, for instance a discount program available to beneficiaries from already existing
social safety network scheme.
95.
Catalysts for private financing have often been used by governments to achieve higher
private financing with lower or maintained public commitments. BNDES could take this role by: (i)
seeking a higher leverage in the funds committed, to improve the amount of infrastructure financed
per real mobilized, and (ii) developing the ability of local markets to provide for more structured
43
44
45
40
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
finance, long-term debt lines or even a retail equity market. Several paths could be explored, such as
standard credit enhancers (for instance full or partial credit guarantee schemes) or equity or
subordinated debt lines. The recent experience of the European Investment Bank (EIB) in this regard
is interesting. The bank recently set up a billion euro fund whose purpose is to enhance the financeability of transport concessions in Europe. According to the sophisticated design of the instrument, 46
the EIB provides guarantees to commercial banks stand-by credit lines (up to 10 percent of senior
debt) that can be used during the ramp-up phase of demand, id est during the first five years after
commercial operation date. If called, those credit lines function as standard subordinated debt lines,
which are subrogated to the EIB in case of default. By setting up this instrument, the EIB expects to
both increase the amount of financeable projects and to provide a financial value-added to the
projects, reducing the cost of their debt. The EIB expects that this instrument will be financially viable
and will catalyze about EUR 20 billion of private debt financing twenty times the value of the fund.
In the rest of the world, multinational donors, including the World Bank, have a varied experience in
setting up and financing such structured infrastructure finance funds.
96.
Creation of a PPP guarantee fund is considered inside the 2004 PPP law. This fund was
designed to back-stop the payment obligations of the governments in long-term PPP projects but was
not implemented, probably due to the lack of PPP projects. At that time, several aspects of its design
needed to be improved, as low liquidity and relatively high volatility of the assets combined with
potential problematic political governance issues were likely to limit its aggregated value for private
investors. Actually, it is probable that counterpart risk decreased strongly for Brazil, which became in
2008 investment grade. Similar experience in Peru show that after investment grade had been
achieved, this kind of credit-enhancer for public contributions to transport PPP projects were not
necessary anymore to attract investors 47 given that public payments hold a status close enough to
public debt. Creating a special PPP fund managed by the BNDES might still be useful, but probably
with a very different structure and objectives, such as providing leveraged financing lines as
mentioned previously.
97.
Incorporation of road users into capital structures could facilitate social acceptability of
tolls and marginally expand capital sources. This could be realized for instance through the
incorporation of municipalities in the equity structure, such as what happens in France through
subsidies with profit sharing clauses, or even limited shareholder participation. In addition, as
mentioned in section III.B, for investment-intensive projects, the sale of long-term passes during
construction period could constitute a source of user equity.
46
47
EIB (2008)
IIRSA Sur, Project Finance Magazine (2007)
REFERENCES
A. Jadresic (2006). Expert Panels in Regulation of Infrastructure in Chile, PPIAF
ABCR (2006). Highway concessions, a worldwide trend. Associao Brasileira de Concessionrias de
Rodovias.
Autostrade (2006), Annual Report, Autostrade
Bousquet & Fayard (2001). Road infrastructure concession practice in Europe, The World Bank
Institute
Chinese National Audit Office (2008) Audit Investigation Findings on Construction, Operation and
Management of Toll Expressways in 18 Cities and Provinces, Chinese National Audit Office
website
CNT (2003 and 2007), Pesquisa Rodoviaria, Confederao nacional dos transportes
Correa & Al (2007). How to revitalize infrastructure investments in Brazil: Public policies for better
private participation. The World Bank
Correa, P. & Al (2006). Regulatory governance in infrastructure industries, Assessment and
measurement of Brazilian regulators. The World Bank / PPIAF
EIB
Network
Projects.
Estache A. & Rus G. (2000). Privatization and regulation of Transport Infrastructure, The World Bank
Institute
Estache A. & Strong J. (2000) The rise, the fall and... the emerging recovery of project finance in
transport. World Bank Institute (2000).
Estache A., Romero M. & Strong J. (2000). The long and winding path to private financing and
regulation of toll roads. The World Bank Institute
Fenabrave (2007). Relatorio Anual. Fenabrave
Fitch Ratings, (2008). Brazils toll road concessions: a new cycle of opportunities in a more stable
environment. Fitch Ratings
Gomes-Lobo A. and Hijinosa S. (1999). Broad roads in a thin country: Infrastructure Concessions in
Chile, The World Bank Institute
Guasch, J.L. (2004). Granting and Renegotiating Infrastructure Concessions Doing it Right. The
World Bank Institute Development Studies: Washington, D.C.
Kerf M., Gray D., Irwin T., Levesque C., Taylor R. & M. Klein (1998) Concessions for Infrastructure, a
guide to their design and award, The World Bank & The InterAmerican Development Bank
Project Finance Magazine (2007) Latin American Bond Deal of the Year, in Project Finance Magazine,
Feb 2007
Quinet E., Trujillo L. & Estache A. (2000). Global Toll Road Study, Knowledge database. PPIAF
Sernam, C. (2007). Analise dos aspectos crticos em processos de concesso de rodovias,
Universidade Federal do Rio de Janeiro.
Smith G. & Al. (2007). China expressway: connecting people and markets for equitable development,
The World Bank
Urdapilleta, E. & Al (2008) Brazil Second Programmatic Financial Sector Study, An Overview of
Directed Lending. The World Bank
World Bank (2006), Brazil Road Transport Project, Project Appraisal Document, The World Bank
World Bank & Ministry of Construction, Japan (1999). Asian Toll Road Development Program The
World Bank
41
42
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
World Bank & PPIAF (2007). Public-Private Partnerships Units, Lessons for their Design and Use in
Infrastructure, The World Bank & PPIAF 2007
World Economic Forum (2007) Benchmarking National Attractiveness for Private Investment in Latin
American Infrastructure. World Economic Forum
ANNEXES
43
I.
48
Under federal management, contract revisions were realized within their initial contractual framework. Contract
restructuring occurred in State programs such as in Parana. Generally, renegotiation occurs when the original
contract and financial impact of a concession contract is significantly altered and such changes were not the result
of contingencies spelled out in the contract. Cf. Guasch (2004).
45
46
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
Box 1.1.
For very long contracts, regulatory mechanisms governing tariff updates should take into account the current
economic environment, and not only the conditions at contract signing
Typical contracts used in Brazil at the federal level are based on enforcing the financial conditions described in the
concessionaires initial commercial proposal during the contract life (25 years). Experience shows that this
structure fails to push the concessionaire to realize productivity gains and transfer them to the users, as well as
distorts concessionaires incentives to invest. The challenge is then to develop mechanisms that sufficiently protect
the concessionaire while preserving users interests. A multi-annual revision process of the equilibrium to account
for major changes (for example, capital costs, productivity) could be the solution.
For simple projects, fast-track auctions can bring a swift and highly competitive process
Several innovations in the competitive process were introduced by the federal government to foster competition
and reduce processing times: (i) use of a simultaneous tendering without prequalification, backed by proposal and
performance bonds, (ii) two phased bidding through a price auction process and then ratification of technical
proposition, (iii) openness to foreign bids, (iv) openness to consortia without construction/engineering companies,
(v) use of standard, non-negotiable contracts. Clearly, pre-qualification and/or two stage biddings processes
remain justified for more complex or less standard projects (such as projects including large construction works) so
that bidders would be ready to invest the cost of preparing reasonable bids
In the absence of a strong public capacity to structure projects, only a government-wide commitment to the
concession program could allow for success
A reduced capacity of the public administrations, compounded with a lack of political consensus on the role of the
private sector, led to a 10 year halt of the toll road program. When finally the government committed itself to the
program in 2007, finalization of the preparation took only 6 months. In a context of strong market appetite for toll
road concessions, consolidating the governments capacity to structure projects appears as a priority.
49
II.
A.
Initial Framework
Road
Segment
Extension
NOVADUTRA
BR-116/RJ/SP
402.0 km
PONTE
BR-101/RJ
13.2 km
CONCER
BR-040/MG/RJ
179.9 km
CRT
BR-116/RJ
142.5 km
CONCEPA
BR-290/RS
121.0 km
ECOSUL
BR-116/293/392/RS
Plo de Pelotas
623.8 km
Total
1,482.4 km
Source: ANTT
"Brownfield" concessions
10.
While public money was scarce, significant country risk translated also into high costs of
capital, limiting the capacity of the private sector to undertake significant investments, and notably to
build new roads. The concession model was thus, by large, imposed de facto by the environment:
50
See Engel&Al, Privatizing highways in Latin America: is it possible to fix what went wrong? Yale University 2003
In 1998, the management of a package of 623 km of highways in Rio Grande do Sul was transferred back to the
Federation, following previous management attempts, by state government.
51
47
48
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
open toll systems, whereby the users are charged a fixed amount each time they cross a toll
plaza, distance of 70 to 100 km on average, but can bypass the toll plazas by entering or exiting
the road through accesses between the toll plazas without being charged.
mix of urban and interurban segments, urban segments being toll free.
fixed-term 25 year contracts, short by international standards but in line with the reduced
investment requirements and the high interest rates. Contracts signed between 1994 and 1998
are bound to end between 2019 and 2023.
B.
Annexes
49
cancellation of concessions or the impossibility of operating toll gates. Federal concessions fared
better, with no significant contract renegotiation and economic equilibriums upheld by the courts.
17.
Overall the performance of contractors was good. About 10,000 km of highway were quickly
transformed into good driving conditions and road standards increased substantially. Rate of deadly
accidents was halved in ten years on tolled routes. 55 In 2007, 22 of the 23 best quality roads in Brazil
were tolled highways. 56 The private sector invested R$1.2 billion per year between 2002 and 2006
(Figure 2.1), about 12 percent of total investment in the sector during the same period. 57 As a
consequence, while the quality of the rest of the network severely worsened between 1998 and 2006
(in 2004 less than 25 percent of federal highways were in good condition), tolled highways maintained
a sufficient service level. 58
Billion Reais
6
5
4
3
2
1
0
2002
2003
2004
2005
Federation
States
2006
Municipalities
Sernam (2007)
CNT (2007)
ABCR (2006)
CNT (2003) and World Bank Road Transport Project (2005)
See in particular Correa & Al. (2006)
50
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
an increasing amount of cash. The sector is naturally consolidating as several groups (CCR, OHL,
Ecorodovias, TPI, Bertin-Equipav) actively seek expansion fields, either through second-market
purchase or new projects, some of them raising successfully capital through stock exchange listing.
Selected aspects of the regulation of the first phase federal concessions
20.
This section particularly focuses on the concession of the highway linking Rio de Janeiro and
Sao Paulo (Dutra road Novadutra concession), based mostly on data made available by the ANTT,
and reviews of: (i) traffic, (ii) costs, (iii) investment requirements, (iv) and estimated profitability
evolutions.
21.
Traffic on the Dutra road was globally in line with the concessionaire's forecasts. 60 Uncertainty
regarding traffic volumes at the start was limited to the impact tolls would have on existing users.
Traffic growth was slower than estimated (3.45 percent p.a. instead of 5.8 percent) resulting in 2007
in a 15 percent shortage. This is likely to be compensated by concession end, as forecasters proved
overly prudent on long-term perspectives (1.5 to 2 percent p.a. instead of a likely 3 to 4 percent
growth rate). Less expected was the fast growth of toll free urban and suburban traffic.
Figure 1.2. Dutra highway, traffic forecast by concessionaire vs. realized
110,000
100,000
90,000
80,000
70,000
60,000
50,000
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
Realized
22.
Data on concessionaire's operational and investment costs is limited to the initial commercial
proposals and particularly their investment programs. Comparing those (which serve as a basis for the
computation of price escalation) with actual costs (for instance from concessionaire's financial
statements) proved impossible and does not appear to be an exercise undertaken by the regulator. A
comparison of kilometric costs with data from concessions awarded in 2007 is undertaken in Annex
III. D. It hints towards significant productivity gains in real terms (up to 79 percent cost difference) in
operation, maintenance and administration, which can be related to some level of cost-sharing
between different concessions of the same group, and to the introduction of technology improvements
in tolling and road works. Capital costs were halved between the 1990s and 2008, and it is expected
that concessionaires' realized windfall benefits during refinancing. The main indicators on which local
financing are based 61 upon are the inter-bank interest rate (CDI), the long-term interest rate of the
BNDES (TJLP) and the consumer price index (IGP-M). While each of these was high (20-30 percent at
60
Traffic refers here to number of users paying full toll. Traffic forecasts are those specified in the concessionaire's
initial commercial proposition.
61
As such, the sponsor of the NovaDutra, CCR, has the following mix of long-term liabilities: 21 percent on BNDES
loans indexed on the TJLP, 56 percent on debentures indexed for half on the IGP-M and half on the CDI.
Remaining liabilities are mostly based on the CDI.
Annexes
51
contract signing), they had fallen to 8-12 percent in 2007 and only had progressed to a limited extent
by the end of 2008, amidst the global financial crisis. All indicates that, in parallel, company equity
spread fell further with the decrease of regulatory, traffic and cost risks. On the basis of the
concessionaires commercial proposal and financial statements, it is possible to estimate the equity
cost of the NovaDutra in 1996 at a real 24 percent. It is reasonable to assume that the cost might
have dropped below 12 percent by early 2008, at the wake of the financial crisis.
Figure 2.3 Evolution of main Brazilian financing rates 1996-2007
35%
30%
25%
20%
15%
10%
5%
0%
1996
1997
1998
1999
2000
2001
CDI
2002
2003
2004
2005
2006
2007
TJLP
Revisions
12
15
17
13
14
3
Adequacy (DNER)
7
5
4
10
4
?
25.
Two major risks were identified during the implementation of the first phase of concession: (i)
the risk that political pressures by local representatives will lead to the addition or prioritization of
investments that do not benefit the road users, nor are economically justified, nor are paid for by their
beneficiaries such as crosswalks (often on emergency basis for security reasons) or lateral lanes; (ii)
the risk that the concessionaires might have artificially increased their unitary costs in their original
52
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
forecasts to generate increased benefits during investment revision. According to the ANTT, the entity
had only limited power to manage both risks so far.
led to high initial tariff increases
26.
Tariffs evolved in the first ten years of concession under: (i) a yearly inflation computed
according to a formula of sector price inflators specific to each concession (readjustments); (ii)
modifications of the base tariff (revisions) due principally to modifications of the required investments
of the concessionaires or reduction of revenues from annex activities. On average, toll levels were
multiplied by 4 in ten years, a 15 percent yearly rate of increase which was about 40 percent faster
than consumer price index (IGP-M) (Table 2.3). Tariff modifications under inflator yearly adjustments
were responsible for about two thirds of the increase. Inflators progressed on par with inflation (Figure
2.4).
Table 2.3. Tariff evolutions under the first phase of concessions
Ponte
Novadutra
Concer
CRT
Concepa
12/29/1994
10/31/1995
10/31/1995
11/22/1995
03/04/1997
0.78
2.39
1.91
2.46
0.75
3.5
7.8
6.7
6.8
6
Average
Total tariff
evolution in real
terms
230%
202%
202%
202%
181%
-4%
-6%
-9%
-16%
26%
28%
13%
24%
10%
124%
11%
1%
1%
-6%
1%
36%
8%
16%
-9%
185%
204%
-2%
43%
-1%
47%
Note: Base tariff for the Concepa concession was 1cR$/km at contract signing
Source: ANTT, World Bank calculations
Figure 2.4. Compared evolution of the consumer index and the tariff inflator (Dutra road)
300
280
260
240
220
200
180
160
140
120
100
1996
1997
1998
1999
2000
IPC
2001
2002
2003
2004
2005
2006
Annexes
53
27.
Real terms price increases originate from base tariff revisions (Figure 2.5). Revisions were
substantial in the first years of the concession contracts, with an average 39 percent proportional
increase of tariffs under DNER management. ANTT record proved much stricter, and average price
escalation under revisoes was only 1.7 percent during the 2002-2006 period.
28.
Extraordinary revenues remained limited (about 2 percent of total revenues for the
NovaDutra) while reduction in tariffs were allowed to be marginal.
29.
No mechanism allowed users to reap the benefits from the decrease in cost of capital nor from
productivity gains.
Figure 2.5. Tariff evolutions under the first phase of federal concessions until 2008
200%
185%
150%
124%
Ponte
100%
Novadutra
Concer
CRT
50%
36%
26%
Concepa
28%
24%
13%
10%
11%
1% 1%
1%
16%
8%
0%
-4%-6%
-9%
-16%
-50%
Base escalation in
real terms
-6%
Revisions led by
DNER
Revisions led by
ANTT
-9%
real terms
IRR on capital
17.58%
16.3%
IRR on equity
24% (estimated)
18.7%
Source: ANTT data and World Bank calculations
nominal terms
27.0%
29.5%
Simulation with
high
productivity
gains
real terms
80%
120%
54
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
Conclusion
33.
The first phase of federal road concessions gave the basis for the Brazilian road concession
model and notably its regulation by contract. In many ways, this has been a success: (i) the private
sector delivered to the users good quality roads while the country underwent a prolonged and rigorous
fiscal adjustment program, (ii) DNER first, and then ANTT, created a large body of experience,
regulations, and relatively clear regulatory mechanisms, and (iii) road concessions did not have to be
renegotiated, 62 contrasting with the experience in several countries in Latin America such as Mexico,
as well as some Brazilian states.
34.
However, revisiting the first ten years of contract implementation, it appears also that road
users did not get good value for their money as several large efficiency gains were not passed on to
user prices, notably the decrease in the cost of capital and also probably large productivity gains in
operations. In addition, investment allocation was somewhat distorted by the conjunction of local
political pressure as well as contractual mechanisms favoring over-investment. Given the nature of the
regulation, based on contract enforcement, it may not be possible to significantly reverse those trends
before the concession contracts ends, between 2020 and 2025.
62
Under federal management, contract revisions were realized within their initial contractual framework. Contract
restructuring occurred in state programs such as in Parana. Generally, renegotiation occurs when the original
contract and financial impact of a concession contract is significantly altered and such changes were not the result
of contingencies spelled out in the contract. Cf. Guasch (2004).
III.
A.
Concessions are mostly oriented toward operation and service rather than upgrade
35.
The second phase of the federal road concessions program is composed of 7 segments (lots)
for a total of 2,600 km. It more than doubles the extension of the network under concession managed
by the government, previously 1,482 km.
36.
Concessions are private, set for 25 years, with costs shared by the federal government
(limited to upgrades before initiation of the concession) and by part of the users through tolls.
Financing risk is the responsibility of the concessionaire, but through the BNDES, the government can
provide lending for up to 70 percent of investment costs. No co-financing mechanism for local
investments is included.
37.
Extension is in the 300-500 km range. Toll roads are of open toll systems, crossing both urban
and rural areas, implying that a portion of the main roadway users (notably in urban areas) or side
road users (parallel lanes) are not charged tolls. As traffic is mostly concentrated around
agglomerations, concession cost is borne disproportionately by long-distance users through important
cross-subsidies.
38.
Bidding was realized simultaneously, after basic engineering and feasibility studies. Lowest
base toll was the sole concession award criteria. To orient competition, a cap toll level was announced
prior to the bidding. Concession award involves no monetary transfer to or from any public entity.
39.
Toll level is the same at each toll gate, without consideration for the number of kilometers
effectively traveled on the road, as in many open toll systems. Toll levels are increasing proportionally
with the number of axes (a particularity of Brazil), penalizing the large trucks which are often the
most efficient.
40.
Concessions are brownfield with limited upgrade works. To reduce tariffs, tolls are levied only
after completion of initial maintenance works (6 months about $75,000/km). Over the first 6
contracts representing 2,400 km, 283 km are scheduled to be duplicated and 170 km are to be built
(mostly urban rings), id est a total of 19 percent of the total extension. Total concession costs,
excluding taxes and financing costs, are as follows:
Table 3.1. Breakdown of 2nd phase concession costs
% of concession costs
(excluding taxes & financial costs)
7.5-25%
20-33%
Operation
11-13%
User services
9-13%
Administration
11-16%
Toll collection
10-13%
7-8.5%
41.
Additional concession expenditures include: (i) tributos (contributions - an additional 11
percent); (ii) impostos (taxes - additional 1520 percent); (iii) long-term remuneration of capital
(additional 30 percent on the base of an 8.95 percent estimated WACC).
42.
Long-term debt financing would mainly be provided by BNDES and/or international
organizations (IDB, IFC).
55
56
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
The concession contract includes obligations for the concessionaire in terms of performance standards as well
as in required investments, defined in volume, quality and scheduling in the concessions investment program
(PER). As part of the bids, the candidates submit an informed version of the PER that includes unit costs, as
well as their own traffic forecasts taking into account their effective toll. Using a model company spreadsheet,
this information is used to evaluate the projected rate of return of the concessionaire which value will serve as
base for the rest of the concession.
During project life, base toll levels can be revised to mainly take into account: (i) revisions of the investment
program (PER), proposed or validated by the ANTT, (ii) additional resources received by the concessionaire,
(iii) tax evolutions affecting the concession. Revisions could also occur in the case of the first phase of
concessions in case of modifications of input prices and quantities. Impacts on financial equilibrium of the
concession contract of such events are estimated, all other parameters supposedly set at the level proposed
initially by the concessionaire (especially traffic and unit costs), and tariff is modified to maintain the rate of
return of the concession at its initial level.
As evaluations are realized on the basis of initially set parameters, and not on the basis of the observed,
incentives of the contractor to optimize its productive efficiency are preserved.
As traffic, market unit costs and financing rates can widely change with time, the alignment of the incentives
of the concessionaire and the needs of the user cannot be maintained in the long-run. A relative drop in
interest rates or in unit prices will generate incentives for the concessionaire to over-invest, while a drop in
traffic would have the opposite effect.
As all investments are to be amortized by the end of the concession, late additions to the PER can generate a
proportionally higher increase in toll levels.
It remains unclear how this principle affects the incentives of the bidders to disclose their true offer.
B.
Decrease of the country risk (1995: 10-15 percent, 1996: 5-10 percent to be compared with 200250 base points in the end of 2007), containment of inflation (still 66 percent in 1996, below 5
percent since 2006)
Annexes
57
Creation of the ANTT in 2002, with successful experiences in consistently managing the first phase
of concessions for five years, which helped reduce perceived regulatory risk.
Good prospects for sustained growth of both GDP (4.5 percent year forecast to be compared with
2.5 percent for 1995-2004) as well as GDP per capita (about 3 percent forecast compared to 1
percent for 1995-2004) with subsequent expected increases in both households vehicle
equipment and demand for freight transport.
Decrease in cost of debt financing through BNDES by 100 base points after implementation of
PAC.
Necessity for engineering companies to be present in the consortium relaxed: simple service
provision agreement accepted.
Participation from institutional investors, both Brazilian and foreign, clearly authorized.
Use of the leilao procedure, namely permitting: (i) sequencing of bidding phases (financial offer
first, technical second) for a faster process, (ii) no disclosure of competitors names before bid
opening, (iii) limitation of the possibilities for appeals (only one candidates qualification
scrutinized); (iv) realization by the efficient market exchange place Bovespa.
Non serious proposals deterred by imposing: (i) a proposal guarantee, before financial opening;
(ii) a performance guarantee, at contract signature.
Increased competition in the market is apparently leading to reduced consumer prices and higher
productive efficiency. Though, risk of low balling increased.
58
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
will face strong incentives for reducing scope of requisite and complimentary works. This might bring
in a more contentious relationship.
Evolutions of required performance standards
54.
Road condition monitoring is based on (i) IRI <2.7 mm/m (very low level given contractors
capacity to finish the works); (ii) trincas (cracks-absence for class 3, max 15 percent for class 2);
(iii) afundamento da trilha de roda (sinking of surface deterioration<7mm); (iv) skid (<50.10^-2
mm/km apparently little monitored in the first phase); (v) degrau entre faixa direita e acostamento
(elevation between the roadway and shoulder<2.5cm); (vi) panelas (potholes-absence of excessively
remedied areas), and (vii) characteristic deflexion (< 50.10^-2 mm). Dropped parameters used in first
concessions include the Indice de Gravidade Global (IGG) and the Valor de Serventia Atual (VSA).
55.
Highest existing service levels for medical (<15min) and mechanic (<20min) user assistance
have been generalized.
56.
Service level: minimum equivalent to DNITs road level 1 (expressway = level 0), in other
words HCM level C in plane or undulated areas, level D in mountain areas.
57.
Performance standards are increasingly centered on road user comfort, a welcome move. The
discussion should focus now: (i) for ANTT, on ways to monitor effectively performance, and especially
IRI; (ii) for the government, on the regulation of the appropriate standards per volume and type of
traffic.
Other contractual evolutions
58.
Arbitration process clauses were dropped, given their partial incompatibility with local laws
(arbitration left open the possibility of judiciary appeal), without being replaced by any equivalent
process. This absence of a conciliatory (such as an expert panel) or arbitration process might become
more problematic given the modified focus of the contract regulation.
C.
Main lessons of the tendering process for the second concession phase
Lack of consensus on base principles and roles of institutions led to an extremely chaotic preparation
process (Box 3.2)
Box 3.2. History of the preparation of the second phase of concessions
Annexes
59
Consortium composed in 3 equal proportions: WTorre Engenheira, a real estate engineering company, Splice do
Brasil, a specialized telecommunication / electronic company, and Comporte Participacoes S.A., a vehicle controlled
by the Constantino brothers, who fully control GOL.
60
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
for the BR-153, compromising BNDES lending as well as depriving sponsors from any satisfactory
returns.
Table 3.2. Results of the tendering of the second phase of concessions
Road identificatioin
Number of propositions received
Winning propossition
Maximum tariff as specified in tender document
Winning tariff
Tariff reduction obtained
Average base tariff (R$/km)
Traffic (Millions)
Average daily traffic equivalent first year
Average daily traffic equivalent year 25
Toll revenues (R$ millions)
Year 10
Year 25
Investiments (R$ millions)
Road investments
Maintenance
Buildings
Equipment
Total over 25 years
Operational costs (R$ millions)
Road maintenance
User services
Toll collection
Administration
Other operational costs
Total over 25 years
Project economics (R$ millions)
Resultado liquido total apos impostos
Primeir ano de tesoria positiva
Payback (eco)
TIR (eco) real
Project financing (R$ millions)
Bridge loan - Total
Bridge loan - Real interest rate
Debt provider
Total initial debt
Debt - interest rate
Debt - Spread over TJLP
Debt - Amortization period
Total estimated necessary equity
Payback equity
IRR equity (real)
BR-116/SP/PR Sao
Paulo-Curitiba
13
OHL
R$ 2.685
R$ 1.364
49.20%
R$ 0.020
ANTT
studies OHL
Dif
BR-381/MG/SP Belo
Horizonte-Sao Paulo
14
OHL
R$ 2.884
R$ 0.997
65.43%
R$ 0.014
ANTT
studies OHL
Dif
40
173
62
341
55%
97%
35
151
65 86%
350 132%
31
123
65 110%
323 163%
15
62
306
466
258 -16%
0%
465
288
435
199 -31%
350 -20%
239
340
188 -21%
332 -2%
1,296
611
58
202
2,169
2%
1,320
394 -36%
77 33%
109 -46%
1,902 -12%
873
824
107
245
2,051
627
483
99
135
1,345
-28%
-41%
-7%
-45%
-34%
869
489
54
175
1,589
227
314
366
483
780
2,172
286 26%
328
4%
335 -8%
300 -38%
639 -18%
1,890 -13%
317
383
472
483
886
2,543
345
405
383
306
680
2,122
9%
6%
-19%
-37%
-23%
-17%
2,270
5
14
8.95%
2,038 -10%
6
14
8.68%
1,786
6
15
8.95%
1,167 -35%
6
15
8.55%
166
7.7%
BNDES
568
5.2%
3.0%
12
564
15
10.2%
155
7.7%
BNDES
396
5.2%
3.0%
11
252
16
10.4%
33%
76%
9
40
162
239
137 -15%
247
3%
855 -2%
350 -28%
75 39%
98 -44%
1,378 -13%
773
262
45
113
1,194
216
255
326
483
672
1,954
282 31%
273
7%
342
5%
286 -41%
539 -20%
1,724 -12%
1,570
5
14
8.95%
1,260 -20%
6
15
8.00%
135
7.7%
BNDES
396
5.2%
3.0%
12
252
16
10.2%
20
109
22%
28%
9
39
108
166
74 -31%
127 -23%
113
166
110
199
670 -13%
261
0%
50 11%
74 -35%
1,056 -12%
443
222
38
98
801
381 -14%
219 -1%
19 -50%
95 -3%
715 -11%
378
195
49
126
749
374 -1%
230 18%
48 -2%
82 -35%
735 -2%
111
212
246
323
407
1,301
205 85%
241 14%
254
3%
248 -23%
340 -16%
1,290 -1%
97
173
151
254
268
945
174
161
95
219
179
830
79%
-7%
-37%
-14%
-33%
-12%
119
207
182
254
308
1,072
233 96%
235 14%
215 18%
229 -10%
296 -4%
1,210 13%
1,050
5
15
8.95%
870 -17%
5
16
8.01%
666
6
16
8.95%
260 -61%
7
20
4.09%
665
5
15
8.95%
78
7.7%
BNDES
283
5.2%
3.0%
12
197
17
9.5%
11
51
61
?
BNDES / BID
331
?
?
21
176
22
4.2%
14 56%
78 100%
658
6
15
8.64%
84
7.7%
BNDES
213
5.2%
3.0%
11
159
16
10.3%
67.
Uncertainties are the following: (i) are those offers viable in the long-term and if not, who will
bear the consequences? And (ii) do the parameters detailed in the commercial offers reflect the true
economic equilibriums of the offers? and if not why?
68.
Additional factors that could explain the levels of the offers are the following: 64
Winners curse is largely excluded for OHL as the group already manages 1,100 km of concessions
in Brazil and has thus ample insider information. This remains possible for BRVias, whose sponsors
do not have the same experience.
Low balling risks are unclear. On the one hand, no contract of the first phase of concessions
appears to have been substantially renegotiated by ANTT (not accounting for contractual revisions
of the PER) and consolidation of the agency should further decrease risks. As an important caveat,
as OHL will be managing now 50 percent of the Federal program and a third of the total Brazilian
highways under concession, its size might make it too big to fail in the eyes of the government.
64
-3%
20%
-1%
Annexes
61
Contractor sponsor interest prevailed. Unclear risk sharing due to the absence of compensation
clause in case of a concessions early termination may lead a contractor sponsor to artificially
boost construction costs and projected revenues to ensure a fatter compensation by the
government in case of failure (as courts are more likely to settle on the book value of assets
rather than on the discounted expected cash-flows). This provision would act as an implicit
government traffic risk guarantee, in which the trigger level is actually manipulated by a
concessionaires proposal. As OHL covers construction and operation activities, expected benefits
from its construction activities might compound with this guarantee to reduce impacts of traffic
risks on society.
Strategic move. Given the strength of the competition, actors might have had strategic incentives
to accept apparently high risks and low returns: (i) for existing concessionaires, optimizing in the
long run use of productive factors, as first phase concessions are already halfway through their
life-cycle; (ii) for international actors, to consolidate implementation on the emerging Brazilian
market; (iii) for newcomers, to enter a developing market and hedge one transport mode against
the other (BRVias GOL).
69.
Whatever the real rationale for those offers, in this context, challenges for ANTT will differ
from first phase concessions, and include: (i) ensuring timeliness and quality of concessionaires
projects and works (especially for BRVias), (ii) efficiently monitoring traffic, concessionaires
performance and enforcing penalties when necessary, (iii) equating investments to the true
necessities of demand, resisting pressures to reduce investments especially at times when large
shares of operational revenues are dedicated to debt repayments, (iv) ensuring that financial closes
are realized in ways that preserve the long-term concessions interests.
70.
As those concessions will be financially more fragile than the first phase of concessions, the
risk of important renegotiation of contractual terms, or even a public bailout, cannot be excluded. The
experience of Mexico shows how strong competition did not necessarily translate into good
competition (Box 3.3).
Box 3.3. Poor Design, a Hurried Pace, and Financial Disaster: Renegotiation in Mexicos
Highway Program
In 1997 the Mexican government announced that it would spend US$3.3 billion over the next 30 years to
restructure the financing of 52 highways built under private concessions of toll roads in the early 1990s. This
renegotiation and bailout of private operators followed a program riddled with design problems. The first was that
concessions were awarded to the operators that submitted the shortest time to operate each concessiona
questionable criterion by any economic principle.
The second problem was that the government provided extremely optimistic guarantees of traffic volumes, implicit
insurance for construction cost overruns, and a state-run banking sector that provided loans without detailed
analysis of the structure and sustainability of the projects being financed. Finally, the hurried pace of the program
led to incomplete designs and specifications for road construction, and rushed engineering studies and hasty cost
projections created ample opportunity for padding budgets. The resulting bids covered very short concession
periods (with most running 612 years, although one bid was for just 18 months!), caused significant cost
overruns, required high tolls to support the short concession periods, andas should have been anticipated
culminated in economic and financial disaster. Mexicos 1994 financial crisis accelerated the problem. The
government had to retake nearly 80 percent of the concessions at an estimated cost of US$7 billion to US$12
billion. In addition, questions have been raised about the transparency of the program.
Extract from Guasch (2004)
D.
71.
While the first phase of concessions had been marked by the dominance of local construction
companies, a constrained financial market, an uncertain growth outlook and an inexistent sector
history, ten years later, the second phase was initiated under completely changed auspices. With
existing groups looking for opportunities to invest their operating excesses in new projects,
international players eager to invest in the promising Brazilian market and an efficient regulatory
62
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
framework, competition was fierce and led prices to drop. The comparison of two of the main
concessions of each phase brings to light what factors, at first glance, allowed prices to drop four fold.
Nova Dutra (Rio-So Paolo) vs. Ferno Dia (Rio-Belo Horizonte)
72.
The two roads show similar profiles in terms of distance and physical characteristics. It is
difficult to fully compare traffic (as measured in base toll units) as the concessionaire of the Fernao
Dia included in its financial forecasts traffic twice as high as the ANTTs own forecasts. On the base of
the concessionaires forecast, traffic per kilometer at concession start would be 50 percent higher on
the Fernao Dia.
73.
Base tariffs were set in 2007 at 7.8 R$ per toll plaza (0.098 R$/km) for the Nova Dutra and
1.36 R$ (0.019 R$/km) for the Fernao Dia, that is to say five times lower.
74.
Plugging into the financial models of the new concession the values observed for the previous
one at constant prices, it appears that one quarter of the tariff differential is accounted for by the
difference in traffic, another quarter by the different financial conditions at contract signing, and the
remaining half by the difference in investment and operation unit costs. 65
75.
Comparison with ANTT initial forecasts and with other roads concessions of the second phase
brings similar lessons (see tables in Annex I). Particularly striking is the drop in concession costs by
60 to 80 percent, even using ANTT more prudent estimates.
Table3.4. Comparison of cost structure of 1st and 2nd phases concessions at constant prices
Nova Dutra and Fernao Dia highways
1.
3.
402
80
562
70
562
70
162,000
246,000
315,000
244,000
385,000
562,000
51%
57%
78%
132,000 -19%
178,000 -28%
245,000 -22%
115,000
97,000
60,000
272,000
54,000
19,000
24,000
96,000
-53%
-80%
-60%
-65%
92,000
25,000
29,000
146,000
-20%
-74%
-52%
-46%
132,000
472,000
114,000
72,000
106,000
604,000
25,000
104,000
22,000
27,000
29,000
129,000
-81%
-78%
-81%
-63%
-73%
-79%
22,000
134,000
34,000
34,000
27,000
156,000
-83%
-72%
-70%
-53%
-75%
-74%
914,000
247,000 -73%
327,000 -64%
7.80
17.58
1.36 -83%
8.55 -51%
2.88 -63%
8.95 -49%
6.
5.
4.
General data
Length
Length / toll gate
2.
Fernao Dia
(comercial
proposition of
winner)
65
Simulations based on the financial model developed by ANTT for monitoring purposes, using data from the
commercial offers of the concessionaires.
43%
12%
4%
8%
5%
1%
7%
6%
1%
57%
9%
20%
28%
Aditional costs
Taxes: tributos
Taxes: impostos
Capital Costs
689,000
Total expenses
392,000
65,000
134,000
193,000
Aditional costs
Taxes: tributos
Taxes: impostos
Capital Costs
6,921
Total expenses
297,000
84,000
29,000
54,000
31,000
9,000
46,000
41,000
3,000
3,936
651
1,351
1,935
Aditional costs
Taxes: tributos
Taxes: impostos
Capital Costs
2,984
844
288
542
316
91
462
407
35
402
R$ 1995
57%
9%
20%
28%
43%
12%
4%
8%
5%
1%
7%
6%
1%
2,027,000
1,154,000
191,000
396,000
567,000
873,000
247,000
84,000
159,000
92,000
27,000
135,000
119,000
10,000
20,371
11,587
1,915
3,977
5,695
8,784
2,484
848
1,596
929
267
1,359
1,199
102
401.6
50%
9%
14%
27%
50%
15%
12%
4%
5%
3%
4%
5%
1%
751,000
373,000
65,000
105,000
203,000
378,000
112,000
94,000
33,000
35,000
25,000
33,000
38,000
8,000
7,529
3,736
648
1,049
2,039
3,793
1,128
940
335
348
251
328
379
84
39%
9%
10%
20%
61%
21%
6%
7%
7%
4%
7%
7%
1%
408,000
161,000
35,000
43,000
83,000
247,000
87,000
23,000
27,000
30,000
17,000
29,000
29,000
5,000
5,730
2,262
493
601
1,168
3,468
1,224
319
384
415
244
406
406
71
BR-381/MG/SP Belo
Horizonte-Sao Paulo
382.3
43%
9%
12%
23%
57%
18%
11%
6%
6%
4%
5%
7%
1%
574,000
249,000
49,000
68,000
132,000
325,000
101,000
61,000
36,000
33,000
20,000
29,000
38,000
7,000
5,484
2,381
472
649
1,261
3,103
964
585
342
318
194
273
362
63
320.1
41%
9%
11%
22%
59%
17%
13%
6%
6%
2%
6%
7%
1%
501,000
208,000
43,000
56,000
109,000
293,000
84,000
64,000
32,000
30,000
10,000
30,000
37,000
6,000
4,009
1,663
345
447
870
2,347
674
509
254
243
79
241
299
48
321.6
27%
9%
6%
12%
73%
27%
11%
5%
7%
3%
8%
11%
1%
265,000
72,000
23,000
17,000
32,000
193,000
72,000
29,000
12,000
19,000
7,000
20,000
30,000
4,000
2,124
577
183
134
261
1,546
578
232
96
154
56
161
239
29
412.7
40%
9%
11%
20%
60%
22%
5%
7%
7%
2%
7%
9%
1%
313,000
124,000
27,000
33,000
64,000
189,000
70,000
15,000
21,000
23,000
6,000
23,000
27,000
4,000
3,219
1,273
277
338
658
1,946
722
155
216
240
59
236
277
40
Table 3.4. Detailed Comparison of 1st and 2nd Phase Cost Structures and Tariffs on of 1st and 2nd Phase Cost Structures and
Tariffs
Annex
63
43%
12%
4%
8%
5%
1%
7%
6%
1%
57%
9%
20%
28%
Aditional costs
Taxes: tributos
Taxes: impostos
Capital Costs
689,000
Total expenses
392,000
65,000
134,000
193,000
Aditional costs
Taxes: tributos
Taxes: impostos
Capital Costs
6,921
Total expenses
297,000
84,000
29,000
54,000
31,000
9,000
46,000
41,000
3,000
3,936
651
1,351
1,935
Aditional costs
Taxes: tributos
Taxes: impostos
Capital Costs
2,984
844
288
542
316
91
462
407
35
402
R$ 1995
57%
9%
20%
28%
43%
12%
4%
8%
5%
1%
7%
6%
1%
2,027,000
1,154,000
191,000
396,000
567,000
873,000
247,000
84,000
159,000
92,000
27,000
135,000
119,000
10,000
20,371
11,587
1,915
3,977
5,695
8,784
2,484
848
1,596
929
267
1,359
1,199
102
401.6
49%
9%
14%
27%
51%
14%
11%
4%
7%
3%
4%
6%
1%
848,000
415,000
73,000
116,000
226,000
433,000
120,000
95,000
37,000
59,000
25,000
31,000
54,000
12,000
8,514
4,172
733
1,169
2,271
4,342
1,201
951
366
593
251
314
542
122
42%
9%
12%
22%
58%
20%
5%
6%
9%
3%
5%
7%
1%
568,000
241,000
49,000
65,000
127,000
327,000
116,000
29,000
34,000
54,000
17,000
27,000
42,000
8,000
7,988
3,394
688
920
1,787
4,594
1,634
402
472
754
244
383
591
115
BR-381/MG/SP Belo
Horizonte-Sao Paulo
382.3
45%
9%
12%
24%
55%
15%
9%
5%
8%
3%
4%
8%
1%
678,000
307,000
58,000
85,000
164,000
371,000
103,000
64,000
34,000
57,000
20,000
27,000
56,000
10,000
6,480
2,936
558
808
1,571
3,543
984
607
326
545
194
256
538
93
320.1
44%
9%
12%
23%
56%
12%
14%
6%
8%
2%
5%
8%
1%
559,000
247,000
48,000
68,000
131,000
312,000
65,000
79,000
31,000
46,000
10,000
27,000
46,000
8,000
4,472
1,976
385
540
1,051
2,496
522
636
247
366
79
212
369
64
321.6
42%
9%
11%
22%
58%
16%
10%
5%
8%
2%
6%
10%
1%
375,000
158,000
32,000
43,000
83,000
217,000
60,000
36,000
19,000
32,000
7,000
22,000
36,000
5,000
3,016
1,269
260
343
667
1,747
483
291
151
256
56
174
292
43
Table 3.4 (contd). Detailed Comparison of 1st and 2nd Phase Cost Structures and Tariffs on of 1st and 2nd Phase Cost
Structures and Tariffs
412.7
41%
9%
11%
22%
59%
17%
6%
6%
10%
2%
7%
10%
1%
301,000
124,000
26,000
33,000
65,000
177,000
50,000
19,000
18,000
31,000
6,000
20,000
29,000
4,000
3,097
1,275
267
342
666
1,822
514
191
183
320
59
207
303
44
IV.
Introduction
1.
This note is a review of public policy issues and options for public-private partnerships in
roads, in light of Brazils and other countries experiences with road concessions. It aims to contribute
to the current debate on road concessions under the new legal framework of the PPP law.
2.
All Public Private Partnerships in Brazil were, until recently, awarded within the framework of
the Concession Law of 1995. This law specifically forbids direct public subsidies. Road concessions
have therefore been restricted to projects which could be made viable from user toll revenues.
Because of the high cost of capital in Brazil, and low average per capita income, the only viable model
was to concession existing highways for rehabilitation and maintenance, and where feasible, for some
minimum upgrading. Road users have by and large been satisfied with the improved maintenance
condition of those highways, but they have consistently complained about the inequitable toll system
and the high toll rates on those previously free highways (see Part I.A of the report).
3.
The PPP law was approved in 2006 to allow for private participation in projects which, in order
to turn them financially attractive, would require some form of public sector participation, including
possible direct government subsidies. This new legal framework, together with the reduced cost of
capital and increased motorization rates, has several important implications for the governments
strategy in the sector.
4.
First, the scope for private participation could now be extended to less-trafficked roads where
revenues from user tolls would not be sufficient to cover all the concession costs, or even to roads
where tolling would not be efficient and therefore not be collected.
5.
Second, the scope of projects could now be broadened, up to the construction of new, high
standard, access controlled expressway (greenfield project) which, under certain conditions, might be
more efficient and equitable than the tolling and widening of an existing highway (brownfield project).
6.
Third, the scope of public participation could now be expanded from sharing in some risks,
particularly the key traffic or revenue risk over which a private concessionaire has little or no control,
to various forms of direct or indirect payments to the private operator, if and as needed, to turn
economically-feasible projects attractive to private investors.
Scope of Private Participation
7.
The scope of the first phase of the federal road concession program was limited to five hightraffic sections, which did not need major upgrading works, and which had been previously tolled by
DNER. The selection helped minimize traffic risk at a time of uncertain economic prospects.
8.
The second phase of the program, which was bided and contracted in 2007, had actually been
defined in the mid-1990s shortly after the successful bidding of the first phase. Its scope consisted of
six major interstate highway sections totalling about 2,400 km, with substantial capacity investment
needs. But because of the high cost of private capital at that time, the government decided to
undertake the main capacity works, including duplication of important sections, under standard public
works contracts financed through multilateral (IDB) loans.
9.
Another major problem resulting from these two phases of road concessions awarded under
the Concession law is the disparity and inequity of toll rates. Since the award criterion was the lowest
base toll rate, first phase contracts awarded at a time of very high cost of capital and a relatively
limited competition among Brazilian contractors have resulted in much higher toll rates than those
recently awarded under phase 2, with a much reduced cost of capital and real competition from
foreign bidders. This situation raises the issue of the sustainability over time of such disparate toll
rates (see Part I D of the main text for a review of the toll rate issues).
10.
The new legal framework of the PPP law would in principle allow the government to establish
public private partnerships on any road, independently of its current condition, traffic level, and
investment requirements, and to maintain toll rates (or no tolls) in line with users willingness to pay,
65
66
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
coherent among concessions and service levels offered, and that would be efficient and equitable
among user categories. For this purpose, three types of instruments are now available.
11.
First, private concession contracts could continue to be awarded under the framework of the
Concession law where traffic is sufficient to raise enough toll revenues to cover all the capital and
current expenditures needed under the project.
12.
Second, public private partnership contracts could be awarded under the framework of the PPP
law, where some form of public participation would be needed, in addition to tolls, to cover all project
expenditures.
13.
Third, public-private partnership contracts could also be awarded under the framework of the
PPP law, where tolling is not an efficient alternative and would not be implemented, and public
payments would be made to the private partner on the basis of pre-defined outputs, which can include
a combination of asset availability and performance indicators. This form of contract could replace the
existing form of performance/output-based public contracts (the so-called CREMA rehabilitation and
maintenance contracts) where a contract duration of more than five years would be suitable.
14.
In view of these new opportunities, the Ministry of Transport could develop a PPP roads
strategy which would define clear objectives for a PPP program in the sector, including the conditions
under which the above instruments would be used. For this purpose, MT could first formulate coherent
policies regarding service levels and toll rates, consistent with user stated preferences and willingness
to pay for such services (see Part I and Annex III). It could also define minimum traffic volumes below
which tolling (possibly depending on technology) would be considered inefficient. A multi-year PPP
program could then be drafted on this basis, in order to provide guidance to ANTT and DNIT in
developing and implementing their own programs in a coherent manner.
Scope of Projects
15.
In the
concessionaire
existing road.
included in the
first phase of the program, again due to the very high cost of capital at that time,
obligations were essentially limited to the rehabilitation and maintenance of the
The only noticeable exception had been some (marginal) capacity expansion works
contract for the very high traffic (Rio Sao Paulo) Dutra highway.
16.
In the second phase of the program, after major capacity investments were made under
traditional public works contracts, concessionaires obligations were also essentially limited to
rehabilitation and maintenance, with upgrading works representing only 7.5 to 25 percent of total
project costs (see Annex III).
17.
This open toll road concession model, which minimizes investment costs (by improving an
existing highway) and therefore average toll rates, is generally efficient (depending on traffic growth
and urbanization rates) compared to the construction of a new, access-controlled (greenfield) toll
road. But it also has drawbacks, particularly with regard to equity, service levels and safety, in
particular:
a reluctance of users to pay for a previously free road, especially where improvements are
minimal;
reduced traffic speed and service level, particularly in urban areas, due to conflicts with local
traffic and pedestrians;
inadequate traffic safety due to numerous, uncontrolled accesses to the roadway;
traffic disruptions during upgrading and widening works, which can be excessive on sections
operated at or close to congestion, and
unfair toll payments, poorly related to the amount of road use (see below).
18.
Tolls on open toll road concessions must be collected at toll plazas located on the main
roadway (accesses to the road are too numerous to be controlled). In order to maintain an acceptable
service level on the roadway (since most users have to stop at the toll gate for payment), and to keep
the efficiency of the toll system (a ratio of toll revenues net of collection costs over gross revenues)
sufficiently high to justify tolling, toll plazas must be located at some distances, generally between 30
and 100 km. As a result, since all users of a given vehicle category passing through the toll plaza pay
the same toll, independently of the distance driven on that road, the actual toll rate per km of road
Annexes
67
use can vary widely, making such tolling system very inequitable. In order to avoid the problem with
the numerous short distance daily trips in urban areas, toll plazas have been located away from urban
areas. But since concessionaires are generally also responsible for the urban sections of the highway,
long distance traffic is de facto subsidizing urban traffic. These equity issues can, in principle, be
substantially resolved through modern, in motion, toll collection technology.
19.
Greenfield projects, consisting of building new highways, expressways or motorways,
possibly parallel to an existing congested highway, through a BOT type of concession, may be an
effective alternative, under certain conditions, to an open toll road concession. The above mentioned
service level and safety problems are effectively resolved through controlled accesses and better
geometric and safety standards. And tolling at exits is both efficient, due to the small number of
accesses, and equitable, since payments are directly proportional to the distance travelled.
20.
The feasibility of such greenfield projects in Brazil still needs to be assessed, in light of the
new situation (very different from the period when the first two phases of the federal concession
program were conceived), characterized by the countrys stable macroeconomic framework,
favourably perceived risks and capital flows, and much reduced cost of capital, together with a
dynamic economy and export sector, and increasing demand for transport and motorization rate.
21.
Good candidate projects could parallel existing highways operating at or close to capacity, with
a high proportion of urbanized or semi-urbanized segment.
22.
As a reference, the high-standard 2x2 lane motorways currently built in France in flat or rolling
terrain have an average construction cost of about 4 million euros per km. Traffic volumes in the first
years are on the order of 5 to 6,000 vehicles per day per lane. Toll rates for passenger cars are about
8 to 10 euro cents per km, but these rates still reflect the compensation mechanisms which were in
place until recently for cross-subsidizing the construction of higher cost segments.
23.
A new toll road can be built in stages, in line with traffic growth, in order to improve return on
investment. For example, only one carriageway can be built at first, and initially operated as a twolane, high standard highway. The new highway can then be doubled when needed, or, under certain
conditions, the old, parallel highway can be improved to higher standards and serve as a second
carriageway. The government of Colombia is currently studying such alternatives for the upgrading of
the (Bogota Santa Marta) Ruta del Sol highway to motorway standards.
24.
Regional road networks may also be a viable alternative. By conceding a network of
existing roads with different traffic volumes and characteristics, the traffic risk may be somewhat
reduced. Second, large capital investments can be more easily staggered than on an individual road
segment, which can make it easier to secure financing for subsequent rounds of investments. This
advantage is even more important in the case of greenfield projects, where financing for the
construction of a subsequent segment can be guaranteed by the revenues from segments already in
operation. France has developed an extensive network of motorways with minimal government budget
outlays on this basis (Box 4.1).
Box 4.1. Frances regional motorway networks
A national network of high standard toll motorways was built in France, with minimal contributions from the
government budget. Concessions for regional networks were awarded in the 1950s to five mixed public companies
(Societes dEconomie Mixte, SEM). Four more concessions were awarded in the early 1970s to private operators
formed by public works companies and banks. But following the 1973 energy crisis, three private operators had to
be restructured as SEMs and only one (Cofiroute) remained fully private. A public financial institution (Caisse
Nationale des Autoroutes, CNA), was established to secure finances for the SEMs, issuing debt securities on
financial markets.
In the early 1980s, the government established a revenue transfer mechanism among SEMs, managed by
Autoroutes de France (ADF), which allowed sustaining the concessions affected by the energy crisis with toll
revenues from more profitable SEMs. Also, the regional network concessions allowed the SEMs to secure financing
for new network segments with the guarantee of future incomes from segments already in operation, which
facilitated new construction programs.
More recently, however, the revenue transfer mechanism and the piggybacking of new segments on ongoing
operations were discontinued to allow for more commercially-oriented operation of the SEMs and competitive
bidding processes for new segments. The capital of the SEMs was gradually open to the public and in 2006 a major
proportion of SEMs remaining publicly-owned shares were sold to private French and foreign operators.
68
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
26.
Traffic risk is a key determinant of the attractiveness of a toll road concession. The traffic
risk is generally lower in a concession for an existing road, with a history of traffic. It is usually high
for a new toll road, greenfield project. There are many examples of such projects or even programs
which have collapsed and/or needed substantial restructuring when traffic has grown below
projections (first program in Mexico, M5 in Hungary, and so on).
27.
Projects requiring significant capital investment in the initial years of the concession may need
some public sector participation in assuming all or part of the traffic risk. It can be achieved in the
form of traffic or revenue guarantees whereby the government or a public entity would be obligated to
compensate the operator if and when actual traffic volumes are below certain pre-defined thresholds.
Conversely, in the event of higher than expected traffic growth, the contract can obligate the operator
to share surplus revenues with the government. The Chile program is a good, successful example of
such revenue guarantees.
28.
Since such guarantees result in contingent liabilities for the government, which are difficult to
predict and to budget for, Chile developed and implemented an innovative form of minimum revenue
guarantee mechanism whereby the term of the concession is adjusted so as to reach the contractual
present value of toll revenues of the winning bid.
29.
Some governments have preferred to assume the traffic risk entirely considering that the
concessionaire has practically no influence over traffic and therefore is not better placed than the
public sector to assume traffic risk. Transferring traffic risk to a private operator cannot actually be
justified on economic efficiency grounds. In those cases, the concession contracts have been based on
some forms of direct payments to the private operator.
30.
Direct payments by the conceding government or public agency to the private operator are a
widely-used method to fund privately-operated roads, whether tolled or not. In the case of a toll road,
the payments can be designed as a supplement to toll revenues collected by the operator, needed to
make it financially viable. But the payments can also be designed to cover all the costs of the
concession, toll revenues being recovered by the public agency. In this latter case, the conceding
agency assumes the traffic risk entirely. These payments are generally called availability payments
since they are subject to the concessionaire making available to road users certain assets in well
defined conditions. But availability payments can also be linked to service level and performance
indicators.
31.
Norways PPP road program is a good example of such model. Tolls are collected by a public
company and revenues are transferred to the National Road Agency. The availability payments are
then made by the Agency to the operator subject to compliance with output-based specifications
related to both asset availability and levels of service.
32.
The United Kingdoms PPP road program is a good example of availability payments for no-toll
road concessions. After abandoning shadow tolls, the United Kingdom has moved to a system of direct
payments made from the public budget to the private operator, linked to asset availability and quality
specifications, and maintenance performance, independently of traffic volumes. On more recent
transactions such as the Darrington Dishforth A1 segment, service levels specifications have been
incorporated in the form of minimum traffic speeds.
33.
Shadow tolls are payments made by the conceding agency to the operator on the basis of
actual traffic volumes and agreed toll rates. As a result, the allocation of traffic risk is not efficient: the
risk of lower traffic is transferred to the private operator and the risk of higher traffic is assumed by
the government. First introduced in the United Kingdom, the justification for shadow tolls was based
on the public benefits derived from the use of the road. But one can argue that shadow tolls are not
Annexes
69
efficient since they do not charge users for the actual cost of road use as direct toll charges do for
example, and therefore the demand management function of an explicit toll is lost.
34.
Portugal and Spain have used both actual and shadow tolls to finance greenfield projects and
improvements of existing highways. But the governments payment obligations under these contracts
have increased so much that many concessions had or will have to be converted to user-paid tolls.
V.
SERVICE LEVELS
Introduction
1. Concessionaires obligations under road concession contracts in Brazil are specified through the
so-called PER (Programa de Exploracao da Rodovia) which includes:
A program of pre-defined works and services to be carried out in accordance with a given
timetable over the duration of the contract; and
Performance standards (Padroes de desempenho) which generally try to reflect the
services levels to be guaranteed to road users.
The specified programs of works and/or timetables have proved to be inadequate when
traffic differs substantially from original forecasts (as it generally happens), where
urbanization (and prefeitos) require unforeseen investments, or where more effective
technical solutions than those included in the PER are available; such problems have
resulted in numerous contract renegotiations which generally have benefited
concessionaires;
Performance standards are defined by project engineers, case by case, in the absence of a
coherent policy based on user preferences; and
Capacity-related service level obligations are specified through US-based parameters
which are neither applicable to Brazils conditions nor enforceable.
3. This note does not exhaust the issues related to service levels. It focuses on the major issues
which could be effectively addressed through appropriate government policy and related
regulations or norms by ANTT and/or DNIT. The note is structured into three major topics:
Road surface
Pavement structure
Road Capacity
Road Surface
4. Concessionaire or contractor obligations related to road surface are generally specified by
performance standards based on the following main parameters, which are to be measured in
accordance with DNIT norms:
Annexes
71
6. Another issue is that concessionaire obligations vis--vis these parameters have been defined by
project engineers in the course of preparing the PERs of the specific projects or programs, without
clear guidelines or consideration of road user preferences. As a result, some specifications are not
consistent across the network and some may not be realistic. For example, longitudinal roughness
requirements (IRI) may range from 2.5 to 3.5 mm/m among similar highways. An IRI of 2.5
mm/m is neither realistic, particularly when one considers contractors capacity for surface
finishing, nor justified, particularly on a dual-lane highway.
7. The Ministry of Transport, with technical support from ANTT and DNIT, could therefore formulate a
clear policy regarding the levels of service to be guaranteed to road users. Road surface related
levels of services could be differentiated on two-lane versus dualized highways and depending on
whether they are tolled on not. The definition of such service levels would be supported by the
results of road user opinion surveys which would assess user preferences and willingness to pay
for such services levels (see Policy Note on tolls). Such policy would provide the necessary
guidelines to ANTT and DNIT to guarantee adequate and consistent services levels across the
network through consistent concessionaire or contractor obligations and performance parameters.
Pavement Structure
8. Although road users are not directly concerned with pavement structures, the structural capacity
of pavements, being an important determinant of road surface condition, should be clearly
specified in concession contracts and effectively monitored.
9. Current concession contracts, through the PERs, specify actual minimum pavement structures. In
particular, concessionaires are obligated to carry out specific structural works, for example an
asphalt concrete layer of a minimum specified thickness at a specified future date. These
obligations are defined on the basis of the PER traffic forecasts and on the project engineer
preferences for certain technical solutions. There are several problems with such rigid
specifications of pavement structure works. First, actual traffic rarely follows original forecasts,
therefore opening the door for renegotiation of such obligations. Second, specifying technical
solutions does not allow for technological improvements overtime and can therefore be inefficient.
Third, experience has shown that concessionaires generally can demonstrate that they have a
better solution than the one prescribed in the PER, which again leads to some form of contract
renegotiations.
10. The PERs also specify maximum values for deflexions. Deflexions can be a good indicator of
localized structural problems, but they are very sensitive to temperature and humidity, and
therefore cannot be an effective indicator of the structural capacity of an entire road segment.
11. The Structural Number (SN), which is the main parameter used for pavement dimensioning under
the widely-accepted AASHTO methodology, is a good indicator of the structural capacity of a given
pavement. It is defined as:
SN= ai Di
where: ai is the structural coefficient of the material used for pavement layer i; and
Di is layer i thickness in inches.
12. The structural number can also be adjusted into the SNC to take into account the support
contribution of sub-soil through its CBR.
13. The structural coefficients for the various types of materials used in pavements are known. They
can be adjusted for specific conditions, if needed, through their elasticity modules and the
relationships established in AASHTOs pavement dimensioning manual of 1993. Finally, the
structural coefficient of a used asphalt concrete layer can also be derived from its IGG through
empirical relationships developed in Brazil.
14. The Ministry of Transport, with technical support from ANTT and DNIT, could therefore review the
feasibility of using the Structural Number to specify the structural capacity of pavements under
PPP contracts. In addition to clearly specifying minimum structural numbers for homogeneous
sections, depending on traffic, contract specifications should also clearly define the methodology,
72
PRIVATE PARTICIPATION IN THE ROAD SECTOR IN BRAZIL: RECENT EVOLUTION AND NEXT STEPS
including structural coefficients of key materials and relevant relationships, to make such
obligations enforceable.
15. If such parametric specifications are possible, the works programs and related timetables defined
under the project feasibility studies, rather than the obligations under the PER, would then be
considered only indicative and feasible work programs, to be used as a reference by bidders in
establishing their bids. But bidders would be allowed to propose alternative solutions provided that
they meet the specified structural numbers. The timetable for the works could be adjusted in line
with actual traffic, on the basis of the relationship between the structural number and volume of
traffic.
Road Capacity
16. Concessionaire obligations regarding road capacity are specified either through (1) pre-defined
capacity works to be carried out in accordance with a timetable, independent of actual traffic, or
through (2) service level standards generally defined with reference to the service levels of the
Highway Capacity Manual (HCM), or through (3) both pre-defined works and timetables, and
service levels standards.
17. These obligations have raised a number of issues. In particular, pre-defined capacity works had to
be revised and/or postponed where traffic did not follow projections, which has generally been the
case. These changes have led to numerous renegotiations of contracts, probably benefiting
concessionaires. The service level standards could not be effectively monitored and enforced since
they are based upon parameters which are not easily measurable. In addition, these parameters,
which were defined in the United States, where road user behaviour and highway characteristics
are quite different, are not applicable to Brazil conditions without some substantial adjustments.
18. Under the HCM methodology, the service level on a two-lane highway is determined through a
combination of two parameters: the Average Travel Speed (ATS) of vehicles, and the Percent Time
Spent Following (PTSF) another vehicle.
Table 5.1. Service Level Criteria
Level of Service Criteria for a Two-Lane Highway
LOS
A
B
C
D
E
<
>
>
>
>
PTSF
35
35-50
50-65
65-80
80
>
>
>
>
<
ATS
90
80-90
70-80
60-70
60
19. The two parameters are functions of traffic volumes and of some traffic and road characteristics, in
particular regarding passing restrictions. The paved shoulders of highways and the driving custom
of facilitating passing by faster vehicles in Brazil invalidate these US-based relationships under
Brazil conditions. This is particularly important for the PTSF parameter, which, in most cases, is
the determining factor of the service level in the HCM methodology.
20. The Ministry of Transport, with support from ANTT and DNIT, could develop a policy on the service
levels to be guaranteed to road users. The service levels should first be defined on the basis of
clear and measurable indicators, which could be average travel speeds on two-lane highways and
average vehicle densities per lane on multi-lane highways. The service levels could also be
established with the help of appropriate surveys of road user opinions and willingness to pay for
various services levels (see Policy Note on Tolls). In particular, better service levels would be
guaranteed on toll highways.
21. Service levels should also be monitored together with traffic volumes and composition on
highways of various characteristics in order to develop reliable relationships between traffic and
service levels, applicable to Brazils road and driving conditions. After such reliable relationships
are developed, concessionaire obligations regarding capacity works could be more easily specified
through traffic volumes.