A - INTRODUCTION
This sampling plan shall be used within the application of the inspection procedure PG 16. It applies
to the two both PSI and VoC activities of Bureau Veritas GSIT.
It replaces the 2 previous sampling plans (PSI Sampling plan and VOC Sampling plan) from which
concepts have been merged.
The sampling method has been defined taking into account the standards listed in Reference at the
end of the guideline, the extensive experience of Bureau Veritas in PSI and VoC programs and the
recommendations of the World Trade Organization.
In absence of a defined sampling plan determined by the country of destination, this document shall
be applied to determine the minimum number of items that shall be drawn during inspection from the
shipment for visual inspection and generation of Inspection Report and photographing (as required).
The figures indicated in this procedure represent the number of elements to be checked. The inspector
has to select the samples on his own without interference from the exporters (or importers)
representative.
A reinforced sampling plan has been defined and shall be applied when there is not enough details
about the products to be inspected or when there is an increased risk of non-conformity
Otherwise, the normal sampling plan applies.
In this document, a line item is understood to be a quantifiable group -generally by number and unit
nature (Piece, Set, Kg,..) of identical products classified under an unique reference.
It is a type of product identified by a description in the commercial documentation (packing list, PFI).
It usually corresponds to a line of the PFI.
PICs and Issuing offices are encouraged to educate exporters to provide clear and
detailed invoices / Packing lists in order to get the application of the normal sampling
plan.
It is essential that any inspector fully understands this sampling plan and applies it as
specified.
Do not hesitate to request additional guidance from your PIC.
1/9
2014
2/9
2014
C1 LEVEL OF SAMPLING
Normal or reinforced sampling plan ?
The normal sampling plan applies when:
The verification of quantity can be done by counting only (no measurement required)
and
The PFI / Packing list gives a clear and accurate description and quantity of each line item
When one of these conditions is not met or when the issuing office or PIC requests it, the reinforced
sampling plan applies.
Decision chart:
Notes:
The additional sampling plan required in case of detection of a Non-Conformity is always reinforced
(See flowchart of part B and part C4).
1 Verification of quantity by counting?
The answer is yes when the quantity defined in the invoice (or packing list) taken as reference for
the inspection states a quantity that can be verified by Counting only.
Otherwise, the answer is NO (quantity requires measurement).
Examples: the answer is NO when quantities are in: kg, tons, liters, m3, meters, km
2 Clear invoice / packing list?
To be considered as clear, the invoice/Packing list provided prior carrying out the inspection shall
lists the line items and describe them in an appropriate manner:
Appropriate descriptions have to be clear and accurate and normally include: Designation (could
refer to a catalogue easily accessible), Brand name, model number, ratings (as applicable for the
kind of products).
Quantity shall also be clearly defined.
No ambiguous description.
Examples of well detailed line items (considered as clear):
67 Televisions, XKF Brand, Model 3249FR black
[it is understood that the quantity here is units]
3 Re-inspection
In case of a re-inspection, the Issuing office or PIC shall decide the level of the re-inspection based
on the reason of the re-inspection. Without any instruction, the procedure applies as is.
3/9
2014
to
1
10
11
21
22
39
40
69
70
99
100
199
200
299
300 and above
Line items to be checked can also be determined with graphs on next page
4/9
2014
5/9
2014
TABLE C3.1
Quantity* (pieces/box/bag)
of the line item
To Number
From
of pieces
1
1
Blank
packaging
1
Printed
packaging
1
Blank
packaging
Printed
packaging
25
26
90
91
150
151
3200
15
3201
35000
21
35001
and more
27
12
When a non-conformity is detected on part of the samples, then apply a reinforced sampling plan
again on the same line item to try to detect non-conformity on other samples of the same line item
(see C4).
Blank packaging: the product is not visible through its packaging and there is no marking on the
packaging which identifies the product (name, model, trademark, manufacturer ...). Examples:
Printed packaging: The product is in transparent packaging (ex: blister) or the markings on the
packaging identify the product inside: name, brandname, model, manufacturer Examples:
6/9
2014
Outer cartons :
If the products are packed and not
visible in a secondary packaging
(parcel, carton) containing the
identical number of the same
products (more than one unit /
parcel): the inspector decides the number of units to be taken per parcel respecting the
following rules:
Example B:
1 line item to be checked. Quantity = 200 units. Blank packaging, reinforced sampling plan
Samples to be checked (C3.1) = 15
Carton packaging containing 3 Pieces.
Sampling method:
Number of cartons to be checked shall be more than 4 as 4 cartons only include 4x3=12
products.
Number of cartons to be checked: 5
Select the 15 samples from 5 cartons (all products in this case)
PG16 Sampling plan VoC
Edition 1.0
7/9
2014
C4 ADDITIONAL SAMPLING
After being reported in the inspection report, the first non-conformity detected shall result in the
application of the additional sampling plan.
The additional sampling plan applies even if the non-conformity has been corrected on the sample
checked.
The reinforced level applies to the additional sampling plan.
The additional sampling plan applies in addition to the first sampling plan.
Once the first Non Conformity is detected, 2 actions shall be taken:
1 Additional sampling applied on the line item itself and
2 Additional sampling plan applied on the shipment
as detailed below and in the flowchart on next page.
Line items and samples selected under the additional sampling plan shall be different from the ones
selected during the first sampling plan.
1 Additional sampling applied on the line item itself
The reinforced sampling plan is applied again on the line item (table C3.1).
This is to identify whether the Non Conformity is for all the units of the line item or not. There is no
need to apply the additional sampling on the same line item when it is obvious that the non-conformity
applies to the entire quantity of the line item ).
2 Additional sampling plan on the shipment
When a non-conformity (or several non-conformities) is detected on one line item, it shall result in the
application of an additional sampling plan on the consignment.
The number of additional line items to be checked is determined with the application of the reinforced
sampling of table C2.1 and table C3.1.
The additional sampling plan is applied only once (two sampling plans maximum). See flowchart of
part B.
The entire consignment shall be reconsidered by the exporter when non conformities are detected
during the application of the additional sampling plan.
8/9
2014
D - References
ISO 2859-x: Sampling procedures for inspection by attributes.
ISO/IEC 17020: Conformity assessment General criteria for the operation of various type of bodies performing inspection
Technical Barriers to Trade Agreement of the World Trade Organization
ISO 3951: Acceptance sampling plans to the inspection by variables in statistical process control (SPC). Part 1: Sampling
procedures for inspection by variables. Specification for single sampling plans indexed by acceptance quality limit (AQL) for lotby-lot inspection for a single quality characteristic and a single AQL
ISO 8422: Sequential sampling for inspection by attributes.
ISO 8423: Sequential sampling plans for inspection by variables for percent nonconforming (known standard deviation)
ISO 14560: Acceptance sampling procedures by attributes. Specified quality levels in nonconforming items per million.
ISO 8423: Sequential sampling plans for inspection by variables for percent nonconforming (known standard deviation).
ISO 2854: Statistical interpretation of data. Techniques of estimation and tests relating to means and variances.
ISO 10725: Acceptance sampling plans and procedures for the inspection of bulk materials.
ISO 21247: Combined accept-zero sampling systems and process control procedures for product acceptance.
ISO/TR 8550: Guidance on the selection and usage of acceptance sampling systems for inspection of discrete items lots
(acceptance sampling; guide to sampling by attributes and sampling by variables)
ISO 3494: Statistical interpretation of data. Power of tests relating to means and variances.
ISO 5725: Accuracy of Measurement Methods and Results (Package provides the general principles necessary to accurately
assess measurement methods, results, applications and practical.
ISO 7002: Agricultural food products. Layout for a standard method of sampling from a lot.
ISO 11648: Statistical aspects of sampling from bulk materials. General principles and sampling of particulate materials.
9/9