GENERAL
1.1
SUMMARY
1.2
DEFINITIONS
1.2.1
Submittal Descriptions (SD)
1.2.2
Approving Authority
1.2.3
Work
1.3
SUBMITTALS
1.4
SUBMITTAL CLASSIFICATION
1.4.1
Designer of Record Approved (DA)
1.4.2
Government Approved [G]
1.4.3
Government Conformance Review of Design (CR)
1.4.4
Designer of Record Approved/Government Conformance Review
(DA/CR)
1.4.4.1
Deviations to the Accepted Design
1.4.4.2
Substitutions
1.4.5
Designer of Record Approved/Government Approved (DA/GA)
1.4.6
Information Only
1.5
FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL
1.5.1
Submittals Required from the Contractor
1.5.1.1
O&M Data
1.5.1.2
Submittals Reserved for NAVFAC Atlantic Approval
1.5.1.3
Overseas Shop Drawing Submittals
1.6
PREPARATION
1.6.1
Transmittal Form
1.6.2
Identifying Submittals
1.6.3
Format for SD-02 Shop Drawings
1.6.4
Format of SD-03 Product Data and SD-08 Manufacturer's
Instructions
1.6.5
Format of SD-04 Samples
1.6.6
Format of SD-05 Design Data and SD-07 Certificates
1.6.7
Format of SD-06 Test Reports and SD-09 Manufacturer's Field
Reports
1.6.8
Format of SD-10 Operation and Maintenance Data (O&M)
1.6.9
Format of SD-01 Preconstruction Submittals and SD-11 Closeout
Submittals
1.7
QUANTITY OF SUBMITTALS
SECTION 01 33 00
Page 1
1.7.1
Number of Copies of SD-02 Shop Drawings
1.7.2
Number of Copies of SD-03 Product Data and SD-08
Manufacturer's Instructions
1.7.3
Number of Samples SD-04 Samples
1.7.4
Number of Copies SD-05 Design Data and SD-07 Certificates
1.7.5
Number of Copies SD-06 Test Reports and SD-09 Manufacturer's
Field Reports
1.7.6
Number of Copies of SD-10 Operation and Maintenance Data
1.7.7
Number of Copies of SD-01 Preconstruction Submittals and SD-11
Closeout Submittals
1.8
INFORMATION ONLY SUBMITTALS
1.9
VARIATIONS
1.9.1
Considering Variations
1.9.2
Proposing Variations
1.9.3
Warranting That Variations Are Compatible
1.9.4
Review Schedule Is Modified
1.10
SUBMITTAL REGISTER AND DATABASE
1.10.1
Use of Submittal Register
1.10.2
Contractor Use of Submittal Register
1.10.3
Approving Authority Use of Submittal Register
1.10.4
Action Codes
1.10.4.1
Government Review Action Codes
1.10.4.2
Contractor Action Codes
1.10.5
Copies Delivered to the Government
1.11
SCHEDULING
1.11.1
Reviewing, Certifying, Approving Authority
1.11.2
Constraints
1.11.3
QC Organization Responsibilities
1.11.4
Government Reviewed Design
1.12
GOVERNMENT APPROVING AUTHORITY
1.12.1
Review Notations
1.13
DISAPPROVED[ OR REJECTED] SUBMITTALS
1.14
APPROVED[/ACCEPTED] SUBMITTALS
1.15
APPROVED SAMPLES
1.16
WITHHOLDING OF PAYMENT
1.17
PROGRESS SCHEDULE
1.17.1
Bar Chart
1.17.2
Project Network Analysis
1.18
STATUS REPORT ON MATERIALS ORDERS
1.19
STAMPS
PART 2
PRODUCTS
PART 3
EXECUTION
SECTION 01 33 00
Page 2
**************************************************************************
USACE / NAVFAC / AFCEC / NASA
UFGS-01 33 00 (May 2011)
Change 3 - 11/13
----------------------------Preparing Activity: NASA
Superseding
UFGS-01 33 00 (February 2011)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
**************************************************************************
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11
**************************************************************************
NOTE: This guide specification covers the
requirements for general procedures regarding
submittals, data normally submitted for review to
establish conformance with the design concept and
contract documents, called for in other sections of
the specifications.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable items(s) or insert
appropriate information.
Remove information and requirements not required in
respective project, whether or not brackets are
present.
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
This guide specification includes tailoring options
for Army, Navy, NASA and for NAVFAC component
requirements. Army tailoring options also include
DESIGN-BUILD (DB) and DESIGN-BID-BUILD, and at least
one of these options must be deselected. Do not use
this section for Navy DB projects. Use the DB specs
in the NAVFAC DB Master posted within the Whole
Building Design Guide. Selection or deselection of
a tailoring option will include or exclude that
option in the section, but editing the resulting
section to fit the project is still required.
**************************************************************************
PART 1
1.1
GENERAL
SUMMARY
Page 3
Approving Authority
Work
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A G following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a G. Only
delete an existing G if the submittal item is not
complex and can be reviewed through the Contractors
QC system. Only add a G if the submittal is
sufficiently important or complex in context of the
project.
For submittals requiring Government approval on Army
SECTION 01 33 00
Page 7
Information Only
**************************************************************************
NOTE: Use this article and the following paragraphs
only in LANTNAFVFACENGCOM Division projects. In the
following paragraphs select only the applicable
information in brackets. On A/E projects, the A/E
should insert the firm name in the spaces shown,
unless it is known that the A/E will not be checking
samples and other submittals, including shop
drawings and product data.
**************************************************************************
1.5.1
O&M Data
[The Architect-Engineer for this project] [NAVFAC Atlantic] will review and
SECTION 01 33 00
Page 10
Page 6
Approving Authority
Work
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A G following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a G. Only
delete an existing G if the submittal item is not
complex and can be reviewed through the Contractors
QC system. Only add a G if the submittal is
sufficiently important or complex in context of the
project.
For submittals requiring Government approval on Army
SECTION 01 33 00
Page 7
SUBMITTAL CLASSIFICATION
**************************************************************************
NOTE: Section 01 33 16 DESIGN AFTER AWARD is not a
UFGS. The purpose of the section is to specify
design process and submittal requirements in a
Design-Build contract. Section 01 33 16 has been
developed for the MILCON Business Process (MBP)
Model RFP and is available from the RFP Wizard
Portal at
http://mrsi.usace.army.mil/rfp/SitePages/Home.aspx.
**************************************************************************
Designer of Record (DOR) approval is required for extensions of design,
critical materials, any deviations from the solicitation, the accepted
proposal, or the completed design, equipment whose compatibility with the
entire system must be checked, and other items as designated by the
Contracting Officer. Within the terms of the Contract Clause entitled,
"Specifications and Drawings for Construction," they are considered to be
"shop drawings." Contractor to provide the Government with the number of
copies designated hereinafter of all DOR approved submittals. The
Government may review any or all Designer of Record approved submittals for
conformance to the Solicitation, Accepted Proposal and the completed
design. The Government will review all submittals designated as deviating
from the Solicitation or Accepted Proposal, as described below. Design
submittals to be in accordance with Section 01 33 16 DESIGN AFTER AWARD.
Generally, design submittals should be identified as SD-05 Design Data
submittals.
SECTION 01 33 00
Page 8
**************************************************************************
**************************************************************************
NOTE: Use bracketed items for Army projects only.
**************************************************************************
**************************************************************************
NOTE: Use the first bracketed sentence of the
paragraph if the Contractor is required by the
contract to use the Army Quality Control System
(QCS). Use the second bracketed sentence of the
paragraph if QCS not required. It may not be
necessary or beneficial to use the QCS in small,
simple, short duration contracts/delivery orders for
construction, or for other contracts where its use
would not be in the best interest of the Government.
**************************************************************************
Prepare and maintain submittal register, as the work progresses. Use
electronic submittal register program furnished by the Government or any
other format. Do not change data which is output in columns (c), (d), (e),
and (f) as delivered by Government; retain data which is output in columns
(a), (g), (h), and (i) as approved. A submittal register showing items of
equipment and materials for which submittals are required by the
specifications is provided as an attachment. This list may not be all
inclusive and additional submittals may be required. Maintain a submittal
register for the project in accordance with Section 01 45 00.10 10 QUALITY
CONTROL SYSTEM (QCS).[ The Government will provide the initial submittal
register ][in electronic format][ with the following fields completed, to
the extent that will be required by the Government during subsequent usage.]
Column (c):
required.
Column (d): Lists each submittal description (SD No. and type,
e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification
section where a material or product is specified. This listing is
only to facilitate locating submitted requirements. Do not
consider entries in column (e) as limiting project requirements.
Column (f):
**************************************************************************
NOTE: Use the following paragraph for NASA projects
only.
**************************************************************************
The database and submittal management program will be furnished to
Contractor on a Writable Compact Disk (CD-R), for operation on Windows
based personal computer.
[ Thereafter, the Contractor is to track all submittals by maintaining a
complete list, including completion of all data columns, including dates on
which submittals are received and returned by the Government.
]
**************************************************************************
NOTE: Use the following paragraph for Army
SECTION 01 33 00
Page 19
Information Only
**************************************************************************
NOTE: Use this article and the following paragraphs
only in LANTNAFVFACENGCOM Division projects. In the
following paragraphs select only the applicable
information in brackets. On A/E projects, the A/E
should insert the firm name in the spaces shown,
unless it is known that the A/E will not be checking
samples and other submittals, including shop
drawings and product data.
**************************************************************************
1.5.1
O&M Data
[The Architect-Engineer for this project] [NAVFAC Atlantic] will review and
SECTION 01 33 00
Page 10
approve for the Contracting Officer O&M Data to verify the submittals
comply with the contract requirements; submit data specified for a given
item within 30 calendar days after the item is delivered to the contract
site.
In the event the Contractor fails to deliver O&M Data within the time
limits specified, the Contracting Officer may withhold from progress
payments 50 percent of the price of the item with which such O&M Data
are applicable.
[1.5.1.2
**************************************************************************
NOTE: Include this optional paragraph for all
projects designed by Architect-Engineer consulting
firms. Fill in the appropriate specification
section numbers and titles for the respective
products.
**************************************************************************
As an exception to the standard submittal procedure specified above, submit
the following to the Commander, NAVFAC Atlantic, Code CI4A1, 6506 Hampton
Blvd, Norfolk, VA 23508-1278:
**************************************************************************
NOTE: Add Section Reference tags where appropriate
below when blanks are filled.
**************************************************************************
[ a.
][b.
][c.
][d.
][e.
][f.
][g.
][h.
][i.
][j.
][k.
][l.
SECTION 01 33 00
Page 11
SD-06 field
All
All
All
All submittals
Transformer
Transformer submittals
Transformer submittals
PROGRESS SCHEDULE
1.17.1
[ a.
Bar Chart
Submit the progress chart, for approval by the Contracting Officer, at
the Preconstruction Conference in one reproducible and 4 copies.
b.
Prepare the progress chart in the form of a bar chart utilizing form
"Construction Progress Chart" or comparable format acceptable to the
Contracting Officer.
c.
d.
(2)
(3)
(4)
A materials bar and a separate labor bar for each line item.
Both bars will show the scheduled percentage complete for any
given date within the contract performance period. Labor bar will
also show the number of men (man-load) expected to be working on
any given date within the contract performance period.
(5)
(6)
]1.17.2
Page 28
a.
b.
c.
d.
e.
f.
g.
h.
1.6.3
Shop drawings are not to be less than 210 by 297 mm 8 1/2 by 11 inches nor
more than 1189 by 841 mm 30 by 42 inches, except for full size patterns or
templates. Prepare drawings to accurate size, with scale indicated, unless
other form is required. Drawings are to be suitable for reproduction and
be of a quality to produce clear, distinct lines and letters with dark
lines on a white background.
Present 210 by 297 mm 8 1/2 by 11 inches sized shop drawings as part of the
bound volume for submittals required by section. Present larger drawings
in sets.
Include on each drawing the drawing title, number, date, and revision
numbers and dates, in addition to information required in paragraph
entitled, "Identifying Submittals," of this section.
Number drawings in a logical sequence. [Contractors may use their own
number system.] Each drawing is to bear the number of the submittal in a
uniform location adjacent to the title block. Place the Government
contract number in the margin, immediately below the title block, for each
drawing.
Reserve a blank space, no smaller than [_____] millimeter inches on the
right hand side of each sheet for the Government disposition stamp.
Dimension drawings, except diagrams and schematic drawings; prepare
drawings demonstrating interface with other trades to scale. Use the same
unit of measure for shop drawings as indicated on the contract drawings.
Identify materials and products for work shown.
Include the nameplate data, size and capacity on drawings. Also include
applicable federal, military, industry and technical society publication
references.
SECTION 01 33 00
Page 13
1.6.4
Full size.
b.
c.
Page 14
Built up to
e.
f.
g.
Sample Panel:
h.
Sample Installation:
750 ml Pint.
Examples of non-solid
Page 15
QUANTITY OF SUBMITTALS
**************************************************************************
NOTE: The quantities suggested below are consistent
with the quantities to be retained by the
Government, in paragraph entitled, "QC Organization
Responsibilities," of this section; maintain the
coordination.
**************************************************************************
1.7.1
**************************************************************************
NOTE: For NAVFAC, require one sample in paragraph
"a" and delete the second sentence of paragraph "a".
**************************************************************************
a.
b.
c.
d.
1.7.4
SECTION 01 33 00
Page 16
1.7.5
Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field
Reports
Submit in compliance with quantity and quality requirements specified for
shop drawings other than field test results that will be submitted with QC
reports.
1.7.6
**************************************************************************
NOTE: NAVFAC requires three copies of O&M Data
unless OMSI manual is specified. Coordinate with
OMSI requirements.
**************************************************************************
Submit [Five][three][_____] copies of O&M Data to the Contracting Officer
for review and approval.
1.7.7
Number of Copies of SD-01 Preconstruction Submittals and SD-11
Closeout Submittals
Unless otherwise specified, submit [two][three] sets of administrative
submittals.
1.8
**************************************************************************
NOTE: Use the following paragraph for Army projects.
**************************************************************************
Normally submittals for information only will not be returned. Approval of
the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any
item found not to comply with the contract. This does not relieve the
Contractor from the obligation to furnish material conforming to the plans
and specifications; will not prevent the Contracting Officer from requiring
removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples
for testing by the Government laboratory or for check testing by the
Government in those instances where the technical specifications so
prescribe. For design-build construction the Government will retain
[_____] copies of information only submittals.
1.9
VARIATIONS
Considering Variations
Page 17
Proposing Variations
**************************************************************************
NOTE: Allow a longer additional review period if
the construction phase will have geographically
scattered reviewers.
**************************************************************************
In addition to normal submittal review period, a period of [10] [_____]
working days will be allowed for consideration by the Government of
submittals with variations.
**************************************************************************
NOTE: Use the term "Database" in the following
paragraphs on NASA projects only.
**************************************************************************
1.10
**************************************************************************
NOTE: Create the submittal register from the
project specification files, at the conclusion of
the design. In SPECSINTACT, choose "Export
Submittal Register" from "Process" pull-down menu.
Local procedures should be responsive to the
requirement that the submittal register, required
with the QC plan, is usually due from the Contractor
within 20 days after the Notice of Award.
SECTION 01 33 00
Page 18
**************************************************************************
**************************************************************************
NOTE: Use bracketed items for Army projects only.
**************************************************************************
**************************************************************************
NOTE: Use the first bracketed sentence of the
paragraph if the Contractor is required by the
contract to use the Army Quality Control System
(QCS). Use the second bracketed sentence of the
paragraph if QCS not required. It may not be
necessary or beneficial to use the QCS in small,
simple, short duration contracts/delivery orders for
construction, or for other contracts where its use
would not be in the best interest of the Government.
**************************************************************************
Prepare and maintain submittal register, as the work progresses. Use
electronic submittal register program furnished by the Government or any
other format. Do not change data which is output in columns (c), (d), (e),
and (f) as delivered by Government; retain data which is output in columns
(a), (g), (h), and (i) as approved. A submittal register showing items of
equipment and materials for which submittals are required by the
specifications is provided as an attachment. This list may not be all
inclusive and additional submittals may be required. Maintain a submittal
register for the project in accordance with Section 01 45 00.10 10 QUALITY
CONTROL SYSTEM (QCS).[ The Government will provide the initial submittal
register ][in electronic format][ with the following fields completed, to
the extent that will be required by the Government during subsequent usage.]
Column (c):
required.
Column (d): Lists each submittal description (SD No. and type,
e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification
section where a material or product is specified. This listing is
only to facilitate locating submitted requirements. Do not
consider entries in column (e) as limiting project requirements.
Column (f):
**************************************************************************
NOTE: Use the following paragraph for NASA projects
only.
**************************************************************************
The database and submittal management program will be furnished to
Contractor on a Writable Compact Disk (CD-R), for operation on Windows
based personal computer.
[ Thereafter, the Contractor is to track all submittals by maintaining a
complete list, including completion of all data columns, including dates on
which submittals are received and returned by the Government.
]
**************************************************************************
NOTE: Use the following paragraph for Army
SECTION 01 33 00
Page 19
**************************************************************************
NOTE: Include the bracketed text, invoking the use
of the electronic database for submittals, in most
projects. The alternative is a manually processed
submittal register initially created from the
Submittal Register Program, which may be appropriate
for small projects.
**************************************************************************
Submit submittal register as an electronic database, using submittals
management program furnished to Contractor. Submit with QC plan and
project schedule. Verify that all submittals required for project are
listed and add missing submittals. Coordinate and complete the following
fields on the register database submitted with the QC plan and the project
schedule:
[
][
][
][
]1.10.2
Page 20
Action Codes
Entries for columns (j) and (o), are to be used are as follows (others may
be prescribed by Transmittal Form):
1.10.4.1
1.10.4.2
1.10.5
**************************************************************************
NOTE: For NASA projects only. Include the use of
the electronic database for submittals, in most
projects. The alternative is a manually processed
submittal register initially created from the
SECTION 01 33 00
Page 21
SCHEDULING
b.
c.
d.
e.
**************************************************************************
NOTE: At bracket, use 30 working days for projects
estimated to require 180 or more calendar days to
construct. For projects requiring less than 180
calendar days to complete, use at least 20 working
days.
**************************************************************************
f.
g.
Page 22
submittal.
**************************************************************************
NOTE: Delete this part if submittal schedule is
specified elsewhere or is not required due to size
or nature of the project.
**************************************************************************
[Within [30][15] calendar days of notice to proceed][At the Preconstruction
conference], provide, for approval by the Contracting Officer, the
following schedule of submittals:
a.
b.
1.11.1
**************************************************************************
NOTE: Use this subpart for NAVFAC projects only.
**************************************************************************
The QC organization is responsible for reviewing and certifying that
submittals are in compliance with contract requirements. Approving
authority on submittals is QC Manager unless otherwise specified for
specific submittal. At each "Submittal" paragraph in individual
specification sections, a notation "G," following a submittal item,
indicates Contracting Officer is approving authority for that submittal
item.
1.11.2
Constraints
**************************************************************************
NOTE: Use this subpart for NAVFAC projects only.
**************************************************************************
Conform to provisions of this section, unless explicitly stated otherwise
for submittals listed or specified in this contract.
Submit complete submittals for each definable feature of work. Submit at
the same time components of definable feature interrelated as a system.
When acceptability of a submittal is dependent on conditions, items, or
materials included in separate subsequent submittals, submittal will be
returned without review.
Approval of a separate material, product, or component does not imply
approval of assembly in which item functions.
SECTION 01 33 00
Page 23
1.11.3
QC Organization Responsibilities
**************************************************************************
NOTE: Use this subpart for NAVFAC projects only.
**************************************************************************
a.
b.
Review each submittal; and check and coordinate each submittal with
requirements of work and contract documents.
c.
d.
(2)
e.
f.
"I hereby certify that the (equipment) (material) (article) shown and
marked in this submittal is that proposed to be incorporated with
contract Number [_____], is in compliance with the contract drawings
and specification, can be installed in the allocated spaces, and is
submitted for Government approval.
Certified by Submittal Reviewer _____________________, Date _______
(Signature when applicable)
Certified by QC Manager _____________________________, Date ______"
(Signature)
(2)
"I hereby certify that the (material) (equipment) (article) shown and
marked in this submittal and proposed to be incorporated with contract
Number [_____], is in compliance with the contract drawings and
specification, can be installed in the allocated spaces, and is
SECTION 01 33 00
Page 24
h.
i.
1.11.4
**************************************************************************
NOTE: Use this subpart for Army Design-Build
projects only.
Section 01 33 16 DESIGN AFTER AWARD is not a UFGS.
It is part of the MBP Model RFP and is available
from the RFP Wizard Portal at
http://mrsi.usace.army.mil/rfp/SitePages/Home.aspx.
**************************************************************************
The Government will review design submittals for conformance with the
technical requirements of the solicitation. Section 01 33 16 DESIGN AFTER
AWARD covers the design submittal and review process in detail. Government
review is required for deviation from the completed design. Review will be
only for conformance with the contract requirements. Included are only
those construction submittals for which the Designer of Record design
documents do not include enough detail to ascertain contract compliance.
The Government may, but is not required, to review extensions of design
such as structural steel or reinforcement shop drawings.
1.12
b.
c.
Page 25
Review Notations
b.
c.
d.
1.13
APPROVED[/ACCEPTED] SUBMITTALS
**************************************************************************
NOTE: For Navy or NASA projects choose construction
text. On Army projects choose either construction
or design-build text.
**************************************************************************
The Contracting Officer's approval or acceptance of submittals is not to be
construed as a complete check, and indicates only that the general method
of construction, materials, detailing and other information are
SECTION 01 33 00
Page 26
APPROVED SAMPLES
incorporated in the
which may be damaged
expense, upon
also be returned to
WITHHOLDING OF PAYMENT
**************************************************************************
NOTE: Choose either construction or design-build
construction text.
**************************************************************************
Payment for materials incorporated in the work will not be made if required
approvals have not been obtained. No payment for materials incorporated in
the work will be made if all required Designer of Record or required
Government approvals have not been obtained. No payment will be made for
any materials incorporated into the work for any conformance review
submittals or information only submittals found to contain errors or
SECTION 01 33 00
Page 27
PROGRESS SCHEDULE
1.17.1
[ a.
Bar Chart
Submit the progress chart, for approval by the Contracting Officer, at
the Preconstruction Conference in one reproducible and 4 copies.
b.
Prepare the progress chart in the form of a bar chart utilizing form
"Construction Progress Chart" or comparable format acceptable to the
Contracting Officer.
c.
d.
(2)
(3)
(4)
A materials bar and a separate labor bar for each line item.
Both bars will show the scheduled percentage complete for any
given date within the contract performance period. Labor bar will
also show the number of men (man-load) expected to be working on
any given date within the contract performance period.
(5)
(6)
]1.17.2
Page 28
b.
c.
d.
1.18
Within [_____] calendar days after notice to proceed, submit, for approval
by the Contracting Officer, an initial material status report on all
materials orders. This report will be updated and re-submitted every
[_____] calendar days as the status on material orders changes.
Report to include list, in chronological order by need date, materials
orders necessary for completion of the contract. The following information
will be required for each material order listed:
a.
b.
Bar chart line item or CPM activity number affected by the order.
c.
d.
e.
When item d exceeds item c, the effect that delayed delivery date will
have on contract completion date.
f.
Page 29
STAMPS
**************************************************************************
NOTE: Use the following paragraph and stamps for
Army projects only.
**************************************************************************
Stamps used by the Contractor on the submittal data to certify that the
submittal meets contract requirements is to be similar to the following:
SECTION 01 33 00
Page 30
________________________________________________________________________
|
CONTRACTOR
|
|
|
|
(Firm Name)
|
|
|
|
|
|
|
| _____ Approved
|
|
|
|
|
| _____ Approved with corrections as noted on submittal data and/or
|
| attached sheets(s)
|
|
|
|
|
|
|
| SIGNATURE: __________________________________________________________ |
|
|
| TITLE: ______________________________________________________________ |
|
|
| DATE: _______________________________________________________________ |
|
|
|________________________________________________________________________|
For design-build construction, both the Contractor Quality Control System
Manager and the Designer of Record are to stamp and sign to certify that
the submittal meets contract requirements.
PART 2
PRODUCTS
Not Used
PART 3
EXECUTION
Not Used
-- End of Section --