Beruflich Dokumente
Kultur Dokumente
A. General....................................................................................................................23
C. Preparation of Bids................................................................................................23
Descriptions
A. General
ITB 1.1
ITB 1.2
C. Preparation of Bids
ITB 8.1
23
ITB 9.3(b)
i)
ii)
Representative.
Qualification requirements for bidders including members of joint
ventures, subcontractors, manufacturers or vendors:
i)
status
(true
copy
of
current
Memorandum
of
24
25
ix) The Bidder must demonstrate that he has access to, or has
available liquid assets, unencumbered real assets, lines of
credit, and other financial means sufficient to meet the supply
cash flow for a period of four (4) months estimated, net of the
Bidders commitment for other contracts.
In case of joint venture, sub-items vi, vii and viii above shall apply as
follows:
1
The lead partner shall meet not less than 50 percent of all
the qualifying criteria given in sub-items viii, ix and x;
The other partners shall meet not less than 25 percent of all the
qualifying criteria given in sub-items viii, ix and x.
The joint venture must satisfy collectively the criteria of subitems viii through x for which purpose the relevant figures for
each of the partners shall be added together to arrive at the
joint ventures total capacity
x) Litigation History
Bidders shall demonstrate that the Bidder has a history which is
free of litigation and arbitration or an absence of awards against
the Bidder in any court of law or arbitration.
xi) The Bidder shall submit the following additional documents in
its bid: Brochures and catalogues.
26
ITB 11.6
ITB 12.1
component.
Source of exchange rate is Commercial Bank of Ethiopia.
Date of exchange rate: 28 days prior to the deadline of bid submission
date.
ITB 13.1
Bid security Amount no less than specified under for each lot or in a
freely convertible currency in one of the following forms:
(a)
ITB 14.1
The Bid validity period shall be six (6) months from the bid submission
deadline.
Original and two (2) copies. The copies must be clearly labeled, Copy
27
ITB 16.2
Attention: :
Project
1
GK-3 Lot 3
ITB 16.5
28
ITB 17.1
ITB 20.1
Bids will be evaluated for each Lot, and the Contract will comprise the Lot
awarded to the successful Bidder.
ITB 26.1
Not Applicable
F. Award of Contract
ITB 33
ITB 36
29