Beruflich Dokumente
Kultur Dokumente
INTRODUCTION........................................................................................................... 2
CHALLENGES........................................................................................................... 3
2.1. High and low solution....................................................................................... 3
2.2. Alternative routes............................................................................................. 4
2.3. Proposals for the viaduct..................................................................................5
2.4. The piers issue................................................................................................. 7
2.5. The deck issue.................................................................................................. 8
2.6. The curve of the viaduct................................................................................ 10
CONSTRUCTION.................................................................................................. 11
3.1. Construction of piers...................................................................................11
3.1.1. Foundations................................................................................................. 13
3.1.2. Base plate................................................................................................ 13
3.1.3. How to construct...................................................................................... 14
3.2.1. Construction of deck................................................................................15
3.2.2. Movement of the decks............................................................................17
3.2.3. Launch nose operation............................................................................. 19
3.2.4. Pylons....................................................................................................... 21
3.3. Funding....................................................................................................... 22
3.3.2. Conclusion and main attributes of success..............................................23
3.3.3 Continuity of the work.............................................................................. 24
MILLAU VIADUCT
INTRODUCTION
The erection of the viaduct over the river Tarn, at Millau in central France,
began in October, 2001 and is to be completed in January, 2005. This will
be a major step forward in the design of cable-stayed bridges, with a series
of six main spans 342 meters long suspended from seven pylons. The road
will pass 270 meters above the river, and two of the piers will be about 235
Metres tall; with the corresponding pylon 90 meters tall on top, they both
will be higher than the Eiffel Tower. Two designs have been developed, one
in prestressed concrete and one in steel. The Millau Viaduct is a seminal
civil engineering structure on the Motorway A75, linking Clermont-Ferrand
to Montpellier. It belongs to the same family as the Normandy Bridge: the
family of bridges with multiple cablestayed spans. Its civil engineering
structure was originally designed by the same author, the French engineer
Michel Virlogeux, before being improved and enhanced by the collaboration
with Norman Foster & Partners, the British architectural practice.
Fig
ure 1 MILLAU BRIDGE
CHALLENGES
2.1. High and low solution
Two sets of technical solutions to cross the Tarn Valley were examined
thoroughly by the CETE Mediterranean:
the low solution whereby the road sloped down to the valley;
The high solution which comprised a bridge 200m above the valley.
Initially, the low solution was considered as the sole solution but, in the final
instance, the high solution was preferred due to safety reasons, economic
considerations the solution was shorter and thus cheaper and
geotechnical constraints. In addition, the high solution had a limited impact
on the environment and urbanization, and subsumed sufficient access to
the city of Millau via the interchange of St German.
For the reasons mentioned, the high solution was welcomed by local
officials. Indeed, the Director of Roads, Jean Berthier, was convinced of the
relevance of this solution and approved it. This led to the Ministry Decision
of 29 October 1991, but additional studies were still required by the Minister
of the Equipment, Paul Quiles. During 1992, a project team within SETRA
led by Michel Virlogeux undertook the studies and investigated seven
bridge types. These proposed bridges were selected from amongst eight
sets of solutions, comprising technical variants of steel and concrete.
These preliminary studies confirmed the feasibility of a single bridge of
2.46km to cross the Tarn Valley. This pre-project was approved by another
Ministry Decision on 12 July 1993. Four projects were retained:
A project with a large span of 280m above the Tarn. This project had
a concrete deck at variable height level and constant access spans
150m long;
The same project as project 1, with a steel deck;
A project with cable-stayed spans of 320m, with a concrete deck and
access spans at a constant height level;
A project with a large cable-stayed span of 400m, with access spans
of 170m and a steel deck at a constant height level.
Figur
e 3 Different routes
The last option was selected on 28 June 1989 under a Ministry Decision
which required further technical studies for the route and consideration of
the most appropriate type of bridge.
To avoid the interference of air the wind ducts were provided in the decks
because due to the interference of air a bridge in the US was collapsed so
to prevent the damage they got the services of a wind engineer.
Fi
gure 9 wind ducts
The actual form of the deck selected after the two different proposals by the
engineers and the architects was that
CONSTRUCTION
3.1. Construction of piers
The Eiffage Group made a proposal for each of the two options, steel and
prestressed concrete. For the prestressed concrete option, Eiffage
Construction developed a solution with heavy precast segments, about
than 200 metric tons in weight. But the group, including a steel contractor
Eiffel Construction Mtallique could prepare a very efficient steel option.
Figure 12
Construction of piers
Figure
13 Construction of piers
3.1.1. Foundations
Each pier is founded on a plate or base, and four posts or piles.
The piles are each 5m diameter and extend down to a max depth of
14m.
On top is the base itself, which for P2 is 6m deep.
The Initial Launch pour for the pier is conventionally shuttered.
Figur
e 14 Foundation of pier
Figure 15 Base
plate of pier
sliding advance plate at this stage. The advance cylinder is in the extended
position and the raise cylinders are in the retracted position. Per wedge
there is one raise cylinder and two advance cylinders. One advance
cylinder is mounted on either side of the wedge.
2. Raising the raise cylinder is extended causing the blue wedge to
force the two adjoining plates apart. The result of this is the top advance
plate is raised a small distance which in turn raises the deck clear of the
orange cradle. Either side of the wedge is a low friction treatment of PTFE
on one surface and polished stainless steel sheet on the other. The raising
capacity of each translator is 250t. The lifting forces are transferred into the
deck directly through the vertical web of the central box core of the deck.
3. Advancing while the raise cylinder is still extended, the advance
cylinders are slowly retracted, advancing the deck by 600mm. The advance
cylinders have a combined force capacity of 120t.
4. Lowering the advance cylinders remain fully retracted and the raising
cylinder is slowly retracted. As the blue wedge is retracted, the top advance
plate and deck are lowered. As soon as the deck rests on the orange
cradle, the weight is removed from the top advance plate as there is now a
small clearance between it and the underside of the deck.
5. Return to start the advance cylinders are extended, returning the
unloaded top advance plate to the initial starting position. The hydraulically
powered translators have an overall launch rate of 10 m/h or 16 cycles per
hour. During the launch, the balance jacks of the two translators on the
same side of the deck are hydraulically linked to ensure equal pressure is
maintained by all jacks on that side of the deck. This is to allow for
variations in longitudinal rotation of the deck due to deck deflection. This
load sharing feature ensures that the supporting load was evenly
distributed over each pair of longitudinally aligned translators. The
translator jacks on either side of the decks longitudinal centerline were not
normally hydraulically linked as this would create a virtual pin joint and
allow the deck to roll about its longitudinal axis. As a safety measure, the
balance jacks could be mechanically locked off by a large nut mounted to
each jacks piston. The outer advance cylinders on each translator have a
Positional transducer that indicates the amount of travel. The end of the
deck sagged under its own weight.
Figure 21
launch nose before the first and last launch
3.2.4. Pylons
After the closure above the Tarn River, on May 18, 2004, the pylons which
had been fabricated in different factories and assembled behind the bridge
abutments, were transported one by one onto the deck, each by two
crawlers. The weight of a convoy reached 8 MN, producing an extreme
load test for the structure. Then the pylon, in a horizontal position, was
tilted up by Sarens with the help of a cable-stayed temporary support tower.
The structure construction ended with the installation and tension of staycables by Freyssinet.
Figure 22
erecting of pylons
3.3. Funding
The ultimate funding of the Millau Viaduct relies on users, trucks and
motorists, and depends on the BFOT PPP type of procurement.
From the opening of the Millau Viaduct the level of traffic was superior to
the forecast. The tariff policy proposed by the concession contract was
based on the predicted revenues. Eiffage relied on SETEC for the traffic
forecast. In 2005, 4,400,000 vehicles crossed the Viaduct, 20% more than
anticipated. In 2008, there were 4,670,449 vehicles and heavy goods traffic
represented 8.39% of the traffic.
OPERATION
The toll barriers of the Viaduct comprised 14 lanes in 2004, and were
extended to 18 lanes since 2005 due to traffic flows which were greater
than forecast. In this regard:
traffic flow varies from 1 to 17, from 2,500 to 62,300 vehicles per day
in July and August;
recruitment of employees adapts to the flows, with 54 permanent
cashiers and 33 additional persons over the summer;
fees are collected manually, as subscriptions systems are not
appropriate due to the absence of other tolls on the highway (the
Viaduct is on the A75 a free highway).
Besides the toll activities, the Viaduct includes four additional services:
security: five employees and five polyvalent cashiers for July and
August;
Maintenance: four employees for day-to-day maintenance (technical
care of the lanes, machines, electrical systems, etc.);
communication: six employees including four permanent tourist
guides.
The importance of the communication service could be explained by an
unexpected effect: the Viaduct became one of the most important tourist
sites in the region and receives from 600,000 to 900,000 visits per year,
15,000 visits with charge. Spin offs from the Viaduct also generate revenue.
3.3.2. Conclusion and main attributes of success
Recalling the FNTPs Conference in October 2003 chaired by the Director
of the Road Directorate Patrice Paris, Jean Francois Coste, Pascal
Lechanteur and Marc Legrand outlined the main factors of success as
decisions related to:
the initial planning and route;
the procurement decisions and the concession;
the technical choices, in particular the decision to build the bridge in
steel;
the people who contributed to the different phases of the Viaduct.
Taking the whole project process into consideration, the success of the
Millau Viaduct is manifested in:
The planning: from the studies of the initial route to the choice of the
project. The design of the Millau Viaduct consists of the original
design proposal of the Administration (SETRA) conceived by Michel
Virlogeux. However, expert and public scrutiny challenged this initial
Fi
gure 27 construction continuity