Beruflich Dokumente
Kultur Dokumente
..v1
Standard Specification
1. Definition
A Pressure Injected Footing (PIF)
shall consist of an expanded base
formed by ramming zero-slump
concrete into the soil with impact
pressure of up to (see Table 1) footpounds of energy per blow, and a
concrete or steel-and-concrete shaft
designed to transmit the superstructure load to the expanded base.
2. Qualifications
Installation of PIF shall be performed
by a specialty contractor, hereinafter
called the Subcontractor, whose
qualifications as regards experience
in work of this type and scope,
suitability of equipment, competent
personnel and reputation shall be
subject to the approval of the
Architect. As a minimum, the Subcontractor
shall submit
sq~j.sf~qtory..
TABLE I
Type
Tons
50
100
200
250
300
Mini
Medium
Standard
Large
Maxi
Tons
1.5
2.5
3.5
3.5
5.0
Inehes Cu.ft.
2
12-3/4
16
5
21
5
22
5
24
5
para~le
concreteshaft*
Inehes
Ft.lbs.
60,000
100,000
140.000
140,000
200,000
NIA
17
10-5/8,11-1/8
22
23
16,17-5/8
19
25
22
12-1/4 to 14
Uncased zero-slump concrete shafts, in which concrete is rammed out against the
soil, are conservatively assigned nominal diameter 1" greater than drive-tube. Uncased
high-slump concrete shafts are normally taken as equal in diameter to drive-tube.
Casing referred to here is corrugated steel shell, 01 no structural value. When steel
pipe is used, structural value is allowed i1 wall thickness exce~ds,Q..1'.',..resultingin
diameters somewhat less than those listed.
. ,~.. :" .',
..
".".,:.~._ _
..!.i
,,',:' . _>-'
v.'..
f-I;
Nominal
diameter
cased
shaW*
Inehes
The
Seetion
shall conform
~.
::..': .: ~v'
..:,., >'.r<~
:: ,; _'[~::~~.2:Base:::At
.~ ..,
th:is.:depth, the
to generally
acp,e,pteQ,engin.e.eriJ.l,9 and~q':lstn~c-;._,.
..., r~l"Qi.rg
~fJ.r9 ~lumPij:;oncrete
into
acceptance of respons.!:>III.ty,.!::?y,the.
. . " :. ;tic;>npr~tice.
:<-."', .-,
.' ..;. .". ...,..,..thesdil~~th tfrdP-h~~~er blows
Ar~~ltect for the Subcon~ractor ~i ..: . ,', J' ,. '.0;.-';. .:,
L..',
."
:'dfivering {see Tabfe'I)'foot-pounds
ablllty to perform the wo~k. i .~> .,-, 0., " 5~.Basis of.:Contract "',
; ~i;' .":.
of.energy. Retor.~ishatl{\)e kept both
3. Guarantee
.'
,,. ,':
for
J.
'99.ntr~~t
Sra,IJ~Cj!,bas~d.on.tlT~
I')ym~.. i.
6.Installatl.o~
subsoil.
~qq~e: vpluf!1~pf.c!ln<;~ete
inject~d
closure
cubic feet
t t (N t A)
=. ~
cons an
o ~
2.1/Fr-1
&RAN<I
Structural Design
6.3 Shaft: (Separateparagraphs
6.3a ,6.3b and 6.3c are provided,
coveringthe shaft proceduresin most
commonuse.Deletethose which do
not apply.)
6.3a Uncased zero-slump concrete shaft: Upon completion of the
expanded base, the concrete shaft
shall be made by compacting charges
of zero-slump concrete, not exceeding 5 cubic feet each, with drophammer blows of at least 20,000
foot-pounds, as the drive-tube is
withdrawn in short steps. During
shaft construction the tip of the
drive-tube shall at all times be below
the level of concrete within the tu be.
Concreting shaU.terminate at or
above the cut-off elevation shown on
the plans. The shaft head shall be
trimmed, after e~cavation, to remove
excess concrete and indentation
caused by the drop-hammer, providing a level surface at correct cut-off
elevation.
6.3b Uncflsed high-slump concrete shaft: Pnor to completion of the
expanded base, a full-Iength reinforc-
:l
is present,
then
given:
uncased
compacted
concrete
shaft:
243
2.1/Fr-1
V = 20 kips
PIF diameter = 22 inches, fixed head condition
fe' = 4000 psi
f1 = 60,000 psi
= AxVx
(~)
l/S
E
I
n
A
A
1]50
0.78
Soil Condition
'Typical n Values
medium dense sand. above water table
50
dense sand above water table
100
30
medium dense sand below water table
dense sand below water table
60
4
soft clay
13
mediumclay
25
hard clay
This table does not inelude loose sand, beeause sueh material
wlll be densified by the PIF installation proeess.
..v1
Bearing Capacity
Under this heading the transfer of
load from the expanded PIF base to
the soil is examined. The problem
can be approached from the dynamic
or the static viewpoint and preferably
from both. In practice, substantially
all PIF installations are controlled in
the field by a dynamic formula, the
key clause in the Specification; a
static analysis is employed to ensure
that the overall concept is geotechnically sound. Note that the
dynamic approach assumes pure
GAOI,IHD
--.
SOR'ACE\
L = S H X Y2/3
-in which the constant K provides
empirically for such other variables
as type of soil, energy losses, etc.
Derivation of the formula is presented
below.
Proof
Lu
dE =
F x dr =
rl
r2
Pll X 4 'Ir r2 x dr
rl
(: 'lrr23-;
E=pu
Pu
r2
'lrr13)
= Pu (V'2 - V'l)
but E = e x W x H x n
then p. (V'2
(1) niEORETICAL
DYNAMIC
(2)ACTUAL
OYNAMIC CO~ITION
(3) ACTUAL
STATIC
V'l) = e x W x H x n
CONDITION
CONDI1lON
FIGURE1
Smce '
V
Symbols
lu = ultimate bearing capacity of PIF base
Lw = working load allowed (service load) on base
Pu = ultimate unit bearing capacity of soil surrounding
the base
W
= weight
s,
- v ,1 =
= e x W x H x S' X 'Ir r2
3fE
but'lr r2 = .v 16
of drop-hammer
x (V')2/3
A, = surface
'Ir r2
V' 1
3rfi.
16 x (V')2/3
or Lw=
~ 169;
x W x H x Sx V2/3
W x H x S X Y2f3
--
2.1/Fr-1
~I
The values of K are different for a compacted concrete
shaft than for a cased shaft. When a compacted concrete
shaft is made, the concrete in the shaft is rammed
against the surrounding soil creating major lateral pressures. When a cased shaft is made, these lateral pressures
are virtually absent. The incipient failure zone in the soil
surrounding the base arches back to the shaft of the PIF
and the presence or absence of the lateral pressures
from the shaft on this failure zone significantly affects
the resisting shear stress es and strains developed on the
failure plane. The greater the lateral pressure, the greater
is the resisting shear and the lesser the resulting strain.
Lower values of K for PIFs with compacted concrete
shafts reflect this phenomenon.
On major projects, a load-test is a common requirement. The value of K should lhen, of course, be determined for each site from its own load-test. For example,
suppose the test proves a service load of 400 kips for
the PIF. Suppose also that the test data shows that the
total volume of bulk concrete in the base of the test PIF
is 20 cf and that 45 blows of a 7000 lb. drop hammer
falling 20 feet were required to ram the last 5 cf of bulk
concrete into the base.
From the above data:
Lw = 400 kips
W = 7 kips
H = 20 feet
45
B = 5" = 9 blows average per cu. ft. for
last 5 cu. ft.
and V = 20 cf
T ABLE 11
SoilDescription
gravel
medium
to coarsesand
fineto mediumsand
coarsesand
medium
sand
finesand
veryfinesand
siltymedium
to coarsesand
siltyfineto medium
sand
siltyfinesand
Recommended
K
K
withCompactedRecommended
Concrete
Shaft withCased
Shaft
9
12
11
14
14
18
18
23
22
28
27
35
32
40
14
.18
17
22
24
30
18.
residualso!!common
to Southeast
U.S. 600but1:
N
finesandwith"limerock"fragments
18
and/orshells
20
glacialtill, granularmatrix
30
glacialtill, claymatrix
bedrock
10
1800
N but<j:50.
formula
B x W x H X V2/3
23.3
25
27
40
10
the general
then
and
B x 7 x 20 X V2/3
23.3
B x V2/3 = 66.6
400
Min.Brequiredpercf
Notapplicable
15
11
9
8
Min.Brequiredfor last5cf
Notapplicable
75
55
45
40
LEGEND
B V 2/3
o
400 -:1
LOAD) ON BASE
Lw
B W H . V 2/3
o
WITHTHESAMESYMBOLS
(.
.w..:J:L
5-,
K. Lw
Lw
r- 2,000
50
300 -1
10
200
e
;:
u..
"C
el)
()
-!
'-eel)
5
'O
el)
c:
c:
...
Q.
Q)
:::1
8
9
10
'u
ea
>-
D.
ea
O
4,000
Q) CJ
m :
50
300
6,000
70
50
80
30
60
1-20
400
500
600
70
100
8,000
15
100
90
110,000
150
70
20
5,000
l:- 1,000
t=....
200j
300
50
10
",000
IO
1,500
6
20,000
40 -j
1-5
4
15
QC'\I
ea :)
125
, r30 25
['00200
e w
.C a:
40
-V
0
0
20
150
C-5O
3,000
30
o
o
JL
b-40
250
fn
C)
. .)
20.
2J
30,000
301
25
..
20J
..
'--3
40,000
IX)
2.1/Fr-1
~I
Static Analysis (Method 1)
Static
...
...J
Q.
'"
..
x
....
;!;
o
...
'"
::>
'"
'"
..
o!!!
---'
LTO=
BEARING STRATUM
Analysis
(Method
2)
GROUND SURFACE
Dlameter
=
.
-:;-6 x 10 = 2.67'
7r
x 4.222/4 = 14 ft.2
:.
consider
only
.9
-..
~I
BearingCapacity-continued
Pressure Injected Footings in Tension
The geometry of the PIF makes it obviously advantageous
as an uplift or tension unit. Determination of ultimate uplift
resistance is a complex problem in soil mechanics: one
simplified approach, iIIustrated below, equates ultimate
capacity to the weight of the cone of soil above the base,
the sides of the cone assumed to be at 30 to the
vertical in granular material.
FINISHED FLOOR
AREA AT TH IS LEVEL
= A2
TOP OF CAP
MISCELLANEOU8 FILL
BOTTOM OF CAP
~
DESIGN G.W.L.
80FT CLAY
REINFORCING CAGE
SAND
"SUBI
HI
RE1NFORCING CAGE
ANCHORED IN BASE
Groups ofPIF's are similarly analyzed but due to overlapping of "cones" the efficiency is reduced. Normally
it is assumed that the PIFs mobilize the entire mass of
soil within the group, plus that within the pyramidal
configuration outside the group.
The above method, while simplistic, is consorvative,
especially at relatively shallow depths. A factor of safety
of 1.5 is usually applied to establish working tension load.
10
2.1/Fr-1
..vK1
Normal
Clearance Requirements of
Franki Driving Rig
A=3'-0"
8=6'-0"
C=30'-0"
~~
.wAN<1
Reinforcing
Pressure Injected Footings are never
reinforced where compression loads
only are to be resisted, which is the
normal case. Reinforcing can,
however, be provided where moment,
shear or tension conditions so
dictate.
In cased-shaft PIFs the shaft
concrete is placed at 4 to 6~inch
slump after the driving machine has
left. Thus, if it is desired to reinforce
the shaft, the steel cage can be
designed and detailed in the
standard manner. Bends or hooks at
the top must be avoided where cutoff elevation is well below working
grade.
Cased shafts are usually reinforced
for shear only. Their use for tension
resistance is confined to special
situations, beyond the scope of this
note.
Significant moment, shear or
tension usually demand the uncased
compacted zero-slump concrete
shaft PIF. For this type of shaft, the
cage design must satisfy certain
requi rements.
For tension PIFs, the reinforcing
cage is placed inside the drive-tube
before the base is completed so that
the cage will be anchored in the
base. For PIFs required to resst
shear loads but not tension loads,
the cage is placed inside the drivetube at the appropriate depth below
the top of the PIF as the shaft is
being made. In both cases, the zeroslump concrete is rammed out of the
end of the drive-tube through the
cage and against the surrounding
soil. In order for the concrete to be
rammed out through the cage
effectively, the space between the
individuallongitudinal
reinforcing
bars and the encircling 114inch
diameter spiral binding must not be
so small as to impede the ejection
of the concrete. From experience
over many years, it has been learned
what this limit is. The outside of the
spiral (marked y on Figure 1) should
be about 112inch less than the inside
diameter of the drive-tube; pitch of
the spiral binding should be 6 to 8
inches. The number and size of the
bars have limits which are dictated
by the size of the drive-tube.as well
as by stress considerations. In
general, however, the number of
longitudinal bars should not be less
than 5 nor more than 8 and the size
of the bars should not be smaller
than #5 nor greater than #9. Franki
12
REINFORCING BAR
1/4"
SPIRAL TIE
PLAN
TOP OF P.I.F.
ORIVE
TUBE
0.0.
1/4"
~ SPIRAL
6"-8"
PITCH
TIE
16"
13.5"
20.5"
"'7.5"
21"
18.5"
22"
19.5"
24"
20.5"
1--
:5
en
o
1--,
:J:
1-<!)
Z
LLI
-1
REINFORCING BAR
SECTION
DETAlL
OF REINFORCING
CAGE
2.1/Fr-1
..v1
Typical Details at Head of
Single Pressure Injected Footing
I~ --:~\
~(\tH
~/t
I
::
" ,~
'-
PLAN
~/
PLAN
ANCHOR
ANCHOR
BOLTS
BOLTS
DOWELS
GRADE BEAM
POURED MONO'LlTHIC WITH
PILASTER
DOWELS
DOWELS
.
EXT E RIO R
COLU
MN
~NTERIOR
'GRADE' BEAM
COL.UMN
;TI:;:"!:...o
..1
:1]:1
DOWELS
GRADE BEAM
WITH COLUMN
OVER
13