REQUEST FOR INSPECTION


Project Title
Job No
Client
Main Contractor
(Client Name:

Senoro Gas Development Project


9608/SU2573
JOB Pertamina Medco E & P Tomori Sulawesi
Tripatra-Samsung Consortium
Attn. Mr. Sri Adi. W
QC Manager

Gentlemen,

We would like to have your presence for inspection according to the followin

Date and time


19-Jun-15

Place/Area
CPP 1

09.00 WITA

Inspection Item
Final Inspection
GT 9027 A/B/C

Piping

Civil

Instrument

Pipeline

Structural

Electrical

COMMENT
:

Involvement
Party
Signature
Name
Sign Date
Job Title
Form Code : SNO-Q-FM-0001 Rev.0

Performed By

Approved By
Vendor

Reviewed B
TSC

ST FOR INSPECTION
Sub-Contracto
Report No. SNO-Q-BPK-RFI-802
Date
18-Jun-15
Page
of

spection according to the following schedules.

Inspection Item
Final Inspection

Remarks
(PK 9027)

GT 9027 A/B/C

Mechanical

Reviewed By
TSC

Reviewed By
JOB PMTS

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 A

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

The detailed checks within the Gas Turbine


package shall follow Manufacturers Procedures
and instructions.

The equipment supplied should be checked


against the Purchase Order and all Variations. It is
necessary to ensure that the equipment is as
specified on the Order in all respects which include
basic equipment, extras and materials of
construction.

The Manufacturers instructions and document


should be checked to ensure that they are the
correct type for the equipment supplied and
information is available for all bought in items and
generally that the documentation is adequate to
cover installation, commissioning, operation and
maintenance of the equipment.

The nameplate details should comply with the


equipment and give all the information requested
in the Purchase Order. The nameplate should be
attached to the equipment in an accessible
position and be securely fastened.

The setting down of the package shall be checked


in accordance with drawings. If AVMs are used,
the manufacturers data shall be checked for
correct installation.

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 A

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

All piping, valves, instruments, and filters shall be


checked using the appropriate check list.

Check that the inlet air filter and ducting is


correctly installed as per the drawings.

Check that the exhaust ducting is adequately


supported, and the silencer is correctly located
and fitted in accordance with the drawings and
manufacturers procedures and instructions.

Check enclosure ventilation ducting, fans and


auxiliaries such as gas detection, thermal
detection, pressure / temperature / limit switches
are correctly fitted as per manufacturer's
drawings.

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 A

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

10

Check the oil cooler installation against the


drawing. If cooler is remote from package, ensure
piping is run to avoid traps.

11

All other appurtenances such as oil tank vents


which are site fitted, shall be checked for correct
installation as per manufacturers drawings and
procedure. (Loose shipped items will be listed in
Appendix)

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

Remarks :

Involvement Party

Signature

Performed By

Reviewed By
TSC

Approved
JOB PMT

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 A

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

Signature
Name
Sign Date
Job Title
Form Code : SNO-Q-FM-0165 Rev.0

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001A
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

REMARKS

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001A
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

REMARKS

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001A
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

Approved By
JOB PMTS

TPI

REMARKS

(If applicable)

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001A
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

REMARKS

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 C

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

The detailed checks within the Gas Turbine


package shall follow Manufacturers Procedures
and instructions.

The equipment supplied should be checked


against the Purchase Order and all Variations. It is
necessary to ensure that the equipment is as
specified on the Order in all respects which include
basic equipment, extras and materials of
construction.

The Manufacturers instructions and document


should be checked to ensure that they are the
correct type for the equipment supplied and
information is available for all bought in items and
generally that the documentation is adequate to
cover installation, commissioning, operation and
maintenance of the equipment.

The nameplate details should comply with the


equipment and give all the information requested
in the Purchase Order. The nameplate should be
attached to the equipment in an accessible
position and be securely fastened.

The setting down of the package shall be checked


in accordance with drawings. If AVMs are used,
the manufacturers data shall be checked for
correct installation.

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 C

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

All piping, valves, instruments, and filters shall be


checked using the appropriate check list.

Check that the inlet air filter and ducting is


correctly installed as per the drawings.

Check that the exhaust ducting is adequately


supported, and the silencer is correctly located
and fitted in accordance with the drawings and
manufacturers procedures and instructions.

Check enclosure ventilation ducting, fans and


auxiliaries such as gas detection, thermal
detection, pressure / temperature / limit switches
are correctly fitted as per manufacturer's
drawings.

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 C

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

10

Check the oil cooler installation against the


drawing. If cooler is remote from package, ensure
piping is run to avoid traps.

11

All other appurtenances such as oil tank vents


which are site fitted, shall be checked for correct
installation as per manufacturers drawings and
procedure. (Loose shipped items will be listed in
Appendix)

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

Remarks :

Involvement Party

Signature

Performed By

Reviewed By
TSC

Approved
JOB PMT

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 C

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

Signature
Name
Sign Date
Job Title
Form Code : SNO-Q-FM-0165 Rev.0

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001C
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

REMARKS

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001C
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

REMARKS

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001C
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

Approved By
JOB PMTS

TPI

REMARKS

(If applicable)

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001C
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

REMARKS

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 B

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

The detailed checks within the Gas Turbine


package shall follow Manufacturers Procedures
and instructions.

The equipment supplied should be checked


against the Purchase Order and all Variations. It is
necessary to ensure that the equipment is as
specified on the Order in all respects which include
basic equipment, extras and materials of
construction.

The Manufacturers instructions and document


should be checked to ensure that they are the
correct type for the equipment supplied and
information is available for all bought in items and
generally that the documentation is adequate to
cover installation, commissioning, operation and
maintenance of the equipment.

The nameplate details should comply with the


equipment and give all the information requested
in the Purchase Order. The nameplate should be
attached to the equipment in an accessible
position and be securely fastened.

The setting down of the package shall be checked


in accordance with drawings. If AVMs are used,
the manufacturers data shall be checked for
correct installation.

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 B

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

All piping, valves, instruments, and filters shall be


checked using the appropriate check list.

Check that the inlet air filter and ducting is


correctly installed as per the drawings.

Check that the exhaust ducting is adequately


supported, and the silencer is correctly located
and fitted in accordance with the drawings and
manufacturers procedures and instructions.

Check enclosure ventilation ducting, fans and


auxiliaries such as gas detection, thermal
detection, pressure / temperature / limit switches
are correctly fitted as per manufacturer's
drawings.

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 B

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

10

Check the oil cooler installation against the


drawing. If cooler is remote from package, ensure
piping is run to avoid traps.

11

All other appurtenances such as oil tank vents


which are site fitted, shall be checked for correct
installation as per manufacturers drawings and
procedure. (Loose shipped items will be listed in
Appendix)

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

Remarks :

Involvement Party

Signature

Performed By

Reviewed By
TSC

Approved
JOB PMT

GAS TURBINE INSPECTION CHECK

Senoro Gas Development Project


Sub-Con
9608/SU2573
Report
JOB Pertamina Medco E & P Tomori Sulawesi Date
TRIPATRA-SAMSUNG CONSORTIUM
Page

Project Title
Job No
Client
Main Contractor
Equipment Tag Number

: GT-9027 B

Reference Drawing

Equipment Name

: Gas Turbine

Revision

Manufacturer

: Solar Turbine

No.

ITEM TO CHECK

Signature
Name
Sign Date
Job Title
Form Code : SNO-Q-FM-0165 Rev.0

RESULT
ACC

REJ

DATE

ACCEPT
SUBCON

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001B
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

REMARKS

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001B
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

REMARKS

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001B
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

Approved By
JOB PMTS

TPI

REMARKS

(If applicable)

INSPECTION CHECK LIST


Sub-Contractor
SNO-Q-BPK-GTI-001B
Report No.
Date
18-Jun-15
Page
of
Reference Drawing

: 3R111-149692
: C

ACCEPTED
SUBCON

REVIEWED

TSC JOB PMTS

REMARKS