Table of Contents
Title
Page
No.
1.
2. General Conditions / Requirements for Approval of Substation [Supply provided at LV (0.4 kV)]:
a.
------------------------------------------------------------4
b.
---------------------------------------------7
c.
Floor---------------------------------------------------------------11
d.
Plot------------------------------------------------------16
32
e.
Plot-------------------------------------------18
f.
Plot---------------------------20
Supply-----------------------------21
a.
Industrial / Special
Loads-------------------------------------------------------------------------------
b.
High Rise
Towers--------------------------------------------------------------------------------------------
4. Annexure-----------------------------------------------------------------------------------------------------------
-------
Annex1: General Conditions/Requirements for Wet Areas above Substation----------------------------Annex 2: Guarantee against Damages due to Water Leakages----------------------------------------------Annex 3: Wet Area Checklist------------------------------------------------------------------------------------------------33
Annex 4: DEWA Regulations for Electrical Installation-------------------------------------------------------------Annex 5: Chiller / Motor Loads Proposed to be Connected to DEWA Transformer---------------------Annex 6: Checklist for Chiller / Motor Loads Proposed to be Connected to DEWA Transformer--Annex 7: Substation Door Details------------------------------------------------------------------------------------------Annex 8: Section T-T------------------------------------------------------------------------------------------------------------Annex 9: Section B-B-----------------------------------------------------------------------------------------------------------Annex 10: UNDERTAKING (Ground Floor Split Substation)--------------------------------------------------------Annex 11: Detail of Fixed Aluminium Wire Mesh/Grill --------------------------------------------------------------Annex 12: Diagram of Fixed Ventilation System---------------------------------------------------------------------Annex 13: UNDERTAKING (Transformer Room in Basement)-----------------------------------------------------Annex 14: Undertaking for Shared Substation------------------------------------------------------------------------Annex 15: NOC Demarcation Form--------------------------------------------------------------------------------------Annex 16: Piont of Supply/Responsibility Diagram -----------------------------------------------------------------Annex 17: Guidelines of 11-22 kV Network
Design-----------------------------------------------------------------------Annex 18: DEWA Meter/Control Room Requirements (High-rise Towers)-----------------------------------Annex 19: Guide Lines for Protection Requirement for Private Substations--------------------------------Annex 20: Checklist for Private Supply-----------------------------------------------------------------------------------Annex 21: Sample operation philosophy (Interlocking arrangement)--------------------------------------Annex 22: DEWA Meter/Control Room Requirements (Industrial / Special Loads)-----------------------
GENERAL NOTES
1) Submission of the following services are available on line through DEWA
Website www.dewa.gov.ae :a) Distribution Substation Approval
b) Request For Distribution Substation Layout Drawing
c) Request for Inspection of Distribution Substation
34
1)
1.1) 32.56m2 for 1x1000/1500 kVA transformer (with minimum width of 4.57m towards
door side)
1.2) 53.95m2 for 2 x1000/1500 kVA transformers (with minimum width of 6.1m towards
door side)
35
2.7) Finish Floor Level (FFL) of the substation is to be maintained 0.15m to 0.30m higher
than the outside adjacent ground level (towards door side).
2.8) LV electrical room should be adjacent/near to the substation, if main panel is private
(as per circular for LV room attached Annex-4). Separate approval for location and size
of LV room to be obtained from Consumer Services Department.
2.9) Wet areas (i.e. kitchen, bath, toilet etc.) above substation are not acceptable. Only in
exceptional unavoidable cases, this may be accepted at the discretion of DEWA subject
to complying with the following: a)
b)
c)
d)
2.10)
Chillers/Motors Loads:
a) For Chillers/Motors with capacities more than (100kW), follow the Circular of
Chiller/Motor loads proposed to be connected to DEWA Transformer [as per
Annex-5].
b) For Chillers/Motors with capacities between [50kW 100kW], The total
connected load should not exceed the following:
b-1)
b-2)
3.7) One copy of Substation Room details drawing plan showing sections (x-x & y-y). LV
route and LV opening are to be indicated.
3.8) One copy of Load Summary Sheet indicating Total Connected Load (TCL), Max
Demand (MD) and KWH metering for each transformer along with a realistic Power
Requirement Date.
3.9) Chiller/Load checklist to be duly filled and submitted by the consultant, if applicable
(refer to Annex- 6).
3.10) One copy of Schematic Diagram showing load intake & metering arrangement.
37
General Conditions / Requirements for Approval of Location & Size of Split Room
Substation(s) RMU & Transformer Rooms in Ground Floor within Building (only
Dedicated)
1. Area Requirement:
1.1. Transformer Room(Ground Floor)
a) 21m2 for 1x1000/1500 kVA transformer (with minimum width of 4.57m towards door
side)
b) 42m2 for 2 x1000/1500 KVA transformers (with minimum width of 6.1m towards door
side)
(For every additional transformer, approximately 21m additional space is required)
1.2. RMU Room (Ground Floor)
a) 9.3m2 area (with minimum width of 3.05mtrs towards door side) for one set of RMU
(controlling up to two transformers)
(For each additional RMU set, approximately 7m 2 additional space** is required)
** For S/S having four and more Transformers an additional space of (10
m2) shall be required with minimum width of 5m towards roadside]
2. Conditions for RMU room:
38
a) In case of cable trench arrangement, clear depth of 0.95m from FFL (finished floor
level) of the Substation is to be provided.
b) In case of cable tray arrangement, clear depth of 0.95m from FFL of the substation
up to bed of the cable tray with minimum clearance of 0.45mtrs is to be maintained
in between bottom of the slab and the bed of the cable tray. For cable maintenance
minimum of 1.2m free spaces is to be provided towards of the cable tray (at least
one side). The cable tray should pass through public/open area and not through any
closed area / room (there shall be no services, pipes, etc, below the cable tray).
3. Conditions for Transformer room:
3.1) Clear direct unhindered access (of minimum 3.05m width & minimum 3.05m clear
height) from RTA/Public road or sikka.
3.2) Clear height 3.66m (minimum).
3.3) Must have minimum two-side ventilation with aluminum louver doors and fixed
aluminum louvers window. Fixed aluminum louver window(s) should be located at 0.30
m above out side level.
3.4) Transformer Room aluminum louver door(s) clear height 2.75m & clear width 3.05m
(2.44m in exceptional cases) as per door details ref. drawing nos. P-DS/DOOR/01/96
(Rev.A) and P-DS/DOOR/02/96 (as per Annex-7).
3.5) Finish Floor Level (FFL) of the transformer room is to be maintained 0.15m to 0.30m
higher than the outside adjacent ground level (towards door side).
39
One copy of Schematic Diagram showing load intake & metering arrangement.
5.11)
One copy of Architectural plan indicating HV cable route between RMU room &
Transformer room, along with its sectional details showing the typical
horizontal/vertical clearances available for the route.
5.12)
Undertakings in prescribed form duly signed by the owner of the plot (officially
stamped if owner is a company) for Ground Floor Split Substation (refer to Anex10). Signature should match the owners passport copy. In case owner is a
company, undertaking letter should show the companys official stamp.
311
312
in between bottom of the slab and the bed of the cable tray. For cable maintenance
minimum of 1.2m free space is to be provided towards of the cable tray (at least one
side). The cable tray should pass through public/open area and not through any
closed area / room (there shall be no services, pipes, etc, below the cable tray.
3.7) Transportation of Equipments in transformer room:
a) In case of transportation through ramp:
a-1) The ramp up to the transformer room should be straight with 3.05m (minimum)
width and clear height from main road up to the transformer room.
a-2) Slope of the ramp to be maintained 1:10 (10%) (Maximum) and should be
straight without sloped curves and speed breakers (bumps).
b) In case of transportation through slab cut out opening:
b-1) The cut out size to be 3 m x 3 m and to be adjacent to the main RTA/Public
roadside.
b-2) The area below the cut out at basement must be designated as loading /
unloading bay.
b-3) The area above the cut out is to be open to sky. If above-floor exists, then the
clear height is to be maintained 7m (for the boom of the crane to transport the
transformer, etc.).
b-4) If the cut out slab is directly located above the transformer room, then the slab
cut out cover is to be weather proof type with removable covering arrangement.
4. Common Conditions
4.1) Transportation of Transformer(s) from the main road up to and from the transformer
room is Owners responsibility
4.2) Cable route between RMU and transformer room:
a) In case of cable tray arrangement, clear depth of 0.95m from FFL of the substation
up to bed of the cable tray with minimum clearance of 0.45mtrs is to be maintained
in between bottom of the slab and the bed of the cable tray. For cable maintenance
minimum of 1.2m free space is to be provided towards of the cable tray (at least one
side). The cable tray should pass through public/open area and not through any
closed area / room (there shall be no services, pipes, etc, below the cable tray.
b) The cable route from RMU room in ground floor to transformer room (at basement) is
preferred to be straight (Without turns / bends); in case of bending the bending
radius to be considered R = 0.95m.
4.3) Wet areas (i.e. kitchen, bath, toilet etc.) above substation are not acceptable. Only in
exceptional unavoidable cases, this may be accepted at the discretion of DEWA subject
to complying with the following:a) Annexure-1 (Regulation for wet area)
b) Anexexure-2 (Guarantee letter)
c) Annexure-3 (Checklist to be filled and signed by consultant/contractor)
314
d) Substation clear height is to be maintained no less than 3.66m from substation FFL
up to bottom of the attic slab.
4.6) LV electrical room should be adjacent/near to the substation, if main panel is
private (as per circular for LV room attached Annex-4). Separate approval for
location and size of LV room to be obtained from Consumer Services Department.
4.7) Chillers/Motors Loads:
a) For Chillers/Motors with capacities more than (100kW), follow the Circular of
Chiller/Motor loads proposed to be connected to DEWA Transformer [as per Annex-5].
b) For Chillers/Motors with capacities between [50kW 100kW] The total connected
load should not exceed the following:
b-3) 650kW from 1000kVA.
b-4) 950kW from 1500kVA.
c) For No Chiller/Motors available:c-1) Conformation note is to be mentioned on Load Summary Sheet.
5. Proposal should be submitted along with the following Documents /Details:
5.1) Copy of full set of valid DEWA Building NOC.
5.2) One copy of valid affection /site plan issued by DM or any competent authority
5.3) One copy of site setting out plan, showing the location & size of the proposed and
existing (if any) substation(s).
5.4) Three copies of Architectural plan drawing indicating the location & size of the
proposed RMU room in Ground Floor (existing substation(s) to be shown also, if
any).
5.5) Three copies of Architectural plan drawing indicating the location & size of the
proposed transformer room in Basement Floor (existing substation(s) to be shown
also, if any).
5.6) One copy of Above-Ground Floor Plan drawing.
5.7) One copy of Below-Basement Floor Plan drawing (if applicable).
5.8) One copy of RMU & Transformer Room details drawing plan showing sections (x-x &
y-y). LV route and LV opening are to be indicated.
5.9) One copy of sectional details for Ramp showing the access width and height from
the ramp up to transformer room in basement floor (if applicable).
5.10)
One copy of Load Summary Sheet indicating Total Connected Load (TCL), Max
Demand (MD) and KWH metering for each transformer along with a realistic Power
Requirement Date.
5.11)
One copy of Schematic Diagram showing load intake & metering arrangement.
315
5.12)
One copy of Architectural plan indicating HV cable route between RMU room &
Transformer room, along with its sectional details showing the typical
horizontal/vertical clearances available for the route and indicating the
entry/turning points details.
5.13)
Undertakings in prescribed form duly signed by the owner of the plot for
Basement Floor Split Substation (refer to Anex-13). Signature should match the
owners passport copy. In case owner is a company, undertaking letter should
show the companys official stamp.
5.14)
Method statement of transportation of transformer(s) to and from the
Transformer Room.
1. Area Requirement:
1.1. Substation Location (Outside Building)
a) 6.1m X 6.1m (Open to sky) for 1X1000/1500KVA and 1xRMU {Substation with extra
large kiosk}
b) LV Room must be adjacent to the substation space
2. Area/space conditions:
2.1) Directly located on RTA/Public Road or Sikka.
2.2) In case substation is located on Sikka, the sikka should have a minimum clear width of
6.1m. However if the proposed substation location is less than 12m away from the
main road then the sikka can be accepted with minimum clear width of 3.05 m.
2.3) The height of the compound wall around the substation should not be more than 2.13m
(7ft)
2.4) Soak-away should be 3.66m (minimum) away from the substation.
2.5) Substation space should be open to sky (to be mentioned).
2.6) LV electrical room should be adjacent/near to the substation, if main panel is
private (as per circular for LV room attached Annex-4). Separate approval for
location and size of LV room to be obtained from Consumer Services Department.
2.7) Chillers/Motors Loads:
a) For Chillers/Motors with capacities more than (100kW) follow the Circular of
Chiller/Motor loads proposed to be connected to DEWA Transformer [refer to Annex5].
316
b) For Chillers/Motors with capacities between [50kW 100kW] The total connected
load should not exceed the following:
b-1) 650kW from 1000kVA.
b-2) 950kW from 1500kVA.
c) For No Chiller/Motors available:c-1) Conformation note is to be mentioned on Load Summary Sheet.
317
318
319
Proposal should be submitted along with the following documents for approval
of private equipments substation.
1. Copy of DEWA Building NOC along with affection / site plan from DM/Competent
2. Copy (3 Nos.) of setting out plan indicating DEWA Control/Metering room. Partys
circuit Breaker room should be adjacent to Metering/Control room.
3. Soft copy of setting out plan in Microstation (J) with DLTM coordinates.
4. Copy of Control/Metering room layout drawings details plan to be shown through
horizontal & vertical sectional views. For Control/Metering room size requirements
(refer to Annex-22).
5. Copy (4 Nos.) of single line diagram (schematic) showing load intake arrangement
with details of protection scheme as following: a) CT & VT rating, Burden, Class etc.
b) Details of O/C & E/F relay.
c) Bus section details along with Interlocking arrangement for more than 1 feeder
d) TCL & MD for each feeder.
e) TCL & MD for each Transformer, motor etc.
f) Metering arrangement
g) Details of Power Transformer (Type, Rating, Ratio, % Imp, etc)
h) Starting current of motors & the motor details (if applicable)
i) All earthing points
j) DEWA point of supply & ownership boundary.
k) Please refer to Protection guidelines (Annex-19)
6. Copy of load schedule including TCL & maximum demand load with kWh Meter
(metering arrangement at DEWA s Meter/Control room).
7. A checklist for the protection scheme is to be filled and signed by consultant (refer to
Annex-20). Also a guideline attached for the reference of the same (Annex-19).
8. You are requested to obtain written acceptance from the owner of the project to the
effect that, maintenance/replacement of breaker, fuse switch and transformers,
cables which will be procured by you shall be done by the owner in future and forward
the same to us. We will require this before commencement of works for the project.
9. (a) Calculation of voltage drop & (b) Harmonics at DEWA source ensuring that these
are within limits specified by DEWA (planning voltage guideline attached Anex-19).
10.
Operation philosophy
320
PART-II
The following documents/information should be submitted subsequently after
approval of above for energization of private equipment and release of power
through private equipment.
1. Revised/updated copy of single line diagram (schematic, if applicable- 4 copies)
2. Step by step relay setting calculations. The relay co-ordination shall be made based
on maximum fault current and the grading margin shall be kept at 0.300 seconds
between DEWA end to private partys panel end. (submission should be at least
one month before the power requirement for the project)
3. Owners undertaking stating Our equipment are suitable for energisation in line with
DEWA network system& confirm that relays are set as per DEWA approved settings.
4. HV cable Jointers list in details (approved by DEWA).
5. Names and telephone numbers of contact person for the project who should be
available 24 hours day & night.
6. Name of competent technical staff, who know the switchgear operation and capable of
issuing work permit stating that cable is safe for works and also ensure no one will
operate during testing & repairing time.
7. Operation philosophy (interlocking details)[attached sample Anex-21]
8. All catalogue for CT, VT, Relay & motor to be submitted.
9. Formal application form for the supply to DEWA is to be filled and submitted to the
Consumer Services Department (CSD).
10.Payment against the estimate
11.Handing over of DEWA Meter/Control room getting it inspected and approved.
(Submitted through DEWA website)
12.You are requested to obtain written acceptance from the owner of the project to the
effect that, maintenance of breaker, fuse switch and transformers, which will be
procured by you shall be done by the owner in future and forward the same to us. This
will be required before commencement of works for the project.
NOTE: Please note that under normal circumstances we shall require a period of 16 weeks for
commissioning the substation after the comply of all the requirement as stated in PART-III
321
2. Beyond DEWA point of supply all the equipments (like switchgear, transformer cable
etc.) has to be procured, installed, commissioned, operated and maintained by the
owner.
3. DEWA will not supply, operate or maintain any equipment to be installed above
ground level.
4. All equipment (Circuit Breaker, Transformer etc) procured by party should be dual
ratio (6.6/11/22 KV) unless clearly advised by DEWA that it is 11/22KV.
5. All equipments should be compliant with international standards (IEC standards)
6. Total losses of transformer should not exceed 1.5% of rated capacity due to
conservation reasons.
7. Power factor at partys point of supply should be maintained at 0.95 or higher.
8. Partys incomer should be Switchgear with CB, E/F & O/C protection and should be
located adjacent to DEWAs Meter/Control room.
9. Guidelines for 11-22KV-network design should be followed (Annex-17).
10.LV distribution shall comply with DEWA guidelines and standards.
11. Only Cast Resin transformers (fire resistant transformers) will be allowed to be
installed in Residential / Commercial buildings.
322
Copy of DEWA Building NOC along with affection / site plan from DM/Competent.
2.
Copy (3 Nos.) of setting out plan indicating DEWA Control/Metering room (soft copy of
setting out plan in Microstation (J) with DLTM coordinates). Partys circuit Breaker
room should be adjacent to Metering/Control room.
3.
4.
Copy (4 nos.) of single line diagram (schematic) showing load intake arrangement
with details of protection scheme as following: a) CT & VT rating, Burden, Class etc.
b) Details of O/C & E/F relay.
c) Bus section details along with Interlocking arrangement for more than 1 feeder
d) TCL & MD for each feeder.
e) TCL & MD for each Transformer, motor etc.
f) Metering arrangement
g) Details of Power Transformer (Type, Rating, Ratio, % Imp, etc)
h) Starting current of motors & the motor details (if applicable)
i) All earthing points
j) DEWA point of supply & ownership boundary.
k) Please refer to Protection guidelines (Annex-19)
323
5.
Copy of load schedule including TCL & maximum demand load with kWh Meter,
(metering arrangement at DEWA Meter/Control room)
6. A checklist for the protection scheme is to be filled and signed by consultant (refer to
Annex-20). Also a guideline attached for the reference of the same (Annex-19).
7.
You are requested to obtain written acceptance from the owner of the project to the
effect that, maintenance/replacement of breaker, fuse switch and transformers,
cables which will be procured by you shall be done by the owner in future and forward
the same to us. We will require this before commencement of works for the project.
8.
(a) Calculation of voltage drop & (b) Harmonics at DEWA source ensuring that these
are within limits specified by DEWA (planning voltage guideline attached (Anex-19)
9.
Note: Generally, review of the above documents shall be done within one month
PART-III
The following documents/information should be submitted subsequently after
approval of above for energization of private equipment and release of power
through private equipment.
1. Revised/updated copy of single line diagram (schematic, if applicable- 4 copies)
2. Step by step relay setting calculations. The relay co-ordination shall be made based
on maximum fault current and the grading margin shall be kept at 0.300 seconds
between DEWA end to private partys panel end. The calculation should be submitted
minimum one month before the actual power requirement for the project.
3. Owners undertaking stating Our equipment are suitable for energisation in line with
DEWA network system& confirm that relays are set as per DEWA approved settings.
4. HV cable Jointers list in details (approved by DEWA).
5. Names and telephone numbers of contact person for the project who should be
available 24 hours day & night.
6. Name of competent technical staff, who know the switchgear operation and capable of
issuing work permit stating that cable is safe for works and also ensure no one will
operate during testing & repairing time.
7. Operation philosophy (interlocking details)[attached sample Anex-21]
324
325
of
Wet
Areas
Above
In principle there shall not be any wet facilities above the substation/Ring Main Unit
Room. Only in exceptional unavoidable cases this may be allowed at the discretion of
the Authority and the following requirements must be fulfilled
1.
A Reinforced Concrete Attic slab above the entire substation/Ring Main Unit
Room shall be provided.
2.
The entire attic slab and floor slab above including the vertical sides above
attic slab shall be waterproofed by an approved system.
3.
4.
All pipes, joints, traps, etc. running in wet areas shall be wrapped with
approved Waterproofing membrane. No pipes shall pass through the void
between floor and attic slab.
326
5.
The void between floor and attic slab shall be minimum 60cms clear height.
Access to the void above attic slab shall be 120cm x 60cm fitted with
aluminum louvered door. The void shall not be used for any other purpose
and shall have permanent lighting arrangement. Drain pipe to be provided
for the attic slab to drain out any water leakage through floor slab. Tiles are
not compulsory above attic slab.
6.
The consultant shall forward complete floor plans showing location of Wet
Area and Substation/Ring Main Unit Room. Extent of attic slab shall be
clearly marked in the plans. Typical cross sections through the Wet
Area/Substation/Ring Main Unit Room and Attic Slab shall be shown in the
drawings including waterproofing arrangement/systems/materials. The
drawings shall be forwarded to Dubai Electricity and Water Authority Civil
Engineering Department for Wet Area Approval.
7.
16-09-
To:
M/s. Dubai Electricity & Water Authority
P.O. Box 564,
DUBAI,
Date: ___________
Dear Sirs,
SUB: GUARNTEE AGAINST DAMAGES DUE
TO WATER LEAKAGES IN DEWAS
ELECTRICAL SUBSTATION ROOM,
__________________________________________
Location:
__________________________________________
__________________________________________
__________________________________________
327
__________________________________________
We hereby undertake that we are fully responsible for any leakages due to any defect in the waterproofing system
and/or construction method adopted, and in such an event we shall immediately repair the leakages at our cost.
We also undertake that if any damages are caused to DEWAs equipments due to the leakages and/or while any
repair works are carried out we shall compensate such damages, failing which DEWA reserves the right to take any
appropriate measures deemed fit.
__________________________________________
DATE:
__________________________________________
__________________________________________
__________________________________________
TEL. NO. :
__________________________________________
4
5
6
7
8
9
10
11
Description
Reinforced concrete attic slab above entire substation/ring
main unit
A clear depth (void) of 600mm between attic slab and floor
slab.
An access aluminum lowered door of 1200x600mm to above
clear depth (void) from outside substation
Water proofing of attic slab , floor slab above attic slab and
vertical side walls
Drain pipe of 1.5 projecting out of the attic slab
Screed in slope towards drain
Water proofing of All pipe joints, traps etc running in wet
areas
Lighting inside the void space
Drawings showing the above details attached
Guarantee letter
Any deviation of above
Submission should be duly filled and signed with tick mark is must.
328
Remarks
Name of Consultant/Consultant
Signature of authorized person
329
Seal
330
331
Description
1000 kVA
Transformer
Maximum Total
Connected Load
permitted
(Diversity Factor
= 1.0)
Maximum
permissible
Starting Current
of each
compressor /
motor
Sequential start
of chillers /
compressors
650 kW
950 kW
400 A
(Higher values may
be permitted subject
to submission of
specific justifications)
540 A
(Higher values may
be permitted subject
to submission of
specific justifications)
Requirement of
starters
Confirme
d
( Tick)
1500 kVA
Transformer
Confirmed
( Tick)
Address:_______________________
Page 1 of 2
333
Page 2 of 2
334
UNDERTAKING
(Ground Floor Split Substation)
335
To
Dubai Electricity & Water Authority
I shall be fully responsible for transportation of transformers and other equipment from DEWAs truck and
placing it on the foundations in the substation room (or vice versa), as required by DEWA.
2.
I shall arrange adequate insurance to cover the damage to DEWA equipment while handling by our
personnel as mentioned in (1) above. [The cost of one transformer is Dhs.110, 000/- (approx.) and weight is
about 6.5 Ton].
3.
I shall not modify any parts of the building that affect the access to DEWA equipments. I shall not make any
alteration / modification in substation without the prior approval of DEWA.
4.
DEWA will not be held responsible for any delay in restoring power caused due to non-availability of the
equipment transportation arrangement. The responsibility for such delay will be mine.
5.
My contact address/telephone number (of an authorized representative) will always be available at the
project site.
6.
In the event that I transfer or lease the property to any other party, the above conditions will be made known
to that party.
8.
All future maintenance of substation (civil works) including repairs / replacement of the door will be carried
out by me.
------------------Signature
Name:
P.O. Box.
Telephone No.
Telefax No.
Place:
_______________
______________
_______________
_______________
Contact Person
NB: Owners Passport Copy To Be Attached
Name:
_______________
P.O. Box
_______________
Telephone No. _______________
Telefax No.
_______________
NK:IA/08.04.02
336
337
UNDERTAKING
Transformer Room in Basement
To
Dubai Electricity & Water Authority
338
I, ____________________________ (full address given under) the owner of the above building agree t
the following conditions:
1. I shall be fully responsible for transportation of transformers and other equipment from DEWAs truck and placing it on th
foundations in the substation at the basement (or vice versa), as required by DEWA.
2. When RMU is located in the ground floor, I shall make the arrangement to lay the HV cable from the transformer located at th
basement to the RMU in the ground floor. Facility for supporting the cables will be provided through out the HV cable route an
we shall not allow any other services underneath.
3. I shall make the arrangement to lay the LV single core cable from the transformer located at the basement to our LVDBs in th
LV room and we shall terminate those cables in our LVDBs end.
4. In the eventuality of cable fault, I shall make arrangement similar to that provided at the time of initial installation as given in (
and 3) above.
5. I shall arrange adequate insurance to cover the damage to DEWA equipment while handling by our personnel as mentioned i
(1) above. [The cost of one transformer is Dhs.110, 000/- (approx.) and weight is about 6.5 Ton].
6. I shall not modify any parts of the building that affect the access to DEWA equipments. I shall not make any alteration
modification in substation without the prior approval of DEWA.
7. DEWA will not be held responsible for any delay in restoring power caused due to non-availability of the equipmen
transportation arrangement. The responsibility for such delay will be mine.
8. My contact address/telephone number (of an authorized representative) will always be available at the project site.
9. In the event that I transfer or lease the property to any other party, the above conditions will be made known to that party.
10.All future maintenance of substation including repairs / replacement of the door will be carried out by me.
------------------Signature
Name:
_______________
P.O. Box.
______________
Telephone No. _______________
Telefax No.
_______________
Place:
Contact Person
Name:
_______________
P.O. Box
_______________
Telephone No. _______________
Telefax No.
_______________
NK:IA/08.04.02
339
For
Shared Substations
Undertaking
To:
Dubai Electricity & Water Authority
P. O. Box 564
Dear Sirs,
....
Subject: Electric supply to my Residential/
Commercial
Building
on
Plot
No.
..at
I, ...
(Full address given under) the owner of the
above, building agree to the following
conditions:-
: /
..................... ...........................
....................................................
) (
: 1. .............
.
.
2.
/
3.
.
4.
.
Signature
.....................
)(Address
P. O. Box:
Telephone No.: .
Telefax No.: ..
Telex No.: .
)(
. ......................................................
: ...............................................
: ...............................................
: ...............................................
)(Contact Person
Name: ...
P. O. Box: .
Telephone No.: .
Telefax No.: ..
) (
: ......................................................
.: ....................................................
: .....................................................
....................................................
340
341
Partys HV switchgear
342
Page 1 of 2
343
344
Note :
Sikka / road should have a minimum clear width of 6.1m. However if the proposed substation
space is less than 12m away from the main road then the sikka should have minimum clear
width of 3.05m.
345
346
347
Sl.No.
1
2
3
Condition
Normal
Loss of Incomer-1
Loss of Incomer-2
IC-1
I
O
I
Bus coupler
O
I
I
IC-2
I
I
O
7. RMU room must have cross ventilation (2 sides) with aluminum louvers / doors
8. 3-2 of clear depth from finished floor level (FFL) to be provided for trench and for cable entry to the
RMU room.
9. FFL of the RMU room should be higher (6 to 12) with respect to adjacent ground level (on the other side
of substation door).
Note : If RMU space/room is located on sikka, sikka should have a minimum clear width of 3.05 m as long as
proposed substation is not more than 12m away from the main road. Otherwise, the sikka should have minimum
clear width of 6.1m.
349