Beruflich Dokumente
Kultur Dokumente
BACKGROUND OF
THE PROBLEM
80
Me ga Ohm s
PROJECT TITLE
PROBLEM
PURPOSE / GOAL
40
30
PROBLEM
INVESTIGATION
JAN ' 09
JUN ' 09
AUG ' 09
Cable
spliced
portion
Bell-mouth STN. 435
STN. 87
SOLUTION
FORMULATION
A104R/ B111R
Junction
STN. 80
IMPLEMENTATION
IMPLEMENTED
COUNTER
MEASURE
Remove old taping
AVGalaura-DM
50
INVESTIGATION /
DIAGNOSIS
RRBordo-MGR
60
10
ELECTRICAL DEPARTMENT
MAINTENANCE DIVISION
5. Sep. 20, 2011 - Verification activity from at spliced portion at STN 80 revealed spliced portion is good
insulation deterioration has already creep from STN 80 to yard center.
70
20
DEPARTMENT
DIVISION
Cleaning of cable
Commisioning
Splicing of cable at junction box
Insulation test at bell mouth
7. October 22, 2011 - Solution option 2 yeild remarkable results up to 500 M.
Retaping of splice
Before:
After:
RESULT AND
CONCLUSION
4. A year after the implementation of first countermeasure low insulation resistance problem recu
8. TANGIBLE BENEFITS
ENCOUNTERED
PROBLEM
BENEFITS
Total savings: P 2,050,000.00 - 220,000.00 = P 1,830,000.00
SCHEDULE OF
ACTIVITIES
2009
2010
SEP 2011
Problem Recur
OCT 2011
Present
2nd solution
Project
: Hydrated Lime Plant PLC Replacement Project
Department : Electrical
Subject
: Gantt Chart of Activities
LEGEND:
- actual work
- plan work
ACTIVITY
March
Weeks
1
April
Weeks
4
May
Weeks
4
Weeks
4
June
Days
2###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###1
1) Material Preparation
1.01) Evaluation of existing PLC condition
1.02) Data gathering of existing PLC system configuration
1.03) Preparation of DPRs
1.04) Approval ( PO items)
1.05) Delivery / arrival of materials at PSC warehouse
a) Installation materials
b) PLC modules and accessories
2) Engineering Works
2.01) Generation of construction drawings
2.02) Preparation of wiring schedule
2.03) Preparation of wire markers
2.04) Programming of ladder diagram in SIEMENS PLC
2.05) Checking / debugging of PLC program
2.06) Wiring PLC front connectors
2.07) Loop checking of PLC wirings
3) Cabling works
3.01) Layout of power cable from BLP UPS to HLP HL41 panel
3.02) Layout of control cable in HLP (HL 41-45)
4) Fabrication / Installation works
4.01) Installation of MCCB for PLC supply (from BLP UPS)
4.02) Insulation test of power and control cables
4.03) Termination works of control cable (FUJI PLC section)
4.04) Assemble new PLC modules/hardware at HL 41 Panel
4.05) Installation of terminal blocks and PVC ducts in HL 41
4.06) Installation of wired PLC front connectors in modules
4.07) Termination of PLC wirings to HL 41 terminal blocks
4.08) Loop checking of PLC external signals
5) Commissioning
5.01) No load test
5.02) Operation test
5.03) End / Turnover
July
Days
NO HLP OPERATION
COMPLETED
PERCENT
DATE
3
REMARKS
(%)
(mm.dd.yyyy
)
100
100
100
100
03.07.2011
03.07.2011
03.09.2011
04.25.2011
100
04.28.2011
100
06.11.2011
100
04.11.2011
100
04.11.2011
100
04.25.2011
100
04.20.2011
100
05.25.2011
100
06.18.2011
100
06.20.2011
100
04.16.2011
100
04.20.2011
100
04.14.2011
100
05.02.2011
100
05.16.2011
100
06.18.2011
100
05.17.2011
100
06.20.2011
100
06.25.2011
100
06.28.2011
100
06.30.2011
100
07.01.2011
100
S
70
67
78
T
1.9
2.8
3.9
23.9
38.6
35
Mega Ohms
R
JAN ' 09
JUN ' 09
AUG ' 09
JUN ' 09
R
S
T
JUN ' 09
AUG ' 09
1,234 T
898 T
112 T
2,244
15,113,340php
socomec
mitsubishi
ss / mo (@7,300php/T)
9,009,660 php
ss / mo (@6,800php/T)
6,103,680 php
### php