Beruflich Dokumente
Kultur Dokumente
INTRODUCTION
II.
cos
(1)
where
(2)
(3)
1
(4)
(5)
cos
Value (p.u.)
Parameter
Value (p.u.)
.1
.01
.098
.014
5
4
3
2
1
.025
.05
.075
.1
time (s)
Rr
(p.u.)
Xr
(p.u.)
Xm
(p.u.)
0.0787
0.0092
0.0547
3.642
If
(p.u.)
If
(p.u.)
3rd
cycle
5rd
cycle
1.95
0.81
Manufacturer
P
(MW)
Nordex
Negmicon
1.5
0.0227
0.0795
0.0156
0.0597
3.755
0.82
0.2
Negmicon
0.0225
0.173
0.008
0.13
3.428
1.84
1.31
WindWorld
0.6
0.0197
0.1271
0.0089
0.0956
4.667
2.01
1.21
Bonus
0.6
0.0065
0.0894
0.0093
0.1106
3.887
1.99
1.1
Bonus
0.0062
0.1362
0.0074
0.1123
3.911
2.16
1.48
Vestas
1.66
0.0077
0.0697
0.0062
0.0834
3.454
2.93
1.75
0.0062
Xs
(p.u.)
Phase a
Phase b
Phase c
.05
.1
.15
.2
time (s)
3.5
2
,
B. DFIG
Fig. 3 shows a DFIG. According to this figure, this type
of IG has a wound rotor which is connected to the
distribution system through power electronics converters.
With this structure, the DFIG is able to operate at the speed
range from -30% to +30%. Besides, the power electronics
provide the generator with the ability to control the reactive
power independent to its active power. Due to these
advantages, almost all IGs manufactured these days to be
used in conjunction with wind turbines are DFIGs.
Mechanical torque
Substation
AC/DC
DC/AC
Crowbar
.04
.08
.12
.16
.2
time (s)
If
(p.u.)
3rd
cycle
5rd
cycle
3.642
0.14
0.01
0.0597
3.755
0.01
0.00
0.008
0.13
3.428
0.66
0.24
0.1271
0.0089
0.0956
4.667
0.44
0.1
0.0065
0.0894
0.0093
0.1106
3.887
0.34
0.06
0.0062
0.1362
0.0074
0.1123
3.911
0.69
0.224
0.0077
0.0697
0.0062
0.0834
3.454
0.63
0.14
Manufacturer
P
(MW)
Rs
(p.u.)
Xs
(p.u.)
Rr
(p.u.)
Xr
(p.u.)
Xm
(p.u.)
Nordex
0.0062
0.0787
0.0092
0.0547
Negmicon
1.5
0.0227
0.0795
0.0156
Negmicon
0.0225
0.173
WindWorld
0.6
0.0197
Bonus
0.6
Bonus
Vestas
1.66
III.
PF
.93
.94
Load
L3
L4
PF
.93
.94
A. Phase-to-phase faults
As Fig. 5 shows, the feeder is protected by two breakers,
B1 and B2, and the laterals L1 to L4 are protected by fuses.
Each breaker is associated with two O.C. relays, one shorttime delay and one inverse-time. The short-time delay
elements are set to protect 80% of their sections, and the
inverse-time relays are set to be in coordination with the next
protection elements, and act as back-up. For further
illustration, the pick-up current of the short-time delay
element of B2 is set equal to the fault current at F2, and the
pick-up current of the instantaneous relay of B1 is set equal
to the fault current at F1. In addition, TSM of the inversetime relay of B2 is set so that B2 act as back-up for the fuse
at L3 in case of fault at F4. Similarly, the TSM of the
inverse-time relay of B1 is set to act as back-up for the shorttime delay element of B2 in case of fault at F3. Table 5
shows the relays settings, and Table 6 shows their operation
times for different fault locations when there is no DG in the
system.
Table. 5 Relays settings
B1
B2
Inverse-time relay
Ipick-up (A)
TSM
320
.2775
240
.1447
Table. 6 O.C. devices current and operation times for various fault
locations when there is no DG unit
Fault
F1
F2
F3
F4
IR1(A)
4440
4038
4190
3996
TR1(s)
.05
.745
.73
.75
IR2(A)
4030
4187
4002
TR2(s)
.05
.05
.35
6000
2000
0.05
0.1
0.15
0.2
0.25
.3
time (s)
9MW Induction DG
Coordination boundary
2000
0.05
0.1
0.15
0.2
0.25
IV.
.3
time (s)
B. Phase-to-ground faults
Table 7 shows the LG fault current at F3 for different
scenarios, and its increment due to the insertion of 9MW
SFIG. According to this table, in most cases, in contrast to
what was expected, the SFIG decreased the single phase to
ground fault few percents. Only in four scenarios in which
substation transformer (Ts) at low voltage side has Yg
connection, the SFIG has positive contribution to fault, and
its maximum contribution is 6.7%.
In order to investigate the impact of the SFIG on the
coordination consider the worst condition in which it has
6.7% contribution, and imagine that B1 and B2 are equipped
with inverse O.C. relays (with IEC 60255 characteristic
equation) for ground fault protection with the settings
tabulated in Table 8. In this case, when there is no DG, for
phase-to-ground fault at F3, B2 operates at .073 sec. and B1
operates at .32 sec., and there is a .25 sec. interval between
main and back-up operation. When a 9MW SCIG is
embedded at substation, the ground fault current is increased
from 5528A to 5900A. In this case, B2 as the main
protection operates at .0728 and B1 as the back-up operates
at .319 sec, and still there is a .246 sec. interval between the
main and back-up protection, and the coordination
maintains.
Ts
YY
YD
YYg
DY
DD
DYg
YgYg
YgY
YgD
678
678
693
678
678
5528
3973
678
678
Fault current
(A)
(9MW IG,
TIG: DYg)
665
665
676
665
665
5900
4153
665
665
Incremental
current due to IG
(%)
-1.92
-1.92
-2.45
-1.92
-1.92
6.73
4.53
-1.92
-1.92
Fault current
(A)
(9MW IG,
TIG: YgYg)
667
667
678
667
667
5753
4082
666
667
CONCLUSION
[2]
[3]
[4]
[5]
[6]
TSM
.05
.2
Due to the short contribution time window in phase-tophase faults, the IG has no impact on coordination unless
there are instantaneous elements in protection system.
In case of single phase faults, simulations showed that
the maximum contribution of the SFIG is limited to 7% of
original fault current which is not sufficient to cause
miscoordination.
4000
Ipick-up (A)
80
60
B1
B2
4000
Incremental
current due to
IG (%)
-1.62
-1.62
-2.16
-1.62
-1.62
4.07
2.74
-1.77
-1.62
[7]
[8]
[9]