Beruflich Dokumente
Kultur Dokumente
6-1
Figure 6.1
The prototype wall consists of nails and tiebacks at regularly spaced vertical and horizontal intervals.
Reducing three-dimensional problems with regularly spaced reinforcement to two-dimensional
problems involves averaging the reinforcement effect in three dimensions over the distance between
the reinforcement. Donovan et al. (1984) suggest that linear scaling of material properties is a simple
and convenient way of distributing the discrete effect of reinforcement over the distance between
reinforcement in a regularly spaced pattern.
6-2
Example Applications
This approach is used in this analysis, based upon a one-foot problem width and the spacing for
reinforcement shown in Table 6.1. See Section 1.9.4 in Structural Elements for a description of
the properties that are scaled using this approach.
Table 6.1
Row
1
2
3
4
5
6
7
Reinforcement spacing
Spacing (feet)
4.5
3.5
9.0
4.5
4.5
4.5
4.5
Note that the spacing is the horizontal reinforcement spacing (in feet) for each of the seven rows
for which the support components are installed.
The nails and tiebacks are assumed to be homogeneous, isotropic, linearly elastic materials represented as cables with the properties shown in Table 6.2:
Table 6.2
Property
Row 1 Nails
Row 2 Nails
Row 3 Nails
Grouted Tieback
Ungrouted Portion
4.2 10
4.2 10
4.2 10
4.2 10
4.2 10
4.2 10
Area (ft )
Bond Stiffness (lbf /ft/ft)
8.5 10
-3
6.3 10
8.5 10
-3
6.3 10
8.5 10
-3
6.3 10
.0103
.0103
6.3 10
8.5 10
-3
6.3 10
5000
5000
6000
9000
6000
73620
73620
73620
222750
222750
73620
The pressure dependency of the grout bond strength for the soil nails and tiebacks is neglected
for this analysis. See Section 9 for an example that includes the pressure dependency of the bond
strength.
The tiebacks are assumed to be installed and pretensioned to a lockoff load of 168.0 kips before
further excavation is performed.
6-3
Poissons ratio
0.2
moment of inertia
area
0.333 ft2
Note that the Youngs modulus is adjusted in the FLAC analysis to account for plane-strain conditions
by dividing by (1 2 ). A value for E of 5.00 108 psf is used in the analysis.
The soil is assumed both to be homogeneous and to behave as a Mohr-Coulomb material with the
following properties.
density
3.63 slugs/ft3
friction
36
cohesion
dilation
7.5
bulk modulus
shear modulus
6-4
Example Applications
(*10^2)
1.150
1.050
1-Jun-15 14:25
step
0
-5.333E+01 <x< 1.333E+01
5.100E+01 <y< 1.170E+02
0.950
Grid plot
0
2E 1
0.850
0.750
0.650
0.550
-3.500
-2.500
-1.500
-0.500
0.500
(*10^1)
Figure 6.2
Roller-boundary conditions are applied to the bottom and side boundaries. The ground surface is
free (i.e., no applied stress). An initial stress state given by a coefficient of earth pressure at rest of
0.45 is assumed. The problem is then timestepped to equilibrium.
Excavation Stage I
The first increment of excavation is modeled by deleting elements to a depth of 5 feet. At the same
time, liner elements representing the shotcrete face support and cable elements representing the
first row of soil nails are introduced. The model is stepped to equilibrium for this stage.
Excavation Stage II
The next increment is modeled by deleting elements equivalent to 2 feet of excavation. Again,
shotcrete and nail support are installed via liner and cable elements, and the problem is stepped to
equilibrium.
6-5
(*10^2)
1.150
1.050
18-Jun-15 12:35
step 69030
-5.333E+01 <x< 1.333E+01
5.100E+01 <y< 1.170E+02
0.950
Cable Plot
Axial Force on
Structure
Max. Value
# 5 (Cable) -1.435E+05
# 6 (Cable) -1.860E+05
Boundary plot
0
0.850
2E 1
0.750
0.650
0.550
-3.500
-2.500
-1.500
-0.500
0.500
(*10^1)
Figure 6.3
6-6
Example Applications
(*10^2)
1.150
1.050
1-Jun-15 14:25
step 142021
-5.333E+01 <x< 1.333E+01
5.100E+01 <y< 1.170E+02
0.950
Grid plot
0
2E 1
0.850
0.750
0.650
0.550
-3.500
-2.500
-1.500
-0.500
0.500
(*10^1)
Figure 6.4
6-7
6.3 Results
The results presented in Figures 6.5 through 6.8 represent the state of the analysis following all
excavation and support installation (i.e., the end of the analysis).
Figure 6.5 plots the actual axial forces in the soil nails and tiebacks at the last stage. Note that
when spacing is specified with the STRUCTURE prop command, the actual forces (and moments)
are displayed in printed and plotted output for spaced structural elements.
Figures 6.6 and 6.7 plot the actual forces along the tieback and soil nails, respectively, at the last
stage. These plots are created using the FISH function tabforce contained in WALL.FIS.
Scaled values for axial force are accessed directly in FLAC by the FISH offset $kelfax. These
forces must be multiplied by the spacing to obtain the actual values, which are then stored in tables.
The table numbers for the soil nail forces correspond to the excavation stages in which the nails were
installed. Note that the peak value in the tieback force distribution plot in Figure 6.6 corresponds
to the maximum axial force in cable ID 6 (184.6 kips) (shown in Figure 6.5).
Figure 6.8 shows the displacement vectors at the last stage and indicates the effect of the pretensioning in the tieback on reducing the movement of the wall.
Intermediate results at the end of each stage, as well as displacement and loads in the shotcrete,
are also available but are not presented here. Further discussion on this application is available in
Lorig (1991).
JOB TITLE : FULL-SCALE TEST WALL IN SAND
(*10^2)
1.150
1.050
4-Jun-15 15:33
step 142021
-5.333E+01 <x< 1.333E+01
5.100E+01 <y< 1.170E+02
0.950
Boundary plot
0
2E 1
Cable Plot
0.850
Axial Force on
Structure
Max. Value
# 2 (Cable) -6.277E+03
# 3 (Cable) -3.656E+03
# 4 (Cable) -1.133E+03
# 5 (Cable) -1.475E+05
# 6 (Cable) -1.846E+05
# 7 (Cable) -1.191E+04
# 8 (Cable) -1.395E+04
# 9 (Cable) -1.356E+04
#10 (Cable) -1.080E+04
Cable Plot
Shear Spring Bond Yields
0.750
0.650
0.550
-3.500
-2.500
-1.500
-0.500
0.500
(*10^1)
Figure 6.5
Actual axial tensile forces in the soil nails and tieback at the end
of the analysis
6-8
Example Applications
02
LEGEND
1.800
1-Jun-15 14:25
step 142021
1.600
Table Plot
Axial Tensile Force (kips)
1.400
1.200
1.000
0.800
0.600
0.400
0.200
-40
-35
-30
-25
-20
-15
Figure 6.6
01
LEGEND
1-Jun-15 14:25
step 142021
1.200
Table Plot
Stage I nail
1.000
Stage II nail
Stage III nail
0.800
Stage IV nail
Stage V nail
0.600
Stage VI nail
Stage VII nail
0.400
0.200
-10
-8
-6
-4
-2
Figure 6.7
6-9
(*10^2)
1.150
1.050
1-Jun-15 14:25
step 142021
-5.333E+01 <x< 1.333E+01
5.100E+01 <y< 1.170E+02
0.950
Displacement vectors
scaled to max = 5.000E-02
max vector = 2.263E-02
0
0.850
1E -1
Boundary plot
0
2E 1
0.750
0.650
0.550
-3.500
-2.500
-1.500
-0.500
0.500
(*10^1)
Figure 6.8
6.4 References
ASCE (American Society of Civil Engineers). Full Scale Wall Tests Soil Nailing in Sand, Civil
Engineering, 58(5) (1988).
Donovan, K., W. G. Pariseau and M. Cepak. Finite Element Approach to Cable Bolting in Steeply
Dipping VCR Stopes, in Geomechanics Applications in Underground Hardrock Mining, pp. 6590. New York: AIME (1984).
Lorig, L. J. Analysis of Novel Retaining Structures Using Explicit Finite Difference Codes, in
Computer Methods and Advances in Geomechanics, pp. 157-164. Rotterdam: A. A. Balkema
(1991).