Beruflich Dokumente
Kultur Dokumente
A person named as such in the Part II of the Conditions of contract which once
given cannot be changed without the consent of the Contractor (sub clause
1.1(a) (i).
Clause
Failure
of 6.4
Engineer
to
supply within
reasonable time
drawings
notified
by
contractor.
Adverse
12.2
physical
obstructions.
Discovery
fossils
of 27.1
Tests
not 36.5
provided for
Uncovering as 38.2
per engineers
instructions
Employer
to Engineer
pay
As notified by To
Engineer
determine
Eot/ costs,
notify the
employer
and
contractor.
As notified by Suggest
Engineer after action and
consultation
determine
with Employer Eot and cost
and contractor
in
consultation
and notify
contractor
and
employer
As notified by Give
engineer
instructions
to preserve
and notify
Eot
and
costs after
consultation
.
As notified by Tests
in
engineer
addition to
those
provided for
Cost of such Determine
uncovering
the
found to be additional
contract
cost in case
compliant
the works
found to be
Contractor
To notify
Engineer
(6.3)
regarding
disruption
of progress.
Forthwith
give notice
to engineer.
Preserve
articles,
notify
engineer
and follow
instructions
X
Uncover
and make
good.
Claim costs
if
works
found to be
contact
compliant
Suspension on 40.2
the instructions
of the Engineer
Delay
in
handing
over
possession
of
site
Variations
claims
and
Termination by
Employer/
As notified by Determine
Engineer after Eot
and
consultation
costs
in
consultation
with
employer
and
contractor
42.2
As determined Determine
by the Engineer Eot
and
in consultation costs due to
Failure of
the
Employer to
hand over
as
much
possession
of site as
required
under
contract to
commence
works
52
As determined Make
&53.5
by
Engineer assessments
after
due as
per
consultation
contract
provisions
and
with
due
consultation
with
the
employer
and
contractor
63.3/65. As determined Engineer to
8/69.3/ by the engineer make
contract
compliant
Suspend the
work
as
instructed
by
the
engineer
and claim
costs and
Eot
Notify the
engineer.
Prepare and
submit
claims after
completion
of
all
required
formalities
Notify the
engineer
contractor
69.4
in the event of
the contractor
terminated by
employer
or
contractor
or
due to special
risks
As determined
by Engineer
determinati
on
in
consultation
with
employer
and
contractor
Determine
Notify the
after
due engineer
consultation
9 INDEMINITY BY EMPLOYER:
The Employer is required to indemnify the Contractor, against:
a) Claims, arising out of the Risks attributed to the Employer.
( exceptions sub clause 22.2)
b) Death or injury to any person.
c) Responsibilities as specified under clause 26 for obtaining any
planning ,zoning or other similar permissions for the works to
proceed
22.3 Indemnity by Employer
The Employer shall indemnify the Contractor against all claims,
proceedings, damages, costs, charges and expenses in respect of the
matters referred to in the exceptions defined in Sub-Clause 22.2
22.2 Exceptions
The "exceptions" referred to in Sub-Clause 22.1 are:
(a) the permanent use or occupation of land by the Works, or any part
thereof,
(b) the right of the Employer to execute the Works, or any part thereof,
on, over, under, is or through any land,
(c) damage to property which is the unavoidable result of the execution
and completion of the Works, or the remedying of any defects therein, in
accordance with the Contract, and (95)
(d) death of or injury to persons or loss of or damage to property
resulting from any act or neglect of the Employer, his agents servants or
other contractors, not being employed by the Contractor, or in respect of
any claims, proceedings, damages, costs, charges and expenses in
respect thereof or in relation thereto or, where the injury or damage was
contributed to by the Contractor, his servants or agents, such part of the
said injury or damage as may be just and equitable having regard to the