Beruflich Dokumente
Kultur Dokumente
The project also includes 800m long approach bridge from the north (Bandra),
1600m long approach bridge from the South (Worli) and 811m long Link bridge
to Worli.
The Cable Stayed bridges are designed to be built by cantilevering method and
the approach bridges are designed for span-by-span method using an overhead
launching gantry. The Link bridge connecting main bridge to Worli is in two
parts, a PSC girder bridge with in-situ deck slab and a precast segmental bridge.
(Refer
Table
1a,
Fig.
1b).
Approach
Road with
Toll Plaza
Part 2
North End
Approach
bridge from
Bandra
Precast
segmental
continuous
box girder
Bandra Cable
Stayed
Bridge
Precast
segmental
South End
Approach
bridge
Precast
segmental
continuous
box girder
Part 3
Span
Configuration
546m
Worli Cable
Stayed
Bridge
Precast
segmental
Part 4
South End
Approach
bridge to
Worli
Precast
segmental
continuous
box girder
Part 5
Link Bridge
to Worli
Precast
segmental
continuous
box girder
Erection
Method
Span by span
using
overhead
Launching
Gantry
Balanced
cantilever
using Lifting
frame
(derrick).
50m back
spans by
Launching
gantry
Span by span
using
overhead
Launching
Gantry
Stayed
cantilever
using Lifting
frame
(derrick).
50m back
spans by
Launching
gantry
Span by span
using
overhead
Launching
Gantry
Span by span
using
overhead
Launching
Gantry
A1 to
P17
50m x 16
P17 to
P21
50m +
250m +
250m +
50m
P21 to
P25
50m x 4
P25 to
P32
50m +
50m +
150m +
50m +
50m
P32 to
P60
50m x 28
R1 to R4,
R4 to
R12
50m x 3,
30m x 8
PSC girders
PSC girder
erection with
in-situ deck
slab
R12 to
R29
24m x 17
+ 13m x
1
(Table 1a)
BANDRA
A1
P6
P12
600m
350m
BANDRA CABLE STAY
WORLI CABLE STAY
500m
4X50=200m
PRECAST SEGMENTAL
150m
(BALANCED CANTILEVER) (SPAN-BY-SPAN)
PRECAST SEGMENTAL
P19
(FORWARD CANTILEVER)
WORLI
P17
R
AD
ND
RO
BA
6m CH ZA
54 OA LA
P
PR L L
AP TO
&
811m
LINK BRIDGE
WORLI
A1
NO
0m
80
H
RT
AP
PR
OA
CH
BR
IDG
E
P19
600m
BANDRA CABLE STAY
200m
350m
WORLI CABLE STAY
1400m
SOUTH APPROACH BRIDGE
500m
250m
126m
250m
50m
2m DIAMETER PILE
37200
(7X4=28 NOS.)
19x15.2mm
TENDONS (TYP.)
PLAN
Tower
CABLE ANCHOR
ZONE 10 LIFTS
3m (TYP.)
UPPER TOWER
24 LIFTS
70m
31m
LONGITUDINAL ELEVATION
LOWER TOWER
8 LIFTS
25m
TRANSVERSE ELEVATION
CL OF TOWER
C
L OF SOUTH BOUND
C
L OF BWSL
C
L OF NORTH BOUND
Though the lower and upper tower legs are RC sections, tower head cable
anchorage zone is also provided with transverse and longitudinal PT bars to
resist local splitting forces caused tension in stay cables. (Fig. 2.2f). The tower
transverse diaphragm, connecting individual legs at deck level, is prestressed
with 10 nos. 19-15.2mm transverse PT cables. (Fig. 2.2g)
L
L
OF TOWER
5735 (VARIES)
1500
2220
2500
T
950
4177 (VARIES)
2500
36 P.T.BARS
JACKING FORCE 7
Considering the complexity of upper tower legs and the time required, DOKA
automatic
climbing
formwork
SKE100
was
adopted
to
construct
the
R.L. +72.356
('X' = + 43.990)
R.L. +60.796
('X' = + 32.430)
R.L. +49.236
('X' = + 20.870)
R.L. +37.676
('X' = + 9.310)
ELEVATION
Deck
The superstructure comprises of twin precast concrete triple cell box segments
with a fish belly cross sectional shape, identical to the approaches. BWSL deck is
designed to carry total eight lanes of traffic, four in each direction on its twin
independent bridges.
22.7m
15m
15m
3m
3m
22.7m
SEGMENT
11
13
15
10
12
14
16
17 18 19
20 21 22
.
(Fig. 2.3.2c Temporary PT bar locations in segments during construction)
The deflections of the stayed cantilever decks were continuously monitored
during every erection stage. The surveys were done in early morning as well as
in the afternoon to ascertain the effect of temperature and wind on the deck
elevation and plan alignment. A continuous record of surveys was maintained
and compared with theoretical profiles. Apart from global profile survey, the
stage deflections of cantilever tip were also surveyed and compared with theory
deflections. During erection, the observed deviations, between surveyed deck
profile and theory stage profile, are generally the result of sum of 1) difference
between actual structure behaviour and computer model results because of
uncertainties in material properties like elastic modulus, weights etc.2) erection
setting-out errors 3) segments casting errors 4) environmental effects due to
changes in temperature, changes in wind magnitude and direction. The proper
record of casting errors, erection errors and surveys performed at different time,
is helpful in separating and comparing the actual structural behaviour against
computer model results. During erection, after evaluating the deck behaviour
and surveyed alignment, separate instruction sheets were issued for each cycle,
which defined the amendments in cable forces to fine adjust the alignment.
These deviations were later incorporated in the structural model while designing
the Fine tuning operation after completion of deck and prestressing.
During the erection, the length of stayed cantilever deck reached as much as
215m and maximum stage deflection of cantilever was 225mm.
Stay Cables
Stay Cables used are Parallel Wire Stay Cables. They were manufactured by
Shanghai Pujiang Cable Co. Ltd China. Each cable consists of a group of
different number of galvanized steel wires. Each wire is made up of high tensile
steel having UTS of 1650Mpa. The diameter of single wire is 7mm with a
breaking load of 6.3MT. Six different sizes of cables are used in the Bandra cable
stayed portion. Six different types used are of 61, 73, 85, 91, 109 and 121
numbers steel wires. The seventh type with 139 nos. of wires is used in Worli
cable stayed bridge. Group of these wires were extruded/packed in two layers of
HDPE (High Density Polyethylene) material to protect them from the
atmospheric effects. The cable surface is also provided with 2mm helical fillet. A
total of 264 (132 for each carriageway) stay cables are used in Bandra cable
stay with cable lengths varying from 85m minimum to nearly 250m maximum.
For Worli cable stayed bridge, total 160 (80 for each carriageway) stay cables
are used.
LM7-61
LM7-73
LM7-85
LM7-91
LM7-109
LM7-121
LM7-139
(Table 2.4a)
STEEL BOOT
TOWER
HELICAL FILLET
COLOR HIGH DENSITY
POLYETHYLENE
WIRE BUNDLE
BLACK HIGH DENSITY
POLYETHYLENE
DECK
BEARING PLATE
TENSILE END ANCHORAGE
2.5mm
2.5mm
2.5mm
2.5mm
2.5mm
2.5mm
2.5mm
Type
Min
Load
Max
Load
Lateral
Load
Movement Rotation
Range
Capacity
(MN)
(MN)
(MN)
(mm)
(rad)
P17, P21
Expansion,
Unidirectional
2.0
7.5
2.35
+125, 300
0.02
P18, P20
Sliding,
Unidirectional
7.5
18.5
4.20
+300, 300
0.02
(Table 2.5a)
Modular Expansion Joints are provided at P17, P21, with movement rating of
480mm (6*80mm).
3. Worli Cable Stayed Bridge
The cable-stayed bridge on the Worli channel is 350m in overall length between
expansion joints and consists of 150m cable supported main span, flanked by
two 50m conventional side spans. (Fig. 3a). Two pylons, with an overall height
of 55m above the pile cap level, support the superstructure by means of four
planes of stay cables in a semi-harp arrangement. Cable spacing here is also 6.0
meters along the bridge deck.
350m
50m
150m
50m
50m
55m
50m
CL OF SB
CL OF NB
19m
19m
2000 PILE
12m
12m
PYLON LEG
11.975m
11.975m
UPPER PYLON
11 LIFTS
34m
UPPER PYLON
11 LIFTS
LOWER PYLON
7 LIFTS
21m
LOWER PYLON
7 LIFTS
(Fig. 3.2c Tower leg deflection profiles at various stages of construction and
temporary struts)
The anchorage boxes were fabricated at site. The assembled boxes were then
erected on the tower legs.
Deck
Elevation [mm]
50
25
00
75
50
Chainage x [m]
25
320
310
300
290
280
270
260
250
240
230
220
210
200
190
180
170
160
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
-10
-20
30
25
50
75
00
25
50
75
The details of the deck cross-section are similar to Bandra CSB deck. The two
side spans of 50m on either side were erected by overhead launching gantry.
The gantries also erected 5 nos. cantilever segments ahead of tower at P27 and
behind tower at P30. (Fig. 3b). These 5 cantilever segments are supported by PT
cables in top slab.
The derricks were then assembled on the cantilevers at P27 and P30, for further
erection cable stayed cantilever deck. The typical segment lifting and cable
installation cycle is similar to Bandra CSB. The erection cantilevers was
monitored and compared with theory profiles defined by construction analysis.
Pier No.
Type
Min
Load
Max
Load
Lateral
Load
Movement Rotation
Range
Capacity
(MN)
(MN)
(MN)
(mm)
(rad)
P25, P32
Expansion,
Unidirectional
2.0
7.0
1.10
+75, -150
0.02
P26, P31
Sliding,
Unidirectional
0.2
12.0
1.30
+150, 150
0.02
(Table 3.4a)
Modular Expansion Joints are provided at P25, P32 with movement rating of
320mm (4*80mm).
Conclusion
The summary report presented above. covering construction aspects of the two
cable stayed bridges, viz. Bandra Cable Stay and Worli Cable Stay Bridge of the
Bandra Worli Sea Link , gives an idea about detailed planning for construction of
cable stayed bridges which includes Detailed Construction Stage Analysis, Design
and fabrication of specialist equipments, meticulous planning for survey and
monitoring with precision equipment to achieve Geometry Control to demanding
accuracy, Fabrication of special embedments like guide pipes, anchorage boxes
for Stay Cable anchorages to the complicated 3 dimensional geometry, Use of
specialized self climbing formwork for construction of pylons, use of special form
liners to achieve the architectural finish. All this was instrumental in construction
of both the stay cable bridges, and especially the Bandra Stay Cable Bridge,
which is a unique example of one of the longest span cable Stayed bridges
supported on a Single central pylon.
Acknowledgement and References
Most of the details presented in this paper were taken from Construction
Methodology documents of BWSL project, prepared by HCC and team of experts
during execution and MSRDC/DAR project drawings.