ATA SYSTEM: 27

TITLE:

FLIGHT CONTROLS - SLAT/FLAP - INSPECTION - PREVENTIVE


MONITORING OF SLAT/FLAP TRANSMISSION UNIVERSAL JOINT

**CONF ALL
MODIFICATIONS
None
REASON/DESCRIPTION/OPERATIONAL CONSEQUENCES
Some events of slat or flap lock were reported to Airbus that were caused by a disconnection in the
transmission drive system, which resulted from rupture of an universal joint assembly. Investigation
revealed that the universal joint failed as consequence of the fork end bushes wear out. The lugs of the
universal joints ruptured because the pivot pins were wearing through the fork end bushes and then
coming into direct contact with the fork end. The wear out of the fork end continued until it was
weakened to the point of rupture.
This Inspection Service Bulletin provides instructions for the periodic check of the universal joints of the
slat and flap transmission systems to monitor the wear out damage. This check is based on the
rotational backlash measurement on the specified key universal joint positions.
Accomplishment of this Inspection Service Bulletin will allow a preventive monitoring of the universal
joints for a potential wear damage, which is beneficial from operational and economic point of views.
The immediate replacement of a transmission drive system in which the universal joint is integrated can
be costly.
The Operational/Maintenance Consequences of this Service Bulletin are covered by the update of the
affected publications detailed in "PLANNING INFORMATION".
GENERAL EVALUATION

COMPLIANCE

EVALUATION TABLE
RECOMMENDED (1)
CANCELS INSPECTION SB

NO

POTENTIAL AD
RELIABILITY AFFECTED
COST SAVING
STRUCTURAL LIFE EXTN

NO
NO
NO
NO

NO
NO
NO
NO

DATE: Sep 11/15

A/C OPERATION AFFECTED


PAX COMFORT AFFECTED
ETOPS AFFECTED
VENDOR SB INVOLVED

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 1
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN
SUMMARY
NOTE (1):

Service Bulletin recommended to be accomplished to prevent significant operational


disruptions.

MATERIAL PRICE INFORMATION


MATERIAL PRICE INFORMATION TABLE
QTY PER PRICE PER
MAIN PARTS
A/C
A/C (USD)
1
See SB
Transmission Shaft

MATERIAL SET
Equipment BFEA01
Equipment BFEA02

See SB

Steady Bearing

Equipment BFEA03

See SB

Coupling Box

Equipment BFEA04

See SB

Stepback Gearbox

Equipment BFEA05

See SB

Transmission Shaft

Equipment BFEA06

See SB

Tee Gearbox

Equipment BFEA07

See SB

Bevel Gearbox

Equipment BFEA08

See SB

Steady Bearing

Equipment BFEA09

See SB

Downdrive Gearbox

Equipment BFEA10

See SB

Coupling Box

Equipment BFEA11

See SB

Transmission Shaft

Equipment BFEA12

See SB

Transmission Shaft

Equipment BFEA13

See SB

Bevel Gearbox

EFFECTIVITY
This Service Bulletin is applicable to this (these) operator(s) :
001
TIW

22P
TNO

81T
TSY

ABR

AFG

CEL

F2I

IAW

IRA

IRM

KZU

MSR

RUN

CONCURRENT REQUIREMENTS
None
REFERENCES / REPERCUSSIONS
TFU
OEB
AOT
SIL
ISI
LINE MAINTENANCE AFFECTED
LIFE LIMIT
OTHER

None
None
None
None
27.54.00054
No
None
None

NATURE OF THE WORK


AIRCRAFT
EQUIPMENT
HARD
5

YES
YES
NO

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 2
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN
SUMMARY
SOFT
OBRM

NO
NO

MANPOWER
Task 270205-832-801-001: Special Detailed Inspection of the Slat and Flap Transmission
Universal Joints on LH and RH Sides
TOTAL MANHOURS
48.00
ELAPSED TIME (HOURS)
11.50
Task 270205-833-801-001: Replacement of the Equipments linked to the affected Slat and Flap
Transmission Universal Joints on LH and RH Sides
TOTAL MANHOURS
70.00
ELAPSED TIME (HOURS)
42.00
APPENDICES
None

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 3
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN
SUMMARY

**CONF ALL

A
Z600

Z500

SLAT KEY TRANSMISSION UNIVERSAL


JOINTS TO BE INSPECTED

FLAP KEY TRANSMISSION UNIVERSAL


JOINTS TO BE INSPECTED

A
LH SHOWN
RH SYMMETRICAL

A_SB_270205_5_SAAA_01_02

Figure A-FSAAA - Sheet 01

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 4
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

AIRBUS
CUSTOMER SERVICES DIRECTORATE
1 Rond Point Maurice Bellonte
31707 BLAGNAC CEDEX
FRANCE
Tel : (33) 5 61 93 33 33
Telex : AIRBU 530526F
Fax : (33) 5 61 93 42 51
ATA SYSTEM: 27

TITLE:

FLIGHT CONTROLS - SLAT/FLAP - INSPECTION - PREVENTIVE


MONITORING OF SLAT/FLAP TRANSMISSION UNIVERSAL JOINT

MODIFICATION No.:

None

This document contains AIRBUS PROPRIETARY INFORMATION and shall at all times remain the
property of AIRBUS; no intellectual property right or licence is granted by AIRBUS in connection with
any information contained in it. It is delivered on the express condition that said document and the
information contained in it shall be treated as confidential, shall not be used for any purpose other than
that for which it is hereby delivered. It shall not be disclosed in whole or in part to third parties and shall
not be duplicated in any manner (except for the purposes of performing the tasks described hereunder
and provided that any recipient of such document shall comply with the conditions herein), without
AIRBUS prior written consent.
1.

PLANNING INFORMATION

**CONF ALL
A.

EFFECTIVITY
(1)

Models
B2-203

(2)

B2K-3C

B4-103

B4-203

B4-2C

C4-203

F4-203

Effectivity by MSN
0045 0075 0080 0090 0105 0107 0117 0126 0129 0139 0151-0152 0154 0157 0160
0173 0175 0180 0183 0185 0203 0210 0212 0218 0220 0226-0227 0234-0236 0239
0244 0247 0255-0256 0259 0261 0274 0277 0292 0299 0302

(3)

Effectivity by Operator
The Operator/MSN relationship is provided for information only and is correct at the time
of issue in accordance with the information available to AIRBUS. Any future changes
resulting from transfer of an aircraft from one operator to another will not be reflected in
this list unless the Service Bulletin is revised for another reason.
OPERATOR
001
22P
81T
ABR
AFG

MSN
0203 0218
0236
0126 0157 0277 0292
0152 0220 0259
0180

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 1
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

OPERATOR
CEL
F2I
IAW
IRA
IRM
KZU
MSR
RUN
TIW
TNO
TSY
(4)

0139 0151 0173 0185 0226 0256 0299 0302


0160 0175 0244

0105 0107 0154 0183


0261 0274
0210 0227 0247

Configuration by MSN

0045
0152
0212
0255
(5)

MSN
0212
0235
0239
0080
0090
0117
0255
0075
0234
0045
0129

0075
0154
0218
0256

0080
0157
0220
0259

0090
0160
0226
0261

0105
0173
0227
0274

MSN
0107 0117
0175 0180
0234 0235
0277 0292

0126
0183
0236
0299

CONFIGURATION
001

0129 0139 0151


0185 0203 0210
0239 0244 0247
0302

Configuration definition
**CONF 001
Config. 001 is valid for all the aircraft given in the effectivity of this Service Bulletin as a
standard configuration.

(6)

Material Effectivity
MATERIAL
Equipment BFEA01

B.

QTY PER A/C


1

Equipment BFEA02

Equipment BFEA03

Equipment BFEA04

Equipment BFEA05

Equipment BFEA06

Equipment BFEA07

Equipment BFEA08

Equipment BFEA09

Equipment BFEA10

Equipment BFEA11

Equipment BFEA12

Equipment BFEA13

SEE NOTES

CONCURRENT REQUIREMENTS
None

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 2
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

C.

REASON
(1)

History
Some events of slat or flap lock were reported to Airbus that were caused by
a disconnection in the transmission drive system, which resulted from rupture of
an universal joint assembly. Investigation revealed that the universal joint failed as
consequence of the fork end bushes wear out. The lugs of the universal joints ruptured
because the pivot pins were wearing through the fork end bushes and then coming into
direct contact with the fork end. The wear out of the fork end continued until it was
weakened to the point of rupture.

(2)

Objective/Action
This Inspection Service Bulletin provides instructions for the periodic check of the
universal joints of the slat and flap transmission systems to monitor the wear out
damage. This check is based on the rotational backlash measurement on the specified
key universal joint positions.

(3)

Advantages
Accomplishment of this Inspection Service Bulletin will allow a preventive monitoring of
the universal joints for a potential wear damage, which is beneficial from operational and
economic point of views. The immediate replacement of a transmission drive system in
which the universal joint is integrated can be costly.

(4)

Operational/Maintenance Consequences
The Operational/Maintenance Consequences of this Service Bulletin are covered by the
update of the affected publications detailed in "PLANNING INFORMATION".

D.

DESCRIPTION
To accomplish this Service Bulletin it is necessary to :
Task 270205-832-801-001: Special Detailed Inspection of the Slat and Flap Transmission
Universal Joints on LH and RH Sides
(1) Do a Check of the Rotational Backlash of each Key Slat Universal Joints from
Outboard to Inboard for LH Side
(2) Do a Check of the Rotational Backlash of each Key Slat Universal Joints from
Outboard to Inboard for RH Side
(3) Do a Check of the Rotational Backlash of each Key Flap Universal Joints from
Outboard to Inboard for LH Side
(4) Do a Check of the Rotational Backlash of each Key Flap Universal Joints from
Outboard to Inboard for RH Side
(5) Depending on inspection results, do a Check of the Rotational Backlash of each
Single Slat Universal Joints located Inboard of the affected Key Slat Universal Joint on
LH Side

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 3
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(6) Depending on inspection results, do a Check of the Rotational Backlash of each


Single Slat Universal Joints located Inboard of the affected Key Slat Universal Joint on
RH Side
(7) Depending on inspection results, do a Check of the Rotational Backlash of each
Single Flap Universal Joints located Inboard of the affected Key Flap Universal Joint on
LH Side
(8) Depending on inspection results, do a Check of the Rotational Backlash of each
Single Flap Universal Joints located Inboard of the affected Key Flap Universal Joint on
RH Side
Task 270205-833-801-001: Replacement of the Equipments linked to the affected Slat and
Flap Transmission Universal Joints on LH and RH Sides
(1) Depending on inspection results, replace the Transmission Shaft linked to the
affected Slat Universal Joints on LH Side
(2) Depending on inspection results, replace the Transmission Shaft linked to the
affected Slat Universal Joints on RH Side
(3) Depending on inspection results, replace the Steady Bearing linked to the affected
Slat Universal Joints on LH Side
(4) Depending on inspection results, replace the Steady Bearing linked to the affected
Slat Universal Joints on RH Side
(5) Depending on inspection results, replace the Coupling Box linked to the affected Slat
Universal Joints on LH Side
(6) Depending on inspection results, replace the Coupling Box linked to the affected Slat
Universal Joints on RH Side
(7) Depending on inspection results, replace the Stepback Gearbox linked to the affected
Slat Universal Joints on LH Side
(8) Depending on inspection results, replace the Stepback Gearbox linked to the affected
Slat Universal Joints on RH Side
(9) Depending on inspection results, replace the Transmission Shaft linked to the
affected Flap Universal Joints on LH Side
(10) Depending on inspection results, replace the Transmission Shaft linked to the
affected Flap Universal Joints on RH Side
(11) Depending on inspection results, replace the Tee Gear Box linked to the affected
Flap Universal Joints on LH Side
(12) Depending on inspection results, replace the Tee Gear Box linked to the affected
Flap Universal Joints on RH Side
(13) Depending on inspection results, replace the Bevel Gearbox linked to the affected
Flap Universal Joints on LH Side

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 4
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(14) Depending on inspection results, replace the Bevel Gearbox linked to the affected
Flap Universal Joints on RH Side
(15) Depending on inspection results, replace the Steady Bearing linked to the affected
Flap Universal Joints on LH Side
(16) Depending on inspection results, replace the Steady Bearing linked to the affected
Flap Universal Joints on RH Side
(17) Depending on inspection results, replace the Downdrive Gearbox linked to the
affected Flap Universal Joints on LH Side
(18) Depending on inspection results, replace the Downdrive Gearbox linked to the
affected Flap Universal Joints on RH Side
(19) Depending on inspection results, replace the Coupling Box linked to the affected
Flap Universal Joints on LH Side
(20) Depending on inspection results, replace the Coupling Box linked to the affected
Flap Universal Joints on RH Side
E.

COMPLIANCE
(1)

Classification
RECOMMENDED: Service Bulletin recommended to be accomplished to prevent
significant operational disruptions.

(2)

Accomplishment Timescale
Accomplishment of this Service Bulletin is recommended, refer to compliance table.

Table 1, Config. 001 - Special Detailed Inspection of the Slat and Flap Transmission Universal Joints
on LH and RH Sides
Condition
Action
Compliance time (which occurs first)
Repetitive Interval
All aircraft

Do a special
detailed inspection
of the slat and flap
transmission
universal joints on
LH and RH sides in
accordance with
TASK
270205-832-801
001
See NOTE (*)

Threshold
25000 Flight
Cycles (FC) since
aircraft first flight

DATE: Sep 11/15

Grace Period
None

None

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 5
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Table 1, Config. 001 - Special Detailed Inspection of the Slat and Flap Transmission Universal Joints
on LH and RH Sides
Condition
Action
Compliance time (which occurs first)
Repetitive Interval
Rotational
backlash greater
than 5 degrees

Threshold
Do a check the
Before next flight
rotational backlash
of each single slat
and/or flap
universal joints
located inboard of
the affected key
universal joints on
LH and/or RH
sides in
accordance with
SUBTASK
270205-832-007
001 and/or
270205-832-008
001 and/or
270205-832-009
001 and/or
270205-832-010
001
See NOTE (**)
And
Replace the
Before 250 FC
equipments linked
to the affected slat
and/or flap
transmission
universal joints on
LH and/or RH
sides in
accordance with
TASK
270205-833-801
001
And
Repeat the special None
detailed inspection
of the slat and flap
transmission
universal joints on
LH and RH sides in
accordance with
TASK
270205-832-801
001

DATE: Sep 11/15

Grace Period
None

None

None

None

None

2500 FC

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 6
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Table 1, Config. 001 - Special Detailed Inspection of the Slat and Flap Transmission Universal Joints
on LH and RH Sides
Condition
Action
Compliance time (which occurs first)
Repetitive Interval
Rotational
backlash greater
than 3.5 degrees
and inferior or
equal to 5 degrees

Threshold
Do a check the
Before next flight
rotational backlash
of each single slat
and/or flap
universal joints
located inboard of
the affected key
universal joints on
LH and/or RH
sides in
accordance with
SUBTASK
270205-832-007
001 and/or
270205-832-008
001 and/or
270205-832-009
001 and/or
270205-832-010
001
See NOTE (**)
And
Replace the
Before 2500 FC
equipments linked
to the affected slat
and/or flap
transmission
universal joints on
LH and/or RH
sides in
accordance with
TASK
270205-833-801
001
And
Repeat the special None
detailed inspection
of the slat and flap
transmission
universal joints on
LH and RH sides in
accordance with
TASK
270205-832-801
001

DATE: Sep 11/15

Grace Period
None

None

None

None

None

2500 FC

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 7
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Table 1, Config. 001 - Special Detailed Inspection of the Slat and Flap Transmission Universal Joints
on LH and RH Sides
Condition
Action
Compliance time (which occurs first)
Repetitive Interval
Threshold
Grace Period
Repeat the special None
None
2500 FC
detailed inspection
of the slat and flap
transmission
universal joints on
LH and RH sides in
accordance with
TASK
270205-832-801
001
NOTE (*): In case of the rotational backlash is greater than 3.5 degrees, check the key universal joints
from outboard to inboard for avoiding to repeat the inspection of the same universal joints.
NOTE (**): In case of the rotational backlash is greater than 3.5 degrees, each single universal joint
located inboard must be checked (including the key universal joints). When all single universal joints
located inboard are checked, the overall inspection is completed.
Rotational
backlash inferior
or equal to 3.5
degrees

F.

APPROVAL
The technical content of this document is approved under the authority of Design
Organisation Approval No. EASA.21J.031.
If an aircraft listed in the effectivity has a modification or repair embodied that is not of
AIRBUS origin, and which affects the content of this Service Bulletin, the operator is
responsible for obtaining approval by its airworthiness authority for any adaptation necessary
before incorporation of the Service Bulletin.

G.

MANPOWER
The manpower estimates given in this Service Bulletin are based on the direct labor cost to
do the work. These estimates assume that the work will be done by experienced personnel,
and may need to be revised upwards to suit operators circumstances. The estimates do not
include the time to prepare, plan or inspect the work. Manufacture and procurement of parts
and tools, drying times for paints, sealants, etc., and general administration work are also not
included.

Task 270205-832-801-001: Special Detailed Inspection of the Slat and Flap Transmission
Universal Joints on LH and RH Sides
Get Access
6.00
On Aircraft
Do a Check of the Rotational Backlash of each Key
2.00
Slat Universal Joints from Outboard to Inboard for LH
Side
Do a Check of the Rotational Backlash of each Key
2.00
Slat Universal Joints from Outboard to Inboard for RH
Side

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 8
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Task 270205-832-801-001: Special Detailed Inspection of the Slat and Flap Transmission
Universal Joints on LH and RH Sides
Do a Check of the Rotational Backlash of each Key
2.00
Flap Universal Joints from Outboard to Inboard for LH
Side
Do a Check of the Rotational Backlash of each Key
2.00
Flap Universal Joints from Outboard to Inboard for RH
Side
Depending on inspection results, do a Check of the
8.00
Rotational Backlash of each Single Slat Universal
Joints located Inboard of the affected Key Slat
Universal Joint on LH Side
Depending on inspection results, do a Check of the
8.00
Rotational Backlash of each Single Slat Universal
Joints located Inboard of the affected Key Slat
Universal Joint on RH Side
Depending on inspection results, do a Check of the
6.00
Rotational Backlash of each Single Flap Universal
Joints located Inboard of the affected Key Flap
Universal Joint on LH Side
Depending on inspection results, do a Check of the
6.00
Rotational Backlash of each Single Flap Universal
Joints located Inboard of the affected Key Flap
Universal Joint on RH Side
Close-Up
6.00
TOTAL MANHOURS
ELAPSED TIME (HOURS)

48.00
11.50

Task 270205-833-801-001: Replacement of the Equipments linked to the affected Slat and Flap
Transmission Universal Joints on LH and RH Sides
Get Access
10.00
On Aircraft
Depending on inspection results, replace the
2.00
Transmission Shaft linked to the affected Slat Universal
Joints on LH Side
Depending on inspection results, replace the
2.00
Transmission Shaft linked to the affected Slat Universal
Joints on RH Side
Depending on inspection results, replace the Steady
2.00
Bearing linked to the affected Slat Universal Joints on
LH Side
Depending on inspection results, replace the Steady
2.00
Bearing linked to the affected Slat Universal Joints on
RH Side
Depending on inspection results, replace the Coupling 2.00
Box linked to the affected Slat Universal Joints on LH
Side
Depending on inspection results, replace the Coupling 2.00
Box linked to the affected Slat Universal Joints on RH
Side
5

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 9
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Task 270205-833-801-001: Replacement of the Equipments linked to the affected Slat and Flap
Transmission Universal Joints on LH and RH Sides
Depending on inspection results, replace the Stepback 2.00
Gearbox linked to the affected Slat Universal Joints on
LH Side
Depending on inspection results, replace the Stepback 2.00
Gearbox linked to the affected Slat Universal Joints on
RH Side
Depending on inspection results, replace the
2.00
Transmission Shaft linked to the affected Flap
Universal Joints on LH Side
Depending on inspection results, replace the
2.00
Transmission Shaft linked to the affected Flap
Universal Joints on RH Side
Depending on inspection results, replace the Tee Gear 2.00
Box linked to the affected Flap Universal Joints on LH
Side
Depending on inspection results, replace the Tee Gear 2.00
Box linked to the affected Flap Universal Joints on RH
Side
Depending on inspection results, replace the Bevel
2.00
Gearbox linked to the affected Flap Universal Joints on
LH Side
Depending on inspection results, replace the Bevel
2.00
Gearbox linked to the affected Flap Universal Joints on
RH Side
Depending on inspection results, replace the Steady
2.00
Bearing linked to the affected Flap Universal Joints on
LH Side
Depending on inspection results, replace the Steady
2.00
Bearing linked to the affected Flap Universal Joints on
RH Side
Depending on inspection results, replace the
2.00
Downdrive Gearbox linked to the affected Flap
Universal Joints on LH Side
Depending on inspection results, replace the
2.00
Downdrive Gearbox linked to the affected Flap
Universal Joints on RH Side
Depending on inspection results, replace the Coupling 2.00
Box linked to the affected Flap Universal Joints on LH
Side
Depending on inspection results, replace the Coupling 2.00
Box linked to the affected Flap Universal Joints on RH
Side
Tests
10.00
Close-Up
10.00
TOTAL MANHOURS
ELAPSED TIME (HOURS)
NOTE:

70.00
42.00

The minimum manhours necessary to accomplish this Service Bulletin are

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 10
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

those for the Inspection. Depending on the inspection result, additional


manhours can apply.
H.

WEIGHT AND BALANCE


Not Changed

I.

ELECTRICAL LOAD DATA


Not Changed

J.

REFERENCES

Aircraft Maintenance Manual (AMM)

06-21-00
27-51-23
27-51-35
27-51-38
27-81-17
27-81-21
20-55-00

Elec. Std. Practices Manual (ESPM)


K.

24-00-00
27-51-24
27-51-36
27-80-00
27-81-18

27-50-00
27-51-34
27-51-37
27-81-16
27-81-19

PUBLICATION AFFECTED
Impact on scheduled maintenance: Refer to MPD

L.

INTERCHANGEABILITY/MIXABILITY
Not Applicable

M.

SPARES
None

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 11
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

This Page Intentionally Left Blank

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 12
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

2.

MATERIAL INFORMATION

**CONF ALL
A.

MATERIAL - PRICE AND AVAILABILITY


(1)

Procurement Addresses
Vendor parts are to be procured from:

Equipment
Equipment
Equipment
Equipment
Equipment
Equipment
Equipment
Equipment
Equipment
Equipment
Equipment
Equipment
Equipment
(2)

BFEA01
BFEA02
BFEA03
BFEA04
BFEA05
BFEA06
BFEA07
BFEA08
BFEA09
BFEA10
BFEA11
BFEA12
BFEA13

UTC AEROSPACE SYSTEMS


STAFFORD ROAD, FORDHOUSES
WOLVERHAMPTON
WV10 7EH
WEST MIDLANDS
UNITED KINGDOM
Phone: +(44) 1902 624 644
Fax: +(44) 1902 787 720
E-Mail: 24-7@utas.utc.com

Price and Availability


From Equipment BFEA01 to Equipment BFEA13:
No AIRBUS kit will be provided.
Procurement terms for the equipment must be negotiated with the equipment supplier.

B.

INDUSTRY SUPPORT INFORMATION


From Equipment BFEA01 to Equipment BFEA13:
Industry support terms for the equipment must be negotiated with the equipment supplier.

C.

LIST OF COMPONENTS
No Kit

D.

LIST OF MATERIALS - OPERATOR SUPPLIED


(1)

Consumable Materials
None

(2)

Components
None

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 13
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(3)

Equipment
Equipment BFEA01

ITEM NEW PART N


CHA704-220
CHA704-220L
CHA704-221
CHA704-221L
CHA704-223
CHA704-223L
CHA704-224
CHA704-224L
CHA704-225
CHA704-225L
CHA704-226
CHA704-226L
CHA704-227
CHA704-227L
CHA704-228
CHA704-228L
CHA704-229
CHA704-229L
CHA704-231
CHA704-231L
CHA704-232
CHA704-232L
CHA704-235
CHA704-235L
CHA704-236
CHA704-236L
CHA704-239
CHA704-239L
CHA704-242
CHA704-242L
CHA704-354
CHA704-354L
CHA704-357
CHA704-357L
CHA704-369
CHA704-369L
CHA704-416
CHA704-419
CHA704-425
CHA704-427
CHA704-428
CHA704-430
5

QTY (UM) KEYWORD


1
1
2
2
1
1
1
1
1
1
1
1
2
2
2
2
1
1
1
1
1
1
1
1
1
1
2
2
1
1
2
2
1
1
1
1
1
2
1
1
1
2

ITEM OLD PART N

INT

SEE
NOTES

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 14
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-431
CHA704-433
CHA704-434
CHA704-435
CHA704-436
CHA704-437
CHA704-438
CHA704-439
CHA704-443
CHA704-444
CHA704-450
CHA704-453
CHA704-697
CHA704-700
CHA704-702
CHA704-704
CHA704-705
CHA704-706
CHA704-707
CHA704-708
CHA704-711
CHA704-714
CHA704-716
CHA704-717
CHA704-718
CHA704-720
CHA704-721
CHA704-722
CHA704-723
CHA704-726
CHA704-729
CHA704-730
CHA704-731
CHA704-732
CHA704-737
CHA704-740
CHA704-742
CHA704-743
CHA704-744
CHA704-747
CHA704-750
CHA704-752
CHA704-753
CHA704-755
CHA704-756
CHA704-757
5

QTY (UM) KEYWORD


1
1
2
1
1
1
1
1
2
2
1
1
1
2
1
1
1
1
1
1
2
2
1
1
1
1
1
2
1
2
1
1
1
1
1
2
1
1
1
2
2
1
1
1
1
2

ITEM OLD PART N

INT

SEE
NOTES

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 15
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-760
CHA704-783
NOTE:

QTY (UM) KEYWORD


2
1

ITEM OLD PART N

INT

SEE
NOTES

SHAFT
SHAFT

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA02
ITEM NEW PART N
CHA704-168
CHA704-168L
CHA704-215
CHA704-215L
CHA704-216
CHA704-216L
CHA704-217
CHA704-217L
CHA704-370
CHA704-413
CHA704-441
CHA704-449
CHA704-695
CHA704-696
CHA704-710
CHA704-719
CHA704-727
CHA704-736
CHA704-746
CHA704-754
CHA704-820
CHA722-189
CHA722-189L
CHA722-300
CHA722-392
CHA722-419
NOTE:

QTY (UM) KEYWORD


1
1
1
1
3
3
2
2
1
2
1
3
1
2
1
3
2
1
1
3
3
8
8
8
8
8

ITEM OLD PART N

INT

SEE
NOTES

BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA03
ITEM NEW PART N
CHA704-214
CHA704-214L
CHA704-424

QTY (UM) KEYWORD


1
1
1

ITEM OLD PART N

INT

SEE
NOTES

COUPLING
COUPLING
COUPLING

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 16
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-703
CHA704-728
NOTE:

QTY (UM) KEYWORD


1
1

ITEM OLD PART N

INT

SEE
NOTES

COUPLING
COUPLING

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA04
ITEM NEW PART N
CHA1001-002
CHA1001-004A
CHA1001-005
CHA1001-005A
CHA1001-006A
CHA1001-008B
CHA1001-008C
CHA701-002
CHA701-002L
CHA701-002R
CHA701-003A
CHA701-004A
CHA701-005A
CHA701-006A
NOTE:

QTY (UM) KEYWORD


2
2
2
2
2
2
2
2
2
2
2
2
2
2

ITEM OLD PART N

INT

SEE
NOTES

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA05
ITEM NEW PART N
CHA722-147
CHA722-147L
CHA722-155
CHA722-155L
CHA722-158
CHA722-158L
CHA722-159
CHA722-159L
CHA722-161
CHA722-161L
CHA722-162
CHA722-162L
CHA722-170
CHA722-170L
CHA722-191

QTY (UM) KEYWORD


1
1
1
1
1
1
2
2
1
1
1
1
1
1
1

ITEM OLD PART N

INT

SEE
NOTES

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 17
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA722-191L
CHA722-192
CHA722-192L
CHA722-303
CHA722-304
CHA722-305
CHA722-307
CHA722-308
CHA722-309
CHA722-310
CHA722-311
CHA722-318
CHA722-388
CHA722-389
CHA722-393
CHA722-394
CHA722-396
CHA722-398
CHA722-399
CHA722-400
CHA722-402
CHA722-403
CHA722-404
CHA722-410
CHA722-411
CHA722-424
CHA722-436
CHA722-438
CHA722-439
CHA722-442
CHA722-443
NOTE:

QTY (UM) KEYWORD


1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
2
1
1
2
1
1
2
1
1
1
1
1
1
1

ITEM OLD PART N

INT

SEE
NOTES

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA06
ITEM NEW PART N
CHA707-002L
CHA707-003A
CHA707-004A
CHA707-005A
CHA707-005B
CHA707-005C

QTY (UM) KEYWORD


1
1
1
1
1
1

ITEM OLD PART N

INT

SEE
NOTES

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 18
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

NOTE:

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA07
ITEM NEW PART N
CHA1154-001AL
CHA1154-002A
CHA1154-003A
CHA1154-003AL
CHA1154-004A
CHA1159-001
CHA1159-001A
CHA1159-002A
CHA1159-003A
CHA1159-005A
CHA1159-006B
CHA1159-006C
NOTE:

QTY (UM) KEYWORD


2
2
2
2
2
2
2
2
2
2
2
2

ITEM OLD PART N

INT

SEE
NOTES

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA08
ITEM NEW PART N
CHA722-189
CHA722-189L
CHA722-300
CHA722-392
CHA722-419
NOTE:

QTY (UM) KEYWORD


5
5
5
5
5

ITEM OLD PART N

INT

SEE
NOTES

BEARING
BEARING
BEARING
BEARING
BEARING

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA09
ITEM NEW PART N
CHA1006-003
CHA1006-003B
CHA1006-003BL
CHA1006-003BR
CHA1006-003L
CHA1006-003R
CHA1006-005A
CHA1006-006A
CHA1006-007A
CHA719-002

QTY (UM) KEYWORD


1
1
1
1
1
1
1
1
1
1

ITEM OLD PART N

INT

SEE
NOTES

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 19
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA719-002L
CHA719-002R
CHA719-003A
CHA719-004A
CHA719-005A
CHA719-005B
CHA720-002
CHA720-002L
CHA720-002R
CHA720-003A
CHA720-004A
CHA720-005A
CHA720-005B
NOTE:

QTY (UM) KEYWORD


1
1
1
1
1
1
3
3
3
3
3
3
3

ITEM OLD PART N

INT

SEE
NOTES

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA10
ITEM NEW PART N
CHA722-188
CHA722-188L
CHA722-336
CHA722-397
CHA722-416
NOTE:

QTY (UM) KEYWORD


1
1
1
1
1

ITEM OLD PART N

INT

SEE
NOTES

CPLGBOX
CPLGBOX
CPLGBOX
CPLGBOX
CPLGBOX

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA11
ITEM NEW PART N
CHA704-220
CHA704-220L
CHA704-222
CHA704-222L
CHA704-223
CHA704-223L
CHA704-224
CHA704-224L
CHA704-225
CHA704-225L
CHA704-226
CHA704-226L
CHA704-227

QTY (UM) KEYWORD


1
1
2
2
1
1
1
1
1
1
1
1
2

ITEM OLD PART N

INT

SEE
NOTES

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 20
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-227L
CHA704-228
CHA704-228L
CHA704-229
CHA704-229L
CHA704-231
CHA704-231L
CHA704-232
CHA704-232L
CHA704-235
CHA704-235L
CHA704-236
CHA704-236L
CHA704-239
CHA704-239L
CHA704-242
CHA704-242L
CHA704-243
CHA704-243L
CHA704-357
CHA704-357L
CHA704-369
CHA704-369L
CHA704-416
CHA704-420
CHA704-425
CHA704-427
CHA704-428
CHA704-429
CHA704-431
CHA704-433
CHA704-434
CHA704-435
CHA704-436
CHA704-437
CHA704-438
CHA704-439
CHA704-443
CHA704-444
CHA704-450
CHA704-453
CHA704-697
CHA704-698
CHA704-702
CHA704-704
CHA704-705
5

QTY (UM) KEYWORD


2
2
2
1
1
1
1
1
1
1
1
1
1
2
2
1
1
2
2
1
1
1
1
1
2
1
1
1
2
1
1
2
1
1
1
1
1
2
2
1
1
1
2
1
1
1

ITEM OLD PART N

INT

SEE
NOTES

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 21
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-706
CHA704-707
CHA704-708
CHA704-711
CHA704-714
CHA704-716
CHA704-717
CHA704-718
CHA704-720
CHA704-721
CHA704-722
CHA704-723
CHA704-724
CHA704-729
CHA704-730
CHA704-731
CHA704-732
CHA704-737
CHA704-738
CHA704-742
CHA704-743
CHA704-744
CHA704-747
CHA704-750
CHA704-752
CHA704-753
CHA704-755
CHA704-756
CHA704-757
CHA704-758
CHA704-783
NOTE:

QTY (UM) KEYWORD


1
1
1
2
2
1
1
1
1
1
2
1
2
1
1
1
1
1
2
1
1
1
2
2
1
1
1
1
2
2
1

ITEM OLD PART N

INT

SEE
NOTES

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Equipment BFEA12
ITEM NEW PART N
CHA722-146
CHA722-146L
CHA722-155
CHA722-155L
CHA722-158
CHA722-158L
CHA722-159

QTY (UM) KEYWORD


1
1
1
1
1
1
2

ITEM OLD PART N

INT

SEE
NOTES

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 22
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA722-159L
CHA722-161
CHA722-161L
CHA722-162
CHA722-162L
CHA722-170
CHA722-170L
CHA722-191
CHA722-191L
CHA722-192
CHA722-192L
CHA722-302
CHA722-304
CHA722-305
CHA722-307
CHA722-308
CHA722-309
CHA722-310
CHA722-311
CHA722-318
CHA722-388
CHA722-389
CHA722-393
CHA722-394
CHA722-396
CHA722-398
CHA722-399
CHA722-400
CHA722-402
CHA722-403
CHA722-404
CHA722-410
CHA722-411
CHA722-424
CHA722-435
CHA722-437
CHA722-439
CHA722-442
CHA722-443
NOTE:

QTY (UM) KEYWORD


2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
2
1
1
2
1
1
2
1
1
1
1
1
1
1

ITEM OLD PART N

INT

SEE
NOTES

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 23
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Equipment BFEA13
ITEM NEW PART N
CHA1170-001A
CHA1170-001AL
CHA1170-002
CHA1170-002A
CHA1170-003A
CHA1170-003AL
CHA1170-004A
CHA1171-001
CHA1171-001A
CHA1171-002A
CHA1171-003A
CHA1171-004A
CHA1171-005A
NOTE:

E.

QTY (UM) KEYWORD


2
2
2
2
2
2
2
2
2
2
2
2
2

ITEM OLD PART N

INT

SEE
NOTES

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

PARTS TO BE RE-IDENTIFIED BY OPERATOR


None

F.

TOOLING
(1)

Tooling - Price and Availability


None

(2)

Tools
NOTE:

(3)

To accomplish this Service Bulletin it is necessary to use the tools listed


in the subsequent referenced tasks:
-

AMM 27-50-00, Page Block 601

AMM 27-80-00, Page Block 601

Special Tools
None

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 24
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

3.

ACCOMPLISHMENT INSTRUCTIONS
Task 270205-832-801-001 - Special Detailed Inspection of the Slat and Flap Transmission
Universal Joints on LH and RH Sides
WARNING:

MAKE SURE THAT YOU OBEY ALL THE WARNINGS AND ALL THE CAUTIONS
INCLUDED IN THE REFERENCED PROCEDURES

CAUTION:

ALWAYS OBEY THE PRECAUTIONS THAT FOLLOW TO KEEP


ELECTRICAL WIRING IN A SATISFACTORY CONDITION (ELECTRICALLY
AND MECHANICALLY SERVICEABLE). WHEN YOU DO MAINTENANCE
WORK, REPAIRS OR MODIFICATIONS, ALWAYS KEEP ELECTRICAL WIRING,
COMPONENTS AND THE WORK AREA AS CLEAN AS POSSIBLE. TO DO
THIS:
-

PUT PROTECTION, SUCH AS PLASTIC SHEETING, CLOTHS, ETC. AS


NECESSARY ON WIRING AND COMPONENTS.

REGULARLY REMOVE ALL SHAVINGS, UNWANTED MATERIAL AND


OTHER CONTAMINATION.

THESE PRECAUTIONS WILL DECREASE THE RISK OF CONTAMINATION


AND DAMAGE TO THE ELECTRICAL WIRING INSTALLATION.
IF THERE IS CONTAMINATION REFER TO ESPM 20-55-00.
NOTE:

The accomplishment instructions of this Service Bulletin include procedures given


in other documents or in other sections of the Service Bulletin. When the words
"refer to" are used and the operator has a procedure accepted by the local
authority he belongs to, the accepted alternative procedure can be used. When the
words "in accordance with" are used then the given procedure must be followed.

NOTE:

The access and close-up instructions, not comprising return to service tests, in this
Service Bulletin do not constitute or affect the technical intent of the Service
Bulletin. Operators can therefore, as deemed necessary, omit or add access and/or
close-up steps to add flexibility to their maintenance operations as long as the
technical intent of the Service Bulletin is met within the set parameters.

NOTE:

Manual titles given in the accomplishment instructions are referred to by acronyms.


Refer to paragraph 1.J., References, for the definition of acronyms.

NOTE:

The purpose of flow charts is to supplement the information given in the Procedure
and Compliance paragraphs and not to serve as the primary source for tasks or
compliance times given in this Service Bulletin.

Task Associated Data


Zone
From
From
From
From

510
570
610
670

to
to
to
to

520
580
620
680

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 25
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Manpower
TOTAL MANHOURS
ELAPSED TIME (HOURS)
A.

48.00
11.50

GENERAL
(1)

Subtask 270205-910-003-001 - Standard Practices


Manpower Resources

Skills

NON SPECIFIC

Aircraft Maintenance Manual (AMM)


(a)
(2)

References
06-21-00, Page Block 001

For the identification of zones, refer to AMM 06-21-00, Page Block 001.

Subtask 270205-839-001-001 - Administrative


Manpower Resources

Skills

NON SPECIFIC
Write in the applicable aircraft records that you have done all the work given in this
Service Bulletin.

B.

PREPARATION
(1)

Subtask 270205-941-001-001 - Job Set-up


Manpower Resources

Skills

NON SPECIFIC

Aircraft Maintenance Manual (AMM)


NOTE:

References
24-00-00, Page Block 301

The items given in this note shall be considered as the basic Aircraft
configuration before you start a maintenance task:
-

Aircraft on the ground resting on landing gear (the ground safety


locks and the wheel chocks are in position on the landing gear)

Engine shut down, thrust reversers closed and locked

Aircraft in clean configuration

Parking brake applied

Aircraft electrical network de-energized

Hydraulic systems depressurized

Access to the cockpit and cabin is available

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 26
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(a)

(2)

All circuit breakers are in closed position

All controls in NORM, AUTO or OFF position.

Make sure that the aircraft is electrically grounded, refer to AMM 24-00-00, Page
Block 301.

Subtask 270205-941-002-001 - Job Set-up for LH Side


Manpower Resources

Skills

NON SPECIFIC

References
Aircraft Maintenance Manual (AMM)
27-50-00, Page Block 601
27-80-00, Page Block 601

(3)

(a)

Put an access platform in position at zones 510, 520, 570 and 580.

(b)

Do the job set-up procedure as specified in the Check of the Rotational Backlash of
the Universal Joints - Slats and Krueger Flaps, refer to AMM 27-80-00, Page Block
601.

(c)

Do the job set-up procedure as specified in the Check of the Rotational Backlash of
the Universal Joints - Flaps, refer to AMM 27-50-00, Page Block 601.

Subtask 270205-941-006-001 - Job Set-up for RH Side


Manpower Resources

Skills

NON SPECIFIC

Aircraft Maintenance Manual (AMM)

C.

(a)

Put an access platform in position at zones 610, 620, 670 and 680.

(b)

Do the job set-up procedure as specified in the Check of the Rotational Backlash of
the Universal Joints - Slats and Krueger Flaps, refer to AMM 27-80-00, Page Block
601.

(c)

Do the job set-up procedure as specified in the Check of the Rotational Backlash of
the Universal Joints - Flaps, refer to AMM 27-50-00, Page Block 601.

PROCEDURE
(1)

From
To
5

References
27-50-00, Page Block 601
27-80-00, Page Block 601

Subtask 270205-832-001-001 - Do a Check of the Rotational Backlash of each Key


Slat Universal Joints from Outboard to Inboard for LH Side

Zone
510
520

Work Zones and Access Panels


Access/Work location

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 27
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME

References
Aircraft Maintenance Manual (AMM)
27-80-00, Page Block 601
Fig. A-FBBAA
Slat Universal Joints - Measuring
positions

Sheet 01

Fig. A-FFAAA
Flow Chart

Sheet 01

(a)

At the threshold given in PLANNING INFORMATION paragraph E.(2):


Do a check of the rotational backlash of each key slat universal joints from
outboard to inboard.
NOTE:

For the slat transmission, the "key" universal joint positions to be


checked are (from the most outboard to the most inboard):
-

27, 26, 22, 21, 13, 9 and 1

Refer to Fig. A-FFAAA


Refer to Fig. A-FBBAA
Refer to AMM 27-80-00, Page Block 601
NOTE:

In case of the rotational backlash is greater than 3.5 degrees, check


the key universal joints from outboard to inboard to avoid to repeat
the inspection of the same universal joints.

NOTE:

In case of the rotational backlash is greater than 3.5 degrees, each


single universal joint located inboard must be checked (including the
key universal joints). When all single universal joints located inboard
are checked, the overall inspection is completed.

If the rotational backlash is greater than 5 degrees:


-

Do a check of the rotational backlash of each single slat universal joints


located inboard of the affected key slat universal joint on LH side in
accordance with SUBTASK 270205-832-007 001 Depending on inspection
results, do a Check of the Rotational Backlash of each Single Slat
Universal Joints located Inboard of the affected Key Slat Universal Joint
on LH Side before next flight.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 28
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Replace the equipment linked to the affected universal joint in accordance


with TASK 270205-833-801 001 Replacement of the Equipments linked to
the affected Slat and Flap Transmission Universal Joints on LH and RH
Sides at the threshold given in the PLANNING INFORMATION paragraph
E.(2).

Repeat the check of the rotational backlash of each key slat universal
joint from outboard to inboard for LH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

If the rotational backlash is greater than 3.5 degrees and inferior or equal to 5
degrees:
-

Do a check of the rotational backlash of each single slat universal joints


located inboard of the affected key slat universal joint on LH side in
accordance with SUBTASK 270205-832-007 001 Depending on inspection
results, do a Check of the Rotational Backlash of each Single Slat
Universal Joints located Inboard of the affected Key Slat Universal Joint
on LH Side before next flight.

Replace the equipment linked to the affected universal joint in accordance


with TASK 270205-833-801 001 Replacement of the Equipments linked to
the affected Slat and Flap Transmission Universal Joints on LH and RH
Sides at the threshold given in the PLANNING INFORMATION paragraph
E.(2).

Repeat the check of the rotational backlash of each key slat universal
joint from outboard to inboard for LH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

If the rotational backlash is inferior or equal to 3.5 degrees:


-

(2)

From
To

Repeat the check of the rotational backlash of each key slat universal
joint from outboard to inboard for LH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

Subtask 270205-832-002-001 - Do a Check of the Rotational Backlash of each Key


Slat Universal Joints from Outboard to Inboard for RH Side
Work Zones and Access Panels
Access/Work location

Zone
610
620

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME

Aircraft Maintenance Manual (AMM)


5

DATE: Sep 11/15

References
27-80-00, Page Block 601
SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 29
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Fig. A-FBBAA
Slat Universal Joints - Measuring
positions
Fig. A-FFAAA
Flow Chart
(a)

References
Sheet 01

Sheet 01

At the threshold given in PLANNING INFORMATION paragraph E.(2):


Do a check of the rotational backlash of each key slat universal joints from
outboard to inboard.
NOTE:

For the slat transmission, the "key" universal joint positions to be


checked are (from the most outboard to the most inboard):
-

27, 26, 22, 21, 13, 9 and 1

Refer to Fig. A-FFAAA


Refer to Fig. A-FBBAA
Refer to AMM 27-80-00, Page Block 601
NOTE:

In case of the rotational backlash is greater than 3.5 degrees, check


the key universal joints from outboard to inboard to avoid to repeat
the inspection of the same universal joints.

NOTE:

In case of the rotational backlash is greater than 3.5 degrees, each


single universal joint located inboard must be checked (including the
key universal joints). When all single universal joints located inboard
are checked, the overall inspection is completed.

If the rotational backlash is greater than 5 degrees:


-

Do a check of the rotational backlash of each single slat transmission


universal joints located inboard of the affected key slat universal joint on
RH side in accordance with SUBTASK 270205-832-008 001 Depending
on inspection results, do a Check of the Rotational Backlash of each
Single Slat Universal Joints located Inboard of the affected Key Slat
Universal Joint on RH Side before next flight.

Replace the equipment linked to the affected universal joint in accordance


with TASK 270205-833-801 001 Replacement of the Equipments linked to
the affected Slat and Flap Transmission Universal Joints on LH and RH
Sides at the threshold given in the PLANNING INFORMATION paragraph
E.(2).

Repeat the check of the rotational backlash of each key slat universal
joint from outboard to inboard for RH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 30
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

If the rotational backlash is greater than 3.5 degrees and inferior or equal to 5
degrees:
-

Do a check of the rotational backlash of each single slat transmission


universal joints located inboard of the affected key slat universal joint on
RH side in accordance with SUBTASK 270205-832-008 001 Depending
on inspection results, do a Check of the Rotational Backlash of each
Single Slat Universal Joints located Inboard of the affected Key Slat
Universal Joint on RH Side before next flight.

Replace the equipment linked to the affected slat universal joint


in accordance with TASK 270205-833-801 001 Replacement of the
Equipments linked to the affected Slat and Flap Transmission Universal
Joints on LH and RH Sides at the threshold given in the PLANNING
INFORMATION paragraph E.(2).

Repeat the check of the rotational backlash of each key slat universal
joint from outboard to inboard for RH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

If the rotational backlash is inferior or equal to 3.5 degrees:


-

(3)

From
To

Repeat the check of the rotational backlash of each key slat universal
joint from outboard to inboard for RH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

Subtask 270205-832-003-001 - Do a Check of the Rotational Backlash of each Key


Flap Universal Joints from Outboard to Inboard for LH Side
Work Zones and Access Panels
Access/Work location

Zone
570
580

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME

Aircraft Maintenance Manual (AMM)

References
27-50-00, Page Block 601

Fig. A-FBAAA
Flap Universal Joints - Measuring
positions

Sheet 01

Fig. A-FFAAA
Flow Chart

Sheet 01

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 31
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(a)

At the threshold given in PLANNING INFORMATION paragraph E.(2):


Do a check of the rotational backlash of each key flap universal joints from
outboard to inboard.
NOTE:

For the flap transmission, the "key" universal joint positions to be


checked are (from the most outboard to the most inboard):
-

16, 15, 14, 13, 8 and 5

Refer to Fig. A-FFAAA


Refer to Fig. A-FBAAA
Refer to AMM 27-50-00, Page Block 601
NOTE:

In case of the rotational backlash is greater than 3.5 degrees, check


the key universal joints from outboard to inboard to avoid to repeat
the inspection of the same universal joints.

NOTE:

In case of the rotational backlash is greater than 3.5 degrees, each


single universal joint located inboard must be checked (including the
key universal joints). When all single universal joints located inboard
are checked, the overall inspection is completed.

If the rotational backlash is greater than 5 degrees:


-

Do a check of the rotational backlash of each single flap universal joints


located inboard of the affected key flap universal joint on LH side in
accordance with SUBTASK 270205-832-009 001 Depending on inspection
results, do a Check of the Rotational Backlash of each Single Flap
Universal Joints located Inboard of the affected Key Flap Universal Joint
on LH Side before next flight.

Replace the equipment linked to the affected universal joint in accordance


with TASK 270205-833-801 001 Replacement of the Equipments linked to
the affected Slat and Flap Transmission Universal Joints on LH and RH
Sides at the threshold given in the PLANNING INFORMATION paragraph
E.(2).

Repeat the check of the rotational backlash of each key flap universal
joint from outboard to inboard for LH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

If the rotational backlash is greater than 3.5 degrees and inferior or equal to 5
degrees:
-

Do a check of the rotational backlash of each single flap universal joints


located inboard of the affected key flap universal joint on LH side in
accordance with SUBTASK 270205-832-009 001 Depending on inspection
results, do a Check of the Rotational Backlash of each Single Flap
Universal Joints located Inboard of the affected Key Flap Universal Joint
on LH Side before next flight.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 32
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Replace the equipment linked to the affected universal joint in accordance


with TASK 270205-833-801 001 Replacement of the Equipments linked to
the affected Slat and Flap Transmission Universal Joints on LH and RH
Sides at the threshold given in the PLANNING INFORMATION paragraph
E.(2).

Repeat the check of the rotational backlash of each key flap universal
joint from outboard to inboard for LH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

If the rotational backlash is inferior or equal to 3.5 degrees:


-

(4)

Repeat the check of the rotational backlash of each key flap universal
joint from outboard to inboard for LH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

Subtask 270205-832-004-001 - Do a Check of the Rotational Backlash of each Key


Flap Universal Joints from Outboard to Inboard for RH Side
Work Zones and Access Panels
Access/Work location

Zone
670
680

From
To

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME

Aircraft Maintenance Manual (AMM)

References
27-50-00, Page Block 601

Fig. A-FBAAA
Flap Universal Joints - Measuring
positions

Sheet 01

Fig. A-FFAAA
Flow Chart

Sheet 01

(a)

At the threshold given in PLANNING INFORMATION paragraph E.(2):


Do a check of the rotational backlash of each key flap universal joints from
outboard to inboard.
NOTE:

For the flap transmission, the "key" universal joint positions to be


checked are (from the most outboard to the most inboard):
-

16, 15, 14, 13, 8 and 5

Refer to Fig. A-FFAAA


Refer to Fig. A-FBAAA

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 33
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Refer to AMM 27-50-00, Page Block 601


NOTE:

In case of the rotational backlash is greater than 3.5 degrees, check


the key universal joints from outboard to inboard to avoid to repeat
the inspection of the same universal joints.

NOTE:

In case of the rotational backlash is greater than 3.5 degrees, each


single universal joint located inboard must be checked (including the
key universal joints). When all single universal joints located inboard
are checked, the overall inspection is completed.

If the rotational backlash is greater than 5 degrees:


-

Do a check of the rotational backlash of each single flap universal joints


located inboard of the affected key flap universal joint on RH side in
accordance with SUBTASK 270205-832-010 001 Depending on inspection
results, do a Check of the Rotational Backlash of each Single Flap
Universal Joints located Inboard of the affected Key Flap Universal Joint
on RH Side before next flight.

Replace the equipment linked to the affected key universal joint


in accordance withTASK 270205-833-801 001 Replacement of the
Equipments linked to the affected Slat and Flap Transmission Universal
Joints on LH and RH Sides at the threshold given in the PLANNING
INFORMATION paragraph E.(2).

Repeat the check of the rotational backlash of each key flap universal
joint from outboard to inboard for RH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

If the rotational backlash is greater than 3.5 degrees and inferior or equal to 5
degrees:
-

Do a check of the rotational backlash of each single flap universal joints


located inboard of the affected key flap universal joint on RH side in
accordance with SUBTASK 270205-832-010 001 Depending on inspection
results, do a Check of the Rotational Backlash of each Single Flap
Universal Joints located Inboard of the affected Key Flap Universal Joint
on RH Side before next flight.

Replace the equipment linked to the affected key universal joint


in accordance with TASK 270205-833-801 001 Replacement of the
Equipments linked to the affected Slat and Flap Transmission Universal
Joints on LH and RH Sides at the threshold given in the PLANNING
INFORMATION paragraph E.(2).

Repeat the check of the rotational backlash of each key flap universal
joint from outboard to inboard for RH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 34
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

If the rotational backlash is inferior or equal to 3.5 degrees:


-

(5)

Repeat the check of the rotational backlash of each key flap universal
joint from outboard to inboard for RH side at the interval given in the
PLANNING INFORMATION paragraph E.(2).

Subtask 270205-832-007-001 - Depending on inspection results, do a Check of the


Rotational Backlash of each Single Slat Universal Joints located Inboard of the
affected Key Slat Universal Joint on LH Side
Work Zones and Access Panels
Access/Work location

Zone
510
520

From
To

Manpower Resources
Manhours
Minimum number of person

8.00
1

Subtask elapsed time

8.00

Skills

AIRFRAME

References
Aircraft Maintenance Manual (AMM)
27-80-00, Page Block 601
Fig. A-FBBAA
Slat Universal Joints - Measuring
positions
(a)

Sheet 01

Before next flight, do a check of the rotational backlash of each single slat universal
joint located inboard of the affected key slat universal joint on LH side.
Refer to Fig. A-FBBAA
Refer to AMM 27-80-00, Page Block 601

(6)

From
To

Subtask 270205-832-008-001 - Depending on inspection results, do a Check of the


Rotational Backlash of each Single Slat Universal Joints located Inboard of the
affected Key Slat Universal Joint on RH Side
Work Zones and Access Panels
Access/Work location

Zone
610
620

Manpower Resources

Manhours
Minimum number of person

8.00
1

Subtask elapsed time

8.00

Skills

AIRFRAME

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 35
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Aircraft Maintenance Manual (AMM)


Fig. A-FBBAA
Slat Universal Joints - Measuring
positions
(a)

References
27-80-00, Page Block 601
Sheet 01

Before next flight, do a check of the rotational backlash of each single slat universal
joint located inboard of the affected key slat universal joint on RH side.
Refer to Fig. A-FBBAA
Refer to AMM 27-80-00, Page Block 601

(7)

Subtask 270205-832-009-001 - Depending on inspection results, do a Check of the


Rotational Backlash of each Single Flap Universal Joints located Inboard of the
affected Key Flap Universal Joint on LH Side
Work Zones and Access Panels
Access/Work location

Zone
570
580

From
To

Manpower Resources
Manhours
Minimum number of person

6.00
1

Subtask elapsed time

6.00

Skills

AIRFRAME

Aircraft Maintenance Manual (AMM)


Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

References
27-50-00, Page Block 601
Sheet 01

Before next flight, do a check of the rotational backlash of each single flap universal
joint located inboard of the affected key flap universal joint on LH side.
Refer to Fig. A-FBAAA
Refer to AMM 27-50-00, Page Block 601

(8)

From
To

Subtask 270205-832-010-001 - Depending on inspection results, do a Check of the


Rotational Backlash of each Single Flap Universal Joints located Inboard of the
affected Key Flap Universal Joint on RH Side

Zone
670
680

Work Zones and Access Panels


Access/Work location

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 36
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Manpower Resources
Manhours
Minimum number of person

6.00
1

Subtask elapsed time

6.00

Skills

AIRFRAME

References
Aircraft Maintenance Manual (AMM)
27-50-00, Page Block 601
Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

Sheet 01

Before next flight, do a check of the rotational backlash of each single flap universal
joint located inboard of the affected key flap universal joint on RH side.
Refer to Fig. A-FBAAA
Refer to AMM 27-50-00, Page Block 601

D.

TEST
None

E.

CLOSE-UP
NOTE:

(1)

If you intend to accomplish an associated TASK 270205-833-801 001


Replacement of the Equipments linked to the affected Slat and Flap
Transmission Universal Joints on LH and RH Sides during the same layover
period, the subsequent Close-up procedure is not necessary.

Subtask 270205-942-001-001 - Close-up for LH Side


Manpower Resources

Skills

NON SPECIFIC

References
Aircraft Maintenance Manual (AMM)
27-50-00, Page Block 601
27-80-00, Page Block 601

(2)

(a)

Do the close-up procedure as specified after the Check of the Rotational Backlash
of the Universal Joints - Slats and Krueger Flaps, refer to AMM 27-80-00, Page
Block 601.

(b)

Do the close-up procedure as specified after the Check of the Rotational Backlash
of the Universal Joints - Flaps, refer to AMM 27-50-00, Page Block 601.

Subtask 270205-942-002-001 - Close-up for RH Side


Manpower Resources

Skills

NON SPECIFIC

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 37
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Aircraft Maintenance Manual (AMM)

(3)

References
27-50-00, Page Block 601
27-80-00, Page Block 601

(a)

Do the close-up procedure as specified after the Check of the Rotational Backlash
of the Universal Joints - Slats and Krueger Flaps, refer to AMM 27-80-00, Page
Block 601.

(b)

Do the close-up procedure as specified after the Check of the Rotational Backlash
of the Universal Joints - Flaps, refer to AMM 27-50-00, Page Block 601.

Subtask 270205-942-003-001 - Close-up


Manpower Resources

Skills

NON SPECIFIC
(a)

Make sure that the work areas are clean and clear of tools and other items of
equipment.

(b)

Remove the access platform(s)

(c)

Put the aircraft back to its initial configuration.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 38
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Task 270205-833-801-001 - Replacement of the Equipments linked to the affected Slat and
Flap Transmission Universal Joints on LH and RH Sides
WARNING:

MAKE SURE THAT YOU OBEY ALL THE WARNINGS AND ALL THE CAUTIONS
INCLUDED IN THE REFERENCED PROCEDURES

CAUTION:

ALWAYS OBEY THE PRECAUTIONS THAT FOLLOW TO KEEP


ELECTRICAL WIRING IN A SATISFACTORY CONDITION (ELECTRICALLY
AND MECHANICALLY SERVICEABLE). WHEN YOU DO MAINTENANCE
WORK, REPAIRS OR MODIFICATIONS, ALWAYS KEEP ELECTRICAL WIRING,
COMPONENTS AND THE WORK AREA AS CLEAN AS POSSIBLE. TO DO
THIS:
-

PUT PROTECTION, SUCH AS PLASTIC SHEETING, CLOTHS, ETC. AS


NECESSARY ON WIRING AND COMPONENTS.

REGULARLY REMOVE ALL SHAVINGS, UNWANTED MATERIAL AND


OTHER CONTAMINATION.

THESE PRECAUTIONS WILL DECREASE THE RISK OF CONTAMINATION


AND DAMAGE TO THE ELECTRICAL WIRING INSTALLATION.
IF THERE IS CONTAMINATION REFER TO ESPM 20-55-00.
NOTE:

The accomplishment instructions of this Service Bulletin include procedures given


in other documents or in other sections of the Service Bulletin. When the words
"refer to" are used and the operator has a procedure accepted by the local
authority he belongs to, the accepted alternative procedure can be used. When the
words "in accordance with" are used then the given procedure must be followed.

NOTE:

The access and close-up instructions, not comprising return to service tests, in this
Service Bulletin do not constitute or affect the technical intent of the Service
Bulletin. Operators can therefore, as deemed necessary, omit or add access and/or
close-up steps to add flexibility to their maintenance operations as long as the
technical intent of the Service Bulletin is met within the set parameters.

NOTE:

Manual titles given in the accomplishment instructions are referred to by acronyms.


Refer to paragraph 1.J., References, for the definition of acronyms.

Task Associated Data


Zone
From
From
From
From

510
570
610
670

to
to
to
to

520
580
620
680
Manpower

TOTAL MANHOURS
ELAPSED TIME (HOURS)

DATE: Sep 11/15

70.00
42.00

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 39
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

A.

GENERAL
(1)

Subtask 270205-910-002-001 - Standard Practices


Manpower Resources

Skills

NON SPECIFIC

Aircraft Maintenance Manual (AMM)


(a)
(2)

References
06-21-00, Page Block 001

For the identification of zones, refer to AMM 06-21-00, Page Block 001.

Subtask 270205-839-003-001 - Administrative


Manpower Resources

Skills

NON SPECIFIC
Write in the applicable aircraft record that you have done all the work given in this
Service Bulletin.

B.

PREPARATION
NOTE:

(1)

If you intend to accomplish this Task during the same layover


period as the associated Inspection, the subsequent Job Set-up
procedure SUBTASK 270205-941-014-001, SUBTASK 270205-941-016-001
and SUBTASK 270205-941-017-001 are not necessary.

Subtask 270205-941-014-001 - Job Set-up


Manpower Resources

Skills

NON SPECIFIC

References
Aircraft Maintenance Manual (AMM)
24-00-00, Page Block 301
NOTE:

The items given in this note shall be considered as the basic Aircraft
configuration before you start a maintenance task:
-

Aircraft on the ground resting on landing gear (the ground safety


locks and the wheel chocks are in position on the landing gear)

Engine shut down, thrust reversers closed and locked

Aircraft in clean configuration

Parking brake applied

Aircraft electrical network de-energized

Hydraulic systems depressurized

Access to the cockpit and cabin is available

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 40
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(a)

(2)

All circuit breakers are in closed position

All controls in NORM, AUTO or OFF position.

Make sure that the aircraft is electrically grounded, refer to AMM 24-00-00, Page
Block 301.

Subtask 270205-941-016-001 - Job Set-up for LH Side


Manpower Resources

Skills

NON SPECIFIC

References
Aircraft Maintenance Manual (AMM)
27-50-00, Page Block 601
27-80-00, Page Block 601

(3)

(a)

Put an access platform in position at zones 510, 520, 570 and 580.

(b)

Do the job set-up procedure as specified in the Check of the Rotational Backlash of
the Universal Joints - Slats and Krueger Flaps, refer to AMM 27-80-00, Page Block
601.

(c)

Do the job set-up procedure as specified in the Check of the Rotational Backlash of
the Universal Joints - Flaps, refer to AMM 27-50-00, Page Block 601.

Subtask 270205-941-017-001 - Job Set-up for RH Side


Manpower Resources

Skills

NON SPECIFIC

Aircraft Maintenance Manual (AMM)

(4)

References
27-50-00, Page Block 601
27-80-00, Page Block 601

(a)

Put an access platform in position at zones 610, 620, 670 and 680.

(b)

Do the job set-up procedure as specified in the Check of the Rotational Backlash of
the Universal Joints - Slats and Krueger Flaps, refer to AMM 27-80-00, Page Block
601.

(c)

Do the job set-up procedure as specified in the Check of the Rotational Backlash of
the Universal Joints - Flaps, refer to AMM 27-50-00, Page Block 601.

Subtask 270205-941-015-001 - Job Set-up for replacement of the equipment linked


to the affected Universal Joint
Manpower Resources

Skills

NON SPECIFIC

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 41
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Aircraft Maintenance Manual (AMM)

References
27-51-23,
27-51-24,
27-51-34,
27-51-35,
27-51-36,
27-51-37,
27-51-38,
27-81-16,
27-81-17,
27-81-18,
27-81-19,
27-81-21,

Page
Page
Page
Page
Page
Page
Page
Page
Page
Page
Page
Page

Block
Block
Block
Block
Block
Block
Block
Block
Block
Block
Block
Block

401
401
401
401
401
401
401
401
401
401
401
401

If necessary, do the job set-up procedure as specified in the removal/installation of


the Transmission Shafts, refer to AMM 27-81-19, Page Block 401.

If necessary, do the job set-up procedure as specified in the removal/installation of


the Steady Bearings, refer to AMM 27-81-21, Page Block 401 and AMM 27-81-17,
Page Block 401.

If necessary, do the job set-up procedure as specified in the removal/installation of


the Coupling Box, refer to AMM 27-81-18, Page Block 401.

If necessary, do the job set-up procedure as specified in the removal/installation of


the Stepback Gearbox, refer to AMM 27-81-16, Page Block 401.

If necessary, do the job set-up procedure as specified in the removal/installation of


the Transmission Shafts, refer to AMM 27-51-36, Page Block 401.

If necessary, do the job set-up procedure as specified in the removal/installation of


the Tee Gearbox, refer to AMM 27-51-23, Page Block 401.

If necessary, do the job set-up procedure as specified in the removal/installation of


the Simplex Bevel Gearbox, refer to AMM 27-51-24, Page Block 401.

If necessary, do the job set-up procedure as specified in the removal/installation of


the Steady Bearing, refer to AMM 27-51-38, Page Block 401.

If necessary, do the job set-up procedure as specified in the removal/installation of


the Downdrive Gearbox, refer to AMM 27-51-34, Page Block 401 for inner flaps
and/or AMM 27-51-35, Page Block 401 for center or outer flaps.

If necessary, do the job set-up procedure as specified in the removal/installation of


the Coupling Box, refer to AMM 27-51-37, Page Block 401.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 42
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

C.

PROCEDURE
(1)

From
To

Subtask 270205-833-001-001 - Depending on inspection results, replace the


Transmission Shaft linked to the affected Slat Universal Joints on LH Side
Work Zones and Access Panels
Access/Work location

Zone
510
520

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA01
ITEM NEW PART N
CHA704-220
CHA704-220L
CHA704-221
CHA704-221L
CHA704-223
CHA704-223L
CHA704-224
CHA704-224L
CHA704-225
CHA704-225L
CHA704-226
CHA704-226L
CHA704-227
CHA704-227L
CHA704-228
CHA704-228L
CHA704-229
CHA704-229L
CHA704-231
CHA704-231L
CHA704-232
CHA704-232L
CHA704-235
CHA704-235L
CHA704-236
CHA704-236L
CHA704-239
5

QTY (UM)

KEYWORD

1
1
2
2
1
1
1
1
1
1
1
1
2
2
2
2
1
1
1
1
1
1
1
1
1
1
2

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SEE
NOTES

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 43
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-239L
CHA704-242
CHA704-242L
CHA704-354
CHA704-354L
CHA704-357
CHA704-357L
CHA704-369
CHA704-369L
CHA704-416
CHA704-419
CHA704-425
CHA704-427
CHA704-428
CHA704-430
CHA704-431
CHA704-433
CHA704-434
CHA704-435
CHA704-436
CHA704-437
CHA704-438
CHA704-439
CHA704-443
CHA704-444
CHA704-450
CHA704-453
CHA704-697
CHA704-700
CHA704-702
CHA704-704
CHA704-705
CHA704-706
CHA704-707
CHA704-708
CHA704-711
CHA704-714
CHA704-716
CHA704-717
CHA704-718
CHA704-720
CHA704-721
CHA704-722
CHA704-723
CHA704-726
CHA704-729
5

QTY (UM)

KEYWORD

2
1
1
2
2
1
1
1
1
1
2
1
1
1
2
1
1
2
1
1
1
1
1
2
2
1
1
1
2
1
1
1
1
1
1
2
2
1
1
1
1
1
2
1
2
1

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SEE
NOTES

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 44
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-730
CHA704-731
CHA704-732
CHA704-737
CHA704-740
CHA704-742
CHA704-743
CHA704-744
CHA704-747
CHA704-750
CHA704-752
CHA704-753
CHA704-755
CHA704-756
CHA704-757
CHA704-760
CHA704-783
NOTE:

QTY (UM)

KEYWORD

1
1
1
1
2
1
1
1
2
2
1
1
1
1
2
2
1

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

References
Aircraft Maintenance Manual (AMM)
27-81-19, Page Block 401
Fig. A-FBBAA
Slat Universal Joints - Measuring
positions
(a)

Sheet 01

Replace the transmission shaft linked to the affected slat universal joint on LH side:
Refer to Fig. A-FBBAA
Refer to AMM 27-81-19, Page Block 401
1

For the transmission shaft linked to the affected slat universal joint in position
4:
-

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-220


or

Shaft-Slat Transmission CHA704-220L


or

Shaft-Slat Transmission CHA704-697


or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 45
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Slat Transmission CHA704-416


or

Shaft-Slat Transmission CHA704-737


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
5 and 6:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-221


or

Shaft-Slat Transmission CHA704-221L


or

Shaft-Slat Transmission CHA704-700


or

Shaft-Slat Transmission CHA704-419


or

Shaft-Slat Transmission CHA704-740


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
7:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-223


or

Shaft-Slat Transmission CHA704-223L


or

Shaft-Slat Transmission CHA704-702


or

Shaft-Slat Transmission CHA704-428


or

Shaft-Slat Transmission CHA704-742

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 46
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

NOTE:

For the transmission shaft linked to the affected slat universal joint in position
9:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-224


or

Shaft-Slat Transmission CHA704-224L


or

Shaft-Slat Transmission CHA704-704


or

Shaft-Slat Transmission CHA704-427


or

Shaft-Slat Transmission CHA704-729


or

Shaft-Slat Transmission CHA704-369


or

Shaft-Slat Transmission CHA704-369L


or

Shaft-Slat Transmission CHA704-705


or

Shaft-Slat Transmission CHA704-450


or

Shaft-Slat Transmission CHA704-730


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
12:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-225


or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 47
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Slat Transmission CHA704-225L


or

Shaft-Slat Transmission CHA704-706


or

Shaft-Slat Transmission CHA704-431


or

Shaft-Slat Transmission CHA704-743


or

Shaft-Slat Transmission CHA704-357


or

Shaft-Slat Transmission CHA704-357L


or

Shaft-Slat Transmission CHA704-707


or

Shaft-Slat Transmission CHA704-453


or

Shaft-Slat Transmission CHA704-731


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
13:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-226


or

Shaft-Slat Transmission CHA704-226L


or

Shaft-Slat Transmission CHA704-708


or

Shaft-Slat Transmission CHA704-435


or

1
5

Shaft-Slat Transmission CHA704-744

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 48
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

NOTE:

For the transmission shaft linked to the affected slat universal joint in position
15 or 16:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-227


or

Shaft-Slat Transmission CHA704-227L


or

Shaft-Slat Transmission CHA704-711


or

Shaft-Slat Transmission CHA704-443


or

Shaft-Slat Transmission CHA704-747


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
17 or 18:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-228


or

Shaft-Slat Transmission CHA704-228L


or

Shaft-Slat Transmission CHA704-714


or

Shaft-Slat Transmission CHA704-444


or

Shaft-Slat Transmission CHA704-750


NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 49
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

For the transmission shaft linked to the affected slat universal joint in position
19:
-

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-229


or

Shaft-Slat Transmission CHA704-229L


or

Shaft-Slat Transmission CHA704-716


or

Shaft-Slat Transmission CHA704-425


or

Shaft-Slat Transmission CHA704-752


NOTE:

10

For the transmission shaft linked to the affected slat universal joint in position
22:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-231


or

Shaft-Slat Transmission CHA704-231L


or

Shaft-Slat Transmission CHA704-717


or

Shaft-Slat Transmission CHA704-439


or

Shaft-Slat Transmission CHA704-732


NOTE:

11

For the transmission shaft linked to the affected slat universal joint in position
23:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 50
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Slat Transmission CHA704-232


or

Shaft-Slat Transmission CHA704-232L


or

Shaft-Slat Transmission CHA704-718


or

Shaft-Slat Transmission CHA704-433


or

Shaft-Slat Transmission CHA704-753


NOTE:

12

For the transmission shaft linked to the affected slat universal joint in position
27:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-235


or

Shaft-Slat Transmission CHA704-235L


or

Shaft-Slat Transmission CHA704-720


or

Shaft-Slat Transmission CHA704-438


or

Shaft-Slat Transmission CHA704-755


NOTE:

13

For the transmission shaft linked to the affected slat universal joint in position
28:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-236


or

Shaft-Slat Transmission CHA704-236L

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 51
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
1

Shaft-Slat Transmission CHA704-721


or

Shaft-Slat Transmission CHA704-437


or

Shaft-Slat Transmission CHA704-756


NOTE:

14

For the transmission shaft linked to the affected slat universal joint in position
32 or 33:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-239


or

Shaft-Slat Transmission CHA704-239L


or

Shaft-Slat Transmission CHA704-722


or

Shaft-Slat Transmission CHA704-434


or

Shaft-Slat Transmission CHA704-757


NOTE:

15

For the transmission shaft linked to the affected slat universal joint in position
37:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-242


or

Shaft-Slat Transmission CHA704-242L


or

Shaft-Slat Transmission CHA704-723


or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 52
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Slat Transmission CHA704-436


or

Shaft-Slat Transmission CHA704-783


NOTE:

16

For the transmission shaft linked to the affected slat universal joint in position
38 or 39:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-354


or

Shaft-Slat Transmission CHA704-354L


or

Shaft-Slat Transmission CHA704-726


or

Shaft-Slat Transmission CHA704-430


or

Shaft-Slat Transmission CHA704-760


NOTE:

(2)

From
To

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Subtask 270205-833-005-001 - Depending on inspection results, replace the


Transmission Shaft linked to the affected Slat Universal Joints on RH Side
Work Zones and Access Panels
Access/Work location

Zone
510
520

Manpower Resources

Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 53
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Material necessary to do the job


Equipment BFEA11
ITEM NEW PART N
CHA704-220
CHA704-220L
CHA704-222
CHA704-222L
CHA704-223
CHA704-223L
CHA704-224
CHA704-224L
CHA704-225
CHA704-225L
CHA704-226
CHA704-226L
CHA704-227
CHA704-227L
CHA704-228
CHA704-228L
CHA704-229
CHA704-229L
CHA704-231
CHA704-231L
CHA704-232
CHA704-232L
CHA704-235
CHA704-235L
CHA704-236
CHA704-236L
CHA704-239
CHA704-239L
CHA704-242
CHA704-242L
CHA704-243
CHA704-243L
CHA704-357
CHA704-357L
CHA704-369
CHA704-369L
CHA704-416
CHA704-420
CHA704-425
CHA704-427
CHA704-428
CHA704-429

QTY (UM)

KEYWORD

1
1
2
2
1
1
1
1
1
1
1
1
2
2
2
2
1
1
1
1
1
1
1
1
1
1
2
2
1
1
2
2
1
1
1
1
1
2
1
1
1
2

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SEE
NOTES

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 54
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-431
CHA704-433
CHA704-434
CHA704-435
CHA704-436
CHA704-437
CHA704-438
CHA704-439
CHA704-443
CHA704-444
CHA704-450
CHA704-453
CHA704-697
CHA704-698
CHA704-702
CHA704-704
CHA704-705
CHA704-706
CHA704-707
CHA704-708
CHA704-711
CHA704-714
CHA704-716
CHA704-717
CHA704-718
CHA704-720
CHA704-721
CHA704-722
CHA704-723
CHA704-724
CHA704-729
CHA704-730
CHA704-731
CHA704-732
CHA704-737
CHA704-738
CHA704-742
CHA704-743
CHA704-744
CHA704-747
CHA704-750
CHA704-752
CHA704-753
CHA704-755
CHA704-756
CHA704-757
5

QTY (UM)

KEYWORD

1
1
2
1
1
1
1
1
2
2
1
1
1
2
1
1
1
1
1
1
2
2
1
1
1
1
1
2
1
2
1
1
1
1
1
2
1
1
1
2
2
1
1
1
1
2

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SEE
NOTES

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 55
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-758
CHA704-783
NOTE:

QTY (UM)

KEYWORD

2
1

SHAFT
SHAFT

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Aircraft Maintenance Manual (AMM)


Fig. A-FBBAA
Slat Universal Joints - Measuring
positions
(a)

SEE
NOTES

References
27-81-19, Page Block 401
Sheet 01

Replace the transmission shaft linked to the affected slat universal joint on RH side:
Refer to Fig. A-FBBAA
Refer to AMM 27-81-19, Page Block 401
1

For the transmission shaft linked to the affected slat universal joint in position
4:
-

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-220


or

Shaft-Slat Transmission CHA704-220L


or

Shaft-Slat Transmission CHA704-697


or

Shaft-Slat Transmission CHA704-416


or

Shaft-Slat Transmission CHA704-737


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
5 and 6:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-222


or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 56
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Slat Transmission CHA704-222L


or

Shaft-Slat Transmission CHA704-698


or

Shaft-Slat Transmission CHA704-420


or

Shaft-Slat Transmission CHA704-738


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
7:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-223


or

Shaft-Slat Transmission CHA704-223L


or

Shaft-Slat Transmission CHA704-702


or

Shaft-Slat Transmission CHA704-428


or

Shaft-Slat Transmission CHA704-742


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
9:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-224


or

Shaft-Slat Transmission CHA704-224L


or

Shaft-Slat Transmission CHA704-704

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 57
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
1

Shaft-Slat Transmission CHA704-427


or

Shaft-Slat Transmission CHA704-729


or

Shaft-Slat Transmission CHA704-369


or

Shaft-Slat Transmission CHA704-369L


or

Shaft-Slat Transmission CHA704-705


or

Shaft-Slat Transmission CHA704-450


or

Shaft-Slat Transmission CHA704-730


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
12:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-225


or

Shaft-Slat Transmission CHA704-225L


or

Shaft-Slat Transmission CHA704-706


or

Shaft-Slat Transmission CHA704-431


or

Shaft-Slat Transmission CHA704-743


or

Shaft-Slat Transmission CHA704-357


or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 58
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Slat Transmission CHA704-357L


or

Shaft-Slat Transmission CHA704-707


or

Shaft-Slat Transmission CHA704-453


or

Shaft-Slat Transmission CHA704-731


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
13:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-226


or

Shaft-Slat Transmission CHA704-226L


or

Shaft-Slat Transmission CHA704-708


or

Shaft-Slat Transmission CHA704-435


or

Shaft-Slat Transmission CHA704-744


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
15 or 16:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-227


or

Shaft-Slat Transmission CHA704-227L


or

Shaft-Slat Transmission CHA704-711

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 59
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
2

Shaft-Slat Transmission CHA704-443


or

Shaft-Slat Transmission CHA704-747


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
17 or 18:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-228


or

Shaft-Slat Transmission CHA704-228L


or

Shaft-Slat Transmission CHA704-714


or

Shaft-Slat Transmission CHA704-444


or

Shaft-Slat Transmission CHA704-750


NOTE:

For the transmission shaft linked to the affected slat universal joint in position
19:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-229


or

Shaft-Slat Transmission CHA704-229L


or

Shaft-Slat Transmission CHA704-716


or

Shaft-Slat Transmission CHA704-425


or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 60
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Slat Transmission CHA704-752


NOTE:

10

For the transmission shaft linked to the affected slat universal joint in position
22:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-231


or

Shaft-Slat Transmission CHA704-231L


or

Shaft-Slat Transmission CHA704-717


or

Shaft-Slat Transmission CHA704-439


or

Shaft-Slat Transmission CHA704-732


NOTE:

11

For the transmission shaft linked to the affected slat universal joint in position
23:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-232


or

Shaft-Slat Transmission CHA704-232L


or

Shaft-Slat Transmission CHA704-718


or

Shaft-Slat Transmission CHA704-433


or

Shaft-Slat Transmission CHA704-753


NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 61
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

12

For the transmission shaft linked to the affected slat universal joint in position
27:
-

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-235


or

Shaft-Slat Transmission CHA704-235L


or

Shaft-Slat Transmission CHA704-720


or

Shaft-Slat Transmission CHA704-438


or

Shaft-Slat Transmission CHA704-755


NOTE:

13

For the transmission shaft linked to the affected slat universal joint in position
28:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-236


or

Shaft-Slat Transmission CHA704-236L


or

Shaft-Slat Transmission CHA704-721


or

Shaft-Slat Transmission CHA704-437


or

Shaft-Slat Transmission CHA704-756


NOTE:

14

For the transmission shaft linked to the affected slat universal joint in position
32 or 33:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 62
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Slat Transmission CHA704-239


or

Shaft-Slat Transmission CHA704-239L


or

Shaft-Slat Transmission CHA704-722


or

Shaft-Slat Transmission CHA704-434


or

Shaft-Slat Transmission CHA704-757


NOTE:

15

For the transmission shaft linked to the affected slat universal joint in position
37:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-242


or

Shaft-Slat Transmission CHA704-242L


or

Shaft-Slat Transmission CHA704-723


or

Shaft-Slat Transmission CHA704-436


or

Shaft-Slat Transmission CHA704-783


NOTE:

16

For the transmission shaft linked to the affected slat universal joint in position
38 or 39:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Slat Transmission CHA704-243


or

Shaft-Slat Transmission CHA704-243L

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 63
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
2

Shaft-Slat Transmission CHA704-724


or

Shaft-Slat Transmission CHA704-429


or

Shaft-Slat Transmission CHA704-758


NOTE:

(3)

From
To

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Subtask 270205-833-002-001 - Depending on inspection results, replace the Steady


Bearing linked to the affected Slat Universal Joints on LH Side
Work Zones and Access Panels
Access/Work location

Zone
510
520

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA02
ITEM NEW PART N
CHA704-168
CHA704-168L
CHA704-215
CHA704-215L
CHA704-216
CHA704-216L
CHA704-217
CHA704-217L
CHA704-370
CHA704-413
CHA704-441
CHA704-449
CHA704-695
CHA704-696
CHA704-710
CHA704-719
CHA704-727
5

QTY (UM)

KEYWORD

1
1
1
1
3
3
2
2
1
2
1
3
1
2
1
3
2

BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING

DATE: Sep 11/15

SEE
NOTES

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 64
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-736
CHA704-746
CHA704-754
CHA704-820
CHA722-189
CHA722-189L
CHA722-300
CHA722-392
CHA722-419
NOTE:

QTY (UM)

KEYWORD

1
1
3
3
8
8
8
8
8

BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Aircraft Maintenance Manual (AMM)


Fig. A-FBBAA
Slat Universal Joints - Measuring
positions
(a)

SEE
NOTES

References
27-81-17, Page Block 401
27-81-21, Page Block 401
Sheet 01

Replace the steady bearing linked to the affected slat universal joint on LH side:
Refer to Fig. A-FBBAA
Refer to AMM 27-81-21, Page Block 401 and AMM 27-81-17, Page Block 401
1

For the steady bearing linked to the affected slat universal joint in position 1:
-

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA704-168

or
1

Bearing-Steady

CHA704-168L

or
1

Bearing-Steady

CHA704-695

or
1

Bearing-Steady

CHA704-370

or
1

Bearing-Steady
NOTE:

CHA704-736
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 65
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

For the steady bearing linked to the affected slat universal joint in position 2 or
3:
-

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA704-217

or
2

Bearing-Steady

CHA704-217L

or
2

Bearing-Steady

CHA704-696

or
2

Bearing-Steady

CHA704-413

or
2

Bearing-Steady
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the steady bearing linked to the affected slat universal joint in position 14:
-

CHA704-727

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA704-215

or
1

Bearing-Steady

CHA704-215L

or
1

Bearing-Steady

CHA704-710

or
1

Bearing-Steady

CHA704-441

or
1

Bearing-Steady
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the steady bearing linked to the affected slat universal joint in position 20
or 21 or 24 or 25 or 30 or 31 or 34 or 35:
-

CHA704-746

Remove the steady bearing and replace by the same PN:

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 66
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Bearing-Steady

CHA722-189

or
8

Bearing-Steady

CHA722-189L

or
8

Bearing-Steady

CHA722-392

or
8

Bearing-Steady

CHA722-300

or
8

Bearing-Steady
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the steady bearing linked to the affected slat universal joint in position 26
or 29 or 36:
-

CHA722-419

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA704-216

or
3

Bearing-Steady

CHA704-216L

or
3

Bearing-Steady

CHA704-719

or
3

Bearing-Steady

CHA704-449

or
3

Bearing-Steady

CHA704-754

or
3

Bearing-Steady
NOTE:

CHA704-820
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 67
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(4)

From
To

Subtask 270205-833-006-001 - Depending on inspection results, replace the Steady


Bearing linked to the affected Slat Universal Joints on RH Side
Work Zones and Access Panels
Access/Work location

Zone
610
620

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA02
ITEM NEW PART N
CHA704-168
CHA704-168L
CHA704-215
CHA704-215L
CHA704-216
CHA704-216L
CHA704-217
CHA704-217L
CHA704-370
CHA704-413
CHA704-441
CHA704-449
CHA704-695
CHA704-696
CHA704-710
CHA704-719
CHA704-727
CHA704-736
CHA704-746
CHA704-754
CHA704-820
CHA722-189
CHA722-189L
CHA722-300
CHA722-392
CHA722-419
NOTE:

QTY (UM)

KEYWORD

1
1
1
1
3
3
2
2
1
2
1
3
1
2
1
3
2
1
1
3
3
8
8
8
8
8

BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING
BEARING

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 68
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Aircraft Maintenance Manual (AMM)


Fig. A-FBBAA
Slat Universal Joints - Measuring
positions
(a)

References
27-81-17, Page Block 401
27-81-21, Page Block 401
Sheet 01

Replace the steady bearing linked to the affected slat universal joint on RH side
Refer to Fig. A-FBBAA
Refer to AMM 27-81-21, Page Block 401 and AMM 27-81-17, Page Block 401
1

For the steady bearing linked to the affected slat universal joint in position 1:
-

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA704-168

or
1

Bearing-Steady

CHA704-168L

or
1

Bearing-Steady

CHA704-695

or
1

Bearing-Steady

CHA704-370

or
1

Bearing-Steady
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the steady bearing linked to the affected slat universal joint in position 2 or
3:
-

CHA704-736

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA704-217

or
2

Bearing-Steady

CHA704-217L

or
2

Bearing-Steady

CHA704-696

or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 69
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Bearing-Steady

CHA704-413

or
2

Bearing-Steady
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the steady bearing linked to the affected slat universal joint in position 14:
-

CHA704-727

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA704-215

or
1

Bearing-Steady

CHA704-215L

or
1

Bearing-Steady

CHA704-710

or
1

Bearing-Steady

CHA704-441

or
1

Bearing-Steady
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the steady bearing linked to the affected slat universal joint in position 20
or 21 or 24 or 25 or 30 or 31 or 34 or 35:
-

CHA704-746

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA722-189

or
8

Bearing-Steady

CHA722-189L

or
8

Bearing-Steady

CHA722-392

or
8

Bearing-Steady

CHA722-300

or
8
5

Bearing-Steady

DATE: Sep 11/15

CHA722-419
SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 70
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

NOTE:

For the steady bearing linked to the affected slat universal joint in position 26
or 29 or 36:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA704-216

or
3

Bearing-Steady

CHA704-216L

or
3

Bearing-Steady

CHA704-719

or
3

Bearing-Steady

CHA704-449

or
3

Bearing-Steady

CHA704-754

or
3

Bearing-Steady

CHA704-820

NOTE:

(5)

From
To

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Subtask 270205-833-003-001 - Depending on inspection results, replace the


Coupling Box linked to the affected Slat Universal Joints on LH Side
Work Zones and Access Panels
Access/Work location

Zone
510
520

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA03
ITEM NEW PART N
CHA704-214
5

QTY (UM)

KEYWORD

COUPLING

DATE: Sep 11/15

SEE
NOTES

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 71
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA704-214L
CHA704-424
CHA704-703
CHA704-728
NOTE:

QTY (UM)

KEYWORD

1
1
1
1

COUPLING
COUPLING
COUPLING
COUPLING

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

References
Aircraft Maintenance Manual (AMM)
27-81-18, Page Block 401
Fig. A-FBBAA
Slat Universal Joints - Measuring
positions
(a)

Sheet 01

Replace the coupling box linked to the affected slat universal joint on LH side:
Refer to Fig. A-FBBAA
Refer to AMM 27-81-18, Page Block 401
1

For the coupling box linked to the affected slat universal joint in position 8:
-

Remove the coupling box and replace by the same PN:

Box-Coupling

CHA704-214

or
1

Box-Coupling

CHA704-214L

or
1

Box-Coupling

CHA704-703

or
1

Box-Coupling

CHA704-424

or
1

Box-Coupling

CHA704-728
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

NOTE:

(6)

From

Subtask 270205-833-007-001 - Depending on inspection results, replace the


Coupling Box linked to the affected Slat Universal Joints on RH Side

Zone
610

Work Zones and Access Panels


Access/Work location

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 72
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

To

620
Manpower Resources

Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA03
ITEM NEW PART N
CHA704-214
CHA704-214L
CHA704-424
CHA704-703
CHA704-728
NOTE:

QTY (UM)

KEYWORD

1
1
1
1
1

COUPLING
COUPLING
COUPLING
COUPLING
COUPLING

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Aircraft Maintenance Manual (AMM)


Fig. A-FBBAA
Slat Universal Joints - Measuring
positions
(a)

SEE
NOTES

References
27-81-18, Page Block 401
Sheet 01

Replace the coupling box linked to the affected slat universal joint on RH side:
Refer to Fig. A-FBBAA
Refer to AMM 27-81-18, Page Block 401
1

For the coupling box linked to the affected slat universal joint in position 8:
-

Remove the coupling box and replace by the same PN:

Box-Coupling

CHA704-214

or
1

Box-Coupling

CHA704-214L

or
1

Box-Coupling

CHA704-703

or
1

Box-Coupling

DATE: Sep 11/15

CHA704-424

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 73
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
1

Box-Coupling

CHA704-728

NOTE:

(7)

From
To

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Subtask 270205-833-004-001 - Depending on inspection results, replace the


Stepback Gearbox linked to the affected Slat Universal Joints on LH Side
Work Zones and Access Panels
Access/Work location

Zone
510
520

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA04
ITEM NEW PART N
CHA1001-002
CHA1001-004A
CHA1001-005
CHA1001-005A
CHA1001-006A
CHA1001-008B
CHA1001-008C
CHA701-002
CHA701-002L
CHA701-002R
CHA701-003A
CHA701-004A
CHA701-005A
CHA701-006A
NOTE:

QTY (UM)

KEYWORD

2
2
2
2
2
2
2
2
2
2
2
2
2
2

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Aircraft Maintenance Manual (AMM)


Fig. A-FBBAA
Slat Universal Joints - Measuring
positions

SEE
NOTES

DATE: Sep 11/15

References
27-81-16, Page Block 401
Sheet 01

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 74
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(a)

Replace the stepback gearbox linked to the affected slat universal joint on LH side:
Refer to Fig. A-FBBAA
Refer to AMM 27-81-16, Page Block 401
1

For the stepback gearbox lint to the affected slat universal joint in position 10
or 11:
-

Remove the stepback gearbox and replace by the same PN:

Gearbox-Stepback

CHA701-002

or
2

Gearbox-Stepback

CHA701-002L

or
2

Gearbox-Stepback

CHA701-002R

or
2

Gearbox-Stepback

CHA701-003A

or
2

Gearbox-Stepback

CHA701-004A

or
2

Gearbox-Stepback

CHA701-005A

or
2

Gearbox-Stepback

CHA701-006A

or
2

Gearbox-Stepback

CHA1001-002

or
2

Gearbox-Stepback

CHA1001-004A

or
2

Gearbox-Stepback

CHA1001-005

or
2

Gearbox-Stepback

CHA1001-005A

or
2

Gearbox-Stepback

DATE: Sep 11/15

CHA1001-006A

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 75
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
2

Gearbox-Stepback

CHA1001-008B

or
2

Gearbox-Stepback
NOTE:

(8)

CHA1001-008C
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

Subtask 270205-833-008-001 - Depending on inspection results, replace the


Stepback Gearbox linked to the affected Slat Universal Joints on RH Side
Manpower Resources

Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

NON SPECIFIC
Material necessary to do the job

Equipment BFEA04
ITEM NEW PART N
CHA1001-002
CHA1001-004A
CHA1001-005
CHA1001-005A
CHA1001-006A
CHA1001-008B
CHA1001-008C
CHA701-002
CHA701-002L
CHA701-002R
CHA701-003A
CHA701-004A
CHA701-005A
CHA701-006A
NOTE:

QTY (UM)

KEYWORD

2
2
2
2
2
2
2
2
2
2
2
2
2
2

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Aircraft Maintenance Manual (AMM)


Fig. A-FBBAA
Slat Universal Joints - Measuring
positions

SEE
NOTES

DATE: Sep 11/15

References
27-81-16, Page Block 401
Sheet 01

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 76
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(a)

Replace the stepback gearbox linked to the affected slat universal joint on RH side:
Refer to Fig. A-FBBAA
Refer to AMM 27-81-16, Page Block 401
1

For the stepback gearbox lint to the affected slat universal joint in position 10
or 11:
-

Remove the stepback gearbox and replace by the same PN:

Gearbox-Stepback

CHA701-002

or
2

Gearbox-Stepback

CHA701-002L

or
2

Gearbox-Stepback

CHA701-002R

or
2

Gearbox-Stepback

CHA701-003A

or
2

Gearbox-Stepback

CHA701-004A

or
2

Gearbox-Stepback

CHA701-005A

or
2

Gearbox-Stepback

CHA701-006A

or
2

Gearbox-Stepback

CHA1001-002

or
2

Gearbox-Stepback

CHA1001-004A

or
2

Gearbox-Stepback

CHA1001-005

or
2

Gearbox-Stepback

CHA1001-005A

or
2

Gearbox-Stepback

DATE: Sep 11/15

CHA1001-006A

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 77
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
2

Gearbox-Stepback

CHA1001-008B

or
2

Gearbox-Stepback
NOTE:

(9)

From
To

CHA1001-008C
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

Subtask 270205-833-009-001 - Depending on inspection results, replace the


Transmission Shaft linked to the affected Flap Universal Joints on LH Side
Work Zones and Access Panels
Access/Work location

Zone
570
580

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA05
ITEM NEW PART N
CHA722-147
CHA722-147L
CHA722-155
CHA722-155L
CHA722-158
CHA722-158L
CHA722-159
CHA722-159L
CHA722-161
CHA722-161L
CHA722-162
CHA722-162L
CHA722-170
CHA722-170L
CHA722-191
CHA722-191L
CHA722-192
CHA722-192L
CHA722-303

QTY (UM)

KEYWORD

1
1
1
1
1
1
2
2
1
1
1
1
1
1
1
1
1
1
1

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SEE
NOTES

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 78
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA722-304
CHA722-305
CHA722-307
CHA722-308
CHA722-309
CHA722-310
CHA722-311
CHA722-318
CHA722-388
CHA722-389
CHA722-393
CHA722-394
CHA722-396
CHA722-398
CHA722-399
CHA722-400
CHA722-402
CHA722-403
CHA722-404
CHA722-410
CHA722-411
CHA722-424
CHA722-436
CHA722-438
CHA722-439
CHA722-442
CHA722-443
NOTE:

QTY (UM)

KEYWORD

1
1
1
2
1
1
1
1
1
1
1
1
1
2
1
1
2
1
1
2
1
1
1
1
1
1
1

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

References
Aircraft Maintenance Manual (AMM)
27-51-36, Page Block 401
Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

Sheet 01

Replace the transmission shaft linked to the affected flap universal joint on LH side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-36, Page Block 401
1

For the transmission shaft linked to the affected flap universal joint in position
2:
-

Remove the transmission shaft and replace by the same PN:

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 79
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Flap
Transmission

CHA722-147

or
1

Shaft-Flap
Transmission

CHA722-147L

or
1

Shaft-Flap
Transmission

CHA722-436

or
1

Shaft-Flap
Transmission

CHA722-303

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
3:
-

CHA722-438

Remove the transmission shaft and replace by the same PN:

Shaft Assy

CHA722-155

or
1

Shaft-Flap
Transmission

CHA722-155L

or
1

Shaft-Flap
Transmission

CHA722-388

or
1

Shaft-Flap
Transmission

CHA722-304

or
1

Shaft-Flap
Transmission
NOTE:

CHA722-439
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 80
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

For the transmission shaft linked to the affected flap universal joint in position
5:
-

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-170

or
1

Shaft-Flap
Transmission

CHA722-170L

or
1

Shaft-Flap
Transmission

CHA722-389

or
1

Shaft-Flap
Transmission

CHA722-311

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
10:
-

CHA722-411

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-191

or
1

Shaft-Flap
Transmission

CHA722-191L

or
1

Shaft-Flap
Transmission

CHA722-393

or
1

Shaft-Flap
Transmission

CHA722-305

or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 81
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
12:
-

CHA722-442

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-192

or
1

Shaft-Flap
Transmission

CHA722-192L

or
1

Shaft-Flap
Transmission

CHA722-394

or
1

Shaft-Flap
Transmission

CHA722-318

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
13:
-

CHA722-443

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-158

or
1

Shaft-Flap
Transmission

CHA722-158L

or
1

Shaft-Flap
Transmission

CHA722-396

or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 82
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Flap
Transmission

CHA722-307

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
15 or 17:
-

CHA722-424

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-159

or
2

Shaft-Flap
Transmission

CHA722-159L

or
2

Shaft-Flap
Transmission

CHA722-398

or
2

Shaft-Flap
Transmission

CHA722-308

or
2

Shaft-Flap
Transmission

CHA722-402

or
2

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
20:
-

CHA722-410

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-161

or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 83
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Flap
Transmission

CHA722-161L

or
1

Shaft-Flap
Transmission

CHA722-399

or
1

Shaft-Flap
Transmission

CHA722-309

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
23:
-

CHA722-403

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-162

or
1

Shaft-Flap
Transmission

CHA722-162L

or
1

Shaft-Flap
Transmission

CHA722-400

or
1

Shaft-Flap
Transmission

CHA722-310

or
1

Shaft-Flap
Transmission
NOTE:

CHA722-404
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 84
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(10) Subtask 270205-833-010-001 - Depending on inspection results, replace the


Transmission Shaft linked to the affected Flap Universal Joints on RH Side

From
To

Work Zones and Access Panels


Access/Work location

Zone
670
680

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA12
ITEM NEW PART N
CHA722-146
CHA722-146L
CHA722-155
CHA722-155L
CHA722-158
CHA722-158L
CHA722-159
CHA722-159L
CHA722-161
CHA722-161L
CHA722-162
CHA722-162L
CHA722-170
CHA722-170L
CHA722-191
CHA722-191L
CHA722-192
CHA722-192L
CHA722-302
CHA722-304
CHA722-305
CHA722-307
CHA722-308
CHA722-309
CHA722-310
CHA722-311
CHA722-318
CHA722-388
CHA722-389
5

QTY (UM)

KEYWORD

1
1
1
1
1
1
2
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

DATE: Sep 11/15

SEE
NOTES

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 85
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA722-393
CHA722-394
CHA722-396
CHA722-398
CHA722-399
CHA722-400
CHA722-402
CHA722-403
CHA722-404
CHA722-410
CHA722-411
CHA722-424
CHA722-435
CHA722-437
CHA722-439
CHA722-442
CHA722-443
NOTE:

QTY (UM)

KEYWORD

1
1
1
2
1
1
2
1
1
2
1
1
1
1
1
1
1

SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT
SHAFT

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

References
Aircraft Maintenance Manual (AMM)
27-51-36, Page Block 401
Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

Sheet 01

Replace the transmission shaft linked to the affected flap universal joint on RH side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-36, Page Block 401
1

For the transmission shaft linked to the affected flap universal joint in position
2:
-

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-146

or
1

Shaft-Flap
Transmission

CHA722-146L

or
1

Shaft-Flap
Transmission

DATE: Sep 11/15

CHA722-435

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 86
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
1

Shaft-Flap
Transmission

CHA722-302

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
3:
-

CHA722-437

Remove the transmission shaft and replace by the same PN:

Shaft Assy

CHA722-155

or
1

Shaft-Flap
Transmission

CHA722-155L

or
1

Shaft-Flap
Transmission

CHA722-388

or
1

Shaft-Flap
Transmission

CHA722-304

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
5:
-

CHA722-439

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-170

or
1

Shaft-Flap
Transmission

CHA722-170L

or
5

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 87
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Flap
Transmission

CHA722-389

or
1

Shaft-Flap
Transmission

CHA722-311

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
10:
-

CHA722-411

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-191

or
1

Shaft-Flap
Transmission

CHA722-191L

or
1

Shaft-Flap
Transmission

CHA722-393

or
1

Shaft-Flap
Transmission

CHA722-305

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
12:
-

CHA722-442

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-192

or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 88
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Flap
Transmission

CHA722-192L

or
1

Shaft-Flap
Transmission

CHA722-394

or
1

Shaft-Flap
Transmission

CHA722-318

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
13:
-

CHA722-443

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-158

or
1

Shaft-Flap
Transmission

CHA722-158L

or
1

Shaft-Flap
Transmission

CHA722-396

or
1

Shaft-Flap
Transmission

CHA722-307

or
1

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
15 or 17:
-

CHA722-424

Remove the transmission shaft and replace by the same PN:

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 89
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Flap
Transmission

CHA722-159

or
2

Shaft-Flap
Transmission

CHA722-159L

or
2

Shaft-Flap
Transmission

CHA722-398

or
2

Shaft-Flap
Transmission

CHA722-308

or
2

Shaft-Flap
Transmission

CHA722-402

or
2

Shaft-Flap
Transmission
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the transmission shaft linked to the affected flap universal joint in position
20:
-

CHA722-410

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-161

or
1

Shaft-Flap
Transmission

CHA722-161L

or
1

Shaft-Flap
Transmission

CHA722-399

or
1

Shaft-Flap
Transmission

CHA722-309

or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 90
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Shaft-Flap
Transmission

CHA722-403

NOTE:

For the transmission shaft linked to the affected flap universal joint in position
23:
-

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

Remove the transmission shaft and replace by the same PN:

Shaft-Flap
Transmission

CHA722-162

or
1

Shaft-Flap
Transmission

CHA722-162L

or
1

Shaft-Flap
Transmission

CHA722-400

or
1

Shaft-Flap
Transmission

CHA722-310

or
1

Shaft-Flap
Transmission

CHA722-404

NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

(11) Subtask 270205-833-011-001 - Depending on inspection results, replace the Tee


Gear Box linked to the affected Flap Universal Joints on LH Side

From
To

Work Zones and Access Panels


Access/Work location

Zone
570
580

Manpower Resources

Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 91
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Material necessary to do the job


Equipment BFEA06
ITEM NEW PART N
CHA707-002L
CHA707-003A
CHA707-004A
CHA707-005A
CHA707-005B
CHA707-005C
NOTE:

QTY (UM)

KEYWORD

1
1
1
1
1
1

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

References
Aircraft Maintenance Manual (AMM)
27-51-23, Page Block 401
Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

Sheet 01

Replace the tee gear box linked to the affected flap universal joint on LH side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-23, Page Block 401
1

For the tee gear box linked to the affected flap universal joint in position 4:
-

Remove the tee gear box and replace by the same PN:

Gearbox-Flap Tee

CHA707-002L

or
1

Gearbox-Flap Tee

CHA707-003A

or
1

Gearbox-Flap Tee

CHA707-004A

or
1

Gearbox-Flap Tee

CHA707-005A

or
1

Gearbox-Flap Tee

CHA707-005B

or
1

Gearbox-Flap Tee

DATE: Sep 11/15

CHA707-005C

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 92
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

(12) Subtask 270205-833-012-001 - Depending on inspection results, replace the Tee


Gear Box linked to the affected Flap Universal Joints on RH Side
Work Zones and Access Panels
Access/Work location

Zone
670
680

From
To

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA06
ITEM NEW PART N
CHA707-002L
CHA707-003A
CHA707-004A
CHA707-005A
CHA707-005B
CHA707-005C
NOTE:

QTY (UM)

KEYWORD

1
1
1
1
1
1

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

References
Aircraft Maintenance Manual (AMM)
27-51-23, Page Block 401
Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

Sheet 01

Replace the tee gear box linked to the affected flap universal joint on RH side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-23, Page Block 401
1

For the tee gear box linked to the affected flap universal joint in position 4:
-

Remove the tee gear box and replace by the same PN:

Gearbox-Flap Tee

CHA707-002L

or
5

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 93
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Gearbox-Flap Tee

CHA707-003A

or
1

Gearbox-Flap Tee

CHA707-004A

or
1

Gearbox-Flap Tee

CHA707-005A

or
1

Gearbox-Flap Tee

CHA707-005B

or
1

Gearbox-Flap Tee
NOTE:

CHA707-005C
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

(13) Subtask 270205-833-013-001 - Depending on inspection results, replace the Bevel


Gearbox linked to the affected Flap Universal Joints on LH Side

From
To

Work Zones and Access Panels


Access/Work location

Zone
570
580

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA07
ITEM NEW PART N
CHA1154-001AL
CHA1154-002A
CHA1154-003A
CHA1154-003AL
CHA1154-004A
CHA1159-001
CHA1159-001A
CHA1159-002A
CHA1159-003A
CHA1159-005A
CHA1159-006B
5

QTY (UM)

KEYWORD

2
2
2
2
2
2
2
2
2
2
2

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

DATE: Sep 11/15

SEE
NOTES

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 94
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

ITEM NEW PART N


CHA1159-006C
NOTE:

QTY (UM)

KEYWORD

GEARBOX

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

References
Aircraft Maintenance Manual (AMM)
27-51-24, Page Block 401
Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

Sheet 01

Replace the bevel gearbox linked to the affected Flap Universal Joint on LH side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-24, Page Block 401
1

For the bevel gearbox linked to the affected universal joint in position 6 or 7:
-

Remove the bevel gearbox and replace by the same PN:

Gearbox-Bevel LH

CHA1154-001AL

or
2

Gearbox-Bevel LH

CHA1154-002A

or
2

Gearbox-Bevel LH

CHA1154-003A

or
2

Gearbox-Bevel LH

CHA1154-003AL

or
2

Gearbox-Bevel LH

CHA1154-004A

or
2

Gearbox-Bevel LH

CHA1159-001

or
2

Gearbox-Bevel LH

CHA1159-001A

or
2

Gearbox-Bevel LH

CHA1159-002A

or
2

Gearbox-Bevel LH

DATE: Sep 11/15

CHA1159-003A

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 95
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
2

Gearbox-Bevel LH

CHA1159-005A

or
2

Gearbox-Bevel LH

CHA1159-006B

or
2

Gearbox-Bevel LH
NOTE:

CHA1159-006C
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

(14) Subtask 270205-833-014-001 - Depending on inspection results, replace the Bevel


Gearbox linked to the affected Flap Universal Joints on RH Side

From
To

Work Zones and Access Panels


Access/Work location

Zone
670
680

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA13
ITEM NEW PART N
CHA1170-001A
CHA1170-001AL
CHA1170-002
CHA1170-002A
CHA1170-003A
CHA1170-003AL
CHA1170-004A
CHA1171-001
CHA1171-001A
CHA1171-002A
CHA1171-003A
CHA1171-004A
CHA1171-005A
NOTE:

QTY (UM)

KEYWORD

2
2
2
2
2
2
2
2
2
2
2
2
2

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 96
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Aircraft Maintenance Manual (AMM)


Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

References
27-51-24, Page Block 401
Sheet 01

Replace the bevel gearbox linked to the affected Universal Joint on RH side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-24, Page Block 401
1

For the bevel gearbox linked to the affected flap universal joint in position 6 or
7:
-

Remove the bevel gearbox and replace by the same PN:

Gearbox-Bevel RH

CHA1170-001A

or
2

Gearbox-Bevel RH

CHA1170-001AL

or
2

Gearbox-Bevel RH

CHA1170-002

or
2

Gearbox-Bevel RH

CHA1170-002A

or
2

Gearbox-Bevel RH

CHA1170-003A

or
2

Gearbox-Bevel RH

CHA1170-003AL

or
2

Gearbox-Bevel RH

CHA1170-004A

or
2

Gearbox-Bevel RH

CHA1171-001

or
2

Gearbox-Bevel RH

CHA1171-001A

or
2

Gearbox-Bevel RH

CHA1171-002A

or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 97
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Gearbox-Bevel RH

CHA1171-003A

or
2

Gearbox-Bevel RH

CHA1171-004A

or
2

Gearbox-Bevel RH
NOTE:

CHA1171-005A
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

(15) Subtask 270205-833-015-001 - Depending on inspection results, replace the Steady


Bearing linked to the affected Flap Universal Joints on LH Side
Work Zones and Access Panels
Access/Work location

Zone
570
580

From
To

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA08
ITEM NEW PART N
CHA722-189
CHA722-189L
CHA722-300
CHA722-392
CHA722-419
NOTE:

QTY (UM)

KEYWORD

5
5
5
5
5

BEARING
BEARING
BEARING
BEARING
BEARING

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Aircraft Maintenance Manual (AMM)


Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

SEE
NOTES

References
27-51-38, Page Block 401
Sheet 01

Replace the steady bearing linked to the affected Flap Universal Joint on LH side:
Refer to Fig. A-FBAAA

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 98
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Refer to AMM 27-51-38, Page Block 401


1

For the steady bearing linked to the affected flap universal joint in position 8 or
11 or 18 or 21 or 24:
-

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA722-189

or
5

Bearing-Steady

CHA722-189L

or
5

Bearing-Steady

CHA722-392

or
5

Bearing-Steady

CHA722-300

or
5

Bearing-Steady

CHA722-419

NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

(16) Subtask 270205-833-016-001 - Depending on inspection results, replace the Steady


Bearing linked to the affected Flap Universal Joints on RH Side

From
To

Work Zones and Access Panels


Access/Work location

Zone
670
680

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA08
ITEM NEW PART N
CHA722-189
CHA722-189L
CHA722-300
CHA722-392
CHA722-419
5

QTY (UM)

KEYWORD

5
5
5
5
5

BEARING
BEARING
BEARING
BEARING
BEARING

DATE: Sep 11/15

SEE
NOTES

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 99
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

NOTE:

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Aircraft Maintenance Manual (AMM)


Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

References
27-51-38, Page Block 401
Sheet 01

Replace the steady bearing linked to the affected flap universal joint on RH side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-38, Page Block 401
1

For the steady bearing linked to the affected flap universal joint in position 8 or
11 or 18 or 21 or 24:
-

Remove the steady bearing and replace by the same PN:

Bearing-Steady

CHA722-189

or
5

Bearing-Steady

CHA722-189L

or
5

Bearing-Steady

CHA722-392

or
5

Bearing-Steady

CHA722-300

or
5

Bearing-Steady

CHA722-419
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

NOTE:

(17) Subtask 270205-833-017-001 - Depending on inspection results, replace the


Downdrive Gearbox linked to the affected Flap Universal Joints on LH Side

From
To

Zone
570
580

Work Zones and Access Panels


Access/Work location

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 100
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA09
ITEM NEW PART N
CHA1006-003
CHA1006-003B
CHA1006-003BL
CHA1006-003BR
CHA1006-003L
CHA1006-003R
CHA1006-005A
CHA1006-006A
CHA1006-007A
CHA719-002
CHA719-002L
CHA719-002R
CHA719-003A
CHA719-004A
CHA719-005A
CHA719-005B
CHA720-002
CHA720-002L
CHA720-002R
CHA720-003A
CHA720-004A
CHA720-005A
CHA720-005B
NOTE:

QTY (UM)

KEYWORD

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3
3
3
3
3
3
3

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

References
Aircraft Maintenance Manual (AMM)
27-51-34, Page Block 401
27-51-35, Page Block 401
Fig. A-FBAAA
Flap Universal Joints - Measuring
positions

DATE: Sep 11/15

Sheet 01

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 101
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

(a)

Replace the downdrive gearbox linked to the affected flap universal joint on LH
side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-34, Page Block 401
Refer to AMM 27-51-35, Page Block 401
1

For the downdrive gearbox linked to the affected flap universal joint in position
9:
-

Remove the downdrive gearbox and replace by the same PN:

Gearbox-Downdrive

CHA719-002

or
1

Gearbox-Downdrive

CHA719-002L

or
1

Gearbox-Downdrive

CHA719-002R

or
1

Gearbox-Downdrive

CHA719-003A

or
1

Gearbox-Downdrive

CHA719-004A

or
1

Gearbox-Downdrive

CHA719-005A

or
1

Gearbox-Downdrive
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the downdrive gearbox linked to the affected flap universal joint in position
16 or 19 or 22:
-

CHA719-005B

Remove the downdrive gearbox and replace by the same PN:

Gearbox-Downdrive

CHA720-002

or
3

Gearbox-Downdrive

CHA720-002L

or
3

Gearbox-Downdrive

DATE: Sep 11/15

CHA720-002R

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 102
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
3

Gearbox-Downdrive

CHA720-003A

or
3

Gearbox-Downdrive

CHA720-004A

or
3

Gearbox-Downdrive

CHA720-005A

or
3

Gearbox-Downdrive
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the downdrive gearbox linked to the affected flap universal joint in position
25:
-

CHA720-005B

Remove the downdrive gearbox and replace by the same PN:

Gearbox-Downdrive

CHA1006-003

or
1

Gearbox-Downdrive

CHA1006-003B

or
1

Gearbox-Downdrive

CHA1006-003L

or
1

Gearbox-Downdrive

CHA1006-003R

or
1

Gearbox-Downdrive

CHA1006-003BL

or
1

Gearbox-Downdrive

CHA1006-003BR

or
1

Gearbox-Downdrive

CHA1006-005A

or
1

Gearbox-Downdrive

CHA1006-006A

or
1

Gearbox-Downdrive
NOTE:

CHA1006-007A
Cross reference to the associated IPC for other optional

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 103
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

replacing part numbers or contact AIRBUS.


(18) Subtask 270205-833-018-001 - Depending on inspection results, replace the
Downdrive Gearbox linked to the affected Flap Universal Joints on RH Side

From
To

Work Zones and Access Panels


Access/Work location

Zone
670
680

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA09
ITEM NEW PART N
CHA1006-003
CHA1006-003B
CHA1006-003BL
CHA1006-003BR
CHA1006-003L
CHA1006-003R
CHA1006-005A
CHA1006-006A
CHA1006-007A
CHA719-002
CHA719-002L
CHA719-002R
CHA719-003A
CHA719-004A
CHA719-005A
CHA719-005B
CHA720-002
CHA720-002L
CHA720-002R
CHA720-003A
CHA720-004A
CHA720-005A
CHA720-005B
NOTE:

QTY (UM)

KEYWORD

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3
3
3
3
3
3
3

GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX
GEARBOX

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 104
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Aircraft Maintenance Manual (AMM)


Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

References
27-51-34, Page Block 401
27-51-35, Page Block 401
Sheet 01

Replace the downdrive gearbox linked to the affected flap universal joint on RH
side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-34, Page Block 401
Refer to AMM 27-51-35, Page Block 401
1

For the downdrive gearbox linked to the affected flap universal joint in position
9:
-

Remove the downdrive gearbox and replace by the same PN:

Gearbox-Downdrive

CHA719-002

or
1

Gearbox-Downdrive

CHA719-002L

or
1

Gearbox-Downdrive

CHA719-002R

or
1

Gearbox-Downdrive

CHA719-003A

or
1

Gearbox-Downdrive

CHA719-004A

or
1

Gearbox-Downdrive

CHA719-005A

or
1

Gearbox-Downdrive
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the downdrive gearbox linked to the affected flap universal joint in position
16 or 19 or 22:
-

CHA719-005B

Remove the downdrive gearbox and replace by the same PN:

Gearbox-Downdrive

DATE: Sep 11/15

CHA720-002
SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 105
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

or
3

Gearbox-Downdrive

CHA720-002L

or
3

Gearbox-Downdrive

CHA720-002R

or
3

Gearbox-Downdrive

CHA720-003A

or
3

Gearbox-Downdrive

CHA720-004A

or
3

Gearbox-Downdrive

CHA720-005A

or
3

Gearbox-Downdrive
NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

For the downdrive gearbox linked to the affected flap universal joint in position
25:
-

CHA720-005B

Remove the downdrive gearbox and replace by the same PN:

Gearbox-Downdrive

CHA1006-003

or
1

Gearbox-Downdrive

CHA1006-003B

or
1

Gearbox-Downdrive

CHA1006-003L

or
1

Gearbox-Downdrive

CHA1006-003R

or
1

Gearbox-Downdrive

CHA1006-003BL

or
1

Gearbox-Downdrive

CHA1006-003BR

or
1

Gearbox-Downdrive

CHA1006-005A

or

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 106
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Gearbox-Downdrive

CHA1006-006A

or
1

Gearbox-Downdrive
NOTE:

CHA1006-007A
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

(19) Subtask 270205-833-019-001 - Depending on inspection results, replace the


Coupling Box linked to the affected Flap Universal Joints on LH Side
Work Zones and Access Panels
Access/Work location

Zone
570
580

From
To

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA10
ITEM NEW PART N
CHA722-188
CHA722-188L
CHA722-336
CHA722-397
CHA722-416
NOTE:

QTY (UM)

KEYWORD

1
1
1
1
1

CPLGBOX
CPLGBOX
CPLGBOX
CPLGBOX
CPLGBOX

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

Aircraft Maintenance Manual (AMM)


Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

SEE
NOTES

References
27-51-37, Page Block 401
Sheet 01

Replace the coupling box linked to the affected flap universal joint on LH side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-37, Page Block 401

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 107
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

For the coupling box linked to the affected flap universal joint in position 14:
-

Remove the coupling box and replace by the same PN

Coupling Box

CHA722-188

or
1

Coupling Box

CHA722-188L

or
1

Coupling Box

CHA722-397

or
1

Coupling Box

CHA722-336

or
1

Coupling Box

CHA722-416

NOTE:

Cross reference to the associated IPC for other optional


replacing part numbers or contact AIRBUS.

(20) Subtask 270205-833-020-001 - Depending on inspection results, replace the


Coupling Box linked to the affected Flap Universal Joints on RH Side

From
To

Work Zones and Access Panels


Access/Work location

Zone
670
680

Manpower Resources
Manhours
Minimum number of person

2.00
1

Subtask elapsed time

2.00

Skills

AIRFRAME
Material necessary to do the job

Equipment BFEA10
ITEM NEW PART N
CHA722-188
CHA722-188L
CHA722-336
CHA722-397
CHA722-416
NOTE:

QTY (UM)

KEYWORD

1
1
1
1
1

CPLGBOX
CPLGBOX
CPLGBOX
CPLGBOX
CPLGBOX

SEE
NOTES

The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 108
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Aircraft Maintenance Manual (AMM)


Fig. A-FBAAA
Flap Universal Joints - Measuring
positions
(a)

References
27-51-37, Page Block 401
Sheet 01

Replace the coupling box linked to the affected flap universal joint on RH side:
Refer to Fig. A-FBAAA
Refer to AMM 27-51-37, Page Block 401
1

For the coupling box linked to the affected flap universal joint in position 14:
-

Remove the coupling box and replace by the same PN

Coupling Box

CHA722-188

or
1

Coupling Box

CHA722-188L

or
1

Coupling Box

CHA722-397

or
1

Coupling Box

CHA722-336

or
1

Coupling Box
NOTE:

D.

CHA722-416
Cross reference to the associated IPC for other optional
replacing part numbers or contact AIRBUS.

TEST
(1)

Subtask 270205-700-001-001 - Test


Manpower Resources

Skills

NON SPECIFIC

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 109
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Aircraft Maintenance Manual (AMM)

E.

References
27-51-23,
27-51-24,
27-51-34,
27-51-35,
27-51-36,
27-51-37,
27-51-38,
27-81-16,
27-81-17,
27-81-18,
27-81-19,
27-81-21,

Page
Page
Page
Page
Page
Page
Page
Page
Page
Page
Page
Page

Block
Block
Block
Block
Block
Block
Block
Block
Block
Block
Block
Block

401
401
401
401
401
401
401
401
401
401
401
401

If replaced, do the test procedure as specified after the installation of the


Transmission Shafts, refer to AMM 27-81-19, Page Block 401.

If replaced, do the test procedure as specified after the installation of the Steady
Bearings, refer to AMM 27-81-21, Page Block 401 or AMM 27-81-17, Page Block
401.

If replaced, do the test procedure as specified after the installation of the Coupling
Box, refer to AMM 27-81-18, Page Block 401.

If replaced, do the test procedure as specified after the installation of the Stepback
Gearbox, refer to AMM 27-81-16, Page Block 401.

If replaced, do the test procedure as specified after the installation of the


Transmission Shafts, refer to AMM 27-51-36, Page Block 401.

If replaced, do the test procedure as specified after the installation of the Tee
Gearbox, refer to AMM 27-51-23, Page Block 401.

If replaced, do the test procedure as specified after the installation of the Simplex
Bevel Gearbox, refer to AMM 27-51-24, Page Block 401.

If replaced, do the test procedure as specified after the installation of the Steady
Bearing, refer to AMM 27-51-38, Page Block 401.

If replaced, do the test procedure as specified after the installation of the Downdrive
Gearbox, refer to AMM 27-51-34, Page Block 401 for inner flaps and/or AMM
27-51-35, Page Block 401 for center or outer flaps.

If replaced, do the test procedure as specified after the installation of the Coupling
Box, refer to AMM 27-51-37, Page Block 401.

CLOSE-UP
(1)

Subtask 270205-942-004-001 - Close-up for replacement of the equipment linked to


the affected Universal Joint
Manpower Resources

Skills
5

NON SPECIFIC

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 110
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Aircraft Maintenance Manual (AMM)

(2)

References
27-51-23,
27-51-24,
27-51-34,
27-51-35,
27-51-36,
27-51-37,
27-51-38,
27-81-16,
27-81-17,
27-81-18,
27-81-19,
27-81-21,

Page
Page
Page
Page
Page
Page
Page
Page
Page
Page
Page
Page

Block
Block
Block
Block
Block
Block
Block
Block
Block
Block
Block
Block

401
401
401
401
401
401
401
401
401
401
401
401

If replaced, do the close-up procedure as specified after the installation of the


Transmission Shafts, refer to AMM 27-81-19, Page Block 401.

If replaced, do the close-up procedure as specified after the installation of the


Steady Bearings, refer to AMM 27-81-21, Page Block 401 and AMM 27-81-17, Page
Block 401.

If replaced, do the close-up procedure as specified after the installation of the


Coupling Box, refer to AMM 27-81-18, Page Block 401.

If replaced, do the close-up procedure as specified after the installation of the


Stepback Gearbox, refer to AMM 27-81-16, Page Block 401.

If replaced, do the close-up procedure as specified after the installation of the


Transmission Shafts, refer to AMM 27-51-36, Page Block 401.

If replaced, do the close-up procedure as specified after the installation of the Tee
Gearbox, refer to AMM 27-51-23, Page Block 401.

If replaced, do the close-up procedure as specified after the installation of the


Simplex Bevel Gearbox, refer to AMM 27-51-24, Page Block 401.

If replaced, do the close-up procedure as specified after the installation of the


Steady Bearing, refer to AMM 27-51-38, Page Block 401.

If replaced, do the close-up procedure as specified after the installation of the


Downdrive Gearbox, refer to AMM 27-51-34, Page Block 401 for inner flaps and/or
AMM 27-51-35, Page Block 401 for center or outer flaps.

If replaced, do the close-up procedure as specified after the installation of the


Coupling Box, refer to AMM 27-51-37, Page Block 401.

Subtask 270205-942-006-001 - Close-up for LH Side


Manpower Resources

Skills

NON SPECIFIC

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 111
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

Aircraft Maintenance Manual (AMM)

(3)

References
27-50-00, Page Block 601
27-80-00, Page Block 601

(a)

Do the close-up procedure as specified after the Check of the Rotational Backlash
of the Universal Joints - Slats and Krueger Flaps, refer to AMM 27-80-00, Page
Block 601.

(b)

Do the close-up procedure as specified after the Check of the Rotational Backlash
of the Universal Joints - Flaps, refer to AMM 27-50-00, Page Block 601.

Subtask 270205-942-007-001 - Close-up for RH Side


Manpower Resources

Skills

NON SPECIFIC

References
Aircraft Maintenance Manual (AMM)
27-50-00, Page Block 601
27-80-00, Page Block 601

(4)

(a)

Do the close-up procedure as specified after the Check of the Rotational Backlash
of the Universal Joints - Slats and Krueger Flaps, refer to AMM 27-80-00, Page
Block 601.

(b)

Do the close-up procedure as specified after the Check of the Rotational Backlash
of the Universal Joints - Flaps, refer to AMM 27-50-00, Page Block 601.

Subtask 270205-942-005-001 - Close-up


Manpower Resources

Skills

NON SPECIFIC
(a)

Make sure that the work areas are clean and clear of tools and other items of
equipment.

(b)

Remove the access platform(s).

(c)

Put the aircraft back to its initial configuration.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 112
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

**CONF ALL

SPECIAL DETAILED INSPECTION OF THE SLAT AND FLAP TRANSMISSION


UNIVERSAL JOINTS ON LH AND RH SIDES IN ACCORDANCE
WITH TASK 270205832801001 AT THE THRESHOLD
GIVEN IN THE PLANNING INFORMATION PARAGRAPH E.(2) 01

YES

BACKLASH > 5

NO

YES

3,5< BACKLASH < 5

NO

DO A CHECK OF THE ROTATIONAL BACKLASH OF EACH SINGLE SLAT


AND/OR FLAP UNIVERSAL JOINT LOCATED INBOARD OF THE KEY
UNIVERSAL JOINTS ON LH AND/OR RH SIDES IN ACCORDANCE WITH
SUBTASK 270205832007001 AND/OR 270205832008001 AND/OR
270205832009001 AND/OR 270205832010001 BEFORE NEXT FLIGHT 02

REPLACE THE EQUIPMENTS LINKED TO THE AFFECTED SLAT AND/OR


FLAP TRANSMISSION UNIVERSAL JOINTS ON LH AND/OR RH SIDES IN
ACCORDANCE WITH TASK 270205833801001 AT THE THRESHOLD
GIVEN IN THE PLANNING INFORMATION PARAGRAPH E.(2)

REPEAT THE SPECIAL DETAILED INSPECTION OF THE SLAT AND


FLAP TRANSMISSION UNIVERSAL JOINTS ON LH AND RH SIDES
IN ACCORDANCE WITH TASK 270205832801001
AT THE INTERVAL GIVEN IN THE
PLANNING INFORMATION PARAGRAPH E.(2)

NOTE:
THE PURPOSE OF FLOW CHARTS IS TO SUPPLEMENT THE INFORMATION GIVEN IN THE PROCEDURE
AND COMPLIANCE PARAGRAPHS AND NOT TO SERVE AS THE PRIMARY SOURCE FOR TASKS OR
COMPLIANCE TIMES GIVEN IN THIS SERVICE BULLETIN
01

IN CASE OF THE ROTATIONAL BACKLASH IS GREATER THAN 3.5, CHECK THE KEY UNIVERSAL
JOINTS FROM OUTBOARD TO INBOARD FOR AVOIDING TO REPEAT THE INSPECTION OF THE SAME
UNIVERSAL JOINTS

02

IN CASE OF THE ROTATIONAL BACKLASH IS GREATER THAN 3.5, EACH SINGLE UNIVERSAL JOINT
LOCATED INBOARD MUST BE CHECKED (INCLUDING THE KEY UNIVERSAL JOINTS). WHEN ALL SINGLE
UNIVERSAL JOINTS LOCATED INBOARD ARE CHECKED, THE OVERALL INSPECTION IS COMPLETED
A_SB_270205_5_FAAA_01_02

Figure A-FFAAA - Sheet 01


Flow Chart

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 113
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

**CONF ALL
Z670, Z680

A
A

Z570, Z580

A
LH SHOWN
RH SYMMETRICAL

15
18

17

14

13

12

11

10

16
5

19
21

20

22
24

23

25

F
W
D

NOTE:

LH SHOWN
RH SYMMETRICAL

= KEY UNIVERSAL JOINT POSITION


n

= UNIVERSAL JOINT POSITION


= PLIER CLAMP LOCATION (TYPICAL INSTALLATION OF THE ROTATIONAL BACKLASH MEASURING EQUIPMENT)
= MEASURING LEVER LOCATION

A_SB_270205_5_BAAA_01_02

Figure A-FBAAA - Sheet 01


Flap Universal Joints - Measuring positions

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 114
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN

**CONF ALL

A
Z610, Z620

Z510, Z520

34

33

A
LH SHOWN
RH SYMMETRICAL

35
36
37
38
39

18 17

24

23

22

21

20

16 15

14

13

12 11 10

4
3

19

2
25
26
27
28
29

30
NOTE:
32

31

= KEY UNIVERSAL JOINT POSITION


n

F
W
D

= UNIVERSAL JOINT POSITION


= PLIER CLAMP LOCATION (TYPICAL INSTALLATION OF THE ROTATIONAL BACKLASH MEASURING EQUIPMENT)
= MEASURING LEVER LOCATION

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

LH SHOWN
RH SYMMETRICAL
A_SB_270205_5_BBAA_01_02

Figure A-FBBAA - Sheet 01


Slat Universal Joints - Measuring positions

Page: 115
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN
REPORTING SHEET

TITLE:

FLIGHT CONTROLS - SLAT/FLAP - INSPECTION - PREVENTIVE


MONITORING OF SLAT/FLAP TRANSMISSION UNIVERSAL JOINT

MODIFICATION No.:

None

Please complete the appropriate item (A or B):


A - SB WILL BE embodied
YES/NO (if NO please comment)
If YES, aircraft concerned (as per SB effectivity by default) and planned dates (month/year) of
embodiment:

B - SB HAS BEEN embodied on aircraft:

Operator comments:

From Airline:
Name/Title:
Signature:

Date:

If operational documentation is affected (see Paragraph 1.K of this SB): If information is needed prior to
next normal revision or prior to SB embodiment, please indicate required service(s):
Either: Modification Operational Impact (MOI), if available
YES/NO
Or : Intermediate revision
YES/NO
Important Information: This SB will only be incorporated in your maintenance and operational
documentation if this sheet is returned to Airbus and signed by a duly authorised representative. With
the next feasible revision, this will result in
-

Updating of maintenance documentation to show pre and post SB data.


Updating of maintenance and operational documentation to show post SB data after embodiment.

If this SB requires previous or simultaneous accomplishment of other SBs, Airbus shall automatically
include them in the manual revisions. Refer to SIL 00-037 for detailed information.
Please return this completed sheet to:
AIRBUS
CUSTOMER SERVICES DIRECTORATE
1 Rond Point Maurice Bellonte
31707 BLAGNAC CEDEX FRANCE
Attn: SDC32 Technical Data and Documentation Services
FAX: (+33) 5 61 93 28 06
e-mail: sb.reporting@airbus.com
or via your Resident Customer Support Office.
Alternatively, SB lists via letters or fax are also accepted.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 1
AIRBUS S.A.S. 2007. All rights reserved.

@A300
SERVICE BULLETIN
QUALITY PERCEPTION FORM
Use this form to tell us what is your perception of the quality of this Service Bulletin. The reported data
that you provide us will be used to analyse areas of difficulties and to take corrective action to further
improve the quality of our Service Bulletins.
We thank you for the time you have taken in completing this form.
(Please rate on a scale of 1 to 4, with 4 being the highest score)
- Quality rating of this SB

- Quality rating of the Accomplishment Instructions

- Quality rating of the Illustrations

- Is this SB easy to understand ?

Y/N

If you have had difficulties in the accomplishment of this SB please quote below the area(s) and give a
short description of the issue.
Planning

Material

Instructions

X Effectivity

X Kit content

X Preparation

X Reason

X List of Materials Operator Supplied

X Mod/Inspection

X Manpower

X Industry support

X Test

X References

X Re-identification

X Close-Up

X Publication

X Tooling

X Illustrations

Comments:

Operator:

Date:

Name/Title:
Please return this form to:
AIRBUS
CUSTOMER SERVICES DIRECTORATE
1 Rond Point Maurice Bellonte
31707 BLAGNAC CEDEX FRANCE
Attn : SEM4 Service Bulletins Management
FAX : (33) 5 61 93 42 51
Or via your Resident Customer Support Office.

DATE: Sep 11/15

SERVICE BULLETIN No.: A300-27-0205

REVISION No.: 00 - Sep 11/15


Printed in FRANCE

Page: 1
AIRBUS S.A.S. 2007. All rights reserved.