Beruflich Dokumente
Kultur Dokumente
from a violation of the terms of the sales contract but rather for
claims of cargo damages where there is no arbitration agreement. The
Court rendered a decision in favor of the petitioner. Unsatisfied with
the judgment, the respondent appealed and the lowers courts decision
was reversed by the appellate court. Hence this petition. ISSUE:
Whether the phrase "any dispute arising under this contract" in the
arbitration clause of the sales contract covers a cargo claim against
the vessel (owners and/or charterers) for breach of contract of
carriage RULING: Yes. An examination of the sales contract No.
S151.8.01018 shows that it is broad enough to include the claim for
damages arising from the carriage and delivery of the goods subjectmatter thereof. Considering that the private respondent was one of the
signatories to the sales contract . . . all parties are obliged to
respect the terms and conditions of the said sales contract, including
the provision thereof on "arbitration." Arbitration has been held
valid and constitutional. Even before the enactment of Republic Act
No. 876, this Court has countenanced the settlement of disputes
through arbitration. The rule now is that unless the agreement is such
as absolutely to close the doors of the courts against the parties,
which agreement would be void, the courts will look with favor upon
such amicable arrangements and will only interfere with great
reluctance to anticipate or nullify the action of the arbitrator.
Premises considered, we uphold the validity and applicability of the
arbitration clause as stated in Sales Contract No. S151.8.01018 to the
present dispute. WHEREFORE, petition is hereby DISMISSED and the
decision of the court a quo is AFFIRMED.
FACTS:- M a y 1 7 , 1 9 8 9 :
p e t i t i o n e r C h u n g F u Industries and private respondents
R o b l e c o r P h i l i p p i n e s f o r g e d a construction agreeme
n t w h e r e i n R o b l e c o r c o m m i t t e d t o c o n s t r u c t and finish on Dec.
31, 1989, ChungFus industrial/factory complex in Tanawan, Cavite
in consideration of P42MI t w a s s t i p u l a t e d a l s o t h a t i n
t h e event of disputes, the parties will
b e s u b j e c t e d t o a n a r b i t r a t i o n resolution, wherein the
arbitrator will be chosen by both partiesA p a r t
f r o m
t h e
c o n s t r u c t i o n
a g r e e m e n t , t h e p a r t i e s a l s o entered into ancillary
contracts for the construction of a dormitory and
support facilities with a contract
p r i c e o f 3 , 8 7 5 , 2 8 5 . 0 0 t o b e completed on or before
October 31,1989 and the other dated Aug.
12,1 9 8 9
f o r
t h e
i n s t a l l a t i o n
o f
electrical
, w a t e r a n d h y d r a n t systems at the plant site, priced at
1 2 . 1 M a n d r e q u i r i n g c o m p l e t i o n thereof one month after civil
workshave been finishedH o w e v e r ,
R o b l e c o r
f a i l e d
t o complete
t h e w o r k d e s p i t e t h e extension allowed by Chung FuS u b s e q u e n t l y ,
C h u n g
F u
h a d
t o take over the
construction when ithad become evident that Roblecor w a s n o t i n a
p o s i t i o n t o f u l f i l l t h e obligation- C l a i m i n g a n
u n s a t i s f i e d a c c o u n t o f P10, 500, 000 and unpaid progress
b i l l i n g s
o f
P
2 ,
3 7 0 ,
1 7 9 . 2 3 , R o b l e c o r f i
l e d a p e t i t i o n f o r Compulsory Arbitration with
prayerf o r T R O
b e f o r e r e s p o n d e n t R T C , pursuant to the arbitration clausein
the construction agreementC h u n g
F u
m o v e d
t o
d i s m i s s
t h e petition and
further prayed for the quashing of the restraining orderSubsequent negotiations
b e t w e e n the parties eventually led to the
f o r m u l a t i o n o f a n a r b i t r a t i o n agreement which includes
that thedecision of the arbitrator shall
befinal and unappealable, therefore,t h e r e s h a l l b e n o f u r t h e r
j u d i c i a l recourse if either party disagreesw i t h t h e w h o l e o r
a n y p a r t o f t h e arbitrators awardR T C
a p p r o v e d
t h e
a r b i t r a t i o n agreement
a n d A s u n c i o n w a s appointed as the sole arbitratorA r b i t r a t o r
r u l e d
i n
f a v o r
o f
t h e
contractor
Roblecor- C h u n g
F u
m o v e d
t o
r e m a n d
t h e case
for further hearing and
askedf o r
a
r e c o n s i d e r a t i o n
o f
t h e judgment award
claiming that Asuncion committed 12 instancesof grave error by
disregarding theprovisions of the parties contract- R T C d e n i e d
C h u n g F u s
M o t i o n t o Remand and approved RoblecorsMotion for
Confirmation of Award- C h u n g F u e l e v a t e d t h e c a s e t o
this
petition
to
the
JORGE GONZALES and PANEL OF ARBITRATORS vs. CLIMAX MINING LTD.,CLIMAXARIMCO MINING CORP. and AUSTRALASIAN PHILIPPINES MINING INC.,G.R.
No. 161957, January 22, 2007
Facts:
This is a consolidation of two petitions rooted in the same disputed
Addendum Contractentered into by the parties.In one case, the Court
held that the DENR Panel of Arbitrators had no jurisdiction over
thecomplaint for the annulment of the Addendum Contract on grounds of
fraud and violation of theConstitution and that the action should have
been brought before the regular courts as it involved judicial
issues.Gonzales averred that the DENR Panel of Arbitrators Has
jurisdiction because the case involves
a mining dispute that properly falls within the ambit of the Panels
authority.
Respondents Climax Mining Ltd., et al., on the other hand, seek
reconsideration/clarification onthe decision holding that the case
should not be brought for arbitration under R.A. No. 876.They argued
G.R. No.
Congress;
power of
powers]
FACTS:
On October 5, 1994, AEDC submitted an unsolicited proposal to the
Government through the DOTC/MIAA for the development of NAIA
International Passenger Terminal III (NAIA IPT III).
DOTC constituted the Prequalification Bids and Awards Committee (PBAC)
for the implementation of the project and submitted with its
endorsement proposal to the NEDA, which approved the project.
On June 7, 14, and 21, 1996, DOTC/MIAA caused the publication in two
daily newspapers of an invitation for competitive or comparative
proposals on AEDCs unsolicited proposal, in accordance with Sec. 4-A
of RA 6957, as amended.
RULING:
Yes. PIATCO cannot, by mere contractual stipulation, contravene the
Constitutional provision on temporary government takeover and obligate
the government to pay reasonable cost for the use of the Terminal
and/or Terminal Complex.
Article
XII,
Section
17
of
the
1987
Constitution
provides:
Section 17. In times of national emergency, when the public interest
so requires, the State may, during the emergency and under reasonable
terms prescribed by it, temporarily take over or direct the operation
of any privately owned public utility or business affected with public
interest.
The above provision pertains to the right of the State in times of
national emergency, and in the exercise of its police power, to
temporarily take over the operation of any business affected with
public interest. The duration of the emergency itself is the
determining factor as to how long the temporary takeover by the
government would last. The temporary takeover by the government
extends only to the operation of the business and not to the ownership
thereof. As such thegovernment is not required to compensate the
private entity-owner of the said business as there is no transfer of
ownership, whether permanent or temporary. The private entity-owner
affected by the temporary takeover cannot, likewise, claim just
compensation for the use of the said business and its properties as
the temporary takeover by the government is in exercise of its police
power and not of its power of eminent domain.
pursuant
to
Constitution.
the
operation
of
the
business
contravenes
the