Beruflich Dokumente
Kultur Dokumente
**
**
**
**
**
**
**
**
**
**
**
Opportunity costs associated with other projectrelated resources (e.g. land, building space) should
be included within such analyses as well if the
project at hand makes collateral use of such
resources and imputes a cost as a result.
**
**
**
**
**
**
(2)
(3)
>>
>>
>>
**
>>
**
>>
**
>>
>>
**
For capital projects that have similar useful lives in terms of their
investment time horizons, those projects that are preferred tend to
be those that (a) have significant strategic importance to the
organization, (b) are projected to be reasonably profitable as
measured by a positive NPV or an IRR that exceeds CCC, and
(c) entail a manageable/reasonable level of project risk as
measured by breakeven analysis.
**
**
**
**
**
**
**
The Net Present Social Value Model was developed for the
purpose of evaluating capital investment alternatives in a
not-for-profit organizational setting, whereby both the net
present social value (NPSV) of a project is formally
considered along with the financial net present value
(NPV). (TNPV = NPV + NPSV)
**
**
**
**
**
**
II.
Up to this point, it has been acknowledged that the most critical, and least
certain, part of the capital budgeting process involves the estimation of
future project cash flows for the purpose of estimating the profitability
associated with a capital project.
**
**
**
**
**
**
**
**
**
>>
>>
>>
**
**
>>
>>
**
As has been the case time and again in the financial analysis of risk
and return, the assumption of higher levels of financial risk require
greater financial returns to compensate investors for assuming
greater than average levels of risk. So, for projects that are more
risky, as well as less risky, than the businesss average project,
adjustments to the standard required rate of return
(corporate/divisional cost of capital) is necessary.
**
**
**
**
**
If one of the projects is deemed to be more risky than the other, for
whatever reason, such projects should utilize a different
corporate/divisional cost of capital to estimate NPC. Unlike NPV
methods, however, higher risk, non-revenue producing projects
should be discounted using a LOWER/SMALLER
corporate/divisional cost of capital than projects that are less risky.