Sie sind auf Seite 1von 392

1

Removing top soil to a depth not exceeding 6" & depositing as directed within site.

Excavation over site to reduce level, in any material except rock requiring blasting
including depositing and leveling as directed up to distance not exceeding 30' 0"

3 Excavation in trenches for walls/ column pits in soft/ loose soil from 0' 0" to 5' 0" deep
and depositing excavated materiel to a distance not exceeding 30' 0" (Earth work
support to be paid separately where necessary).
4 Excavation in trenches for walls/ column pits in ordinary soil from 0' 0" to 5' 0" deep
and depositing excavated material not exceeding 30' 0".
5 Excavation in trenches for walls/ column pits in Hard/ dense soil up to a depth of 5' 0"
and depositing excavated material up to a distance not exceeding 30' 0".
6 Excavation in trenches for walls/ column pits in Mud/ wet soil up to a depth of 5' 0"
and depositing excavated material to distance not exceeding 30' 0". (Earth work &
dewatering paid for separately.)
7 Excavation in trenches for walls/ column pits in soft disintegrated rock (not requiring
blasting) up to depth of 5' 0" and depositing excavated material to distance not
exceeding 30' 0".
8 Excavation in trenches for walls/ column pits in Hard rock requiring blasting up to a
depth of 5' 0" and depositing excavated material to distance not exceeding 30' 0".
Per cube

9 Benching rock in foundation in 3" - 6" steps. (Blasting prohibited)


Per 10 square feet

ANTI - TERMITE TREATMENT


10 Anti - termite treatment on excavated foundation and compacted soil under floors.

Earth work - Backfilling & Compacting


11 Backfilling to trenches with selected earth available at site.

12 Back filling to trenches with imported material.

13 Filling under floors including leveling, watering & compacting in 3" layers with
available and selected earth at site.

14 Filling under floors including leveling, watering & compacting in 3" layers with
imported selected earth.

15 Cutting turf sods, landing to hand carts and transporting up to 30 yards, laying and
watering for 30 days. (Royalty for turf, pegging and transport beyond 30 yards paid
separately)

Earth work support (open planking) in trenches up to a depth of 5' 0"


16 Consider trench 15' 0" long 3' 0" wide and 5' 0" depth open planking to both faces.
Total area
- 2/ 15' 0" x 5' 0"
.
= 150 sq.ft

Earth work support (close planking) in trenches up to 5' 0" depth.


17 Consider trench 15' 0" long 3' 0" wide and 5' 0" height of planking to both faces.
Total area of planking 2/ 15' 0" x 5' 0" ie 150 sq.ft

18 Earth work support (close planking) in deep excavation in trenches up to 15' 0" depth.
- Consider trench of length of 15' 0" width 5' 6" at top 3' 6" at bottom
Then
area supported is 2/ 15' x 15' ie 450 sq.ft.

CONCRETE
19 Mixing concrete 1: 3: 6 (1 1/2")

20 Mixing concrete 1: 2: 5 (1")

21 Mixing concrete 1: 2: 4 (3/4")

22 Mixing concrete 1: 1: 3 (3/4")

23 Mixing concrete 1: 1: 2 (3/4")

24 2" thick cement concrete screed in foundation at depths not exceeding 5' 0"

25 3" thick cement concrete screed in foundation at depths not exceeding 5' 0"

26 6" thick cement concrete floor (mass concrete).

Cement concrete in 4 1/2" x 6" columns in ground floor.


27 Consider 24 No. columns each 4 1/2" x 6" x 10' 0" ie 0.45 cubes.

28 Cement concrete in 6" x 6" colomns in ground floor. Consider 18 No. columns 6" x 6" each 10' 0" high ie 0.45 cubes.

28 Cement concrete in 6" x 6" colomns in ground floor. Consider 18 No. columns 6" x 6" each 10' 0" high ie 0.45 cubes.

Curing

29 Cement concrete in 9" x 9" colomns in ground floor. - Consider 8 No. 9" x 9" columns
each 10' 0" high ie 0.45 cubes.

Curing

30 Cement concrete in 12" x 12" colomns in ground floor. Consider 5 No. 12" x 12" columns each 10' 0" high.
Per 0.5 cube

31 Cement concrete in 13 1/2" x 13 1/2" colomns in ground floor. Consider 4 No. colomns 13 1/2" x 13 1/2" each 10' 0" high .
I.e 0.51 cubes.

Curing

32 Cement concrete in 6" x 6" beam up to 1st floor level. Consider 180 L.ft of beam 6" x 6"
I.e 0.45 cubes.

Curing

33 Cement concrete in 9" x 6" beam up to 1st floor level. Consider 120 L.ft of beam 9" x 6" beam
I.e 0.45 cubes.

Curing

34 Cement concrete in 9" x 9" beam up to 1st floor level. Consider 80' 0" length 9" x 9" beam
I.e 0.45 cubes.

Curing

35 5" thick R.CC floor slab in 1st floor. Consider 5" thick slab 10' 0" x 12' 0" volume of concrete 50.00 cu.ft

Curing

36 6" thick R.CC floor slab in 1st floor. Consider 10' 0" x 10' 0" panel = 50 cu.ft

Curing

37 Cement concrete in 4 1/2" x 6" lintels in ground floor. Consider 240 l.ft I.e 45 cu.ft

Curing

38 Cement concrete in 9" x 9" lintels in ground floor. Consider 80 L.ft of lintel I.e 45 cu.ft concrete.

Curing

39 Cement concrete in 9" x 12" lintels in ground floor. Consider length 60' 0" of lintel
= 45 cu.ft

Curing

40 Cement concrete in 12" x 15" lintels in ground floor. Consider length 36' 0"
i.e 45 cu.ft

Curing

FORMWORKS
41 Sawn timber form work to 9" x 9" cement concrete column in ground floor.
Making Moulds (15 sqft) Consider column length of 5' 0"

Assembling per use

Demantling per use

42 Sawn timber form work for concrete beams in ground floor. Making Moulds Consider 9" x 12" beam of 20' 0" long. Contact area 55 sq.ft.

Assembling per use

Demantling per use

43 Sawn timber form work for underside of first floor slab. Making Moulds Consider a slab of desmensions 20" 0" x 10' 0"
Contact area = 2.0 sqrs.

Assembling per use

Demantling per use

REINFORCEMENTS
44 Mild steel / for steel reinforcement to lintels slab beams for columns bent to shape laid
in position and tied with G.I. Wire as directed. -

MASONRY
45 Brick work in cement sand 1:5: in foundation up to D.P.C

46 Brick work cement and sand 1:8 in foundation up to D.P.C


Rate per square

47 Brick work in cement and sand 1:5 in 4 1/2" thick walls in ground floor
Rate per square

48 9" thick brick wall cement sand 1:5 in ground floor


Rate per square

49 Brick work 13 1/2" thick in cement sand 1:5 in superstructure in ground floor
Rate per square

50 9" Brick walls in cement sand 1:8in superstructure in ground floor


Rate per square

51 4 1/2" thick brick wall (wire cut) in cement and sand 1:5 in ground floor ( Facing to
brickwork measured separately)
Rate per square

52 9" thick in cement and sand 1:5 with wire cut bricks (Facing to brick work measured
separately)
Rate per square

53 13 1/2" thick brick wall (wire cut) in cement and sand 1:5 in ground floor (Facing to
brick work measured separately)
Rate per square

54 Extra over for facing including raised pointing 1/8" thick in cement and sand 1:1
mixture in ground floor
Rate per square

55 3" thick floor paved in lime mortar 2:5 in ground floor


Rate per square

56 Steps 1' - 1 1/2" x 0' 6" in brick in cement and sand 1:5 with 1/2" thick cement and
sand 1:2 redering including necessary excavation.
Rate per 10 L. ft

57 Brick drains in cement and sand 1:5, 9" wide end 6" - 9" average depth including
cement rendering 1/2" thick 1:2 to exposed faces with 1'6" ramp including necessary
excavation.
Rate per 10 L. ft

58 Brick drains in cement and sand 1:5, 9" wide end 6" - 9" average depth including
cement rendering 1/2" thick 1:2 to exposed faces without ramp including necessary
excavation.
Rate per 10 L. ft

59 8" thick Hollow block work in cement and sand mortar 1:5 in ground floor (cavities
unfilled)
Rate per square

60 4" thick Hollow block mesonry in cement and sand mortar 1:5 with cavities unfilled
Rate per square

61 Random Rubble masonry in cement morter 1:5 in foundation


Rate per cube (14" thick)

62 Random Rubble masonry in cement morter 1:5 in superstructure


Rate per cube (14" thick)

FLOOR FINISHES
63 Pressed floor tiles bedded in 1/2" cement morter 1:2 and pointing in neat cement in
ground floor
Rate per square

64 Glazed tiles fixed to walles including bedding in cement morter 1:2 and raking in
ground floor. (specials measured separately)
Rate per square

65 Terrazzo floor tiles on 1/2" thick cement and sand 1:2 in ground floor
Rate per square

66 Timber framework for calicut pattern tile hip roof in single storey building consisting o
f wall plate, beam, ridge plate, rafters etc. (Preservutive treatment to be measured
separately)
Rate per 6 squares

67 Roof covering with calicut pattern clay tiles in single storeyod building (Timber frame
work & ridge covering measured separately)
Rate per 6 squares

68 Timber framework for corrugated asbestos sheet roof in angle storied building
Rate per 3.6 squares

69 Roof covering with corrugated asbestos sheets (timber frame work & ridge covering
measured separately)
Rate per 3.6 squares

70 One layer half round clay tiles over corrugated asbestos roof covering.
Rate per 3.6 squares

71 Asbestos close fittings ridging fixed complete with roofing screws or bolts (hook)
Rate per 13'4" length

72 Ridging covering with calicut pattern ridge tiles bedded in cement lime mortar 1:1:4
Rate per 12' length

73 3/4" x 9" high valance board fixed with brass screws to ends of rafters ( for tile
roofing)
Rate per 100' length

74

3/4" x 9" high barge board fixed with brass screws at 2' 0" centres to sides of rafters.
Rate per 100' length

75 ROOF PLUMBING 18 B.W.G (1.2 mm) galvanised from sheet valley gutter 3' 0" girth
overall once bent with end laps not less then 9" width including 3/4" tongued and
grooved planks laid to slope and grooved planks laid to slope and profile on timber
members.
Rate per 15' length

76 18 B.W.G (1.2 mm) galvanised iron flashing 1' 6" girth overall 3 times bent with end
laps not less than 6", lead soldered, turned and tucked up to not less than 6" in to
cement mortar 1:2 lower end dressed over roof covering not less than 1' 0" wide.
Rate per 15' length

77 Timber Framework for 4' 0" x 4' 0" flat asbestos ceiling (Sheet measured separately)
comprising of 4" x 2" joists and 2" x 2" bearers in class I timber
Rate per 1.95 squre

78 Horisontal ceiling lining using 4' 0" x 4' 0"flat asbestos cement sheets fixed with and
including beading and cove mouldings on timber framework. (timber framework &
painting measured separated)
Rate per 1.95 squre

79 3/4" thick tongued and grooved Lunumidella ceiling boards fixed horizontal on 4" x 2"
class I timber joists at 2' 0" centers with 1 1/2" brass nails.
Rate per 15' x 13' I.e 1.95 squares

80 3/4" x 6" wide tongued and grooved Lunumidella ceiling boards fixed to underside of
roof rafters, (existing) with 1 1/2" brass nails including leveling with timber strips
where necessary.
Rate per 15' x 12' I.e 1.80 squares

81 Door single hung 3' 3" x 7' 0" high overall with frame having 1 1/4" thick sash and 3
1/4" x 2 1/4" timber frames. (glazing, ironmongery & painting measured separately)
Per 22.75 square feet (3' 3" x 7' 0")

82 Door glazed and panolled double hung 4' 0" x 7' 0" high overall with frame including 1
1/4" thick sash and 3 3/4" x 2 3/4" frame. (glazing, ironmongery and painting measured
separately).
Per 28 square feet (4' 0" x 7' 0")

83 Plywood door single hung 3' 1 1/2" x 6' 1 1/2" overall with frame having 1 1/4" thick
sash and 3 3/4" x 2 3/4" frame. ( iron - mongery and painting measured separately)
Per 21.75 square feet (3' 1 1/2" x 6' 1 1/2")

84 Door ledged, braced and battened single hung 2' 6" x 6' 6" overall, with frame having
7/8" thick tongued & grooved planks and 3 3/4" x 2 3/4" frame.
( Ironmongery and painting measured separately)
Per 16.25 so.ft (2' 6" x 6' 6")

85 Window, glazed 7' 0" x 4' 0" high overall with frame comprising 3 No openable sashes
and 3 3/4" x 2 3/4" frame and mullions
(Clasing, ironmongery and painting measured separately)
Per window 7' 0" x 4' 0" (sashes) ie per 28.00 sq.ft

86 1/4" clear sheet glass panes exceeding 1' 0" but not exceeding 4 square feet cut and
fixed with timber beadings to doors and windows.
Consider sash 3' 0" x 4' 0" high with 3" x 1 1/4" style and 4 Nos.glass
panes.
Per window 9.00 sq.ft

87 IRONMONGERY
Butt hinges 5" x 2 1/2"
Per 1 1/2 pairs

88 Tee hinges 6" x 12"


Per 1 pairs

89 Rim lock
Per 1 No

90 Mortice lock
Per 1 No.

91 Casement stays.
Per 4 Nos.

92 Door closer ( Hydraulic)


Per 1 No.

93 Tower / Skeleton brass bolts


Per 1 No.

94 Barrel bolt 4"


Per 1 No.

95 Casement fasteners.
Per 6 Nos.

96 Spring louded fanlight catches


Per 6 Nos.

97 Draw rings
Per 6 Nos.

98
3/4" thick DPC, in cement sand 1:2 finished with 2 coats hot tar and blinded with sand.

99
5/8" thick plastering to wall in lime and sand 2:5 including floating with lime putty.

100
5/8" thick plastering to wall in cement sand 1:3 including cement floating

101
3/8" thick plastering to soffit slab in cement and sand 1:3 including floating with lime
putty

102
3/8" thick plastering to sides and soffit of beams in cement & sand 1:3 including
floating with lime putty

103
5/8" thick to wall in lime cement and sand 1:1:5 finished semi - rough with wooden
float.

104

5/8" thick plastering to wall in lime and sand 1:1:5 finished smooth with lime putty
floating.

105
1/2" thick rendering in cement and sand 1:3 finished smooth
106
1/2" thick rendering in cement and sand 1:2 in floors, finished smooth.

107

3/4" thick rendering in cement and sand 1:3 finished smooth.

108

3/4" thick rendering in cement and sand 1:2 in floors finished smooth.

109

3/4" thick rendering in cement and sand 1:2 in coloured cement floors finished smooth.

110
1/2" x 6" skirting in cement and sand 1:3 projected or flush to walls finished with
floating including forming groove.

111
Prepare and apply one coat of preservative (oil type) to structural timber including
touching up cut ends etc. after fixing.
112
Prepare surface of steel truse and apply two coats of anti - corrosive primer.

113
Apply one coat of anti - corrosive primer and two coats enamel paint on already shop
rimed and arected steel roof truss.

114
Prepare and apply two coats primer and finishing coat of enemel paint to mild steel
(angle / flat) gate.

115
116

Painting steel on mew work with 2 coats of anti - corrosive paint


Painting new timber work with two coats wood preservative

117
Preparing and painting wood work with primer and 2 coats enamel paint.

118

White or colour washing two coats in single storey.

119
White or colour washing in two storeyed building

120
Prepare and apply one coat of Alkali resistant primer and two coats of emulsion paint
to walls.

121

Cement washing to walls of single storeyed builsing 2 coats

122
Painting walls with emulsion paint ( 2 coats)

123
Prepare and apply one coat alkali resistant primer and two caoats of emulsion paint to
soffit of slabs.
124
Varnishing two coats with copal varnish after sandpapering
125
Wax polishing to timber in panels & floors.

126
PLUMBING - PVC PIPES
1/2" diameter PVC pipes fixed
to walls ( specials paid separately)
127
3/4" dia meter PVC pipes to walls ( specials paid separately)

128
1" dia meter PVC pipes fixed to walls ( specials paid separately)

129
1 1/4" dia meter PVC fixed to walls ( specials paid separately)

130
1 1/2" dia meter PVC pipes laid to walls ( specials paid separately)

131
2" dia meter PVC pipes laid to walls ( specials paid separately)

132
3" dia meter PVC pipes fixed to walls ( specials paid separately)

133
Excavation for laying 1/2" to 3" dia meter PVC pipes in ground not less than 1' 6"
deep, back filling & compacting.
134
Chasing brickwork for laying 1/2" to 1 1/2" dia PVC pipes and making good average
depth 2" - ( Pipes and specials paid separately)
135
Chasing brickwork for laying 1 1/2" to 3" dia PVC pipes in ground or floop and
making good. Average depth 3" - ( Pipes and specials measured separately)

136

1/2" dia PVC specials viz - albows / bends / sockets

137
3/4" dia PVC specials viz elbows / bends / sockets.
138
1" dia PVC specials viz - elbows / bends / sockets.
139
1 1/4" dia PVC specials viz - elbows / bends / sockets.

140
1 1/2" dia PVC specials viz - elbows / bends / sockets.
141
2" dia specials viz elbows / bends / sockets.
142
2 1/2" dia PVC specials viz elbows / bends / sockets.
143
3" dia PVC specials viz elbows / bends / sockets.

144
1/2" dia PVC specials viz. Tees.
145
3/4" dia PVC specials viz. Tees.
146
1" dia PVC specials viz Tees
147
1 1/4" dia PVC specials viz Tees
148
1 1/2" dia PVC specials viz Tees
149
2" dia PVC specials viz Tees
150
2 1/2" dia PVC specials viz Tees
151
3" dia PVC specials viz Tees

152

4" dia glazed earthenware pipes laid on 6" thick bedding in cement concrete 1: 3 : 6 ( 1
1/2") including excavation average 2' 0" depth, backfilling with selected excavated
materials and concrete haunching to joints.

153

4" dia C.I. Soil / vent pipe fixed vertically to walls jointed with cement caulking.
(Specials measured separately)

154

4" dia C.I. Pipes fixed for walls jointed with lead caulking. (Specials measured
separately)

155

4" dia stoneware gulley with 6" x 6" x 6" gulley box including excatatio, 4" cement
concrete 1: 2: 4 ( 3/4") base, surrounded by 4 1/2" thick cement and sand 1: 5 extanded
6" above top of gulley box including making connection, 1/2" cement and sand 1:2
rendering internally and exposed faces finished smooth with neat cement flasting and
providing G.I. grating on top of gulley.

156

Marihole 2' 0" x 2' 0" internally with invert depth not exceeding 2' 0" including
excavation, beckfilling 6" cement concrete 1: 2: 4 ( 3/4") base with 3/8" dia meter mild
steel rods at 4" centres hothways, forming channels and benching in similar concrets, 4
1/2" walls in brick in cement 1 : 5, 1/2" thick cement and sand 1:2 rendering internally
and exposed surfaces including channels, benching and 2" thick RCC removable cover
slab 2' 3" x 2' 3" inlet and outlet connection all complete to working order.

157
22" x 16"glazed fireclay wash basin with 1/2" dia chromium plated pillar tap, waste
plug, chromium plated waste cnain and stay, including fixing wash basin on brackets.
( water supply and waste water connection measured separately)
159
Closet pendestal type with L/L flushing cistern, flush pipe double plastic seat cover,
1/2" dia stop cock, trap supplied & fixed cemplete to working order

160

Closet squatting type with trap including high level cistern fixed complete with flush
pipe and 1/2" dia stop cock, all complete to working order.

161
Vitreous China bidet suite fixed cemplete to working order
162

4 No. Bowl type urinal with trap and 2 gals capacity automatic flushing cestern and
spreaders complete to working orders.

163

6" dia half round PVC eaves gutter fixed to timber valance board including gutter
joiner and brackets fixed at 18" centres. (Other specials paid separately)

Consider an area of 10.00 sqrs. Ie 5.00 cubes of


excavation.10 day a U/Sk labourer.

Per cube

Rate per
cube

1 5/ 8 day U/ Sk labourer

1 day U/ Sk labourer
2 1/4 days U/ Sk labourer.
3 1/2 days U/Sk labourer
3 days U/Sk labourer.

2 1/2 days U/Sk labourer

Labour
1 day Sk labourer
2 days U/Sk labourer
Materials
0.75 lbs blasting powder
10 lft fuse
1 lb jumper steel
Rate per cube

Rate per
sq.ft
Labour
Drilling, chipping & wedging 1 1/2 day Sk labourer
Steel, fuel & forge - 25% of labour cost
Collecting & Disposing 1 1/2 day U/Sk labourer per
10 sq.ft
Material
Rate per Square

Labour
1/2 day U/ Sk labourer

Materials
16 lbs D.D.T. powder (8% in 20 gals of water)
20 gals water
Rate per Square

Labour
1 day U/ Sk labourer
Materials
Rate per cube
Labour
1 1/4 U/Sk labourer
Materials
1.00 cube earth delivered at site.
Allow 15% compaction
Filling & Compacting
Rate per cube

Labour
2 day U/ Sk labourer
Materials
Rate per cube

Labour
2 days U/Sk labourer
Materials
1.00 cube earth delivered at site.
Allow 15% compaction
Rate per cube

Labour

Rate per
sqrare

Note

Royalty for turf


Cutting turf sods, loading and transporting to site and
unloading
2
1/2 day U/ Sk labourer

b)
2,600.00 Transport of
turf
c)

Laying turf rods at site 1 1/2 day U/ Sk labourer


Watering for 30 days 1 1/2 days U/Sk labourer
Materials
60 gals. water
Rate per square

Labour
1 days carpenter
3 days U/ Sk labourer
Materials
17.50 cu.ft class II timber (4 uses)
Add 5% on above for wedges.

1,800.00

Rate per square

3,600.00

Labour
2 days carpenter
6 days U/ Sk labourer.
Materials
30.00 cu.ft class II timber (4 uses)
Add 5% on above for wedges.
Rate per square

12,800.00
Labour
8 days carpenter
20 days U/Sk Labourer
Materials
100.00 cu.ft class II Timber (4 uses)
Add 5% on above for wedge.
Rate per square

Total per 450


sq.ft.

Rate per
cube

a) Water
available at
site.

Labour
1 day skilled labourer
6 days U/ Sk labourer
Materials
13 cwt (50 kg bags) cement
0.53 cubes sand
0.92 cubes 1 1/2" metal
Water (110 gals)
Equipments
1/3 day hire of mixer

b) If, water is
not
Noteavailable
allowances
should be
made for
transport of
water.

Sand a)c)
Water
includes 15%
available
at
for bulking.
site.

Rate per cube


Labour
1 day skilled labourer
5 days U/ Sk labourer
Materials
14 cwt (50 kg bags) cement
0.60 cubes sand
0.92 cubes 1" metal
Water (100 gals)
Equipments
1/3 day hire of mixer

b) If, water is
not
Noteavailable
allowances
should be
made for
transport of
water.

Sand a)c)
Water
includes
available15%
at
for bulking.
site.

Rate per cube


Labour
1 day skilled labourer
6 days U/ Sk labourer
Materials
18 cwt (50 kg bags) cement
0.50 cubes sand
0.88 cubes 3/4" metal
Water (120 gals)
Equipments
1/3 day hire of mixer

b) If, water is
not
Noteavailable
allowances
should be
made for
transport of
water.

Sand a)c)
Water
includes
available15%
at
for
site.bulking.

Rate per cube


Labour
1 day skilled labourer

b) If, water is
not
Noteavailable
allowances
should be
made for
transport of
water.
3,000.00

6 days U/ Sk labourer
Materials
23 cwt (50 kg bags) cement
0.42 cubes sand
0.82 cubes 3/4" metal
Water (150 gals)
Equipments
1/3 day hire of mixer

b) If, water is
not available
allowances
should be
made for
transport of
water.
3,000.00
Sand a)c)
Water
includes
available15%
at
for
site.bulking.

Rate per cube


Labour
1 day skilled labourer
6 days U/ Sk labourer
Materials
31 cwt (50 kg bags) cement
0.44 cubes sand
0.96 cubes 3/4" metal
Water (200 gals)
Equipments
1/3 day hire of mixer
Rate per cube
Labour
1/8 days skilled labourer
1/2 days unskilled labourer
Materials
1/6 cube concrete (Add 10% for wastage )
Rate per square
Labour
1/8 days skilled labourer
3/4 days unskilled labourer
Materials
1/4 cube concrete (Add 10% for wastage )
Rate per square
Labour
1/2 days skilled labourer
1 1/2 days unskilled labourer

b) If, water is
not
Noteavailable
allowances
should be
made for
transport of
water.

c) Sand includes 15%


for bulking.
for laying
concrete at
depths more
than
Note5' 0", add
1/6 day
unskilled
labourer for
each
additional 5'
0" or part
there of per
square

1/3 day hire of


mixer

500.00

Materials
1/2 cube concrete (Add 10% for wastage )
200 gal of water
Rate per square
Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube

Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube

Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

1) For column
in 1 st floor
add 3% to
ground floor
rate.

2)
For column in
2 nd floor add
5% to ground
floor rate.
Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
available at
site.

Rate per cube


5) If
water is not
available
allowance
must be made
for transport
of water.

Labour
1 1/2 days U/Sk labourer

1) For column
in 1 st floor
add 3% to
ground floor
rate.

Materials
Jute Hessian - 80 sq.ft
Water - 140 gals
Rate per cube

Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

2)
For column in
2 nd floor add
5% to ground
floor rate.
Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
available at
site.

Rate per cube


Labour
1/2 days U/Sk labourer
Materials
Jute
Hessian - 60 sq.ft
Water - 100 gals
Rate per cube

Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
0.50 cube concrete (Add 10% for wastage )
40 so.ft - Jute Hessian
Water (100 gals)

Equipments
1 day hire of vibrator

5) If
1)
Foriscolumn
water
not
in
1 st floor
available
add
3% to
allowance
ground
must befloor
made
rate.
for transport
of water.
2)
For column in
2 nd floor add
5%
Noteto ground
floor rate.

3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
available at
site.
5) If
water is not
available
allowance
must be made
for transport
of water.

add 3% to
ground floor
rate.

Rate per cube

Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
0.51 cube concrete (Add 5% for wastage )
Equipments
1 day hire of vibrator
Rate per cube
Labour
1 1/2 days U/Sk labourer
Materials
Jute Hessian - 45 sq.ft
Water - 100 gals
Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube
Labour
1 1/2 days U/Sk labourer
Materials
Jute
Hessian - 90 sq.ft
Water - 180 gals

2)
For column in
2 nd floor add
5% to ground
floor rate.
Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
1) Water
available at
available at
site.
site.
1) For column
5) If
in
1 st floor 2)
Note
water
is not
If water
is not
add
3% to
available
available
ground
floor
allowance
allowance
rate.
must be made
must be made
for transport
for transport
of water.
of water.
2)
For column in
2 nd floor add
5% to ground
floor rate.
Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
1) Water
available at
available at
site.
site.
5) If
Note is not 2)
water
If water is not
available
available
allowance
allowance
must be made
must be made
for transport
for transport
of water.
of water.

add 3% to
ground floor
rate.

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube
Labour
1 1/2 days U/Sk labourer
Materials
Jute Hessian - 75 sq.ft
Water - 150 gals
Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube
Labour
1 1/2 days U/Sk labourer
Materials
Jute
Hessian - 60 sq.ft
Water - 120 gals

2)
For column in
2 nd floor add
5% to ground
floor rate.
Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
1) Water
available at
available at
site.
site.
1) For column
5) If
in
1 st floor 2)
Note
water
is not
If water
is not
add
3% to
available
available
ground
floor
allowance
allowance
rate.
must be made
must be made
for transport
for transport
of water.
of water.
2)
For column in
2 nd floor add
5% to ground
floor rate.
Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
1) Water
available at
available at
site.
site.
5) If
Note is not 2)
water
If water is not
available
available
allowance
allowance
must be made
must be made
for transport
for transport
of water.
of water.

ground floor
rate.

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
50 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube
Labour
1 1/2 days U/Sk labourer
Materials
Jute Hessian - 30 sq.ft
Water - 90 gals
Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
50 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube
Labour
1 1/2 days U/Sk labourer
Materials
Jute
Hessian - 25 sq.ft
Water - 90 gals
Rate per cube

2)
For column in
2 nd floor add
5% to ground
floor rate.
Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
1) Water
available at
available at
site.
site.
1) For column
in 1 st floor
add
3%5)
to If 2)
Note
water
is
not
ground
If waterfloor
is not
available
rate.
available
allowance
allowance
must be made
must be made
for transport
for transport
of water. 2)
of water.
For column in
2 nd floor add
5% to ground
floor rate.
Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
1) Water
available at
available at
site.
site.
5) If
Note is not 2)
water
If water is not
available
available
allowance
allowance
must be made
must be made
for transport
for transport
of water.
of water.

2)
For column in
2 nd floor add
5% to ground
floor rate.
Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
45 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube
Labour
1 1/2 days U/Sk labourer
Materials
Jute
Hessian - 10 sq.ft
Water - 90 gals
Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
45 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube
Labour
1 1/2 days U/Sk labourer
Materials
Jute
Hessian - 60 sq.ft
Water - 90 gals
Rate per cube

Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
1) Water
available at
available at
site.
site.
1) For column
in 1 st floor
add
3%5)
to If 2)
Note
water
is
not
ground
If waterfloor
is not
available
rate.
available
allowance
allowance
must be made
must be made
for transport
for transport
of water. 2)
of water.
For column in
2 nd floor add
5% to ground
floor rate.
Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
1) Water
available at
available at
site.
site.
5) If
2)
Note
water is not
If water is not
available
available
allowance
allowance
must be made
must be made
for transport
for transport
of water.
of water.

rate.

2)
For column in
2 nd floor add
5% to ground
floor rate.
Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
45 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube
Labour
1 1/2 days U/Sk labourer
Materials
Jute Hessian - 55 sq.ft
Water - 90 gals

Note
3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
1) Water
available at
available at
site.
site.
5) If
2)
Note
1)
Foriscolumn
water
not
If
water
is
not
in
1 st floor
available
available
add
3% to
allowance
allowance
ground
must befloor
made
must
be made
rate.
for transport
for transport
of water.
of water.

Rate per cube

2)
For column in
2 nd floor add
5% to ground
floor rate.

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)

Note

Materials
45 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube
Labour
1 3/4 days U/Sk labourer
Materials
Jute
Hessian - 40 sq.ft
Water - 90 gals
Rate per cube

3) For
columns in
3rd floor add
7% to ground
floor rate.

4) Water
1) Water
available at
available at
site.
site.
5) If
2)
Note
water is not
If water is not
available
available
allowance
allowance
must be made
must be made
for transport
for transport
of water.
of water.

Labour
1/2 day carpenter
1/2 day U/Sk labourer
Allowin: 4 uses cost
of mould per use
Materials
18.15" sq.ft 1" thick class II timber
17.10 L.ft 2" x 2" class II timber in yokes.
16.12 L.ft 2" x 1" class II timber battens
1 1/2 lb wire nails.
Labour
1/4 day carpenter
1/4 day U/Sk labourer
Materials
12 Nos. 16 mm 18" long bolts (20 uses)
1/2 liter mould oil
35 L.ft 4" x 2" props (10 uses)
Labour
1/4 day carpenter
1/4 day U/Sk labourer
Rate per square

Labour
1/2 day carpenter
2 day U/Sk labourer
Allowin: 4 uses cost
of mould per use
10% for repair
Materials
60 sq.ft 1" timber planks
24 l.ft 2" x 1" battens
45 l.ft 2" x 2" ledgers
30 l.ft 4" x 2" bearers at bottom of mould.
2 lbs wire mails
10% for repair
Labour
1 day carpenter

2 day U/Sk labourer


Materials
110 l.ft 4" x 2" vertical props
80 l.ft 2" x 2" bracing to mould and props.
50 l.ft 2" x 2" bracing to a set of props
6.0 sq.ft 1" timber base plate to props
22 Nos wdges
Add 10% of cost of materials for repairs
1/2 gal mould oil
1/2 lbs nail
Labour
1/2 day carpenter
2 day U/Sk labourer
Rate per square

Labour
3 days carpenter
3 days U/Sk labourer
Allowin: 4 uses cost
of mould per use
20% for repair
Materials
220 se.ft 1" thick tongue and grooved timber planks.
121 L.ft 4" x 2" runners at 2' 0" centers.
4 lbs. were nails.
Labour
1 day carpenter
4 day U/Sk labourer
1 gal mould oil for assembling.
2 lbs wire nails
Materials
690 l.ft 4" x 2" vertical timber props.(10 uses)
66 l.ft 2" x 2" bracing for props.
122 No. wedges
33 sq.ft 1" bass plates for props
Add 20% of cost of materials for repairs
Labour
1/2 day carpenter
2 day U/Sk labourer
Rate per square

Labour
1 days barbender
1 days U/Sk labourer
Materials
1 cwt M.S. / per steel.rods including transport to site.
(Allow for wastage 15%)
1 1/2 lbs 16 BWG binding wire
Add 1.5% of steel cost for spacers or dhairs.
Rate per cwt

Labour
3 days mason
4 days U/Sk labourer
Materials
1450 bricks Add 5% wastage
4.00 cwt cement (50 kg bags)
0.25 cubes sand
Water (150 gals)
Rate per square
Labour
3 days mason
4 days U/Sk labourer
Materials
1450 bricks Add 5% wastage
2 1/3 cwt cement (50 kg bags)
3/8 cubes sand
Water (150 gals)
Rate per square
Labour
1 1/2 days mason
2 days U/Sk labourer
Scaffolding - Add 5%
Materials
550 bricks Add 5% wastage
1.3 cwt cement (50 kg bags)
0.10 cubes sand

Water (50 gals)


Rate per square
Labour
1 1/4 days mason
3 3/4 days U/Sk labourer
Scaffolding - Add 3%
Materials
1090 bricks Add 5% wastage
3.00 cwt cement (50 kg bags)
0.20 cubes sand
Water (115 gals)
Rate per square
Labour
3 1/2 days mason
5 1/2 days U/Sk labourer
Scaffolding - Add 2%
Materials
1630 bricks Add 5% wastage
4.50 cwt cement (50 kg bags)
0.30 cubes sand
Water (170 gals)
Rate per square
Labour
2 1/4 days mason
3 days U/Sk labourer
Scaffolding - Add 3%
Materials
1090 bricks Add 5% wastage
1.75 cwt cement (50 kg bags)
0.30 cubes sand
Water (115 gals)
Rate per square

Labour
1 1/2 days mason
2 days U/Sk labourer
Scaffolding - Add 5%
Materials

550 wire cut bricks Add 5% wastage


1.20 cwt cement (50 kg bags)
0.08 cubes sand
Water (30 gals)
Rate per square

Labour
2 1/4 days mason
3 3/4 days U/Sk labourer
Scaffolding - Add 3%
Materials
1050 wire cut bricks Add 4% wastage
2.50 cwt cement (50 kg bags)
0.18 cubes sand
Water (100 gals)
Rate per square

Labour
3 3/4 days mason
5 1/2 days U/Sk labourer
Scaffolding - Add 2%
Materials
1630 wire cut bricks Add 2% wastage
4.50 cwt cement (50 kg bags)
0.60 cubes sand
Water (50 gals)
Rate per square

Labour
5 days mason
3 1/2 days U/Sk labourer
Materials
0.50 cwt cement (50 kg bags)
1.00 cubes sand
1/10 gals acid
Water (10 gals)
Rate per square
Labour
1 1/4 days mason

2 1/2 days U/Sk labourer


Materials
350 bricks
1.20 cwt cement (50 kg bags)
0.11 cubes sand
Water (45 gals)
Rate per square

Labour
1/2 days mason
1/2 days U/Sk labourer
Materials
120 bricks
0.50 cwt cement (50 kg bags)
0.05 cubes sand
Water (15 gals)
Rate per L.ft

Labour
1 1/4 days mason
1 1/4 days U/Sk labourer
Materials
140 bricks
0.80 cwt cement (50 kg bags)
0.05 cubes sand
Water (20 gals)
Rate per L.ft

Labour
1 days mason
1 1/4 days U/Sk labourer
Materials
110 bricks
0.70 cwt cement (50 kg bags)
0.04 cubes sand
Water (15 gals)
Rate per L.ft

Labour
1 1/2 days mason
2 1/2 days U/Sk labourer
Scaffolding - Add 3%
Materials
112 Hollow cement blocks Allow 5% for wastage
0.75 cwt cement (50 kg bags)
0.06 cubes sand
Rate per square
Labour
1 days mason
2 days U/Sk labourer
Scaffolding - Add 5%
Materials
112 Hollow cement blocks(size of each block 16" x
8" x 4") Allow 5% for wastage
0.40 cwt cement (50 kg bags)
0.03 cubes sand
Rate per square
Labour
4 days mason
6 days U/Sk labourer
Materials
1.30 cubes 6" - 9" rubble
5.00 cwt cement (50 kg bags)
0.30 cubes sand
Water 100 gals
Rate per cube
Labour
4 1/2 days mason
7 days U/Sk labourer
Scaffolding - Add 3%
Materials
1.30 cubes 6" - 9" rubble
5.00 cwt cement (50 kg bags)
0.30 cubes sand
Water 100 gals

Rate per cube

Labour
4 days mason
4 days U/Sk labourer
1/2 day U/Sk labourer for polishing
Materials
225 pressed tiles 8" x 8" Add 5% for wastage
1 1/4 cwt cement (50 kg bags)
0.07 cubes sand
1/4 lb wax polish
1/4 lb coloured pigment
2 lbs cotton waste
Rate per square

Labour
4 days mason
4 days U/Sk labourer
1/4 day U/Sk labourer for cleaning

4.00
4.00
0.25

Materials
400 glazed tiles 6" x 6" Add 10% for wastage
2 1/2 cwt cement (50 kg bags)
0.11 cubes sand
1 lb white cement

110.00
2.98
0.11
0.45

Rate per square


Labour
4 days mason
3 days U/Sk labourer
1/2 day U/Sk labourer for polishing
Materials
100 12" x 12" terrazzo tiles Add 5% for wastage
1 1/4 cwt cement (50 kg bags)
0.07 cubes sand
coloured pigment (2 lbs)
1/2 lb wax polish
2 lb cotton waste
Rate per square

1,300.00
1,000.00
1,000.00

130.00
872.00
10,512.00
800.00

5200
4000
250
0
0
14300
2598.56
1156.32
362.4
27867.28

3,611.60

Labour
7 days carpenter
8 days U/Sk labourer
1/2 day U/Sk labourer for polishing
Materials
34.00 cu.ft timber Add 10% for wastage
660 1.ft 2" x 1" reepers Add 5% wastage
8 lbs wire nails 6" long
2 lbs wire nails 2" long
Rate per square

Labour
3 days carpenter
3 days U/Sk labourer
Materials
750 tiles
Rate per square
Labour
2 1/2 days carpenter
3 days U/Sk labourer
Materials
13 1/4 cu.ft timber purloins Add 10% for wastage
Rate per square

Labour
1 day carpenter
2 days U/Sk labourer
Materials
420 sq.ft asbestos corrugated sheets.
72 Nos. roofing screws and washers.
Rate per square
Labour
2 days U/Sk labourer
Materials
650 half round clay tiles

Rate per square


Labour
1/4 day carpenter
1/4 day U/Sk labourer
Materials
4 pairs ridges 3' 8" long
16 roofing screws or bolts
Rate per L.ft
Labour
1/4 day carpenter
1/4 day U/Sk labourer
Materials
9 ridge tiles
1/3 cwt cement (50 kg bags)
0.02 cubes sand
15 lbs slaked lime
1/2 lb colouring powder
Rate per L.ft

Labour
3 days carpenter
3 days U/Sk labourer
Scaffolding - Add 5%
Materials
75.00 sq.ft 1" planks Add 5% for wastage
70 Nos. 1 1/2" brass screws
Rate per L.ft

Labour
3 days carpenter
3 days U/Sk labourer
Scaffolding - Add 5%
Materials
75.00 sq.ft 1" planks Add 5% for wastage
50 Nos. 1 1/2" brass screws
Rate per L.ft

Labour
a) Fixing boarding and applying wood pressrvative 1 day carpenter
1 day U/Sk labourer
b) Making and fixing G.I sheets 1/2 day tinker
1/2 day U/Sk labourer
c) Building sides 1/4 day mason
1/2 day U/Sk labourer
Materials
2 G.I sheet (8' x 4')
1/4 gal wood preservative
0.10 cwt cement (50 kg bags)
0.05 cwt slaked lime
1.00 cu.ft sand
50.00 sq.ft planks
2 lbs 1 1/2" wire nails
Rate per L.ft

Labour
Cutting bending, soldering & fixing 1/2 day tinker
1/9 day mason (caulking)
3/4 day U/Sk labourer
Materials
1 G.I sheet (8' x 4')
0.05 cwt cement (50 kg bags)
1.00 cu.ft sand
1 lb soldering lead
Rate per L.ft

Labour
2 1/2 days carpenter
1/2 days mason
1 1/2 days U/Sk labourer
Scaffolding - Add 3%
Materials

8.00 cu.ft timber class I


1 lb 2" nails
25 lbs cement
2.00 cu.ft sand
2" brush - 1/4 use
1/3 gal tarnap
Rate per square

Labour
1 1/2 days carpenter
2 days U/Sk labourer
Scaffolding - Add 3%
Materials
210 sq.ft flat asbestos sheets
60 l.ft 2" x 2" halmilla cove mouldings
125 l.ft 1 1/12" x 1/2" halmilla beadings
3/4 lb - 1/4" lb out nails
8 doz 1 1/2" brass screws
Rate per square

Labour
Making holes, fixing joists & making roof
1 day mason
1 day carpenter
3 days U/Sk labourer
Materials
115 l.ft 4" x 2" timber joists
215 so.ft 6" x 3/4" Lunumidella ceiling planks.
Ceiling planks.
3 lbs cement
4.00 cu.ft sand
4 kg 1 1/2" brass nails
Rate per square

Labour
3 days carpenter
6 days U/Sk labourer
Scaffolding - Add 3%
Materials

220.00 sq.ft ceiling planks


40.00 l.ft 2" x 1/4" timber strips
2.00 kg 3/4" nails
4.00 kg 1 1/2" brass nails.
Rate per square

Labour
5 days carpenter.
1 1/2 days U/Sk labourer
Materials
a) Frame 1 1/2 cu.ft 4" x 3" timber
2 No. spur stones
6 No. fiber/ plastic plugs With 4" long brass screws.
2 No. 5/8" mild steel dowels 4" long,
b) Sash 14 sq.ft 1 1/2" planks
5 sq.ft 1" planks
Rate per sqft

Labour
6 days carpenter.
2 days U/Sk labourer
Materials
a) Frame 1 2/3 cu.ft 4" x 3" timber
2 No. spur stones
6 No. fiber/ plastic plugs With 4" long brass screws.
2 No. 5/8" mild steel dowels 4" long,
b) Sashes 16 sq.ft 1 1/2" planks
7 sq.ft 1" planks
Rate per sqft

Labour
3/4 day carpenter.
3/8 day U/Sk labourer
1/4 day mason (fixing frame)
1/4 day U/Sk labourer ( - do -)

Materials
a) Frame 1.80 cu.ft 4" x 3" timber
2 No. spur stones
6 No. fiber/ plastic plugs With 4" long brass screws.
b) Sashe 1 No 6' 9" x 2' 9" plywood sash.
Rate per sqft

Labour
2 1/4 days carpenter.
1 day U/Sk labourer
1/4 day mason (fixing frame)
1/4 day U/Sk labourer ( - do -)
Materials
a) Frame 1.70 cu.ft 4" x 3" timber
2 No. spur stones
6 No. fiber/ plastic plugs With 4" long brass screws.
2 No 5/8" mild steel dowels
b) Sashe 21.00 sq.ft 1" thick planks
3 doz 1 1/4 long brass screws.
Rate per sqft

Labour
6 days carpenter.
2 1/2 days U/Sk labourer
1/2 day mason (fixing frame)
1/2 day U/Sk labourer ( - do -)
Materials
a) Frame 3.20 cu.ft 4" x 3" timber
4 No. fiber/ plastic plugs With 4" long brass screws.
b) Sashes 9.25 sq.ft 3" x 1 1/2" timber

Rate per sqft

Labour
1/2 day glazier
1/2 day U/Sk labourer
Materials
9.00 sq.ft glass panes
30 L.ft 1/2" x 1/2" beading
4 doz brass panel pins
Rate per sqft

Labour
1/4 day carpenter
1/4 day U/Sk labourer
Materials
1 1/2 pairs butt hinges
2 Doz 3/4" brass screws
Rate per No
Labour
1/4 day carpenter
1/4 day U/Sk labourer
Materials
1 pair Tee hinges
1 1/2 Doz 3/4" brass screws
Rate per pair
Labour
1/4 day carpenter
1/4 day U/Sk labourer
Materials
1 rim lock with screws
Rate per No.
Labour
1/4 day carpenter
1/4 day U/Sk labourer
Materials

1 mortice look with screws


Rate per No.
Labour
1/4 day carpenter
1/4 day U/Sk labourer
Materials
4 casement stays
16 1/2" brass screws
Rate per No.
Labour
1/4 day carpenter
1/4 day U/Sk labourer
Materials
1 door closer
8 3/4" brass screws
Rate per No.
Labour
1/2 day carpenter
1/2 day U/Sk labourer
Materials
1 Tower / Skeleton Bolt
10 1/2" brass screws
Rate per No.
Labour
1/2 day carpenter
1/2 day U/Sk labourer
Materials
1 barrel bolt
8 1/2" brass screws
Rate per No.
Labour
1/2 day carpenter
1/2 day U/Sk labourer
Materials
6 casement fasteners

24 1/2" brass screws


Rate per No.
Labour
1/2 day carpenter
1/2 day U/Sk labourer
Materials
6 brass fanlight catches
2 doz 1/2" brass screws
Rate per No.
Labour
1/8 day carpenter
1/8 day U/Sk labourer
Materials
6 draw rings
1doz 1/2" brass screws
Rate per No.

Per square
Materials
2.25 cwt cement
0.11 cube sand
1 1/2 gals bitumen
Firewood (10 lbs)
Water 10 gals

1.30 cwt slaked lime


0.07 cubes sand
Water 10 gals

Labour

1 1/4 days
mason

1 1/2 days
U/Sk labourer
1
3/4 days U/Sk
labourer

Scaffolding 1.40 cwt cement (50 kg bags)


0.06 cube sand
Water 10 gals.

1
1/2 days U/Sk
labourer
Scaffolding Add 3%

Rate Per
square

0.80 cwt cement (50 kg bags)


0.16 cwt slaked lime
0.05 cubes sand
Water 5 gals.

2 1/2 days
U/Sk labourer

Scaffolding Add 3%
0.80 cwt cement (50 kg bags)
0.16 cwt slaked lime
0.03 cubes sand
Water 5 gals.

2
days U/Sk
labourer
Scaffolding Add 3%

0.80 cwt cement (50 kg bags)


0.40 cwt slaked lime
0.07 cubes sand
Water 10 gals.

1 3/4
days U/Sk
labourer
Scaffolding Add 3%

0.80 cwt cement (50 kg bags)


0.60 cwt slaked lime
0.07 cubes sand
Water 10 gals.

1 1/2 days
U/Sk labourer
(1 1/2)
Scaffolding Add 3%

1.07 cwt cement (50 kg bags)


0.05 cube sand
Water 10 gals

1.50 cwt cement (50 kg bags)


0.05 cubes sand
Water 10 gals.

1 1/2 days
U/Sk labourer
1
1/2 days U/Sk
labourer
1/4 day

1.75 cwt cement ( 50 kg bags)


0.08 cube sand
Water 10 gals

2 days
U/Sk labourer
1/4
day U/Sk

2.25 cwt cement


0.08 cube sand
Water 10 gals

2 days
U/Sk labourer
1/4
day U/Sk

2.25 cwt cement (50 kg bags)


0.08 cube sand
5lbs powdered
pigment
Water 10 gals

2 days
U/Sk labourer
3/4
day U/Sk

Per 10 l.f t
Materials

Labour

0.10 cwt cement ( 50 kg bags)


0.003 cube sand
0.25 lbs powdered pigment

Per one souare


Materials

5/16 U/Sk
3/4Labour
day
painter

2.75 ltr. Wood preservative (oil type)


3" brush (1/10 use)
2 3/4 ltr. Anti - corrosive primer
0.15 ltr. Mineral turpentine or
thinner
1 wire brush
2" brush
(1/3 use)
0.20 lts. Anti - corrosive primer
1 1/3 ltr. Enamel paint
0.20 ltr. Mineral turpentine or
thinner
2" brush (1/5
use)

Consider 50 sq.ft
Materials

1/2 day
1U/Sk
1/2 days
labourer
painter
1
1/2 day U/Sk
labourer
1
day U/Sk
labourer
Scaffolding Add 3%

Labour

1 1/2 lts. Anti - corrosive primer


2/3 ltr. Enamel paint
0.30 ltr. Mineral turpentine or
3/4 day U/Sk
thinner
labourer
1/3 wire brush
2" brush (1/5 use)

Per squere
Materials

Labour

2/3 ltr. Anti - carrosive paint


2" brush ( 1/5 use)
1/2 gal wood preservative
2" brush (1/5 use)
3/4 ltr. Primer
2.50 ltr. Enamel paint (2 coats)
2" brush ( 1/10 use)
2 sand papers

Per 10 square
Materials

1 1/2 days
painter
painter
painter

1/2 day U/Sk

Labour 2
1/2 days U/Sk
labourers

0 - 50 cwt boiled lime


2 lbs salt
1/2 lb yellow ochre
2 ozs blue
6" brush
(1/3 use)
Water 10 gals

(As per above)


Add 1/2 day painter
1/2 day U/Sk labourers
Scaffolding - Add 3%
Total

Per square
Materials
Primer 0.90 ltr. Primer
1.40 ltr. Emulsion pant
Water 0.10 gals
6" brush (1/10 use)
2 sand papers

Per 10 square
Materials

Scaffolding
- Add 3%

Total
per 10.00
squares

Labour

1 1/4 day
painter

Scaffolding Add 3%

Labour
2 days U/Sk
labourer

5/8 cwt cement


1 - 6" coir brush
Water 5 gals

Per square
Materials

Scaffolding Add 3%
Total per
10.00 sqrs.

Labour

painter
1 st coat 1/6 gal emulsion paint
2 nd coat 1/7 gal emulsion paint
6" brush - (1/10 use)
0.10 gals water
0.90 ltr. Primer
1.50 ltr. Emulsion paint
6" brush ( 1/10 use)

Scaffolding Add 3%

Scaffolding
- Add 3%
painter

0.40 gals ( 1.80 ltr.) varnish


3" brush (1/3 use)
1/2 day U/Sk
3/4 lb. Wax polish
1/2 doz. Sheets sandpaper
3 hrs. U/Sk
1/10 floor brush
labourer
1/2 yards flannel cloth

Per 10 l.ft
Materials

Labour

13 l.ft pipes
3 clips and nails
2 grms solvent cement

1 hr. U/Sk
labourer

13 l.ft pipes
3 clips and nails
2 grms solvent cement

1 hr. U/Sk
labourer

Per 100 l.ft


Materials

Labour

plumber

100 L.ft pipes


Add 5% for wastage
1/2 day
8 - 1" dia sockets
U/Sk labourer
32 grams. solvent cement
35 clips and nails
plumber
Total per
100 L.ft pipes
Add 5% for wastage
3/4 day
8 - 1 1/4" dia sockets
U/Sk labourer
48 grams. solvent
cement
35 clips
and nails
Total per

Rate per
L.ft

plumber
100 L.ft pipes
Add 5% for wastage
8 - 1 1/2" dia sockets
64 grams. solvent
cement
35 clips
and nails

3/4 day
U/Sk labourer

100 L.ft pipes


Add 5% for wastage
8 - 2" dia sockets
112 grams. solvent
cement
35 clips
and nails

3/4 day
U/Sk labourer

100 L.ft pipes


Add 5% for wastage
8 - 3" dia sockets
200 grams. solvent
cement
35 clips
and nails

plumber
Total per

Total per
1
day U/Sk
labourer
2Total
1/4 per
days100
U/Sk labourer
Total
per 100 L.ft

0.10 cwt cement


0.01 cube sand

3 days U/Sk
labourer

0.20 cwt cement


0.03 cube sand

3 1/2
days U/Sk
labourer

Per 10 specials
Materials

Labour

10 - 1/2" elbows / bends / socket


20 grms solvent cement
Total per 10
10 - 3/4" dia elbows / bends / sockets
30 grms solvent cement
Total per 10
10 - 1" dia elbows / bends / sockets
40 grms solvent cement
Total per 10
10 - 1 1/4" dia elbows / bends / sockets
60 grms solvent cement
Total per 10

Rate per No.

plumber
10 - 1 1/2" dia elbows / bends / sockets
80 grms solvent cement

10 - 2" dia elbows / bends / sockets


140 grms solvent cement

10 - 2 1/2" dia elbows / bends / sockets


200 grms solvent cement

10 - 3" dia elbows / bends / sockets


240 grms solvent cement

Per 10 Tees
Materials
10 - 1/2" Tees
30 grms solvent cement

10 - 3/4" Tees
45 grms solvent cement

10 - 1" dia Tees


60 grms solvent cement

10 - 1 1/4" dia Tees


90 grms solvent cement

Total
per 10 No.
plumber
Total
per 10 No.
plumber
Total
per 10 No.
plumber
Total
per 10 No.

Labour

plumber

Total
per 10 No.
plumber
Total
per 10 No.
plumber
Total
per 10 No.
plumber
Total
per
10plumber
No.
1 day

10 - 1 1/2" dia Tees


120 grms solvent cement
Total per 10
1 day plumber
No. tees
10 - 2" dia Tees
210 grms solvent cement
Total per 10
No. tees
plumber
10 - 2 1/2" dia Tees
300 grms solvent cement

10 - 3" dia Tees


360 grms solvent cement

Total
per 10 No.
plumber
Total
per 10 No.

Per 100 l.ft


Materials

Labour

bedding - 1
1/2 day U/Sk
labourer

Rate per
L.ft

Laying and
50 - 4" dia Ew pipes
testing pipes 0.75 cubes cement concrete - 1: 3: 6: ( 1 1/2")
2 days
2 lbs yarn
plumber
0.50 cwt cement
(jointing)
4.00 cubes
2 days U/Sk
excavation
labourer
Backfilling - 2
1/2 days U/Sk
labourer

Per 6' 0" length


Materials

Labour
1/4 day
U/Sk labourer

6' 0" L.ft 4" dia C.I. Pipe


Add 10% for wastage
5/16 lbs yarn
1 - timber plug 6" x 6" x 2"
Scaffolding
2 - 3" iron screws
- Add 5%
2 lbs
cement
Total for 6
L.ft
6' 0" L.ft 4" dia C.I. Pipe
Add 10%
(Add 10% for wastage)
for sundries in
6 lbs lead
cement
5/16 lbs yarn
1 - wood plug 6" x 6" x 2"
2 - 3" iron
screws
and sand
1/16 cwt firewood

Per No.
Materials
1 - 4" S.W. gulley
4.00 cu.ft excavation
5.50 sq.ft 4 1/2" brickwork
0.80 cu.ft cement
concrete ( 1: 2 : 4 ( 3/4")
1.00
sq.ft 1/2" cement rendering 1:2
1 - 4" G.I. grating.

Labour
1/2 day mason
1/2
day U/Sk
labourer

Rate per No.

35.00 cu.ft excavation


7.00 cu.ft cement concrete
1 : 2 : 4 (3/4") in base & channels
33.00 sq.ft 4 1/2" brickwork
in cement 1:5
28.00 sq.ft 1/2"
cement rendering 1:2
1RCC cover slab.
1 wash basin complete with brackets
1 - 1/2" tap
Waste plug and chain
4 wooden plugs
6 - 1 1/2" brass screws
2 lbs cement

mason
2 1/2 days
U/Sk labourer

1/2 day mason


1
day U/Sk
labourer

1 low level suite complete


1 - 1/2" dia stop cock
1 day
2 lbs cement
plumber
1/4 cu.ft sand
2 - 1 1/2" brass screws
1 day
1 squatiing pan with trap
1/2 day mason
2 gals C.I cistern with 1 1/4" flush,
pipe , chain and overflow pipe
1 clip
1
5 wooden plugs
day plumber
1
doz. 1 1/2" brass screws
1 - 1/2" stop cock
1 day
1/4 cwt cement
U/Sk labourer
1/2 cu.ft metal
1/4 cu.ft sand
1 day plumber
1 bidet
4 Urinal Bowls
1-2 gal. Cistern
8 rawl plugs
1 spreader
4 wooden plugs
(for cistern)
4-1
1/2" brass screws
4 lbs cement
1/8 cu.ft sand

Consider 24.00 L.ft


Materials

1 day U/Sk
labourer
1 day
plumber
1 day
U/Sk labourer

Labour

Rate per
L.ft

1/2 day
U/Sk labourer
2 - 6" dia eaves gutter lengths
1 joiner
17 gutter brackets
34 - 3/4" brass
screws
20 grms solvent cement

Scaffolding
Add 5%
Total

Rate per
cube

a) Copper
Naphthenat
e (5% in 4
to 8 gals of
fuel oil)

Note.b)Sodium
Alternati
Arsenate
ve Mixes
(10% in 12
to 20 gals)
of water.
C)
Bieldrine
(0.3% in 19

Note

Note

Note

a) Water
available at
site.

b) If,
water is not
available
allowances
should be
3,500.00 made for
transport of
water.

c) Sand includes
15% for
bulking.

4.00
4.00
0.25

1,300.00
1,000.00
1,000.00

70.00
2.98
0.11
0.45

280.00
872.00
10,512.00
800.00

5200
4000
250
0
0
19600
2598.56
1156.32
362.4
33167.28

4,298.48

4.00
4.00
0.25

1,300.00
1,000.00
1,000.00

30.00
2.98
0.11
0.45

950.00
872.00
10,512.00
800.00

5200
4000
250
0
0
28500
2598.56
1156.32
362.4
42067.28

4,634.13

Note
coloured
skirting is
not
required,
delete
provision

4.00
4.00
0.25

110.00
2.98
0.11
0.45

1,300.00
1,000.00
1,000.00

160.00
872.00
10,512.00
800.00

4.00
4.00
0.25

5200
4000
250
0
0
17600
2598.56
1156.32
362.4
31167.28

165.00
2.98
0.11
0.45
3,433.39

1,300.00
1,000.00
1,000.00

110.00
872.00
10,512.00
800.00

5200
4000
250
0
0
18150
2598.56
1156.32
362.4
31717.28

3,493.98

EARTH WORKS
1 Removing top soil to a depth not exceeding 6" & depositing as directed within site

2 Excavation over site to reduce level, in any material except rock requiring blasting
including depositing and leveling as directed up to distance not exceeding 30' 0" per
cube

3 Excavation in trenches for walls/ column pits in soft/ loose soil from 0' 0" to 5' 0" deep
and depositing excavated materiel to a distance not exceeding 30' 0" (Earth work
support to be paid separately where necessary) per cube.

4 Excavation in trenches for walls/ column pits in ordinary soil from 0' 0" to 5' 0" deep
and depositing excavated material not exceeding 30' 0" per cube.

5 Excavation in trenches for walls/ column pits in Hard/ dense soil up to a depth of 5' 0"
and depositing excavated material up to a distance not exceeding 30' 0".

6 Excavation in trenches for walls/ column pits in Mud/ wet soil up to a depth of 5' 0"
and depositing excavated material to distance not exceeding 30' 0". (Earth work &
dewatering paid for separately.)

7 Excavation in trenches for walls/ column pits in soft disintegrated rock (not requiring
blasting) up to depth of 5' 0" and depositing excavated material to distance not
exceeding 30' 0".

Excavation in trenches for walls/ column pits in Hard rock requiring blasting up to a
depth of 5' 0" and depositing excavated material to distance not exceeding 30' 0".
Per cube

9 Benching rock in foundation in 3" - 6" steps. (Blasting prohibited)


Per 10 square feet

ANTI - TERMITE TREATMENT


10 Anti - termite treatment on excavated foundation and compacted soil under floors.

Earth work - Backfilling & Compacting


11 Backfilling to trenches with selected earth available at site.

12 Back filling to trenches with imported material.

13 Filling under floors including leveling, watering & compacting in 3" layers with
available and selected earth at site.

14 Filling under floors including leveling, watering & compacting in 3" layers with
imported selected earth.

15 Cutting turf sods, landing to hand carts and transporting up to 30 yards, laying and
watering for 30 days. (Royalty for turf, pegging and transport beyond 30 yards paid
separately)

Earth work support (open planking) in trenches up to a depth of 5' 0"


16 Consider trench 15' 0" long 3' 0" wide and 5' 0" depth open planking to both faces.
Total area
- 2/ 15' 0" x 5' 0"
.
= 150 sq.ft

Earth work support (close planking) in trenches up to 5' 0" depth.


17 Consider trench 15' 0" long 3' 0" wide and 5' 0" height of planking to both faces.
Total area of planking 2/ 15' 0" x 5' 0" ie 150 sq.ft

18 Earth work support (close planking) in deep excavation in trenches up to 15' 0" depth.
- Consider trench of length of 15' 0" width 5' 6" at top 3' 6" at bottom
Then
area supported is 2/ 15' x 15' ie 450 sq.ft.

Rates

Labour
Consider an area of 10.00 sqrs. Ie 5.00 cubes of
excavation.10 day a U/Sk labourer.

4,000.00

Labour

Materials

4,000.00

Material

0.00

Rate per square

Labour
1 5/ 8 day U/ Sk labourer

4,000.00

650.00

650.00

Material

0.00

Rate per cube

Labour
1 day U/ Sk labourer

650.00

400.00

400.00

Material

0.00

Rate per cube

Labour
2 1/4 days U/ Sk labourer.

400.00

900.00

900.00

Material

0.00

Rate per cube

Labour
3 1/2 days U/Sk labourer

900.00

1,400.00

1,400.00

Material

0.00

Rate per cube

Labour
3 days U/Sk labourer.

Rate per unit

1,400.00

1,200.00

1,200.00

Material

0.00

Rate per cube

Labour
2 1/2 days U/Sk labourer

1,200.00

1,000.00

1,000.00

Material

0.00

Rate per cube

Labour
1 day Sk labourer
2 days U/Sk labourer

1,000.00

600.00
800.00

1,400.00

Materials
0.75 lbs blasting powder
0.00
10 lft fuse

0.00

1 lb jumper steel

0.00

0.00

Rate per cube


Labour
Drilling, chipping & wedging 1 1/2 day Sk labourer
Steel, fuel & forge - 25% of labour cost
Collecting & Disposing 1 1/2 day U/Sk labourer per
10 sq.ft

1,400.00

900.00
225.00
600.00

1,725.00

Material

0.00

Rate per Square

17,250.00

Labour
1/2 day U/ Sk labourer
Materials
16 lbs D.D.T. powder (8% in 20 gals of water)
20 gals water
Rate per Square

200.00

0.00
40.00

200.00

40.00
240.00

Labour
1 day U/ Sk labourer

400.00

400.00

Materials

0.00

Rate per cube


Labour
1 1/4 U/Sk labourer
Materials
1.00 cube earth delivered at site.
Allow 15% compaction
Filling & Compacting

400.00

500.00

500.00

402.50
402.50

Rate per cube

Labour
2 day U/ Sk labourer

902.50

800.00

800.00

Materials

0.00

Rate per cube

800.00

Labour
2 days U/Sk labourer

800.00

Materials
1.00 cube earth delivered at site.
Allow 15% compaction

402.50

800.00

402.50

Rate per cube

1,202.50

Labour
Cutting turf sods, loading and transporting to site and
unloading
2
1/2 day U/ Sk labourer

1,000.00

Laying turf rods at site 1 1/2 day U/ Sk labourer


Watering for 30 days 1 1/2 days U/Sk labourer

600.00
600.00

Materials
60 gals. water

120.00

2,200.00

120.00

Rate per square

Labour
1 days carpenter
3 days U/ Sk labourer
Materials
17.50 cu.ft class II timber (4 uses)
Add 5% on above for wedges.

2,320.00

600.00
1,200.00

1,800.00

0.00

0.00

Rate per square

1,200.00

Labour
2 days carpenter
6 days U/ Sk labourer.
Materials
30.00 cu.ft class II timber (4 uses)
Add 5% on above for wedges.

1,200.00
2,400.00

3,600.00

0.00

0.00

Rate per square

Labour
8 days carpenter
20 days U/Sk Labourer

2,400.00

4,800.00
8,000.00

12,800.00

Materials
100.00 cu.ft class II Timber (4 uses)
Add 5% on above for wedge.
Rate per square

0.00

0.00
2,844.44

Note
Rate does not include for
a) Royalty for turf
b) Transport of turf
c) Pegs on sloping site
d) Water

a) Copper Naphthenate
in 4 to 8 galsMixes
of fuel oil)
Note. -(5%
Alternative
b) Sodium Arsenate (10% in 12 to 20 gals) of
water.
C) Bieldrine (0.3% in 19 gals of
water)

CONCRETE
19 Mixing concrete 1: 3: 6 (1 1/2")

20 Mixing concrete 1: 2: 5 (1")

21 Mixing concrete 1: 2: 4 (3/4")

22 Mixing concrete 1: 1: 3 (3/4")

23 Mixing concrete 1: 1: 2 (3/4")

24 2" thick cement concrete screed in foundation at depths not exceeding 5' 0"

25 3" thick cement concrete screed in foundation at depths not exceeding 5' 0"

26 6" thick cement concrete floor (mass concrete).

Cement concrete in 4 1/2" x 6" columns in ground floor.


27 Consider 24 No. columns each 4 1/2" x 6" x 10' 0" ie 0.45 cubes.

28 Cement concrete in 6" x 6" colomns in ground floor. Consider 18 No. columns 6" x 6" each 10' 0" high ie 0.45 cubes.

Curing

29 Cement concrete in 9" x 9" colomns in ground floor. - Consider 8 No. 9" x 9" columns
each 10' 0" high ie 0.45 cubes.

Curing

30 Cement concrete in 12" x 12" colomns in ground floor. Consider 5 No. 12" x 12" columns each 10' 0" high.
Per 0.5 cube

31 Cement concrete in 13 1/2" x 13 1/2" colomns in ground floor. Consider 4 No. colomns 13 1/2" x 13 1/2" each 10' 0" high .
I.e 0.51 cubes.

Curing

32 Cement concrete in 6" x 6" beam up to 1st floor level. Consider 180 L.ft of beam 6" x 6"
I.e 0.45 cubes.

Curing

33 Cement concrete in 9" x 6" beam up to 1st floor level. Consider 120 L.ft of beam 9" x 6" beam
I.e 0.45 cubes.

Curing

34 Cement concrete in 9" x 9" beam up to 1st floor level. Consider 80' 0" length 9" x 9" beam
I.e 0.45 cubes.

Curing

35 5" thick R.CC floor slab in 1st floor. Consider 5" thick slab 10' 0" x 12' 0" volume of concrete 50.00 cu.ft

Curing

36 6" thick R.CC floor slab in 1st floor. Consider 10' 0" x 10' 0" panel = 50 cu.ft

Curing

37 Cement concrete in 4 1/2" x 6" lintels in ground floor. Consider 240 l.ft I.e 45 cu.ft

Curing

38 Cement concrete in 9" x 9" lintels in ground floor. Consider 80 L.ft of lintel I.e 45 cu.ft concrete.

Curing

39 Cement concrete in 9" x 12" lintels in ground floor. Consider length 60' 0" of lintel
= 45 cu.ft

Curing

40 Cement concrete in 12" x 15" lintels in ground floor. Consider length 36' 0"
i.e 45 cu.ft

Curing

Rates

Labour
1 day skilled labourer
6 days U/ Sk labourer

600.00
2,400.00

Materials
13 cwt (50 kg bags) cement
0.53 cubes sand
0.92 cubes 1 1/2" metal
Water (110 gals)

7,150.00
2,332.00
3,036.00
220.00

Equipments
1/3 day hire of mixer

495.00

Labour

Materials

3,000.00

12,738.00

495.00

Rate per cube

16,233.00

Labour
1 day skilled labourer
5 days U/ Sk labourer

600.00
2,000.00

Materials
14 cwt (50 kg bags) cement
0.60 cubes sand
0.92 cubes 1" metal
Water (100 gals)

7,700.00
2,640.00
3,128.00
200.00

Equipments
1/3 day hire of mixer

495.00

2,600.00

13,668.00

495.00

Rate per cube

16,763.00

Labour
1 day skilled labourer
6 days U/ Sk labourer

600.00
2,400.00

Materials
18 cwt (50 kg bags) cement
0.50 cubes sand
0.88 cubes 3/4" metal
Water (120 gals)

9,900.00
2,200.00
3,080.00
240.00

Equipments
1/3 day hire of mixer

495.00

Rate per cube


Labour
1 day skilled labourer

Rate per unit

3,000.00

15,420.00

495.00
18,915.00

600.00

6 days U/ Sk labourer
Materials
23 cwt (50 kg bags) cement
0.42 cubes sand
0.82 cubes 3/4" metal
Water (150 gals)
Equipments
1/3 day hire of mixer

2,400.00

3,000.00

12,650.00
1,848.00
3,080.00
300.00

495.00

17,878.00

495.00

Rate per cube


Labour
1 day skilled labourer
6 days U/ Sk labourer
Materials
31 cwt (50 kg bags) cement
0.44 cubes sand
0.96 cubes 3/4" metal
Water (200 gals)
Equipments
1/3 day hire of mixer

21,373.00

600.00
2,400.00

3,000.00

17,050.00
1,936.00
3,080.00
400.00

495.00

22,466.00

495.00

Rate per cube


Labour
1/8 days skilled labourer
1/2 days unskilled labourer

25,961.00

75.00
200.00

275.00

Materials
1/6 cube concrete (Add 10% for wastage )

0.00

Rate per square


Labour
1/8 days skilled labourer
3/4 days unskilled labourer

275.00

75.00
300.00

375.00

Materials
1/4 cube concrete (Add 10% for wastage )

0.00

Rate per square


Labour
1/2 days skilled labourer
1 1/2 days unskilled labourer

375.00

300.00
600.00

900.00

Materials
1/2 cube concrete (Add 10% for wastage )
200 gal of water

400.00

400.00

Rate per square


Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)

1,300.00

600.00
600.00
1,200.00
600.00

3,000.00

Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube

Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)

10,000.00

600.00
600.00
1,200.00
600.00

3,000.00

Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube


Labour
1 1/2 days U/Sk labourer

10,000.00

600.00

600.00

Materials
Jute
Hessian - 80 sq.ft
Water - 140 gals

0.00
280.00

280.00

Rate per cube

Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)

880.00

600.00
600.00
1,200.00
600.00

3,000.00

Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube


Labour
1/2 days U/Sk labourer

10,000.00

200.00

200.00

Materials
Jute Hessian - 60 sq.ft
Water - 100 gals

0.00
200.00

200.00

Rate per cube

Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)
Materials
0.50 cube concrete (Add 10% for wastage )
40 so.ft - Jute Hessian
Water (100 gals)

Equipments
1 day hire of vibrator

400.00

600.00
600.00
1,200.00
600.00

3,000.00

0.00
200.00

1,500.00

200.00

1,500.00

Rate per cube

Labour
1 day mason
1day carpenter
3 days U/Sk labourer
1 day Sk labourer (Vibrator)

9,400.00

600.00
600.00
1,200.00
600.00

3,000.00

Materials
0.51 cube concrete (Add 5% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube


Labour
1 1/2 days U/Sk labourer

8,823.53

600.00

600.00

Materials
Jute
Hessian - 45 sq.ft
Water - 100 gals

0.00
200.00

200.00

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)

800.00

600.00
600.00
1,600.00
600.00

3,400.00

Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube


Labour
1 1/2 days U/Sk labourer

10,888.89

600.00

600.00

Materials
Jute
Hessian - 90 sq.ft
Water - 180 gals

0.00
360.00

360.00

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)

960.00

600.00
600.00
1,600.00
600.00

3,400.00

Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube


Labour
1 1/2 days U/Sk labourer

10,888.89

600.00

600.00

Materials
Jute
Hessian - 75 sq.ft
Water - 150 gals

0.00
300.00

300.00

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)

900.00

600.00
600.00
1,600.00
600.00

3,400.00

Materials
0.45 cube concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube


Labour
1 1/2 days U/Sk labourer

10,888.89

600.00

600.00

Materials
Jute
Hessian - 60 sq.ft
Water - 120 gals

0.00
240.00

240.00

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)

840.00

600.00
600.00
1,600.00
600.00

3,400.00

Materials
50 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube


Labour
1 1/2 days U/Sk labourer

9,800.00

600.00

600.00

Materials
Jute
Hessian - 30 sq.ft
Water - 90 gals

0.00
180.00

180.00

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)

780.00

600.00
600.00
1,600.00
600.00

3,400.00

Materials
50 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube


Labour
1 1/2 days U/Sk labourer

9,800.00

600.00

600.00

Materials
Jute
Hessian - 25 sq.ft
Water - 90 gals

0.00
180.00

180.00

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)

780.00

600.00
600.00
1,600.00
600.00

3,400.00

Materials
45 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube

0.00

1,500.00

1,500.00
10,888.89

Labour
1 1/2 days U/Sk labourer

600.00

600.00

Materials
Jute
Hessian - 10 sq.ft
Water - 90 gals

0.00
180.00

180.00

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)

780.00

600.00
600.00
1,600.00
600.00

3,400.00

Materials
45 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube


Labour
1 1/2 days U/Sk labourer

10,888.89

600.00

600.00

Materials
Jute
Hessian - 60 sq.ft
Water - 90 gals

0.00
180.00

180.00

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)

780.00

600.00
600.00
1,600.00
600.00

3,400.00

Materials
45 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator
Rate per cube

0.00

1,500.00

1,500.00
10,888.89

Labour
1 1/2 days U/Sk labourer

600.00

600.00

Materials
Jute Hessian - 55 sq.ft
Water - 90 gals

0.00
180.00

180.00

Rate per cube

Labour
1 day mason
1day carpenter
4 days U/Sk labourer
1 day Sk labourer (Vibrator)

780.00

600.00
600.00
1,600.00
600.00

3,400.00

Materials
45 cuft of concrete (Add 10% for wastage )
Equipments
1 day hire of vibrator

0.00

1,500.00

1,500.00

Rate per cube


Labour
1 3/4 days U/Sk labourer

10,888.89

700.00

700.00

Materials
Jute Hessian - 40 sq.ft
Water - 90 gals
Rate per cube

0.00
180.00

180.00
880.00

a)
Water available at site.
Note

b)
If, water is not available allowances should be
made for transport of water.
c) Sand includes 15% for bulking.

a)
Water available at site.
Note

b)
If, water is not available allowances should be
made for transport of water.
c) Sand includes 15% for bulking.

a)
Water available at site.
Note

b)
If, water is not available allowances should be
made for transport of water.
c) Sand includes 15% for bulking.

a)
Water available at site.
Note

b)
If, water is not available allowances should be
made for transport of water.
c) Sand includes 15% for bulking.
3,000.00

a) Water available at site.


b)
If, water is not available allowances should be
made for transport of water.
c) Sand includes 15% for bulking.
3,000.00

a)
Water available at site.
Note

b)
If, water is not available allowances should be
made for transport of water.
c) Sand includes 15% for bulking.

1/3 day hire of mixer


Note
for laying concrete at depths more than 5' 0", add
1/6 day unskilled labourer for each additional 5'
0" or part there of per square

Note
1)
For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

1) For column in 1 st floor add 3% to ground


floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) Water available at site.
2) If water is not
available allowance must be made for transport
of water.

Note
1)
For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) Water available at site.
2) If water is not
available allowance must be made for transport
of water.

Note
1)
For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) Water available at site.
2) If water is not
available allowance must be made for transport
of water.

Note
1)
For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) Water available at site.
2) If water is not
available allowance must be made for transport
of water.

Note
1)
For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) Water available at site.
2) If water is not
available allowance must be made for transport
of water.

Note
1) For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) Water available at site.
2) If water is not
available allowance must be made for transport
of water.

Note
1)
For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) Water available at site.
2) If water is not
available allowance must be made for transport
of water.

Note
1) For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) Water available at site.
2) If water is not
available allowance must be made for transport
of water.

Note
1)
For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1) Water available at site.
2) If water is not
available allowance must be made for transport
of water.

Note
1) For column in 1 st floor add 3% to ground
floor rate.
2) For column in 2 nd
floor add 5% to ground floor rate.
3) For
columns in 3rd floor add 7% to ground floor rate.
4) Water available at site.
5) If water is not
available allowance must be made for transport
of water.

Note
1)
Water available at site.
2) If water is not
available allowance must be made for transport
of water.

Note

Note

Note

a) Water available at site.


500.00

b) If, water
is not available allowances should be made for
3,500.00
transport of water.
c) Sand - includes 15% for bulking.

FORMWORKS
41 Sawn timber form work to 9" x 9" cement concrete column in ground floor.
Making Moulds (15 sqft) Consider column length of 5' 0"

Assembling per use

Demantling per use

42 Sawn timber form work for concrete beams in ground floor. Making Moulds Consider 9" x 12" beam of 20' 0" long. Contact area 55 sq.ft.

Assembling per use

Demantling per use

43 Sawn timber form work for underside of first floor slab. Making Moulds Consider a slab of desmensions 20" 0" x 10' 0"
Contact area = 2.0 sqrs.

Assembling per use

Demantling per use

44 Mild steel / for steel reinforcement to lintels slab beams for columns bent to shape laid
in position and tied with G.I. Wire as directed. -

Rates

Labour
1/2 day carpenter
1/2 day U/Sk labourer
Allowin: 4 uses cost
of mould per use

300.00
200.00

Materials
18.15" sq.ft 1" thick class II timber
17.10 L.ft 2" x 2" class II timber in yokes.
16.12 L.ft 2" x 1" class II timber battens
1 1/2 lb wire nails.

635.25
222.30
112.84
60.00

Labour
1/4 day carpenter
1/4 day U/Sk labourer

150.00
100.00

Labour

Materials

Rate per unit

500.00

1,030.39

250.00

Materials
12
Nos. 16 mm 18" long bolts (20 uses)
1/2 liter mould oil
35 L.ft 4" x 2" props (10 uses)

300.00
210.00
875.00

Labour
1/4 day carpenter
1/4 day U/Sk labourer

150.00
100.00

1,385.00

250.00

Rate per square

Labour
1/2 day carpenter
2 day U/Sk labourer
Allowin: 4 uses cost
of mould per use
10% for repair
Materials
60 sq.ft 1" timber planks
24 l.ft 2" x 1" battens
45 l.ft 2" x 2" ledgers
30 l.ft 4" x 2" bearers at bottom of mould.
2 lbs wire nails
10% for repair
Labour
1 day carpenter
2 day U/Sk labourer

22,769.27

300.00
800.00

110.00

1,210.00

2,100.00
168.00
585.00
600.00
80.00
353.30

600.00
800.00

3,886.30

1,400.00

Materials
110 l.ft 4" x 2" vertical props
80 l.ft 2" x 2" bracing to mould and props.
50 l.ft 2" x 2" bracing to a set of props
6.0 sq.ft 1" timber base plate to props
22 Nos wdges
Add 10% of cost of materials for repairs
1/2 gal mould oil
1/2 lbs nail
Labour
1/2 day carpenter
2 day U/Sk labourer

1,040.00
650.00
210.00
1,958.00
385.80
60.00
20.00

300.00
800.00

4,323.80

1,100.00

Rate per square

Labour
3 days carpenter
3 days U/Sk labourer
Allowin: 4 uses cost
of mould per use
20% for repair

21,672.91

1,800.00
1,200.00

600.00

Materials
220 se.ft 1" thick tongue and grooved timber planks.
121 L.ft 4" x 2" runners at 2' 0" centers.
4 lbs. were nails.

7,700.00
2,420.00
160.00

Labour
1 day carpenter
4 day U/Sk labourer
1 gal mould oil for assembling.
2 lbs wire nails

600.00
1,600.00
120.00
80.00

Materials
690 l.ft 4" x 2" vertical timber props.(10 uses)
66 l.ft 2" x 2" bracing for props.
122 No. wedges
33 sq.ft 1" bass plates for props
Add 20% of cost of materials for repairs
Labour
1/2 day carpenter
2 day U/Sk labourer
Rate per square

3,600.00

10,280.00

2,400.00

13,800.00
858.00
10,858.00
1,155.00
5,334.20

300.00
800.00

32,005.20

1,100.00
24,692.60

Labour
1 days barbender
1 days U/Sk labourer
Materials
1 cwt M.S. / per steel.rods including transport to site.
(Allow for wastage 15%)
1 1/2 lbs 16 BWG binding wire
Add 1.5% of steel cost for spacers or dhairs.
Rate per cwt

600.00
400.00

1,000.00

69.00
60.00
1.04

130.04
1,130.04

MASONRY
45 Brick work in cement sand 1:5: in foundation up to D.P.C

46 Brick work cement and sand 1:8 in foundation up to D.P.C


Rate per square

47 Brick work in cement and sand 1:5 in 4 1/2" thick walls in ground floor
Rate per square

48 9" thick brick wall cement sand 1:5 in ground floor


Rate per square

49 Brick work 13 1/2" thick in cement sand 1:5 in superstructure in ground floor
Rate per square

50 9" Brick walls in cement sand 1:8in superstructure in ground floor


Rate per square

51 4 1/2" thick brick wall (wire cut) in cement and sand 1:5 in ground floor ( Facing to
brickwork measured separately)
Rate per square

52 9" thick in cement and sand 1:5 with wire cut bricks (Facing to brick work measured
separately)
Rate per square

53 13 1/2" thick brick wall (wire cut) in cement and sand 1:5 in ground floor (Facing to
brick work measured separately)
Rate per square

54 Extra over for facing including raised pointing 1/8" thick in cement and sand 1:1
mixture in ground floor
Rate per square

55 3" thick floor paved in lime mortar 2:5 in ground floor


Rate per square

56 Steps 1' - 1 1/2" x 0' 6" in brick in cement and sand 1:5 with 1/2" thick cement and
sand 1:2 redering including necessary excavation.
Rate per 10 L. ft

57 Brick drains in cement and sand 1:5, 9" wide end 6" - 9" average depth including
cement rendering 1/2" thick 1:2 to exposed faces with 1'6" ramp including necessary
excavation.
Rate per 10 L. ft

58 Brick drains in cement and sand 1:5, 9" wide end 6" - 9" average depth including
cement rendering 1/2" thick 1:2 to exposed faces without ramp including necessary
excavation.
Rate per 10 L. ft

59 8" thick Hollow block work in cement and sand mortar 1:5 in ground floor (cavities
unfilled)
Rate per square

60 4" thick Hollow block mesonry in cement and sand mortar 1:5 with cavities unfilled
Rate per square

61 Random Rubble masonry in cement morter 1:5 in foundation


Rate per cube (14" thick)

62 Random Rubble masonry in cement morter 1:5 in superstructure


Rate per cube (14" thick)

FLOOR FINISHES
63 Pressed floor tiles bedded in 1/2" cement morter 1:2 and pointing in neat cement in
ground floor
Rate per square

64 Glazed tiles fixed to walles including bedding in cement morter 1:2 and raking in
ground floor. (specials measured separately)
Rate per square

65 Terrazzo floor tiles on 1/2" thick cement and sand 1:2 in ground floor
Rate per square

Rates
Labour
3 days mason
4 days U/Sk labourer

1,800.00
1,600.00

Materials
1450 bricks Add 5% wastage
4.00 cwt cement (50 kg bags)
0.25 cubes sand
Water (150 gals)

7,612.50
2,200.00
1,100.00
300.00

Labour

Materials

3,400.00

11,212.50

Rate per square

14,612.50

Labour
3 days mason
4 days U/Sk labourer

1,800.00
1,600.00

Materials
1450 bricks Add 5% wastage
2 1/3 cwt cement (50 kg bags)
3/8 cubes sand
Water (150 gals)

7,612.50
1,281.50
1,650.00
300.00

3,400.00

10,844.00

Rate per square


Labour
1 1/2 days mason
2 days U/Sk labourer
Scaffolding - Add 5%
Materials
550 bricks Add 5% wastage
1.3 cwt cement (50 kg bags)
0.10 cubes sand
Water (50 gals)

Rate per unit

14,244.00

900.00
800.00
85.00

1,785.00

2,887.50
715.00
660.00
100.00

4,362.50

Rate per square

6,147.50

Labour
1 1/4 days mason
3 3/4 days U/Sk labourer
Scaffolding - Add 3%

750.00
1,500.00
67.50

Materials
1090 bricks Add 5% wastage
3.00 cwt cement (50 kg bags)
0.20 cubes sand
Water (115 gals)

5,722.50
1,650.00
880.00
230.00

2,317.50

8,482.50

Rate per square

10,800.00

Labour
3 1/2 days mason
5 1/2 days U/Sk labourer
Scaffolding - Add 2%

2,100.00
2,200.00
86.00

Materials
1630 bricks Add 5% wastage
4.50 cwt cement (50 kg bags)
0.30 cubes sand
Water (170 gals)

8,557.50
2,475.00
1,320.00
340.00

4,386.00

12,692.50

Rate per square

17,078.50

Labour
2 1/4 days mason
3 days U/Sk labourer
Scaffolding - Add 3%

1,350.00
1,200.00
76.50

Materials
1090 bricks Add 5% wastage
1.75 cwt cement (50 kg bags)
0.30 cubes sand
Water (115 gals)

5,722.50
962.50
7,700.00
230.00

2,626.50

14,615.00

Rate per square

Labour
1 1/2 days mason
2 days U/Sk labourer
Scaffolding - Add 5%
Materials
550 wire cut bricks Add 5% wastage
1.20 cwt cement (50 kg bags)
0.08 cubes sand
Water (30 gals)

17,241.50

900.00
800.00
51.00

1,751.00

5,775.00
660.00
352.00
60.00

6,847.00

Rate per square

Labour
2 1/4 days mason
3 3/4 days U/Sk labourer
Scaffolding - Add 3%
Materials

8,598.00

1,350.00
1,500.00
85.50

2,935.50

1050 wire cut bricks Add 4% wastage


2.50 cwt cement (50 kg bags)
0.18 cubes sand
Water (100 gals)

10,920.00
1,375.00
792.00
200.00

13,287.00

Rate per square

Labour
3 3/4 days mason
5 1/2 days U/Sk labourer
Scaffolding - Add 2%
Materials
1630 wire cut bricks Add 2% wastage
4.50 cwt cement (50 kg bags)
0.60 cubes sand
Water (50 gals)

16,222.50

2,250.00
2,200.00
89.00

4,539.00

16,626.00
2,475.00
2,640.00
100.00

21,841.00

Rate per square

26,380.00

Labour
5 days mason
3 1/2 days U/Sk labourer

3,000.00
1,400.00

Materials
0.50 cwt cement (50 kg bags)
1.00 cubes sand
1/10 gals acid
Water (10 gals)

275.00
4,400.00
50.00
20.00

4,400.00

4,745.00

Rate per square

9,145.00

Labour
1 1/4 days mason
2 1/2 days U/Sk labourer

750.00
1,000.00

Materials
350 bricks
1.20 cwt cement (50 kg bags)
0.11 cubes sand
Water (45 gals)

1,750.00
660.00
484.00
90.00

1,750.00

2,984.00

Rate per square

Labour
1/2 days mason
1/2 days U/Sk labourer

4,734.00

300.00
200.00

500.00

Materials
120 bricks
0.50 cwt cement (50 kg bags)
0.05 cubes sand
Water (15 gals)

600.00
275.00
220.00
30.00

1,125.00

Rate per L.ft

162.50

Labour
1 1/4 days mason
1 1/4 days U/Sk labourer

750.00
500.00

Materials
140 bricks
0.80 cwt cement (50 kg bags)
0.05 cubes sand
Water (20 gals)

700.00
440.00
220.00
40.00

1,250.00

1,400.00

Rate per L.ft

265.00

Labour
1 days mason
1 1/4 days U/Sk labourer

600.00
500.00

Materials
110 bricks
0.70 cwt cement (50 kg bags)
0.04 cubes sand
Water (15 gals)

550.00
385.00
176.00
30.00

1,100.00

1,141.00

Rate per L.ft

224.10

Labour
1 1/2 days mason
2 1/2 days U/Sk labourer
Scaffolding - Add 3%

900.00
1,000.00
57.00

Materials
112 Hollow cement blocks Allow 5% for wastage
0.75 cwt cement (50 kg bags)
0.06 cubes sand

1,764.00
412.50
264.00

Rate per square

1,957.00

2,440.50
4,397.50

Labour
1 days mason
2 days U/Sk labourer
Scaffolding - Add 5%
Materials
112 Hollow cement blocks(size of each block 16" x
8" x 4") Allow 5% for wastage
0.40 cwt cement (50 kg bags)
0.03 cubes sand

600.00
800.00
70.00

1,470.00

1,764.00
220.00
132.00

2,116.00

Rate per square

3,586.00

Labour
4 days mason
6 days U/Sk labourer

2,400.00
2,400.00

Materials
1.30 cubes 6" - 9" rubble
5.00 cwt cement (50 kg bags)
0.30 cubes sand
Water 100 gals

2,210.00
2,750.00
1,320.00
200.00

4,800.00

6,480.00

Rate per cube

11,280.00

Labour
4 1/2 days mason
7 days U/Sk labourer
Scaffolding - Add 3%

2,700.00
2,800.00
165.00

Materials
1.30 cubes 6" - 9" rubble
5.00 cwt cement (50 kg bags)
0.30 cubes sand
Water 100 gals

2,210.00
2,750.00
1,320.00
200.00

5,665.00

6,480.00

Rate per cube

Labour
4 days mason
4 days U/Sk labourer
1/2 day U/Sk labourer for polishing
Materials
225 pressed tiles 8" x 8" Add 5% for wastage
1 1/4 cwt cement (50 kg bags)
0.07 cubes sand

12,145.00

2,400.00
1,600.00
200.00

11,812.50
687.50
308.00

4,200.00

1/4 lb wax polish


1/4 lb coloured pigment
2 lbs cotton waste

100.00
62.50
100.00

13,070.50

Rate per square

Labour
4 days mason
4 days U/Sk labourer
1/4 day U/Sk labourer for cleaning
Materials
400 glazed tiles 6" x 6" Add 10% for wastage
2 1/2 cwt cement (50 kg bags)
0.11 cubes sand
1 lb white cement

17,270.50

2,400.00
1,600.00
100.00

4,100.00

26,400.00
1,375.00
484.00
50.00

28,309.00

Rate per square

32,409.00

Labour
4 days mason
3 days U/Sk labourer
1/2 day U/Sk labourer for polishing

2,400.00
1,200.00
200.00

Materials
100 12" x 12" terrazzo tiles Add 5% for wastage
1 1/4 cwt cement (50 kg bags)
0.07 cubes sand
coloured pigment (2 lbs)
1/2 lb wax polish
2 lb cotton waste

5,250.00
687.50
308.00
500.00
200.00
100.00

Rate per square

3,800.00

7,045.50
10,845.50

FINISHING
98

3/4" thick DPC, in cement sand 1:2 finished with 2 coats hot tar and blinded with sand.

99 5/8" thick plastering to wall in lime and sand 2:5 including floating with lime putty.

100 5/8" thick plastering to wall in cement sand 1:3 including cement floating

101 3/8" thick plastering to soffit slab in cement and sand 1:3 including floating with lime
putty

102 3/8" thick plastering to sides and soffit of beams in cement & sand 1:3 including
floating with lime putty

103 5/8" thick to wall in lime cement and sand 1:1:5 finished semi - rough with wooden
float.

104 5/8" thick plastering to wall in lime and sand 1:1:5 finished smooth with lime putty
floating.

105 1/2" thick rendering in cement and sand 1:3 finished smooth

106 1/2" thick rendering in cement and sand 1:2 in floors, finished smooth.

107 3/4" thick rendering in cement and sand 1:3 finished smooth.

108 3/4" thick rendering in cement and sand 1:2 in floors finished smooth.

109 3/4" thick rendering in cement and sand 1:2 in coloured cement floors finished smooth.

110 1/2" x 6" skirting in cement and sand 1:3 projected or flush to walls finished with
floating including forming groove.
Per 10 Lft

111 Prepare and apply one coat of preservative (oil type) to structural timber including
touching up cut ends etc. after fixing.
Per square

112 Prepare surface of steel truse and apply two coats of anti - corrosive primer.
Per square

113 Apply one coat of anti - corrosive primer and two coats enamel paint on already shop
rimed and arected steel roof truss.
Per square

114 Prepare and apply two coats primer and finishing coat of enemel paint to mild steel
(angle / flat) gate.
Consider 50 sq.ft

115 Painting steel on mew work with 2 coats of anti - corrosive paint
Consider per square

116 Painting new timber work with two coats wood preservative
Consider per square

117 Preparing and painting wood work with primer and 2 coats enamel paint.
Consider per square

118 White or colour washing two coats in single storey.

Per 10 square

119 White or colour washing in two storeyed building


Per 10 square

120 Prepare and apply one coat of Alkali resistant primer and two coats of emulsion paint
to walls.
Per square

121 Cement washing to walls of single storeyed builsing 2 coats


Per 10 square

122 Painting walls with emulsion paint ( 2 coats)


Per square

123 Prepare and apply one coat alkali resistant primer and two caoats of emulsion paint to
soffit of slabs.
Per square

124 Varnishing two coats with copal varnish after sandpapering


Per square

125 Wax polishing to timber in panels & floors.


Per square

Rates

Labour
1 1/4 days mason
1 1/2 days U/Sk labourer

750.00
600.00

Materials
2.25 cwt cement
0.11 cube sand
1 1/2 gals bitumen
Firewood (10 lbs)
Water 10 gals
Rate per square
Labour
1 day mason
1 3/4 days U/Sk labourer
Scaffolding - Add 3%

600.00
600.00

Materials
1.30 cwt slaked lime
0.07 cubes sand
Water 10 gals
Rate per square
Labour
1 day mason
11/2 days U/Sk labourer
Scaffolding - Add 3%

600.00
600.00

Materials
1.40 cwt cement (50 kg bags)
0.06 cubes sand
Water 10 gals
Rate per square

Labour
2 1/2 day mason
21/2 days U/Sk labourer
Scaffolding - Add 3%
Materials
0.80 cwt cement (50 kg bags)
0.16 cubes sand

1,500.00
1,000.00

Labour

Materials

Rate per unit

Water 5 gals
Rate per square

Labour
2 day mason
2 days U/Sk labourer
Scaffolding - Add 3%

1,200.00
800.00

Materials
0.80 cwt cement (50 kg bags)
0.16 cubes sand
Water 5 gals
Rate per square

Labour
1 day mason
1 3/4 days U/Sk labourer
Scaffolding - Add 3%

600.00
700.00

Materials
0.80 cwt cement (50 kg bags)
0.40 cubes sand
Water 10 gals
Rate per square

Labour
1 1/2 days mason
1 1/2 days U/Sk labourer
Scaffolding - Add 3%

900.00
600.00

Materials
0.80 cwt cement (50 kg bags)
0.60 cwt slaked lime
0.07 cubes sand
Water 10 gals
Rate per square
Labour
1 days mason
1 1/2 days U/Sk labourer (curing)
Materials
1.07 cwt cement (50 kg bags)

RATES!B4
600.00

0.05 cubes sand


Water 10 gals
Rate per square
Labour
1 days mason
1 1/2 days U/Sk labourer
1/4 day U/Sk labourer (curing)

600.00
600.00
100.00

Materials
1.50 cwt cement (50 kg bags)
0.05 cubes sand
Water 10 gals
Rate per square
Labour
1 1/4 days mason
2 days U/Sk labourer
1/4 day U/Sk labourer (curing)

750.00
800.00
100.00

Materials
1.75 cwt cement (50 kg bags)
0.05 cubes sand
Water 10 gals
Rate per square
Labour
1 1/4 days mason
2 days U/Sk labourer
1/4 day U/Sk labourer (curing)

750.00
800.00
100.00

Materials
2.25 cwt cement (50 kg bags)
0.08 cubes sand
Water 10 gals
Rate per square

Labour
1 1/4 days mason
2 days U/Sk labourer
3/4 day U/Sk labourer (curing)
Materials
2.25 cwt cement (50 kg bags)
0.08 cubes sand

750.00
800.00
300.00

5lbs powdered pigment


Water 10 gals
Rate per square

Labour
3/8 days mason
5/16 days U/Sk labourer

225.00
125.00

Materials
0.10 cwt cement (50 kg bags)
0.003 cubes sand
0.25 lbs powdered pigment
Rate per Lft

Labour
3/4 day painter
1/2 day U/Sk labourer

450.00
200.00

Rate per square

900.00
600.00

Materials
2 3/4 ltr. Anti - corrosive primer
0.15 ltr. Mineral turpentine or
thinner
1 wire brush
2" brush (1/3 use)
Rate per square

Labour
2 1/2 days painter
1 day U/Sk labourer
Scaffolding - Add 3%
Materials
0.20 lts. Anti - corrosive primer
1 1/3 ltr. Enamel paint

1,300.00
1,000.00

0.08
0.00
0.12

872.00
10,512.00
700.00

487.5
312.5
0
0
73.248
31.536
84
98.8784

Materials
2.75 ltr. Wood preservative (oil type)
3" brush (1/10 use)

Labour
1 1/2 days painter
1 1/2 day U/Sk labourer

0.38
0.31

1,500.00
400.00

2" brush (1/5 use)


Rate per square

Labour
1/2 days painter
3/4 day U/Sk labourer

300.00
300.00

Materials
1 1/2 lts. Anti - corrosive primer
2/3 ltr. Enamel paint
1/3 wire brush
2" brush (1/5 use)
Rate per sqft
Labour
1 1/2 days painter

900.00

Materials
2/3 ltr. Anti - carrosive paint
2" brush ( 1/5 use)
Rate per square
Labour
1/2 days painter
Materials
1/2 gal wood preservative
2" brush ( 1/5 use)
Rate per square
Labour
1 1/2 days painter
1/2 day U/Sk labourer
Materials
3/4 ltr. Primer
2.50 ltr. Enamel paint (2 coats)
2" brush ( 1/10 use)
2 sand papers
Rate per square
Labour

900.00
600.00

2 1/2 days painter


2 1/2 days U/Sk labourers
Scaffolding - Add 3%

1,500.00
1,000.00

Materials
0 - 50 cwt boiled lime
2 lbs salt
1/2 lb yellow ochre
2 ozs blue
6" brush (1/3 use)
Water 10 gals
Rate per square
Labour
3 days painter
3 days U/Sk labourers
Scaffolding - Add 6%

1,800.00
1,200.00

Materials
0 - 50 cwt boiled lime
2 lbs salt
1/2 lb yellow ochre
2 ozs blue
6" brush (1/3 use)
Water 10 gals
Rate per square

Labour
1 1/4 day painter
Scaffolding - Add 3%

750.00

Materials
Primer 0.90 ltr. Primer
1.40 ltr. Emulsion pant
Water 0.10 gals
6" brush (1/10 use)
2 sand papers
Rate per square
Labour
2 days painter
2 days U/Sk labourer
Scaffolding - Add 3%
Materials
5/8 cwt cement

1,200.00
800.00

1 - 6" coir brush


Water 5 gals
Rate per square

Labour
3/4 day painter
Scaffolding - Add 3%

450.00

Materials
1 st coat 1/6 gal emulsion paint
2 nd coat 1/7 gal emulsion paint
6" brush - (1/10 use)
0.10 gals water
Rate per square

Labour
1 3/4 day painter
Scaffolding - Add 3%

1,050.00

Materials
0.90 ltr. Primer
1.50 ltr. Emulsion paint
6" brush ( 1/10 use)
Rate per square
Labour
1/2 day painter
1/2 day U/Sk labourer

300.00
200.00

Materials
0.40 gals ( 1.80 ltr.) varnish
3" brush (1/3 use)
Rate per square
Labour
3 hrs. U/Sk labourer
Materials
3/4 lb. Wax polish
1/2 doz. Sheets sandpaper
1/10 floor brush
1/2 yards flannel cloth

150.00

Rate per square

324.42

395.79

66 Timber framework for calicut pattern tile hip roof in single storey building consisting o
f wall plate, beam, ridge plate, rafters etc. (Preservutive treatment to be measured
separately)
Rate per 6 squares

67 Roof covering with calicut pattern clay tiles in single storeyod building (Timber frame
work & ridge covering measured separately)
Rate per 6 squares

68 Timber framework for corrugated asbestos sheet roof in angle storied building
Rate per 3.6 squares

69 Roof covering with corrugated asbestos sheets (timber frame work & ridge covering
measured separately)
Rate per 3.6 squares

70 One layer half round clay tiles over corrugated asbestos roof covering.
Rate per 3.6 squares

71 Asbestos close fittings ridging fixed complete with roofing screws or bolts (hook)
Rate per 13'4" length

72 Ridging covering with calicut pattern ridge tiles bedded in cement lime mortar 1:1:4
Rate per 12' length

73 3/4" x 9" high valance board fixed with brass screws to ends of rafters ( for tile
roofing)
Rate per 100' length

74

3/4" x 9" high barge board fixed with brass screws at 2' 0" centres to sides of rafters.
Rate per 100' length

75 ROOF PLUMBING 18 B.W.G (1.2 mm) galvanised from sheet valley gutter 3' 0" girth
overall once bent with end laps not less then 9" width including 3/4" tongued and
grooved planks laid to slope and grooved planks laid to slope and profile on timber
members.
Rate per 15' length

76 18 B.W.G (1.2 mm) galvanised iron flashing 1' 6" girth overall 3 times bent with end
laps not less than 6", lead soldered, turned and tucked up to not less than 6" in to
cement mortar 1:2 lower end dressed over roof covering not less than 1' 0" wide.
Rate per 15' length

77 Timber Framework for 4' 0" x 4' 0" flat asbestos ceiling (Sheet measured separately)
comprising of 4" x 2" joists and 2" x 2" bearers in class I timber
Rate per 1.95 squre

78 Horisontal ceiling lining using 4' 0" x 4' 0"flat asbestos cement sheets fixed with and
including beading and cove mouldings on timber framework. (timber framework &
painting measured separated)
Rate per 1.95 squre

79 3/4" thick tongued and grooved Lunumidella ceiling boards fixed horizontal on 4" x 2"
class I timber joists at 2' 0" centers with 1 1/2" brass nails.
Rate per 15' x 13' I.e 1.95 squares

80 3/4" x 6" wide tongued and grooved Lunumidella ceiling boards fixed to underside of
roof rafters, (existing) with 1 1/2" brass nails including leveling with timber strips
where necessary.
Rate per 15' x 12' I.e 1.80 squares

81 Door single hung 3' 3" x 7' 0" high overall with frame having 1 1/4" thick sash and 3
1/4" x 2 1/4" timber frames. (glazing, ironmongery & painting measured separately)
Per 22.75 square feet (3' 3" x 7' 0")

82 Door glazed and panolled double hung 4' 0" x 7' 0" high overall with frame including 1
1/4" thick sash and 3 3/4" x 2 3/4" frame. (glazing, ironmongery and painting measured
separately).
Per 28 square feet (4' 0" x 7' 0")

83 Plywood door single hung 3' 1 1/2" x 6' 1 1/2" overall with frame having 1 1/4" thick
sash and 3 3/4" x 2 3/4" frame. ( iron - mongery and painting measured separately)
Per 21.75 square feet (3' 1 1/2" x 6' 1 1/2")

84 Door ledged, braced and battened single hung 2' 6" x 6' 6" overall, with frame having
7/8" thick tongued & grooved planks and 3 3/4" x 2 3/4" frame.
( Ironmongery and painting measured separately)
Per 16.25 sq.ft (2' 6" x 6' 6")

85 Window, glazed 7' 0" x 4' 0" high overall with frame comprising 3 No openable sashes
and 3 3/4" x 2 3/4" frame and mullions
(Clasing, ironmongery and painting measured separately)
Per window 7' 0" x 4' 0" (sashes) ie per 28.00 sq.ft

86 1/4" clear sheet glass panes exceeding 1' 0" but not exceeding 4 square feet cut and
fixed with timber beadings to doors and windows.
Consider sash 3' 0" x 4' 0" high with 3" x 1 1/4" style and 4 Nos.glass
panes.
Per window 9.00 sq.ft

87 IRONMONGERY
Butt hinges 5" x 2 1/2"
Per 1 1/2 pairs

88 Tee hinges 6" x 12"


Per 1 pairs

89 Rim lock
Per 1 No

90 Mortice lock
Per 1 No.

91 Casement stays.
Per 4 Nos.

92 Door closer ( Hydraulic)


Per 1 No.

93 Tower / Skeleton brass bolts


Per 1 No.

94 Barrel bolt 4"


Per 1 No.

95 Casement fasteners.
Per 6 Nos.

96 Spring louded fanlight catches


Per 6 Nos.

97 Draw rings
Per 6 Nos.

Rates

Labour
7 days carpenter
8 days U/Sk labourer
1/2 day U/Sk labourer for polishing
Materials
34.00 cu.ft timber Add 10% for wastage
660 1.ft 2" x 1" reepers Add 5% wastage
8 lbs wire nails 6" long
2 lbs wire nails 2" long

4,200.00
3,200.00
200.00

Labour

Materials

7,600.00

13,090.00
9,900.00
200.00
50.00

23,240.00

Rate per square

Labour
3 days carpenter
3 days U/Sk labourer
Materials
750 tiles

5,140.00

1,800.00
1,200.00

3,000.00

15,750.00

15,750.00

Rate per square

3,125.00

Labour
2 1/2 days carpenter
3 days U/Sk labourer

1,500.00
1,200.00

Materials
13 1/4 cu.ft timber purloins Add 10% for wastage

7,287.50

2,700.00

7,287.50

Rate per square

Labour
1 day carpenter
2 days U/Sk labourer
Materials
420 sq.ft asbestos corrugated sheets.
72 Nos. roofing screws and washers.

2,774.31

600.00
800.00

1,400.00

21,000.00
720.00

21,720.00

Rate per square


Labour
2 days U/Sk labourer

Rate per unit

6,422.22

800.00

800.00

Materials
650 half round clay tiles

3,250.00

3,250.00

Rate per square

1,125.00

Labour
1/4 day carpenter
1/4 day U/Sk labourer

150.00
100.00

Materials
4 pairs ridges 3' 8" long
16 roofing screws or bolts

200.00
96.00

250.00

296.00

Rate per L.ft

40.96

Labour
1/4 day carpenter
1/4 day U/Sk labourer

150.00
100.00

Materials
9 ridge tiles
1/3 cwt cement (50 kg bags)
0.02 cubes sand
15 lbs slaked lime
1/2 lb colouring powder

468.00
181.50
88.00
300.00
125.00

250.00

1,162.50

Rate per L.ft

117.71

Labour
3 days carpenter
3 days U/Sk labourer
Scaffolding - Add 5%

1,800.00
1,200.00
150.00

Materials
75.00 sq.ft 1" planks Add 5% for wastage
70 Nos. 1 1/2" brass screws

5,906.25
560.00

3,150.00

6,466.25

Rate per L.ft

96.16

Labour
3 days carpenter
3 days U/Sk labourer
Scaffolding - Add 5%

1,800.00
1,200.00
150.00

Materials
75.00 sq.ft 1" planks Add 5% for wastage
50 Nos. 1 1/2" brass screws

5,906.25
400.00

3,150.00

6,306.25

Rate per L.ft

94.56

Labour
a) Fixing boarding and applying wood pressrvative 1 day carpenter
1 day U/Sk labourer
b) Making and fixing G.I sheets 1/2 day tinker
1/2 day U/Sk labourer
c) Building sides 1/4 day mason
1/2 day U/Sk labourer
Materials
2 G.I sheet (8' x 4')
1/4 gal wood preservative
0.10 cwt cement (50 kg bags)
0.05 cwt slaked lime
1.00 cu.ft sand
50.00 sq.ft planks
2 lbs 1 1/2" wire nails

600.00
400.00
300.00
200.00
150.00
200.00

1,850.00

4,000.00
62.50
55.00
1.00
44.00
1,250.00
40.00

5,452.50

Rate per L.ft

Labour
Cutting bending, soldering & fixing 1/2 day tinker
1/9 day mason (caulking)
3/4 day U/Sk labourer
Materials
1 G.I sheet (8' x 4')
0.05 cwt cement (50 kg bags)
1.00 cu.ft sand
1 lb soldering lead

486.83

300.00
66.67
300.00

2,000.00
27.50
44.00
50.00

Rate per L.ft

Labour
2 1/2 days carpenter
1/2 days mason
1 1/2 days U/Sk labourer

666.67

2,121.50
185.88

1,500.00
300.00
600.00

Scaffolding - Add 3%
Materials
8.00 cu.ft timber class I
1 lb 2" nails
25 lbs cement
2.00 cu.ft sand
2" brush - 1/4 use
1/3 gal tarnap

72.00

2,472.00

2,000.00
25.00
125.00
88.00
180.00
39.60

2,457.60

Rate per square

Labour
1 1/2 days carpenter
2 days U/Sk labourer
Scaffolding - Add 3%
Materials
210 sq.ft flat asbestos sheets
60 l.ft 2" x 2" halmilla cove mouldings
125 l.ft 1 1/12" x 1/2" halmilla beadings
3/4 lb - 1/4" lb out nails
8 doz 1 1/2" brass screws

2,528.00

900.00
800.00
51.00

1,751.00

5,250.00
960.00
2,000.00
46.50
400.00

8,656.50

Rate per square

5,337.18

Labour
Making holes, fixing joists & making roof
1 day mason
1 day carpenter
3 days U/Sk labourer

600.00
600.00
1,200.00

Materials
115 l.ft 4" x 2" timber joists
215 sq.ft 6" x 3/4" Lunumidella ceiling planks.
3 lbs cement
4.00 cu.ft sand
4 kg 1 1/2" brass nails

2,070.00
8,600.00
15.00
176.00
480.00

2,400.00

11,341.00

Rate per square

Labour
3 days carpenter
6 days U/Sk labourer
Scaffolding - Add 3%

7,046.67

1,800.00
2,400.00
126.00

4,326.00

Materials
220.00 sq.ft ceiling planks
40.00 l.ft 2" x 1/4" timber strips
2.00 kg 3/4" nails
4.00 kg 1 1/2" brass nails.

8,800.00
400.00
240.00
480.00

9,920.00

Rate per square

7,914.44

Labour
5 days carpenter.
1 1/2 days U/Sk labourer

3,000.00
600.00

Materials
a) Frame 1 1/2 cu.ft 4" x 3" timber
2 No. spur stones

270.00
40.00

6 No. fiber/ plastic plugs With 4" long brass screws.


2 No. 5/8" mild steel dowels 4" long,
b) Sash 14 sq.ft 1 1/2" planks
5 sq.ft 1" planks

3,600.00

90.00
240.00
630.00
200.00

1,470.00

Rate per sqft

Labour
6 days carpenter.
2 days U/Sk labourer
Materials
a) Frame 1 2/3 cu.ft 4" x 3" timber
2 No. spur stones
6 No. fiber/ plastic plugs With 4" long brass screws.
2 No. 5/8" mild steel dowels 4" long,
b) Sashes 16 sq.ft 1 1/2" planks
7 sq.ft 1" planks

222.86

3,600.00
800.00

298.80
40.00
90.00
240.00
720.00
280.00

Rate per sqft

Labour
3/4 day carpenter.
3/8 day U/Sk labourer

4,400.00

1,668.80
216.74

450.00
150.00

1/4 day mason (fixing frame)


1/4 day U/Sk labourer ( - do -)

150.00
100.00

Materials
a) Frame 1.80 cu.ft 4" x 3" timber
2 No. spur stones

324.00
40.00

6 No. fiber/ plastic plugs With 4" long brass screws.


b) Sashe 1 No 6' 9" x 2' 9" plywood sash.

850.00

90.00
850.00

1,304.00

Rate per sqft

Labour
2 1/4 days carpenter.
1 day U/Sk labourer
1/4 day mason (fixing frame)
1/4 day U/Sk labourer ( - do -)
Materials
a) Frame 1.70 cu.ft 4" x 3" timber
2 No. spur stones
6 No. fiber/ plastic plugs With 4" long brass screws.
2 No 5/8" mild steel dowels
b) Sashe 21.00 sq.ft 1" thick planks
3 doz 1 1/4 long brass screws.

99.03

1,350.00
400.00
150.00
100.00

2,000.00

306.00
40.00
90.00
240.00
840.00
156.00

1,672.00

Rate per sqft

Labour
6 days carpenter.
2 1/2 days U/Sk labourer
1/2 day mason (fixing frame)
1/2 day U/Sk labourer ( - do -)
Materials
a) Frame 3.20 cu.ft 4" x 3" timber
4 No. fiber/ plastic plugs With 4" long brass screws.
b) Sashes -

225.97

3,600.00
1,000.00
300.00
200.00

576.00
60.00

5,100.00

9.25 sq.ft 3" x 1 1/2" timber

518.00

1,154.00

Rate per sqft

223.36

Labour
1/2 day glazier
1/2 day U/Sk labourer

300.00
200.00

Materials
9.00 sq.ft glass panes
30 L.ft 1/2" x 1/2" beading
4 doz brass panel pins

405.00
660.00
200.00

500.00

1,265.00

Rate per sqft

196.11

Labour
1/4 day carpenter
1/4 day U/Sk labourer

150.00
100.00

Materials
1 1/2 pairs butt hinges
2 Doz 3/4" brass screws

300.00
100.00

250.00

400.00

Rate per No

433.33

Labour
1/4 day carpenter
1/4 day U/Sk labourer

150.00
100.00

Materials
1 pair Tee hinges
1 1/2 Doz 3/4" brass screws

200.00
75.00

250.00

275.00

Rate per pair

525.00

Labour
1/4 day carpenter
1/4 day U/Sk labourer

150.00
100.00

Materials
1 rim lock with screws

450.00

250.00

450.00

Rate per No.


Labour
1/4 day carpenter
1/4 day U/Sk labourer

700.00

150.00
100.00

250.00

Materials
1 mortice look with screws

450.00

450.00

Rate per No.

700.00

Labour
1/4 day carpenter
1/4 day U/Sk labourer

150.00
100.00

Materials
4 casement stays
16 1/2" brass screws

460.00
80.00

250.00

540.00

Rate per No.

197.50

Labour
1/4 day carpenter
1/4 day U/Sk labourer

150.00
100.00

Materials
1 door closer
8 3/4" brass screws

800.00
80.00

250.00

880.00

Rate per No.

1,130.00

Labour
1/2 day carpenter
1/2 day U/Sk labourer

300.00
200.00

Materials
1 Tower / Skeleton Bolt
10 1/2" brass screws

500.00
50.00

500.00

550.00

Rate per No.

1,050.00

Labour
1/2 day carpenter
1/2 day U/Sk labourer

300.00
200.00

Materials
1 barrel bolt
8 1/2" brass screws

150.00
40.00

500.00

190.00

Rate per No.


Labour
1/2 day carpenter
1/2 day U/Sk labourer

690.00

300.00
200.00

500.00

Materials
6 casement fasteners
24 1/2" brass screws

1,200.00
120.00

1,320.00

Rate per No.

303.33

Labour
1/2 day carpenter
1/2 day U/Sk labourer

300.00
200.00

Materials
6 brass fanlight catches
2 doz 1/2" brass screws

624.00
240.00

500.00

864.00

Rate per No.

227.33

Labour
1/8 day carpenter
1/8 day U/Sk labourer

75.00
50.00

Materials
6 draw rings
1doz 1/2" brass screws

270.00
120.00

Rate per No.

125.00

390.00
85.83

Unskil Labour
Carpenter
Mason
Barbender
Skill Labour Vibrator
Skill Labour Blasting
Drilling, chipping & wedging Sk labourer
Tinker
glazier
Painter

400.00
600.00
600.00
600.00
600.00
600.00
600.00
600.00
600.00
600.00

Earth Soil
Class II timber
Cement
Sand
Metal 1 1/2"
Metal 1"
Metal 3/4"
Rubble 6" - 9"
Rubble 6" - 4"
Water
Jute Hussein
Class II timber 1" thick planks
Class II timber 2" x 1"
Class II timber 2" x 2"
Class II timber 2" x 4"
wire nails
Fuse
Jumper steel
D.D.T. powder (8% in 20 gals of water)
16 mm 18" long bolts (20 uses)
mould oil
4" x 2" props
Wedges
mould oil
Steel rebars
binding wires
Bricks
Wirecut Bricks
Acid
Hollow cement blocks
Pressed tiles 8" x 8"
wax polish
coloured pigment
cotton waste
White cement
12" x 12" terrazzo tiles
glazed tiles 6" x 6"
Timber for framework in calicut pattern
tile hip roof in single storey building
consisting of wall plate, beam, ridge
plate, rafters etc. (Preservutive treatment
to be measured separately)
2" x 1" reepers for roof
wire nails 6" long for roof
wire nails 2" long for roof
Calicut tiles
Purlings for roof
asbestos corrugated sheets.
roofing screws and washers.
half round clay tiles
ridges 3' 8" long
roofing screws or bolts
ridge tiles
slaked lime
1" thick planks for valance board
1 1/2" brass screws
G.I sheet (8' x 4')
Wood Preservative
3/4" tongued and grooved planks
1 1/2" wire nails
soldering lead
Class I Timber for Roof frame
2" wire nails
2" brush - 1/4 use
tarnap
flat asbestos sheets
2" x 2" halmilla cove mouldings
1 1/12" x 1/2" halmilla beadings
1/4" out nails
8 doz 1 1/2" brass screws
4" x 2" timber joists
6" x 3/4" Lunumidella ceiling planks.
1 1/2" brass nails for celling
2" x 1/4" timber strips
3/4" nails
4" x 3" timber
spur stones

350.00 per cube


per cube
550.00 cwt
4,400.00 per cube
3,300.00 per cube
3,400.00 per cube
3,500.00 per cube
1,700.00 per cube
2,000.00 per cube
2.00 per gal
0.00 per sqft
35.00 per sqft
7.00 per L.ft
13.00 per L.ft
20.00 per L.ft
40.00 per lb
per lb
per ft
per lb
per lb
25.00 per No
420.00 Lt
25.00 L.ft
89.00 Nos
120.00 gal
60.00 cwt
40.00 per lb
5.00 per No
10.00 per No
500.00 per gal
15.00 per No
50.00 per No
400.00 per lb
250.00 per lb
50.00 per lb
50.00 per lb
50.00 per No
60.00 per No

350.00
15.00
25.00
25.00
21.00
500.00
50.00
10.00
5.00
50.00
6.00
52.00
20.00
75.00
8.00
2,000.00
250.00
25.00
20.00
50.00
250.00
25.00
180.00
120.00
25.00
16.00
16.00
62.00
50.00
18.00
40.00
120.00
10.00
120.00
180.00
20.00

per cuft
per L.ft
per lb
per lb
per No
per cuft
per sqft
per No
per No
per pair
per No
per No
lbs
per sqft
per No
per No
per gal
per sqft
lbs
per lb
per cuft
per lb
per No
per gal
per sqft
per L.ft
per L.ft
per lb
per doz
per L.ft
per sqft
per kg
per L.ft
per kg
per cuft
per No

Mixture
Vibrator

1,500.00 per day


1,500.00 per day

fiber/ plastic plugs With 4" long brass


screws.
5/8" mild steel dowels 4" long,
1 1/2" planks for sash
1" planks for sash
6' 9" x 2' 9" plywood sash.
1 1/4 long brass screws.
3" x 1 1/2" timber
glass panes
1/2" x 1/2" beading
brass panel pins
butt hinges
3/4" brass screws
Tee hinges
rim lock with screws
mortice look with screws
casement stays
1/2" brass screws
door closer
3/4" brass screws
Tower / Skeleton Bolt
barrel bolt 4"
casement fasteners
brass fanlight catches
1/2" brass screws
draw rings

15.00
120.00
45.00
40.00
850.00
52.00
56.00
45.00
22.00
50.00
200.00
50.00
200.00
450.00
450.00
115.00
5.00
800.00
10.00
500.00
150.00
200.00
104.00
120.00
45.00

per No
per No
per sqft
per sqft
per No
per doz
per sqft
per sqft
per L.ft
per doz
per pair
per doz
per pair
per No
per No
per No
per No
per No
per No
per No
per No
per No
per No
per doz
per No

Ref No

Description
Earth Warks
1 Removing top soil to a depth not exceeding 6" & depositing as directed within
site

Rate

4,000.00

2 Excavation over site to reduce level, in any material except rock requiring
blasting including depositing and leveling as directed up to distance not
exceeding 30' 0" per cube

650.00

3 Excavation in trenches for walls/ column pits in soft/ loose soil from 0' 0" to 5'
0" deep and depositing excavated materiel to a distance not exceeding 30' 0"
(Earth work support to be paid separately where necessary) per cube.

400.00

4 Excavation in trenches for walls/ column pits in ordinary soil from 0' 0" to 5' 0"
deep and depositing excavated material not exceeding 30' 0" per cube.
5 Excavation in trenches for walls/ column pits in Hard/ dense soil up to a depth
of 5' 0" and depositing excavated material up to a distance not exceeding 30'
0".
6 Excavation in trenches for walls/ column pits in Mud/ wet soil up to a depth of
5' 0" and depositing excavated material to distance not exceeding 30' 0".
(Earth work & dewatering paid for separately.)
7 Excavation in trenches for walls/ column pits in soft disintegrated rock (not
requiring blasting) up to depth of 5' 0" and depositing excavated material to
distance not exceeding 30' 0".
8 Excavation in trenches for walls/ column pits in Hard rock requiring blasting
up to a depth of 5' 0" and depositing excavated material to distance not
exceeding 30' 0".
9 Benching rock in foundation in 3" - 6" steps. (Blasting prohibited)
10 Anti - termite treatment on excavated foundation and compacted soil under
floors.
11 Backfilling to trenches with selected earth available at site.
12 Back filling to trenches with imported material.
13 Filling under floors including leveling, watering & compacting in 3" layers with
available and selected earth at site.
14 Filling under floors including leveling, watering & compacting in 3" layers with
imported selected earth.
15 Cutting turf sods, landing to hand carts and transporting up to 30 yards, laying
and watering for 30 days. (Royalty for turf, pegging and transport beyond 30
yards paid separately)
Consider trench 15' 0" long 3' 0" wide and 5' 0" depth open planking to both
16 faces.
Total area
- 2/ 15' 0" x 5' 0"
.
= 150 sq.ft
17 Consider trench 15' 0" long 3' 0" wide and 5' 0" height of planking to both
faces.
Total area of planking 2/ 15' 0" x 5' 0" ie 150
sq.ft
Earth work support (close planking) in deep excavation in trenches up to 15'
18 0" depth. - Consider trench of length of 15' 0" width 5' 6" at top 3' 6" at
bottom
Then area supported is 2/ 15' x 15' ie 450 sq.ft.

19
20
21
22

Concrete
Mixing concrete 1: 3: 6 (1 1/2")
Mixing concrete 1: 2: 5 (1")
Mixing concrete 1: 2: 4 (3/4")
Mixing concrete 1: 1: 3 (3/4")

900.00

1,400.00

1,200.00

1,000.00

1,400.00
17,250.00
240.00
400.00
902.50
800.00
1,202.50

2,320.00

1,200.00

2,400.00
2,844.44

16,233.00
16,763.00
18,915.00
21,373.00

23 Mixing concrete 1: 1: 2 (3/4")


24 2" thick cement concrete screed in foundation at depths not exceeding 5' 0"
25
3" thick cement concrete screed in foundation at depths not exceeding 5' 0"
26 6" thick cement concrete floor (mass concrete).
27 Consider 24 No. columns each 4 1/2" x 6" x 10' 0" ie 0.45 cubes.
28 Cement concrete in 6" x 6" colomns in ground floor. Consider 18 No. columns 6" x 6" each 10' 0" high ie 0.45 cubes.
Curing
29 Cement concrete in 9" x 9" colomns in ground floor. - Consider 8 No. 9" x 9"
columns each 10' 0" high ie 0.45 cubes.
Curing
30 Cement concrete in 12" x 12" colomns in ground floor. Consider
5 No. 12"
12"
columns
each
10' 0" high.
Cement concrete
inx13
1/2"
x 13 1/2"
colomns
in ground floor. Consider 4 No. colomns 13 1/2" x 13 1/2" each 10' 0" high .
31
I.e 0.51 cubes.
Curing
32 Cement concrete in 6" x 6" beam up to 1st floor level. Consider 180 L.ft of beam 6" x 6"
I.e 0.45 cubes.
Curing
33 Cement concrete in 9" x 6" beam up to 1st floor level. Consider 120 L.ft of beam 9" x 6" beam
I.e 0.45 cubes.
Curing
34 Cement concrete in 9" x 9" beam up to 1st floor level. Consider 80' 0" length 9" x 9" beam
I.e 0.45 cubes.
Curing
5" thick R.CC floor slab in 1st floor. Consider 5" thick slab 10' 0" x 12' 0" volume of concrete 50.00 cu.ft
35
Curing
36 6" thick R.CC floor slab in 1st floor. Consider 10' 0" x 10' 0" panel = 50 cu.ft
Curing
37 Cement concrete in 4 1/2" x 6" lintels in ground floor. Consider 240 l.ft I.e 45 cu.ft
Curing
Cement concrete in 9" x 9" lintels in ground floor. Consider 80 L.ft of lintel I.e 45 cu.ft concrete.
38
Curing
Cement concrete in 9" x 12" lintels in ground floor. Consider length 60' 0" of lintel
39
= 45 cu.ft
Curing
Cement concrete in 12" x 15" lintels in ground floor. Consider length 36' 0"
40
i.e 45 cu.ft
Curing
Formwork & RF

25,961.00
275.00
375.00
1,300.00
10,000.00
10,000.00
880.00
10,000.00
400.00
9,400.00
8,823.53
800.00

10,888.89
960.00

10,888.89
900.00

10,888.89
840.00
9,800.00
780.00
9,800.00
780.00
10,888.89
780.00
10,888.89
780.00
10,888.89
780.00
10,888.89
880.00

41

Sawn timber form work to 9" x 9" cement concrete column in ground floor.
42 Sawn timber form work for concrete beams in ground floor. 43 Sawn timber form work for underside of first floor slab. 44 Mild steel / for steel reinforcement to lintels slab beams for columns bent to
shape laid in position and tied with G.I. Wire as directed. -

45
46
47
48
49
50
51
52
53
54

Masonry & Floor


Brick work in cement sand 1:5: in foundation up to D.P.C
Brick work cement and sand 1:8 in foundation up to D.P.C
Brick work in cement and sand 1:5 in 4 1/2" thick walls in ground floor
9" thick brick wall cement sand 1:5 in ground floor
Brick work 13 1/2" thick in cement sand 1:5 in superstructure in ground floor
9" Brick walls in cement sand 1:8in superstructure in ground floor
4 1/2" thick brick wall (wire cut) in cement and sand 1:5 in ground floor
( Facing to brickwork measured separately)
9" thick in cement and sand 1:5 with wire cut bricks (Facing to brick work
measured separately)
13 1/2" thick brick wall (wire cut) in cement and sand 1:5 in ground floor
(Facing to brick work measured separately)
Extra over for facing including raised pointing 1/8" thick in cement and sand
1:1 mixture in ground floor
3" thick floor paved in lime mortar 2:5 in ground floor

55
56 Steps 1' - 1 1/2" x 0' 6" in brick in cement and sand 1:5 with 1/2" thick cement
and
1:2inredering
excavation.
Bricksand
drains
cement including
and sandnecessary
1:5, 9" wide
end 6" - 9" average depth
57 including cement rendering 1/2" thick 1:2 to exposed faces with 1'6" ramp
including necessary excavation.
58 Brick drains in cement and sand 1:5, 9" wide end 6" - 9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces without ramp
including necessary excavation.
59 8" thick Hollow block work in cement and sand mortar 1:5 in ground floor
(cavities unfilled)
60 4" thick Hollow block mesonry in cement and sand mortar 1:5 with cavities
unfilled
61 Random Rubble masonry in cement morter 1:5 in foundation
62 Random Rubble masonry in cement morter 1:5 in superstructure
63 Pressed floor tiles bedded in 1/2" cement morter 1:2 and pointing in neat
cement in ground floor
64 Glazed tiles fixed to walles including bedding in cement morter 1:2 and raking
in ground floor. (specials measured separately)
65 Terrazzo floor tiles on 1/2" thick cement and sand 1:2 in ground floor

22,769.27
21,672.91
24,692.60
1,130.04

14,612.50
14,244.00
6,147.50
10,800.00
17,078.50
17,241.50
8,598.00
16,222.50
26,380.00
9,145.00
4,734.00
162.50
265.00

224.10
4,397.50
3,586.00
11,280.00
12,145.00
17,270.50
32,409.00
10,845.50

Capentary
66 Timber framework for calicut pattern tile hip roof in single storey building
consisting o f wall plate, beam, ridge plate, rafters etc. (Preservutive treatment
to be measured separately)
67 Roof covering with calicut pattern clay tiles in single storeyod building (Timber
frame work & ridge covering measured separately)

5,140.00
3,125.00

68

Timber framework for corrugated asbestos sheet roof in angle storied building
69 Roof covering with corrugated asbestos sheets (timber frame work & ridge
covering measured separately)
70 One layer half round clay tiles over corrugated asbestos roof covering.
71 Asbestos close fittings ridging fixed complete with roofing screws or bolts
(hook)
72 Ridging covering with calicut pattern ridge tiles bedded in cement lime mortar
1:1:4
73 3/4" x 9" high valance board fixed with brass screws to ends of rafters ( for tile
roofing)
74 3/4" x 9" high barge board fixed with brass screws at 2' 0" centres to sides of
rafters.

2,774.31
6,422.22
1,125.00
40.96
117.71
96.16
94.56

75 ROOF PLUMBING 18 B.W.G (1.2 mm) galvanised from sheet valley


gutter 3' 0" girth overall once bent with end laps not less then 9" width
including 3/4" tongued and grooved planks laid to slope and grooved planks
laid to slope and profile on timber members.
18 B.W.G (1.2 mm) galvanised iron flashing 1' 6" girth overall 3 times bent
76 with end laps not less than 6", lead soldered, turned and tucked up to not less
than 6" in to cement mortar 1:2 lower end dressed over roof covering not less
than 1' 0" wide.
77 Timber Framework for 4' 0" x 4' 0" flat asbestos ceiling (Sheet measured
separately) comprising of 4" x 2" joists and 2" x 2" bearers in class I timber
78 Horisontal ceiling lining using 4' 0" x 4' 0"flat asbestos cement sheets fixed
with and including beading and cove mouldings on timber framework. (timber
framework & painting measured separated)
79 3/4" thick tongued and grooved Lunumidella ceiling boards fixed horizontal on
4" x 2" class I timber joists at 2' 0" centers with 1 1/2" brass nails.
80 3/4" x 6" wide tongued and grooved Lunumidella ceiling boards fixed to
underside of roof rafters, (existing) with 1 1/2" brass nails including leveling
with timber strips where necessary.
81 Door single hung 3' 3" x 7' 0" high overall with frame having 1 1/4" thick sash
and 3 1/4" x 2 1/4" timber frames. (glazing, ironmongery & painting measured
separately)
82 Door glazed and panolled double hung 4' 0" x 7' 0" high overall with frame
including 1 1/4" thick sash and 3 3/4" x 2 3/4" frame. (glazing, ironmongery
and painting measured separately).
83 Plywood door single hung 3' 1 1/2" x 6' 1 1/2" overall with frame having 1 1/4"
thick sash and 3 3/4" x 2 3/4" frame. ( iron - mongery and painting measured
separately)
84 Door ledged, braced and battened single hung 2' 6" x 6' 6" overall, with frame
having 7/8" thick tongued & grooved planks and 3 3/4" x 2 3/4" frame.
( Ironmongery
and overall
paintingwith
measured
separately)3 No openable
Window, glazed
7' 0" x 4' 0" high
frame comprising
sashes
and
3
3/4"
x
2
3/4"
frame
and
mullions
85 1/4" clear sheet glass panes exceeding 1' 0" but not exceeding 4 square feet
ironmongery
and painting
measured separately)
cut and fixed with(Clasing,
timber beadings
to doors
and windows.
Consider
sash
3'
0"
x
4'
0"
high with 3" x 1 1/4"
86
style and 4 Nos.glass panes.
87 IRONMONGERY
Butt hinges 5" x 2 1/2"
Tee
hinges
6"
x
12"
88

486.83

185.88
2,528.00

5,337.18
7,046.67

7,914.44

222.86

216.74

99.03

225.97
223.36
196.11
433.33
525.00

89
90
91
92
93
94
95
96
97

Rim lock
Mortice lock
Casement stays.
Door closer ( Hydraulic)
Tower / Skeleton brass bolts
Barrel bolt 4"
Casement fasteners.
Spring louded fanlight catches
Draw rings

700.00
700.00
197.50
1,130.00
1,050.00
690.00
303.33
227.33
85.83

Rate per square

Rate per cube

Rate per cube


Rate per cube

Rate per cube

Rate per cube

Rate per cube

Rate per cube


Rate per Square
Rate per Square
Rate per cube
Rate per cube
Rate per cube
Rate per cube

Rate per square

Rate per square

Rate per square


Rate per square

Rate per cube


Rate per cube
Rate per cube
Rate per cube

Rate per cube


Rate per square
Rate per square
Rate per square
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube

Rate per cube


Rate per cube

Rate per cube


Rate per cube

Rate per cube


Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per cube

Rate per square


Rate per square
Rate per square
Rate per cwt

Rate per square


Rate per square
Rate per square
Rate per square
Rate per square
Rate per square
Rate per square
Rate per square
Rate per square
Rate per square
Rate per square
Rate per L.ft
Rate per L.ft

Rate per L.ft


Rate per square
Rate per square
Rate per cube
Rate per cube
Rate per square
Rate per square
Rate per square

Rate per square


Rate per square

Rate per square


Rate per square
Rate per square
Rate per L.ft
Rate per L.ft
Rate per L.ft
Rate per L.ft

Rate per L.ft

Rate per L.ft


Rate per square

Rate per square


Rate per square

Rate per square

Rate per sqft

Rate per sqft

Rate per sqft

Rate per sqft


Rate per sqft
Rate per sqft
Rate per No
Rate per pair

Rate per No.


Rate per No.
Rate per No.
Rate per No.
Rate per No.
Rate per No.
Rate per No.
Rate per No.
Rate per No.

Ref No

Description
Earth Warks
1 Removing top soil to a depth not exceeding 6" & depositing as directed within
site

Rate

4,000.00 Rate per square

2 Excavation over site to reduce level, in any material except rock requiring
blasting including depositing and leveling as directed up to distance not
exceeding 30' 0" per cube

650.00 Rate per cube

3 Excavation in trenches for walls/ column pits in soft/ loose soil from 0' 0" to 5'
0" deep and depositing excavated materiel to a distance not exceeding 30' 0"
(Earth work support to be paid separately where necessary) per cube.

400.00 Rate per cube

4 Excavation in trenches for walls/ column pits in ordinary soil from 0' 0" to 5' 0"
deep and depositing excavated material not exceeding 30' 0" per cube.
5 Excavation in trenches for walls/ column pits in Hard/ dense soil up to a depth
of 5' 0" and depositing excavated material up to a distance not exceeding 30'
0".
11 Backfilling to trenches with selected earth available at site.
12 Back filling to trenches with imported material.
13 Filling under floors including leveling, watering & compacting in 3" layers with
available and selected earth at site.
14 Filling under floors including leveling, watering & compacting in 3" layers with
imported selected earth.

19
20
21
22
23
24
25
26
27
28

Concrete
Mixing concrete 1: 3: 6 (1 1/2")
Mixing concrete 1: 2: 5 (1")
Mixing concrete 1: 2: 4 (3/4")
Mixing concrete 1: 1: 3 (3/4")
Mixing concrete 1: 1: 2 (3/4")
2" thick cement concrete screed in foundation at depths not exceeding 5' 0"
3" thick cement concrete screed in foundation at depths not exceeding 5' 0"
6" thick cement concrete floor (mass concrete).
Consider 24 No. columns each 4 1/2" x 6" x 10' 0" ie 0.45 cubes.

Cement concrete in 6" x 6" colomns in ground floor. Consider 18 No. columns 6" x 6" each 10' 0" high ie 0.45 cubes.
Curing
29 Cement concrete in 9" x 9" colomns in ground floor. - Consider 8 No. 9" x 9"
columns each 10' 0" high ie 0.45 cubes.
Curing
30 Cement concrete in 12" x 12" colomns in ground floor. Consider
5 No. 12"
12"
columns
each
10' 0" high.
Cement concrete
inx13
1/2"
x 13 1/2"
colomns
in ground floor. Consider 4 No. colomns 13 1/2" x 13 1/2" each 10' 0" high .
31
I.e 0.51 cubes.
Curing
32 Cement concrete in 6" x 6" beam up to 1st floor level. Consider 180 L.ft of beam 6" x 6"
I.e 0.45 cubes.
Curing
33 Cement concrete in 9" x 6" beam up to 1st floor level. Consider 120 L.ft of beam 9" x 6" beam
I.e 0.45 cubes.

900.00 Rate per cube

1,400.00 Rate per cube


400.00 Rate per cube
902.50 Rate per cube
800.00 Rate per cube
1,202.50 Rate per cube

16,233.00
16,763.00
18,915.00
21,373.00
25,961.00
275.00
375.00
1,300.00
10,000.00

Rate per cube


Rate per cube
Rate per cube
Rate per cube
Rate per cube
Rate per square
Rate per square
Rate per square
Rate per cube

10,000.00 Rate per cube


880.00 Rate per cube
10,000.00 Rate per cube
400.00 Rate per cube
9,400.00 Rate per cube
8,823.53 Rate per cube
800.00 Rate per cube

10,888.89 Rate per cube


960.00 Rate per cube

10,888.89 Rate per cube

Curing
34 Cement concrete in 9" x 9" beam up to 1st floor level. Consider 80' 0" length 9" x 9" beam
I.e 0.45 cubes.
Curing
5" thick R.CC floor slab in 1st floor. Consider 5" thick slab 10' 0" x 12' 0" volume of concrete 50.00 cu.ft
35
Curing
36 6" thick R.CC floor slab in 1st floor. Consider 10' 0" x 10' 0" panel = 50 cu.ft
Curing
37 Cement concrete in 4 1/2" x 6" lintels in ground floor. Consider 240 l.ft I.e 45 cu.ft
Curing
Cement concrete in 9" x 9" lintels in ground floor. Consider 80 L.ft of lintel I.e 45 cu.ft concrete.
38
Curing
Cement concrete in 9" x 12" lintels in ground floor. Consider length 60' 0" of lintel
39
= 45 cu.ft
Curing
Cement concrete in 12" x 15" lintels in ground floor. Consider length 36' 0"
40
i.e 45 cu.ft
Curing

41
42
43
44

Formwork & RF
Sawn timber form work to 9" x 9" cement concrete column in ground floor.
Sawn timber form work for concrete beams in ground floor. Sawn timber form work for underside of first floor slab. Mild steel / for steel reinforcement to lintels slab beams for columns bent to
shape laid in position and tied with G.I. Wire as directed. -

Masonry & Floor


47 Brick work in cement and sand 1:5 in 4 1/2" thick walls in ground floor
48 9" thick brick wall cement sand 1:5 in ground floor
61 Random Rubble masonry in cement morter 1:5 in foundation

900.00 Rate per cube

10,888.89 Rate per cube


840.00 Rate per cube
9,800.00 Rate per cube
780.00 Rate per cube
9,800.00 Rate per cube
780.00 Rate per cube
10,888.89 Rate per cube
780.00 Rate per cube
10,888.89 Rate per cube
780.00 Rate per cube
10,888.89 Rate per cube
780.00 Rate per cube
10,888.89 Rate per cube
880.00 Rate per cube

22,769.27 Rate per square


21,672.91 Rate per square
24,692.60 Rate per square
1,130.04 Rate per cwt

6,147.50 Rate per square


10,800.00 Rate per square
11,280.00 Rate per cube

Das könnte Ihnen auch gefallen