Draft

Safety Rules for


Operation and Maintenance
at Nam Ngum 1 Power station
(Civil Engineering Facilities
and
Electrical Facilities)

May of 2007

Electricite du Laos (EdL)

Electricite du Laos (EdL)

Contents
Chapter 1 General Provisions
Article 1
Article 2

Purpose....................................................................................................1
Scope ......................................................................................................1

Chapter 2 Safety Management


Article 3
Article 4
Article 5

Organization.............................................................................................1
Safety Management.................................................................................1
Expertise of Chief Engineer.....................................................................2

Chapter 3 Safety Education


Article 6

Safety Education......................................................................................2

Chapter 4 Flood Management Rules


Article 7

Flood Management Rules........................................................................2

Chapter 5 Patrol and Inspection


Article 8
Article 9

Patrol and Inspection...............................................................................3


Measures for the Result of Patrol and Inspection....................................5

Chapter 6 Operation and Maintenance


Article 10
Article 11
Article 12
Article 13
Article 14

Operation Rules.......................................................................................6
Maintenance Program..............................................................................6
Measures against Accidents or Troubles ................................................7
Measures against Disasters or Other Emergencies................................7
Measures in a period of Suspending the Operation................................7

Chapter 7 Records
Article 15 Record Items............................................................................................7

(a)

Electricite du Laos (EdL)

Chapter 1 General Provisions


Article 1 Purpose
The purpose of the Safety Rules founded on the Article 31 of the Guideline on Operating
and Managing Lao Electric Power Technical Standards is to secure the operation and the
maintenance of the power facilities.
The power facilities are defined as to include dams, spillways, waterways and
reservoirs, hydropower stations, substations, switching stations and transmission lines,
and be composed of hydropower civil engineering facilities and electrical facilities.

Article 2 Scope
Safety Rules shall apply to the power facility that is to operate and/or in operation.

Chapter 2 Safety Management


Article 3

Organization for at EdL Nam Ngum P/S


Generation and Project
Department
Mr Sisouvanh SOUVANNAPHASY

Manager of Nam Ngum 1


P/S
Mr Phoumy NETIBANDITH
Deputy Manager of Nam Ngum 1 P/S
Mr Vanthong KHAMLOUNVILAIVONG

Construction and Maintenance


Mr Chanthaboun
KEOKAN

Deputy Manager of Nam Ngum 1 P/S


Mr Phet SICHALEUNE

Mechanical
Mr Khamvane

Electrical
Mr Bounmy

Deputy Manager of Nam Ngum 1 P/S


Mr Bounvan CHANSAVAT

Nam Song Canal


Mr Vorlavankham

Operate - Control
Mr Soulavate

Article 4 Safety Management


The EdL Nam Ngum 1 P/S shall clarify responsibility of each department and/or

Electricite du Laos (EdL)

members in the organization in order to facilitate the smooth communication between


them.
The EdL Nam Ngum 1 P/S shall establish the communication network among concerned
organization, agencies, institutes and local communities at accidents, troubles, disasters
or other emergencie

Article 5 Expertise of Chief Engineer


The EdL Nam Ngum 1 P/S shall deploy a chief hydropower civil engineer and a chief
electrical engineer who have expertise referred to Table 5 for operation.

Table 5 Expertise of Chief Engineers and Power Facilities

Elecyricite du Laos (EdL)

PowerFacilities
Kind
Chief Hydropower Civil Engineer
Mr Vanthong KHAMLOUNVILAIVONG
Facilities
Chief Electircal Engineer
Mr Phet

Expertise Fields
Hydropower Civil Engineering

Electircal l Engineering Facilities

SICHALEUNE

Chapter 3 Safety Education


Article 6 Safety Education
The EdL Nam Ngum 1 P/S shall prepare the education and training program for
members to understand thoroughly the importance of ensuring the safety in operating
the power facilities.
The education and training for members shall be implemented through On the Job
Training, Lecture on knowledge, information and technical skill of operation of the
power facilities and Practical training of measures taken at disasters, troubles and
emergencies.

Chapter 4 Flood Management Rules


Article 7 Flood Management Rules
In case of a dam which has role of flood control, the EdL Nam Ngum 1 P/S shall prepare,
prior to the start of first impoundment, the flood management such rules as discharge
procedure and measures to mitigate danger to downstream areas under flood situation.

Chapter 5 Patrol and Inspection


Article 8 Patrol and Inspection
(1) The EdL Nam Ngum 1 P/S shall monitor and inspect the dam stability and the
progress of sedimentation in the reservoir, and then the results shall be reported
annually to the Department of Electricity (hereinafter referred to as DOE) of the
Ministry of Energy and Mines (hereinafter referred to as MEM).
(2) The items shall be carried out are shown on Table 8-1 (Refers to Article 23 and

Electricite du Laos (EdL)

Article 7 of the Lao Electric Power Technical Standards (hereinafter referred to as


LEPTS)).
(3) The EdL Nam Ngum 1 P/S shall make the implementation rules for patrol and
inspection of the power facilities to operate and maintain them in such good
conditions that they can conform to LEPTS. Items for patrol and inspection are
shown on Table 8-2.
(4) When the accident occurs on the power facilities or when it is recognized that the
accident is likely to occur, proper patrol and inspection are carried out.

Elecyricite du Laos (EdL)

Items &

Monitoring and Inspection Item


Sedimentation

Frequency
Monitoring

Water

External

Uplift

Permeation

Stage

Leakage

Deformation

Stage I

Daily

Daily

Weekly

Stage II

Weekly

Weekly

Monthly

Stage III

Monthly

Monthly

Every

in
Reservoir

Line

Dam Type

Concrete
Gravity

Yearly

Months
Concrete Arch

Stage I

Daily

Daily

Weekly

Stage II

Weekly

Weekly

Monthly

Stage III

Monthly

Monthly

Every

Yearly

Months
Rock fill

Stage I

Daily

Weekly

Stage II

Weekly

Monthly

Stage III

Monthly

Every

Yearly

months
Earth fill

Stage I

Daily

Weekly

Weekly

Stage I

Weekly

Monthly

Monthly

Stage III

Monthly

Every

Every

Months

Yearly

Months

Note:
1) Monitoring frequency for each item is to be determined based on the following three (3)
stages:
Stage I: Two (2) months or more after the first impounding at the Normal Water Level
Stage II: Between Stage I and Stage III
Stage III: After dam and its foundation settle stable condition, which means that
monitoring results are getting steady and/or linear response against the external
load condition such as water level and dam body.
2) The structural and hydraulic conditions of the dam should be inspected and assessed
based on monitoring results and collective data.

Electricite du Laos (EdL)

Table 8-2 EdLs Implementation Rules for Patrol and Inspection of Power Facilities
Facilities

Patrol
Frequency

Hydropower

Monthly

Inspection
Facility

Method

Dam

Civil
Engineering

Remark
Frequency

- External Inspection

1 year

- Internal Inspection

3 years

- Instrument measurement

See

Facilities

Table 8-1

(including

Reservoir

- External Inspection

1 year

- Sedimentation monitoring

1 year

- Water quality measurement

1 year

- External Inspection

1 year

- Internal Inspection

3 years

Headrace

- External Inspection

1 year

Spillway

- Internal Inspection

3 years

and - External inspection

1 years

dam,
reservoir,
waterway

Waterway

and the other


facilities)

Intake
Settling Basin
Penstock
Powerhouse

Steel thickness
of
penstock
should
be
measured
in
20 years after
its installation
and after 20
years it should
be measured
every 6 years
at least.

Tailrace
Spillway Gates
Intake Gates
Other Facilities
Hydropower

Monthly

Electric

Turbine
Generator

Plants

- Measurement and test

1 years

- Internal inspection

During
overhaul

Substations
and

Weekly

Main
Transformer

- External inspection

1 years

- Measurement and test

1 years

- Internal inspection

Properly
1 years

Circuit

- External inspection
- Measurement and test

Breaker

- Internal inspection

Properly

Switching
Stations

Main

1 years

Article 9 Measures to the Result of Patrol and Inspection


For the result of patrol and inspection of the power facilities, whenever the power facility

Electricite du Laos (EdL)

that does not conform with LEPTS or needs the improvement to secure the operation
are confirmed, a tentative measure should be taken appropriately at once, and then a
permanent measure shall be carried out.
In case it should be identified that a facility or equipment does not conform to the
concerned Article of LEPTS, the owner shall report it to MEM (DOE) and follow his
direction.
In the field of Hydropower Civil Engineering Facilities and Hydropower Electrical Plants,
EdL Nam Ngum 1 P/S shall report it to MEM (DOE).

Elecyricite du Laos (EdL)

Chapter 6 Operation and Maintenance


Article 10 Operation Rules
The EdL Nam Ngum 1 P/S shall prepare the operation manual of the power facilities.
The operation manual describes the detail procedures and methods in operating the
power facilities at normal condition, troubles and other emergencies.

Article 11 Maintenance Program


The EdL Nam Ngum 1 P/S shall set the medium and long term programs of repair,
rehabilitation and renewal works for the power facilities that they can keep the
conformance to LEPTS. Maintenance program is shown on Table 11.

Table 11 Maintenance Program for Power Facilities

Program

Facility

Method

Period

Remarks

Power Facilities
Hydropower Civil
Engineering Facilities

Hydropower
Electrical Plants

Substations and
Switching Stations

Electricite du Laos (EdL)

Article 12 Measures against Accidents or Troubles


When the accidents or troubles occur on the power facilities or when it is recognized that
the accidents and troubles are likely to occur, EdL Nam Ngum 1 P/S shall take prompt
measures in order to prevent them from expanding. The owner shall investigate causes
of the accidents or the troubles and report them to MEM (DOE).
In the field of Hydropower Civil Engineering Facilities and Hydropower Electrical Plants,
EdL Nam Ngum P/S shall report it to MEM (DOE).

Article 13 Measures against Disasters or Other Emergencies


When disasters or other emergencies occur, EdL Nam Ngum 1 P/S shall take the proper
measures in order to minimize damage or prevent the operation from danger.

Article 14 Measures in a Period of Suspending the Operation


EdL Nam Ngum 1 P/S shall, prior to stopping the operation of the power facilities,
implement necessary measures such as dust-proof, corrosion-proof, moisture-proof, etc.
in order to maintain the power facilities at good conditions and prevent accidents during
stopping the operation.

Chapter 7 Records
Article 15 Record Items
EdL Nam Ngum 1 P/S shall keep the following records for necessary periods in order to
ensure the safety of the power facilities.
(1)

Records of usual patrol and inspection


- Patrol and Inspection Records for Hydropower Civil Engineering Facilities
- Patrol and Inspection Records for Hydropower Electrical Plants
- Patrol and Inspection Records for Substations and Switching Stations

(2)

Records of periodical detail inspection


- Periodical Inspection Records for Hydropower Civil Engineering Facilities
- Periodical Inspection Records for Hydropower Electrical Plants
- Periodical Inspection Records for Substations and Switching Stations

Electricite du Laos (EdL)

(3)

Records of major repair work


- Major Repair Records for Hydropower Civil Engineering Facilities
- Major Repair Records for Hydropower Electrical Plants
- Major Repair Records for Substations and Switching Stations

(4)

Records of operation
- Operation Records for Hydropower Civil Engineering Facilities
- Operation Records for Hydropower Electrical Plants
- Operation Records for Substations and Switching Stations

(5) Records of accidents


- Accidents Records for Hydropower Civil Engineering Facilities
- Accidents Records for Hydropower Electrical Plants
- Accidents Records for Substations and Switching Stations

Elecyricite du Laos (EdL)