Beruflich Dokumente
Kultur Dokumente
Ts=set time ( hr )
P r=sprinkler precipitation rate(mm/hr )
T s=61. 97 /5 . 16=11 .99 hour s
Q = Nc * Ns * Qs
Q = system capacity (m3/hr)
N c = the number of laterals operating per shift
N s = the number of sprinklers per lateral
Qs = the sprinkler discharge (from the menu factories tables)
Q = 4 * 20 * 1.16 = 92.8 m3/hr.
When preparing the layout of the system one should adhere to two principles, which are
important for the uniformity of water application.
For the rectangular spacing the laterals should be placed across the prevailing wind direction.
Where possible, laterals should run perpendicular to the predominant slope in order to achieve
fairly uniform head lost.
Figure 2
Figure 3
Figure 4
Q = the discharge or flow rate within that section of the pipe, the units depending on the chart
being used (m3/hr).
L= the length of pipe for that section (m)
D = the pipe size diameter (mm).
H L = The friction loss of the pipe (m).
Where the mainline is located at the middle of the field, the maximum length of the lateral is 150
meters.
F for m
=2
Number of
outlets
F for m
=2
Number of
outlets
F for m
=2
Number of
outlets
0.360
19
0.385
10
1.000
0.359
20
0.380
11
0.625
0.357
21
0.376
12
0.518
0.355
22
0.373
13
0.469
0.353
23
0.370
14
0.440
0.351
24
0.367
15
0.421
0.350
25
0.365
16
0.408
0.363
17
0.398
0.361
18
0.391
It will have 13 sprinklers operating at the same time, delivering 1.16 m3/hr each at 350 kPa
pressure.
The flow at the beginning of the lateral will be:
Q = 13 * 1.16 = 15.08 m3/hr
The friction loss for a discharge of 15.08 m3/hr will be:
HL = 0.013 * 150 = 1.95 m
By taking into consideration the F factor corresponding to 13 outlets (sprinklers):
HL = 0.013 * 150 *0.373 = 0.73
If instead of 76 mm, 63 mm pipe is used then:
HL = 0.033 * 150 *0.373 = 1.85m
The friction losses for the 18 m aluminum pipe (header) with flow of 15.08 m3/hr:
HL = 0.013 * 18 = 0.23 m for the 76 mm pipe.
HL = 0.033 * 18 = 0.59 m for the 63 mm pipe
The total friction losses in the 76 mm lateral, when the header is used, are 0.96 m (0.73+0.23).
The total friction losses in the 63 mm lateral, when the header is used, are 2.44 m (1.85+0.59).
Figure 5
Figure 8
Class
600
300
1200
600
12
1800
900
18
2400
1200
24
3000
1500
30
4200
1800
36
4200
2100
42
Class
400
600
1000
10
1600
16
System layout and pipe sizing based on a 12m*18 m spacing and short laterals (first attempt at
pipe sizing)
Figure 9 System layout and pipe sizing based on a 12m*18 m spacing and short
laterals (first attempt at pipe sizing)
The friction losses of positions 1 and 11 are identical, being mirror images of
each other. It suffices therefore to calculate the friction losses of positions 1
and 6
Position 1
As a guideline in selecting the class of a pipe to be used, it is suggested that the sum of the difference in
elevation, sprinkler operating pressure, allowable pressure variation and lateral friction losses is used
Difference in elevation = 3.5 meters (108-104.5)
Sprinkler operating pressure = 35 meters
20% allowable pressure variation = 0.2 *35 = 7 meters
Lateral friction losses = 0.96 meters
The total of 46.46 (3.5 +35 +7+0.96) meters, exceeds the pressure rating of class 4 uPVC pipe, which is
40 meters, obliging the use of the next class of pipe, which is class 6
Q1(6) = 87 m3/hr
Figure 10
2.00
Suction lift
0.88
Supply line
2.49
Main line
0.96
Lateral
2.50
Riser
35.00
43.83
Subtotal
4.38
Fittings 10%
8.00
Elevation difference
56.21
Total