Beruflich Dokumente
Kultur Dokumente
for repairs initially PWHTd pipes constructed of the P-1 steels and P-3 steels,
(except Mn-Mo steels).
23. Local PWHT may be substituted for 360-degree banding on local repairs under certain
precautions
24. Butt joints for repairs shall be full-penetration groove welds
25. The temporary repairs shall be approved by the piping engineer.
The materials used in making repairs or alterations shall be of known weldable quality, shall
conform to the applicable code
26 After welding is completed, a pressure test shall be performed if practical and deemed
necessary by the inspector.
27. Pressure tests are normally required after alterations and major repairs
28.
When a pressure test is not necessary or practical, NDE shall be utilized in lieu of a
pressure test after consultation with the inspector and the piping engineer.
RERATING
29. Rerating piping systems can be done under following conditions
a. Calculations are performed by the piping engineer or the inspector.
b. All reratings shall be established in accordance with the requirements of the
applicable code.
c. Current inspection records verify that the appropriate corrosion allowance is
provided.
d. Rerated piping systems shall be leak tested unless a previous leak test was
performed at greater than or equal to the test pressure for the new condition.
e. Piping flexibility is adequate for design temperature changes.
f. A decrease in minimum operating temperature is justified by impact test results, if
required by the applicable code.
For piping buried in lengths greater than 100 feet (30 m) and not cathodically protected,
evaluations of soil corrosivity should be performed at 5-year intervals
6
Inspection Methods
7.
Intelligent pigging. This method involves the movement of a device (pig) through the.
Five diameter bends are usually required since standard 90-degree elbows may not
pass a pig.
Video cameras. Television cameras are available that can be inserted into the piping.
These cameras may provide visual inspection information on the internal condition of
the line.
Excavation. In many cases, the only available inspection method that can be
performed is unearthing the piping in order to visually inspect the external condition of
the piping
10
The external condition of buried piping that is not cathodically protected should be
determined by either pigging, which can measure wall thickness, or by excavating
according to the frequency given in Table 9-1.
11
12 Intervals for above test are: one-half the length of those shown in Table 9-1 for
piping not cathodically protected and at the same intervals as shown in Table 9-1 for
cathodically protected piping.
13 The leak test should be maintained for a period of 8 hours. Four hours after the initial
pressurizationof the piping system, the pressure should be noted and, if necessary,the
line repressurized to original test pressure and isolated from the pressure source. If,
during the remainder of the test period, the pressure decreases more than 5 percent,
the piping should be visually inspected to find the leak and assess the extent of
corrosion.
14
15
16 If piping leaks are clamped and reburied, the location of the clamp shall be logged in the
inspection record (with the date of installation) also be surface marked.
17 All clamps shall be considered temporary. The piping should be permanently repaired at
the first opportunity.
PUNCH POINTS
ASME - Sec. IX - welding Qualification Code
(DAY 4)
2.
For Procedure Qualifications a test coupon is welded and then tested
for strength (tension tests) and ductility (Bend tests) to ensure that the weld
has req