Beruflich Dokumente
Kultur Dokumente
P
PO
OSST
T--T
TE
EN
NSSIIO
ON
NIIN
NG
GM
ME
ET
TH
HO
OD
DO
OL
LO
OG
GY
Y
I. MATERIALS SPECIFICATIONS
1. REINFORCING STEEL
Non-pre-stressing steel:
All reinforcing bar should comply with ASTM A615-96 Specification for Deformed
and Plain Billet-Steel Bars for Concrete Reinforcement.
Pre-stressing Steel:
Seven-wire uncoated stress-relieved strands conforming to AASHTO M204 Type WA,
ASTM A416 Grade 270.
2. ANCHORAGE ASSEMBLIES
Bulgar Eden Post-Tensioning System Brand of Anchorage (VSL Pattern), Bearing Plate
and Cone Guide will be used. (Manufacturer: Bulgar Eden, Taiwan)
The inch diameter 3-jaw one-time use grips/wedges are made of hard steel pre-fabricated
and imported from the U.S. (supplied by Bulgar Eden Post-Tensioning System).
3. DUCT TUBES
Polyethylene pipes of commercial grade shall be used as duct tubes to provide holes or
voids in the concrete for the placement of post-tensioned bonded tendons. 21/2 diameter
for 8 to 12 strands and 2 diameter for 6 to 7 strands.
II. CONSTRUCTION METHODOLOGY
The POST-TENSIONING is accomplished by the two (2) basic processes listed below:
(1)
(2)
1. After assembly, chairs 8-10mm diameter DRB to form the profile of the pre-stressing
tendons are then tied into place.
2. The duct tubes are then set with the required profile after which the Grade 270 High Tensile
Strands are inserted.
3. After insertion of the strands, the live end anchor guide is set in place with a block- out at
end.
4. The dead end shall be assembled according to embedment length.
5. End forms with block-out shall be done by others.
FULL STRESSING, GROUTING, AND PACKING
After the concrete strength of the post-tensioned beams has attained a compressive strength of
27.60 Mpa, stressing works shall commence.
Stressing. The stressing of girders will be done by one end stressing using a multi- strand
stressing jacks at live end of post-tensioned beam.
Computation of Jacking Force (JF):
JF = S X A
S = grade of 12.7 mm HTS = 1,862 N/mm2 (per mill certificate)
A = area of 12.7mm HTS = 98.71 mm2
Note: Jacking force reduction factor is at 80 % to consider friction losses
For 12 pcs HTS per Tendon;
JF = 12 X 1,862 N/mm2 X 98.71 mm2 X 0.80
JF = 1,764.46 kN
For 7 pcs HTS per Tendon;
JF = 7 X 1,862 N/mm2 X 98.71 mm2 X 0.80
JF = 1,029.27 kN
Cleaning of anchorage.
Checking the allowance of the P.C. Wire from the anchorage.
Removal of rust from P.C. Wire, Anchorage, and Grips.
Gradual stressing force introduction and reading of elongation.
Packing. After completion of stressing, the exposed anchorage shall be covered by concrete
mortar mix. The inlets for the grout will be exposed.
Grouting. After the completion of stressing of all tendons, grouting shall follow. The tendons
shall be cleaned by running pressurized water into the P.E. hose inlet.
The grout shall be made of portland cement and intraplast additive mortar mix.
The grout shall be fed to the inlet using a pressurized grouting pump.
The completion of grouting will be checked by seeing to it that the grout will exit at the outlet
and at the provided air vents.
By:
JONATHAN M. MONTECILLO
PRESTRESSED GIRDER
STRESSING METHODOLOGY
:
:
3. PT Jack
4. PT Pump
5. PT Methodology
:
:
:
I. Before PT
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
II. During PT
1. Initial force introduction
This shall be 5 MPa at both ends simultaneously.
2.
3.
4.
Zero adjustment
Hold the tensioning execution at 50% of the desired final force and connect the points in the graph and
slide the line parallel to the origin then project a line to the final force limit.
5.
measures below
ii) Then increase 5 MPa pressure and observe the effect. If the same situation exists,
inclination of elongation has occurred. Stop stressing operation and release pressure
without wedging. Check the PC tendons for obstruction like concrete inside the duct.
If it is okay repeat the procedures 1-5. If the duct is clogged, this girder maybe
abandoned as per decision of an authorized engineer.
c.) If line is within the limit, proceed with stressing the 50% remaining required force as per
procedure 3.
d.) If the line is out of the limit, stop the operation and detach the jack. Reset the jack and repeat
procedure 1-5.
e.) If repeated procedure resulted the same as 5-d, proceed to find the cause, the following counter
measure steps shall be followed.
Step 1. Check jack and pump
a.) Pump might have unknowingly encountered accident during shipment.
b.) Pump might lack hydraulic fluids. If the mentioned conditions are observed, do
subsequent actions, repair pump or jack and recalibrate.
Step 2. If the jack and pump are normal, proceed to the following cases.
Case I: Elongation is lesser than computed
a.) If the elongation is little bit far from the upper limit, proceed to the next
procedure.
b.) If the elongation is extra-ordinary or negligible to measure, abandon the procedure
by releasing pressure without wedging.
Check duct for some obstructions.
c.) If Case I-1 is frequently observed to other tendons, check Ep & . Re-computation
may be necessary using different value of Ep and .
Ep can be change to present value than the present one. Confirm if actual
elongation is within the adjusted control graph.
Case II: Elongation is greater than computed
a.) If the elongation is little far from the lower limit, proceed to the next procedure.
b.) If the elongation is extra-ordinary abandon the procedure by releasing pressure
without wedging.
Check grips, some wedges may have slip or grips are not properly installed.
PC wire might have low Ep value. Change the whole set if necessary.
Never attempt to proceed the stressing with a low Ep PC wire to avoid
understress.
c.) If Case II-1 is frequently observed to other tendons, check Ep & . Recomputation may be necessary using different value of Ep and .
Ep can be changed to a lower value than the present one up to Ep=1.9x10 6 kg/cm2.
(186.2x103 MPa) If adjusted Ep is lower than the above mentioned value, the
authorized Engineer can decide if the tendon will be used or rejected.
NOTE:
Generally 10% tolerance of computed limit is considered. In any case, if the above-mentioned is
observed, PC wire materials may be substandard. Replacement of the materials with new sets may
be recommendable.
To emphasize above, Allowable Control Limit comparison shall be presented below.
Example:
Table I. Allowable Control Limit Comparison for Elongation
TENDON
C1
ELONGATION
CONTROL
LIMIT
LIMIT
UPPER LIMIT
LOWER LIMIT
LIMIT RANGE
ELONGATION
& PRESSURE
METHOD
222
182
40
FRICTION
COEFFICIENT
METHOD
201
181
20
VARIANCE
+21
+1
+20
NOTE:
Pressure elongation method is more tolerable compared to Friction coefficient.
6.
Pre-final tension
The authorized Engineer decides the pre-final tension value if the plotted actual line is within the limit
line.
7.
Measurement of camber
Camber usually occurs when PT force is more than the dead weight of the girder. The last cable to be
stressed will determine the required camber. Now at pre-final tension, the camber shall be measured and
then proceed as follows:
Step 1. If the camber is near to the designed one, pre-final tension shall represent for the final
tension value. Then proceed to next step.
Step 2. If the camber is far from the designed one, pre-final tension shall be increased in order
to attain the designed camber. This is subject to the decision of the authorized Engineer.
c = (c el) + (c er) = c (el + er)
8.
9.
Release of tension
After wedging, the tension shall be released up to 5 MPa.
The formula below shall be applied for the Adjustment of Tensile Stress
(ATS) to next girder.
ATS = [(la lc) (m)]/l
Where:
DESCRIPTION
Friction Coefficient
Tensile Stress
Total Elongation
Computed pull-in
Actual pull-in
m
l
lc
la
VALUE
0.30
560
186
20
22
11. Individual cable posttensioning shall not be the absolute value of post tension to be considered. It should
consider the sum or the total post tension force introduced.
Adjustment of pull-in losses of slips shall be minimal on the last cable since this cable path is not the
centerline of girder.
III. After PT
1.
Length
Check the total length of PC girder.
2.
Camber
Check the final camber of the PC girder at midspan.
3.
Control graph
Fill-up the necessary data in the control graph and get the signature of the
authorized Engineer.
4.
PC tendon
Cutting shall not be less than 30 mm from the anchor head. Disc type cut-off machine shall be used.
5.
Temporary stocking
Until grouting shall be made, the duct should be free from any water.
6.
Packing
After cutting of PC tendon, packing of the anchor block with cement mortar
is done.
POST-TENSIONED GIRDER
GROUTING METHODOLOGY
2. Cement:
3. Admixture:
4. Grout Pump:
5. Grout Mixer:
Portland Cement
Sika Intraplast Z
Bulgar Eden YM-90
Locally made
GROUTING
Post-tensioned steel shall be bonded to the concrete by grouting a soon as possible after stressing unless
noted otherwise on the drawings when, in the opinion of the Consultant, such grouting is impracticable, the
grouting shall take place as soon as is practicable and in any case not later than 28 days after stressing of the
tendons in any cable duct is completed. All pre-stressing reinforcement enclosures and ducts shall be free of dirt,
loose rust, grease, and other deleterious substances, the ducts shall be flushed out with clean water and compressed
air first. Grout shall be placed within 45 minutes of mixing. Grout shall be placed under pressure of at least 7.0
kg/cm2 or 100 psi, the injection shall be continuous and include a system for re-circulating the route if actual
grouting is not in progress.
GROUTING PROCEDURE
1. Quality Assurance (See details of Quality Test Measurements)
a.)
b.)
c.)
d.)
e.)
Choice of admixture
Preparation of design mix
Execution of trial mix
Conducting quality test
Required quantity computation
cause clogging and to determine whether the duct is not clogged. After flushing, remaining water shall
be removed by introduction of compressed air.
f.) Sieving of Cement
Prior to mixing the grout, cement shall be sieved thru 1.2 mm sieve, so that weathered cement can be
removed. Cement shall be kept in cool dry place.
g.) Grouting Scheme
Position of mixing plant shall be determined considering the site condition. Capacity of mixer and pump
shall be carefully studied for smooth grouting operation.
3. Grouting Operation
a.) Mixing Order
Mixing order shall be strictly followed as mentioned below:
1.
2.
3.
4.
CONSISTENCY
(seconds)
15.0 to 30.0
LESS 0.30
LESS 3.0
LESS 45.0
COMP. ST
(kg/cm2)
OVER 200
Table below represents standard design mix using premix type admixture.
TABLE 6. STANDARD DESIGN MIX
W/C RATIO
WATER
CEMENT
ADMIXTURE
(%)
(kg)
(kg)
FG-10* (kg)
44.0
17.6
40.0
0.40
* in Japan, this is
known as GF630
Consistency Test
This test shall be complied with JA funnel Method of JSCE-1986 PC Grout Test. (See Fig. 3)
a.) Funnel shall be supported by funnel supporter.
After the testing, the grout which remained inside the JA funnel is considered unsuitable.
2.
Bleeding Test
3.
Expansion Test
4.
44%
Admixture
2% of Cement Weight
2. DESIGN MIX
The materials which are needed for 1 m3 of grout shall be computed by the equation below:
1000 = W + C + A
w
c
a
where:
W = Weight of Water
C = Weight of Cement
A = Weight of Admixture
= Specific Gravity of Materials
Since admixture is negligible in quantity compared to water and cement, this shall be neglected:
1000 = W + C
w
c
w = 1.00
c = 3.15
1000 = _W_
1.00
1000 = W
_C_
3.15
0.317 C
MIXTURE
VOLUME
C = 1321.0 kg (Cement)
W = 581.2 kg (Water)
A=
26.4 kg (Sika Intraplast Z)
W/C RATIO
(%)
WATER
(kg)
CEMENT
(kg)
Sika Intraplast Z
(kg)
Per 1.00 m3
44
581.2
1321.0
26.4
Per 1 batch
44
22.0
50.0
1.0