Sie sind auf Seite 1von 16

TOYO-TOBISHIMA JOINT VENTURE

Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

P
PO
OSST
T--T
TE
EN
NSSIIO
ON
NIIN
NG
GM
ME
ET
TH
HO
OD
DO
OL
LO
OG
GY
Y
I. MATERIALS SPECIFICATIONS
1. REINFORCING STEEL
Non-pre-stressing steel:
All reinforcing bar should comply with ASTM A615-96 Specification for Deformed
and Plain Billet-Steel Bars for Concrete Reinforcement.
Pre-stressing Steel:
Seven-wire uncoated stress-relieved strands conforming to AASHTO M204 Type WA,
ASTM A416 Grade 270.
2. ANCHORAGE ASSEMBLIES
Bulgar Eden Post-Tensioning System Brand of Anchorage (VSL Pattern), Bearing Plate
and Cone Guide will be used. (Manufacturer: Bulgar Eden, Taiwan)
The inch diameter 3-jaw one-time use grips/wedges are made of hard steel pre-fabricated
and imported from the U.S. (supplied by Bulgar Eden Post-Tensioning System).
3. DUCT TUBES
Polyethylene pipes of commercial grade shall be used as duct tubes to provide holes or
voids in the concrete for the placement of post-tensioned bonded tendons. 21/2 diameter
for 8 to 12 strands and 2 diameter for 6 to 7 strands.
II. CONSTRUCTION METHODOLOGY
The POST-TENSIONING is accomplished by the two (2) basic processes listed below:
(1)
(2)

Reinforcing Steel Bars Assembly


Full Stressing, Grouting and Packing

REINFORCING STEEL BARS ASSEMBLY


This process deals with the fabrication and assembly of the non-pre-stressed and pre-stressed
reinforcing steel bars and strands.
STAGE ONE:
1. The non-pre-stressing reinforcing steel bars are cut and assembled in place by main
contractor.
STAGE TWO:

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

1. After assembly, chairs 8-10mm diameter DRB to form the profile of the pre-stressing
tendons are then tied into place.
2. The duct tubes are then set with the required profile after which the Grade 270 High Tensile
Strands are inserted.
3. After insertion of the strands, the live end anchor guide is set in place with a block- out at
end.
4. The dead end shall be assembled according to embedment length.
5. End forms with block-out shall be done by others.
FULL STRESSING, GROUTING, AND PACKING
After the concrete strength of the post-tensioned beams has attained a compressive strength of
27.60 Mpa, stressing works shall commence.
Stressing. The stressing of girders will be done by one end stressing using a multi- strand
stressing jacks at live end of post-tensioned beam.
Computation of Jacking Force (JF):
JF = S X A
S = grade of 12.7 mm HTS = 1,862 N/mm2 (per mill certificate)
A = area of 12.7mm HTS = 98.71 mm2
Note: Jacking force reduction factor is at 80 % to consider friction losses
For 12 pcs HTS per Tendon;
JF = 12 X 1,862 N/mm2 X 98.71 mm2 X 0.80
JF = 1,764.46 kN
For 7 pcs HTS per Tendon;
JF = 7 X 1,862 N/mm2 X 98.71 mm2 X 0.80
JF = 1,029.27 kN

The strands will stressed following the procedures listed below;


1.
2.
3.
4.

Cleaning of anchorage.
Checking the allowance of the P.C. Wire from the anchorage.
Removal of rust from P.C. Wire, Anchorage, and Grips.
Gradual stressing force introduction and reading of elongation.

Packing. After completion of stressing, the exposed anchorage shall be covered by concrete
mortar mix. The inlets for the grout will be exposed.

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

Grouting. After the completion of stressing of all tendons, grouting shall follow. The tendons
shall be cleaned by running pressurized water into the P.E. hose inlet.
The grout shall be made of portland cement and intraplast additive mortar mix.
The grout shall be fed to the inlet using a pressurized grouting pump.
The completion of grouting will be checked by seeing to it that the grout will exit at the outlet
and at the provided air vents.
By:

JONATHAN M. MONTECILLO

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

PRESTRESSED GIRDER
STRESSING METHODOLOGY

POSTTENSIONING BASIC INFORMATION


1. Anchorage
2. PC Wire

:
:

3. PT Jack
4. PT Pump
5. PT Methodology

:
:
:

Bulgar Eden BEM-T13-12/BEM-T13-07


Siam Industrial Wire Co., Ltd
Low Relaxation HTS 12.7mm dia.
Bulgar Eden YCW200A
Bulgar Eden ZB4-500
a.) Tensioning Execution
Both ends synchronized stressing
b.) Tensioning Control
Friction and Elongation Method

POSTTENSIONING STANDARD OPERATION PROCEDURE

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

I. Before PT
1.
2.
3.
4.
5.
6.
7.
8.
9.

10.
11.
12.
13.
14.
15.

Preparation of protection board.


Cleaning of anchorage.
Check the PC wire Mill Certificate and confirm if the inserted wires are the same wires certified.
Remove rust of PC wire, anchorages and grips.
Check the allowance of PC wire from anchorage.
Check posttensioning ducts by pushing the PC wire back and forth.
Establish marking points at girder ends and midspan, using a leveling instrument for the measurement of
camber. (See Fig. 1)
Check actual length of girder.
Manpower schedule
Operator 1 @ each side
2
PT Technician
1
PT Engineer
1
Jack Tender
4
Check electric source of pump and do test runs.
Check tendon numbers for the order of tensioning.
Coordination of signal for simultaneous/synchronized pump execution.
To prevent overturning of girder during stressing, lateral bracing should be provided.
Axial center of jack and anchorage shall be properly observed.
Check the PT control graph thru computation sheet, especially Ep, , l(2) and l(3).

II. During PT
1. Initial force introduction
This shall be 5 MPa at both ends simultaneously.
2.

Mark reference point for elongation measurement


This shall be 20 cm reckoned from the push metal at both ends of the PC wire.

3.

Gradual force introduction and reading the corresponding elongation


Gradually increased the pressure 5 MPa per step, and plot the elongation corresponding to the pressure.
The elongation shall be read by subtracting 20 cm at both ends of PC wire.

4.

Zero adjustment
Hold the tensioning execution at 50% of the desired final force and connect the points in the graph and
slide the line parallel to the origin then project a line to the final force limit.

5.

Determination of actual plotted line


Determine whether actual plotted line is within the pre-computed envelope of the control graph.
a.) If elongation at both sides is nearly equal, proceed with stressing the 50% remaining required
force.
b.) If one of the elongations is more than two (2) times with the other, counter
should be applied.
i)

Give instruction to pump operator to synchronized stressing.

measures below

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

ii) Then increase 5 MPa pressure and observe the effect. If the same situation exists,
inclination of elongation has occurred. Stop stressing operation and release pressure
without wedging. Check the PC tendons for obstruction like concrete inside the duct.
If it is okay repeat the procedures 1-5. If the duct is clogged, this girder maybe
abandoned as per decision of an authorized engineer.
c.) If line is within the limit, proceed with stressing the 50% remaining required force as per
procedure 3.
d.) If the line is out of the limit, stop the operation and detach the jack. Reset the jack and repeat
procedure 1-5.
e.) If repeated procedure resulted the same as 5-d, proceed to find the cause, the following counter
measure steps shall be followed.
Step 1. Check jack and pump
a.) Pump might have unknowingly encountered accident during shipment.
b.) Pump might lack hydraulic fluids. If the mentioned conditions are observed, do
subsequent actions, repair pump or jack and recalibrate.
Step 2. If the jack and pump are normal, proceed to the following cases.
Case I: Elongation is lesser than computed
a.) If the elongation is little bit far from the upper limit, proceed to the next
procedure.
b.) If the elongation is extra-ordinary or negligible to measure, abandon the procedure
by releasing pressure without wedging.
Check duct for some obstructions.
c.) If Case I-1 is frequently observed to other tendons, check Ep & . Re-computation
may be necessary using different value of Ep and .
Ep can be change to present value than the present one. Confirm if actual
elongation is within the adjusted control graph.
Case II: Elongation is greater than computed
a.) If the elongation is little far from the lower limit, proceed to the next procedure.
b.) If the elongation is extra-ordinary abandon the procedure by releasing pressure
without wedging.
Check grips, some wedges may have slip or grips are not properly installed.
PC wire might have low Ep value. Change the whole set if necessary.
Never attempt to proceed the stressing with a low Ep PC wire to avoid
understress.
c.) If Case II-1 is frequently observed to other tendons, check Ep & . Recomputation may be necessary using different value of Ep and .
Ep can be changed to a lower value than the present one up to Ep=1.9x10 6 kg/cm2.
(186.2x103 MPa) If adjusted Ep is lower than the above mentioned value, the
authorized Engineer can decide if the tendon will be used or rejected.

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

NOTE:
Generally 10% tolerance of computed limit is considered. In any case, if the above-mentioned is
observed, PC wire materials may be substandard. Replacement of the materials with new sets may
be recommendable.
To emphasize above, Allowable Control Limit comparison shall be presented below.
Example:
Table I. Allowable Control Limit Comparison for Elongation

TENDON
C1
ELONGATION
CONTROL
LIMIT

LIMIT
UPPER LIMIT
LOWER LIMIT
LIMIT RANGE

ELONGATION
& PRESSURE
METHOD
222
182
40

FRICTION
COEFFICIENT
METHOD
201
181
20

VARIANCE
+21
+1
+20

NOTE:
Pressure elongation method is more tolerable compared to Friction coefficient.
6.

Pre-final tension
The authorized Engineer decides the pre-final tension value if the plotted actual line is within the limit
line.

7.

Measurement of camber
Camber usually occurs when PT force is more than the dead weight of the girder. The last cable to be
stressed will determine the required camber. Now at pre-final tension, the camber shall be measured and
then proceed as follows:
Step 1. If the camber is near to the designed one, pre-final tension shall represent for the final
tension value. Then proceed to next step.
Step 2. If the camber is far from the designed one, pre-final tension shall be increased in order
to attain the designed camber. This is subject to the decision of the authorized Engineer.
c = (c el) + (c er) = c (el + er)

8.

Locking the PC tendons


After determination of the final tension value, the tendons are wedged permanently.

9.

Release of tension
After wedging, the tension shall be released up to 5 MPa.

10. Measurement of pull-in


After releasing the tension, PC wire will be pulled into anchorage slightly. This is called pull-in.

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

Actual pull-in shall be measured as follows:


Actual pull-in, la = (l ) L + (l ) R
Where:
l = reading of elongation before wedging
l = reading of elongation after wedging and decreasing the
pressure to 5 MPa.
( )L, ( )R = left and right side elongation reading
Measure the actual pull-in, and take actions as follows:
a.) Actual pull-in < the computed pull-in.
Post-tensioning is greatly successful.
b.) Actual pull-in is *6mm < the computed pull-in.
Post-tensioning is acceptable.
c.) Actual pull-in is *6mm > the computed pull-in.
Post-tensioning on this particular cable is under-stressed. Correction value stress shall be
computed or graphically shown. Actual pull-in shall include the shortening of PC tendons from
tip of the push metal to reference marking point.
*6mm = This is called as the Standard Tolerance Error Reading (STER)
Actual Tolerance Error Reading (ATER) shall be computed as follows:
ATER = [P l/AE] x 2 ends
Where:
P = applied stress
l = length of cable inside the jack from back face of the anchor
block to back of the jack
E = Youngs modulus of PC tendon
A = sectional area of PC tendon
Example:
ATER = [Pl/AE] x 2
= [(570kg/cm2 x 300cm2 x 352mm)/(1184.5mm2 x 19,775.74 kg/mm2)] 2
= 5.14 mm

The formula below shall be applied for the Adjustment of Tensile Stress
(ATS) to next girder.
ATS = [(la lc) (m)]/l
Where:

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

l = actual total elongation (mm)


lc = computed pull-in (mm)
la = actual pull-in (mm)
Example:
a.) By computation

DESCRIPTION

Table 2. Tensioning Data


SYMBOL

Friction Coefficient
Tensile Stress
Total Elongation
Computed pull-in
Actual pull-in

m
l
lc
la

VALUE
0.30
560
186
20
22

ATS = [(la lc) (m)]/l


= [(22 20) (560 kg/cm2)] / 186 mm
= 6.02 kg/cm2
b.) By graphical
Actual pull-in shall follow the Actual Stress-Elongation straight line. Therefore ATS can be
determined by equivalent value of l = -2mm
on the actual graph. ATS = 6.02
ATER = [Pl/AE] x 2
= [(570kg/cm2 x 300cm2 x 352mm)/(1184.5mm2 x 19,775.74 kg/mm2)] 2
= 5.14 mm

11. Individual cable posttensioning shall not be the absolute value of post tension to be considered. It should
consider the sum or the total post tension force introduced.
Adjustment of pull-in losses of slips shall be minimal on the last cable since this cable path is not the
centerline of girder.
III. After PT
1.

Length
Check the total length of PC girder.

2.

Camber
Check the final camber of the PC girder at midspan.

3.

Control graph
Fill-up the necessary data in the control graph and get the signature of the
authorized Engineer.

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

4.

Pre-Stressing Systems Consultancy

PC tendon
Cutting shall not be less than 30 mm from the anchor head. Disc type cut-off machine shall be used.

5.

Temporary stocking
Until grouting shall be made, the duct should be free from any water.

6.

Packing
After cutting of PC tendon, packing of the anchor block with cement mortar
is done.

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

POST-TENSIONED GIRDER
GROUTING METHODOLOGY

PC GROUT BASIC INFORMATION


1. Standard Specifications:

Japan Society of Civil Engineering Standard Specifications

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

2. Cement:
3. Admixture:
4. Grout Pump:
5. Grout Mixer:

Pre-Stressing Systems Consultancy

Portland Cement
Sika Intraplast Z
Bulgar Eden YM-90
Locally made

GROUTING
Post-tensioned steel shall be bonded to the concrete by grouting a soon as possible after stressing unless
noted otherwise on the drawings when, in the opinion of the Consultant, such grouting is impracticable, the
grouting shall take place as soon as is practicable and in any case not later than 28 days after stressing of the
tendons in any cable duct is completed. All pre-stressing reinforcement enclosures and ducts shall be free of dirt,
loose rust, grease, and other deleterious substances, the ducts shall be flushed out with clean water and compressed
air first. Grout shall be placed within 45 minutes of mixing. Grout shall be placed under pressure of at least 7.0
kg/cm2 or 100 psi, the injection shall be continuous and include a system for re-circulating the route if actual
grouting is not in progress.
GROUTING PROCEDURE
1. Quality Assurance (See details of Quality Test Measurements)
a.)
b.)
c.)
d.)
e.)

Choice of admixture
Preparation of design mix
Execution of trial mix
Conducting quality test
Required quantity computation

2. Preparation for Grouting Operation


a.) Installation of Grout Hose for Inlet and Discharge Outlet
Prior to pouring concrete into the girder, grout hose shall be inserted into the grout hose coupler at both
end joint sheaths.
Grout hose shall be of type with meshing reinforcement and can withstand 7kg/cm2 pressure.
Polyethylene hose is not advisable to avoid cracking or bursting of hose due to pressure.
b.) Covering of Anchorage
After pouring of concrete, anchorage portion shall be covered with vinyl sheet until grouting shall start
to prevent entry of water and dust into the anchorage.
c.) Installation of Exhaust Hose for Emitting Air
Hose shall be inserted into the hole of male cone prior to sealing. Hose with meshing reinforcement shall
be used. Polyethylene hose is not advisable.
d.) Sealing of the Block-out of Anchorages
Anchorage at girder ends shall be sealed with cement mortar to prevent leaking of grouting materials
during grouting.
e.) Flushing and Removal of Cleaning Water in the Duct
Enough cleaning water shall be provided to be able to flush clean the 3 ducts. Flushing of ducts with
clean water shall be done to remove dirt, loose rust, grease, and other deleterious substances which may

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

cause clogging and to determine whether the duct is not clogged. After flushing, remaining water shall
be removed by introduction of compressed air.
f.) Sieving of Cement
Prior to mixing the grout, cement shall be sieved thru 1.2 mm sieve, so that weathered cement can be
removed. Cement shall be kept in cool dry place.
g.) Grouting Scheme
Position of mixing plant shall be determined considering the site condition. Capacity of mixer and pump
shall be carefully studied for smooth grouting operation.
3. Grouting Operation
a.) Mixing Order
Mixing order shall be strictly followed as mentioned below:
1.
2.
3.
4.

Pour all the water first.


Gradually pour the cement.
Pour the admixture. See to it that the exact amount of admixture is poured.
Mix the mixture for about 3 minutes with covering lid to avoid spilling of grout mixture.

b.) Grouting Pump Gauge Pressure


The standard pumping pressure is 2-3 kg/cm2. This figure is dependent on the length and diameter of the
hose, conditions of bends and duct to void area.
c.) Observation of Grout
While grouting, normal grouting can be observed by submerging discharged hose into the water in a
small pail. If the air does not come out even if the pressure is increased, duct may be clogged and a
counter measure shall be followed. As the grout comes out at the discharge hose, the density of the grout
should be confirmed if it is the same consistency as the one inside the grout mixer.
d.) Increasing of Pressure
After confirmation of the grout, the discharge hose shall be folded and tied with a tie wire. The pressure
is then added about 5.0 kg/cm2 for a short while. After the ducts are filled the pouring hose shall be
folded and tied with tie wire.
e.) PC Grout Quality Control
Quality control form shall be recorded before, during, and after grouting.
f.) Countermeasure in Case of Clogging Trouble
Countermeasure shall be established before grouting. Clogging is the major trouble during grouting,
therefore a flowchart to solve this problem is provided. See Table 4.
g.) Test Sampling
The sample mould is a cylinder type with dimensions of 5.0 cm diameter and 10.0 cm height.
4. After Grouting Operation

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

a.) Cleaning of Grout Pump and Mixer


Immediately after grouting, mixer and pump shall be washed and cleaned thoroughly.
b.) Cleaning of Girder and Substructure
Upon after grouting, girder shall be washed immediately so that color of grout can be removed to avoid
staining with dirt.
c.) Treatment of Grout Hose
After cutting of grout hose, no treatment is needed if the portion where the hose is placed is covered
with concrete later, otherwise that portion shall be chipped about 3.0 cm deep and sealed with epoxy
mortar.
d.) Curing
Unless otherwise specified, grout shall have a minimum compressive strength of 14 MPa at 28 days.
5. Quality Test Measurement
a.) Choice of Admixture
Cement grout composed of water and cement, will shrink due to evaporation of water and bleeding. To
control shrinkage and bleeding, an admixture should be added. Sika Intraplast Z is recommended.
b.) Preparation of Design Mix
Figures in the table below shall be required to qualify the pc grout.

CONSISTENCY
(seconds)
15.0 to 30.0

TABLE 5. STANDARD SPECIFICATION FOR PC GROUT


EXPANSION
CHLORIDE
BLEEDING
W/C
(%)
(kg/m3)
(%)
(%)
LESS 10.0

LESS 0.30

LESS 3.0

LESS 45.0

COMP. ST
(kg/cm2)
OVER 200

Table below represents standard design mix using premix type admixture.
TABLE 6. STANDARD DESIGN MIX
W/C RATIO
WATER
CEMENT
ADMIXTURE
(%)
(kg)
(kg)
FG-10* (kg)
44.0

17.6

40.0

0.40

* in Japan, this is
known as GF630

c.) Execution of Trial Mix


Mixing shall be water first, then cement is added gradually and then the admixture. Mix the mixture for
about 3.0 minutes.
d.) Conducting Quality Test
1.

Consistency Test
This test shall be complied with JA funnel Method of JSCE-1986 PC Grout Test. (See Fig. 3)
a.) Funnel shall be supported by funnel supporter.

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products
b.)
c.)
d.)
e.)
f.)

Pre-Stressing Systems Consultancy

The inside of the JA funnel shall be wetted.


After pouring of grout, discharge a little amount of grout and shut it with the finger.
Pour the grout up to the top and level it.
Remove the finger and let grout flow until the time when it stops the continuous flow.
Measure the time above. This time represents the magnitude of consistency.

After the testing, the grout which remained inside the JA funnel is considered unsuitable.
2.

Bleeding Test

3.

Expansion Test

4.

Compressive Strength Test

e.) Required Material Quantity Computation


SAMPLE COMPUTATION:
1. DESIGN CRITERIA
Materials to be used

Water, Portland cement, Sika Intraplast Z

Water Cement Ratio

44%

Admixture

2% of Cement Weight

2. DESIGN MIX
The materials which are needed for 1 m3 of grout shall be computed by the equation below:
1000 = W + C + A
w
c
a
where:
W = Weight of Water
C = Weight of Cement
A = Weight of Admixture
= Specific Gravity of Materials
Since admixture is negligible in quantity compared to water and cement, this shall be neglected:

1000 = W + C
w
c
w = 1.00
c = 3.15
1000 = _W_
1.00
1000 = W

_C_
3.15

0.317 C

With water to cement ratio, W/C = 0.44

TOYO-TOBISHIMA JOINT VENTURE


Pre-stressed Concrete Products

Pre-Stressing Systems Consultancy

1000 = 0.44 C + 0.317 C


1000 = 0.757 C
Therefore:

MIXTURE
VOLUME

C = 1321.0 kg (Cement)
W = 581.2 kg (Water)
A=
26.4 kg (Sika Intraplast Z)

W/C RATIO
(%)

WATER
(kg)

CEMENT
(kg)

Sika Intraplast Z
(kg)

Per 1.00 m3

44

581.2

1321.0

26.4

Per 1 batch

44

22.0

50.0

1.0

Das könnte Ihnen auch gefallen