PAGE: 1 of 5
PROVISION OF PROCUREMENT,
FABRICATION, CONSTRUCTION AND
COMMISIONING FOR CDU2/VDU HEAT
RECOVERY (PINCH) PROJECT (PN210062)
Doc No:
PPMSB/210062/JM
S/E
Revision: 01
PAGE: 2 of 5
CONTRACTOR
Rev.
No
Date
Prepared by
Review by
17/10/2016
Mohd
Hanim Abas
M Fadzil
Norrawai
OWNER
Reviewed by
Endorsed by
Approved by
Table of Contents
PAGE
1.0
PURPOSE
2.0
SCOPE OF WORK
3.0
4.0
PROVISION OF PROCUREMENT,
FABRICATION, CONSTRUCTION AND
COMMISIONING FOR CDU2/VDU HEAT
RECOVERY (PINCH) PROJECT (PN210062)
Doc No:
PPMSB/210062/JM
S/E
Revision: 01
PAGE: 3 of 5
1.0 PURPOSE
The purpose of this procedure is to explain and describe detail of cable testing work for electrical
cable for Provision of Procurement, Fabrication, Construction and Commissioning For CDU2/VDU
Heat Recovery (Pinch) Project.
All cable shall be test in accordance with the Petronas Technical Standard (PTS 13.02.01) and
approved engineering drawing.
ii.
All workers shall undergo a safety briefing conducted by PPMSB. Attendance is compulsory.
Without this briefing, the worker shall be denied from entering or working in PPMSB plant
area.
iii.
All workers are mandatory to used basic personal protective equipment (PPE), which includes
safety helmet (yellow color), coverall, safety glasses, safety shoes and others will be follow
according to PTW requirement.
iv.
All equipments machineries and tools entering PPMSB premises shall be inspected prior start
work by PPMSB as part of PPMSB safety control measure.
PROVISION OF PROCUREMENT,
FABRICATION, CONSTRUCTION AND
COMMISIONING FOR CDU2/VDU HEAT
RECOVERY (PINCH) PROJECT (PN210062)
Doc No:
PPMSB/210062/JM
S/E
Revision: 01
PAGE: 4 of 5
v.
All electrical tools such as multimeter, insulation tester, etc shall be inspected by PPMSB
Electrical Department.
vi.
Dominant to prepare the Job Hazard Analysis with reference to the Job Method Statement.
JHA discussion session will be done with PPMSB for ensuring work possible safety hazard
identified and every corrective action implemented prior to commencing WORK.
vii.
All site WORK shall commence after prior authorization from PPMSB via Permit to Work
(PTW) system. PTW shall be submitted a day before start works.
viii.
ix.
Install hard barricade and warning signage at working area where applicable.
i) Insulation tests shall be carried out for cables during pre-commissioning as well before its
energisation.
ii) IR tests shall be conducted by applying a d.c. voltage from an insulation tester to the cable at
recommended voltage level given in Appendix 3 as attached.
a)
PROVISION OF PROCUREMENT,
FABRICATION, CONSTRUCTION AND
COMMISIONING FOR CDU2/VDU HEAT
RECOVERY (PINCH) PROJECT (PN210062)
Doc No:
PPMSB/210062/JM
S/E
Revision: 01
b)
PAGE: 5 of 5
.
iii) The minimum acceptable insulation resistance values are given in Appendix 4 as attached.
iv) The test should be done at two stages of work as below:
c)
d)
v) The IR test should done with presence and witneses by the client.
vi) Record the result into Form E21 & E22 (where applicable) as attached