Beruflich Dokumente
Kultur Dokumente
Procedure For
Installation of Instrument Cables
EPCMD-2-QM00-JEP-CI-003
01
25.06.2013
ALJ / PPP
00
05.06.2012
ALJ / PPP
Rev
Date
Revision
Prepared
By
SD / Karl
KSS/EMK/
SD (Inst.)
Checked
By
SNS
SNS
Approved
By
Reliance
Contents
1. Purpose 3
2. Scope 3
3. References 3
4. Abbreviations and Terms 3
5. Responsibilities .3
6. Methodology 3
7. Attachments ..5
EPCMD-2-QM00-JEP-CI-003, Rev.01
Confidential Reliance. All rights reserved
Page 2 of 5
Reliance
1.
Purpose
The purpose of this procedure is to define the inspection testing method and
criteria for installation of instrument cables to achieve mechanical completion.
2.
Scope
This procedure covers the inspection and test procedure pertaining to the
installation of instrument cables.
3.
References
4.
5.
Safety Requirements
HOD
Head of Department
DCC
OTDR
OFC
Responsibilities
6.
Methodology
6.1
General Requirements
6.1.1
6.1.2
6.1.3
EPCMD-2-QM00-JEP-CI-003, Rev.01
Confidential Reliance. All rights reserved
Page 3 of 5
Reliance
6.2
Material Inspection
6.2.1
Prior to removal to site, cable drum shall be inspected for mechanical damage.
If damage is observed, then damage report to be prepared and stores to take
necessary action for replacement.
6.2.2
Damage report for cable found in twisted condition to be prepared and stores
to take necessary action for replacement. Twisted cable shall not be laid.
6.2.3
6.3
Pre-Installation Test
6.3.1
Cables shall be tested (Belled) on the cable drums prior to removal to the work
site.
6.3.2
b.
The insulation resistance between cores and between individual cores and
screen or armoring as applicable shall be checked.
c.
d.
After completion of the tests the ends of the cable shall be sealed to
prevent the ingress of moisture.
6.4
Installation
6.4.1
6.4.2
Where cable drum schedules are available, the Site Instrument Engineer shall
ensure that the individual cable lengths are taken from the designated drum.
6.4.3
Throughout the cable pulling process the Site Instrument Engineer shall ensure
that undue stress is not applied to the cable. Where a cable winch is used, the
manufacturers permissible pulling tension values will be adhered to.
6.4.4
Where instrument signal cables are run in parallel with power carrying cables,
above or below ground, segregation shall be maintained in accordance with the
specification and drawings. In case of deviation SER approval shall be taken
from engineering.
EPCMD-2-QM00-JEP-CI-003, Rev.01
Confidential Reliance. All rights reserved
Page 4 of 5
Reliance
6.4.5
Where instrument cables cross power carrying cables, they shall be arranged
to do so at right angles. A Separation to be provided as per drawing or
engineering resolution.
Where signal cables pass under roads or under
trenches for electric cables or other services, the signal cables shall be laid in
pipe sleeves of 100 - 150 mm diameter or in a concrete duct.
6.4.6
Where instrument and power carrying non-electrical cables are run in the same
trench, the run shall be inspected to ensure separation is by positive means.
6.4.7
6.4.8
6.4.9
Fiber optic and coaxial cables shall be installed in accordance with supplier
recommendation, giving attention to termination, jointing, supporting and
clamping. OTDR shall be carry out before and after OFC laying.
6.4.10
Inside control rooms only system cables shall run inside cable trays.
cables shall run directly on the floor.
6.4.11
6.5
Testing
6.5.1
6.5.2
6.5.3
For all activities, relevant Inspection and Test Plan shall be followed and signed
copies shall be maintained.
7.
Attachments
Nil
EPCMD-2-QM00-JEP-CI-003, Rev.01
Confidential Reliance. All rights reserved
Page 5 of 5
Other