Programme
Sub-Prog/Project
Prog. Director
Sub Prog/Proj Mgr
Author
Version Date
PACS
National Prog
K Prangley
D Jennings
28/6/04
NPFIT
Version No
Status
DOCUMENT NUMBER
Org
Prog/Proj
Doc
PAC
GEN
PI
V0.03
Final
Seq
0001
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Amendment History:
Version
V0.1
V0.2
Date
22/3/04
16/04/04
V0.3
01/06/04
Amendment History
First draft for comment
Updated version with information from PACSnet
and initial comments from NPfIT PACS
Facilitators
Updated version following comments from
formal Quality Review
Reviewers:
This document must be reviewed by the following.
Name
Signature
Title
Date of Issue
Version
Date of Issue
Version
Approvals:
This document requires the following approvals.
Name
Signature
Title
Document Location
This document is only valid on the day it was printed.
Controller for location details or printing problems.
Page 2 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Related Documents.
These documents will provide additional information.
Ref no
1
Title
Glossary of Terms Consolidated.doc
Version
Latest
Glossary of Terms.
List any new terms created in this document. Mail the librarian to have these included in the
master glossary above [1].
Term
Acronym
Definition
Page 3 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Contents
PACS Practical Experiences..................................................................................................... 1
1.
Introduction.................................................................................................................... 6
1.1
Terms of Reference and Scope..................................................................................6
1.2
Audience..................................................................................................................... 6
1.3
Acknowledgement...................................................................................................... 6
1.4
National Programme for IT.........................................................................................6
1.5
An Introduction to PACS.............................................................................................7
2.
Road Map / Summary.................................................................................................... 7
3.
Lessons Learnt............................................................................................................... 8
3.1
Supplier Management.................................................................................................8
3.2
Executive and Clinical Commitmant...........................................................................8
3.3
Planning...................................................................................................................... 8
3.3.1
Standardisation of numbering and exam codes.................................................9
3.3.2
Migration of Data................................................................................................ 9
3.3.3
Reports and Outputs.......................................................................................... 9
Typical Queries....................................................................................................................... 10
5.
Project Planning........................................................................................................... 11
6.
Review Current Policies, Procedures and Working Practices.......................................11
6.1
Process Change and use of the Modernisation Agency............................................11
7.
System Testing............................................................................................................. 11
8.
Training Guidelines...................................................................................................... 12
9.
Technical and Interfaces............................................................................................... 13
10
Communication............................................................................................................ 13
11
Staffing during Implementation.....................................................................................13
12
Ongoing System Management.....................................................................................14
12.1 Maintenance of System / Database..........................................................................15
12.2 Looking after the Internal Users................................................................................15
12.3 Service Provision for External Users........................................................................15
13.
Supporting the Paperless Environment........................................................................16
14.
Identifying Potential Benefits........................................................................................ 16
15.
Go-Live Period............................................................................................................. 16
16.
Measuring Benefits / Post Implementation Review......................................................17
17.
Business Case Support See Appendix F...................................................................18
A Appendix A Film Digitisers............................................................................................ 19
A.1
Film Digitisers.......................................................................................................... 19
A.1.1
Camera............................................................................................................. 19
A.1.2
CCD (Charge-Coupled Device)........................................................................19
A.1.3
Laser................................................................................................................ 19
A.2
Digitiser Quality Control............................................................................................ 19
B Appendix B Project Planning........................................................................................ 21
B.1
An Example Summary of the rationale behind planning...........................................21
B.2
An Example of Supplier Commitment to Project Management.................................21
B.3 Example Project Plan.................................................................................................... 22
B.4
Example Multi Site Plan............................................................................................ 23
B.4.1
Example 1........................................................................................................ 23
B.4.2
Example 2........................................................................................................ 24
B.5
An Example of a PACS Implementation Reporting Structure....................................25
C Appendix C Technical and Interfaces............................................................................26
C.1
Networking................................................................................................................ 26
C.2
Communication Standards.......................................................................................26
C.2.1
DICOM (Digital Imaging and Communications in Medicine).............................26
C.2.2
IHE (Integrating the Healthcare Enterprise)......................................................26
C.2.3
HL7................................................................................................................... 26
C.3
Interfaces.................................................................................................................. 27
C.4
Digital Image............................................................................................................. 27
C.4.1
Digital Image Capture.......................................................................................27
C.4.2
Acquisition of Digital Data on to the PACS.......................................................28
C.4.3
The Database Server and DICOM Gateway....................................................28
C.4.4
Digital image display......................................................................................... 29
C.4.5
Digital image storage........................................................................................ 29
C.4.5.1
Networked Storage...............................................................................30
C.4.6
Film printers...................................................................................................... 31
PACS Practical Experiences
Page 4 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
C.5
Monitors.................................................................................................................... 32
C.5.1
Image Quality................................................................................................... 32
C.5.2
Displays............................................................................................................ 32
C.5.2.1
Quality Assurance of Display Devices..................................................33
C.6
Web Browsers.......................................................................................................... 34
D.1
Radiologist Office and Reporting Areas....................................................................35
D.2
Radiographer Zone................................................................................................... 36
D.3
PACS Computer Room............................................................................................. 36
E.1
An example of: How has the deployment of the PACS improved services'..............40
F.1
Introduction............................................................................................................... 42
F.2
The Business Case Templates.................................................................................43
F.2.1
Strategic Case.................................................................................................. 43
F.2.2
Economic Case................................................................................................ 43
F.2.3
Commercial Case............................................................................................. 43
F.2.4
Financial Case.................................................................................................. 43
F.2.5
Management Case........................................................................................... 43
F.3
The Toolkit................................................................................................................ 43
F.4
The Workshops......................................................................................................... 43
F.5
Summary.................................................................................................................. 44
Page 5 of 45
1.
Introduction
1.1
NPFIT-PRI-GMP-PI-0001 0.2
16-April 2004 Draft
This document discusses and outlines tasks, considerations, resources and aspects of
preparing to and implementing a Picture Archiving and Communications System (PACS) will
assist when the implementation of new systems or the expansion of current systems are
being considered.
It is intended to be a living document and will be updated by the NPfIT PACS Team as
lessons are learnt and processes develop. The intention is that implementation information
across the NHS can be collated into one document to increase knowledge utilising the
experience of others.
A Picture Archiving and Communications System (PACS) typically comprises data storage
devices, image display devices, database management software and links to image and/or
image data acquisition devices, connected by computer networks. There will be network
connections to other information systems such as the Hospital Information System (HIS),
Patient Administration System (PAS) and the Radiology Information System (RIS).
1.2
Audience
This document covers a wide range of areas and will be useful to Chief Executives, Chief
Information Officers, Directorate and Clinical Managers, Clinical practitioners, IT Teams and
the PACS Implementation Team.
1.3
Acknowledgement
This document has been completed based on the experiences of clinicians and IT personnel
who have undertaken PACS implementations in the past, or who have specific PACS
expertise, such as PACSnet. We acknowledge their help and thank them for taking the time
and effort they gave in supporting us to create this document.
1.4
The National Programme for Information Technology (NPfIT) is one of the worlds largest IT
programmes. To achieve this, the programme plans to ensure that the right information is in
the right place and at the right time. It supports the vision of the NHS Plan by modernising
information systems across the NHS in England. The programme aims to improve the
convenience and quality of care for users and providers of healthcare within the National
Health Service in England.
To take advantage of the possibilities offered by the National Programme, it is expected that
working practices will change.
There are four key elements to the National Programme. These are:
NCRS is the core component of the NPfIT and will completely change the way patient
information is collected, stored, communicated and used. It will provide clinicians across care
professions and organisational boundaries with access to integrated services that are based
around the patient. PACS images may be distributed by the network, but most of the
information will be about PACS images e.g. reports and the location of PACS images rather
that the images themselves. Most of the interaction is with the RIS.
1.5
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
An Introduction to PACS
The investment in PACS will support the Governments vision for filmless diagnostic services.
Advances in digital technologies, particularly in the fields of computing, imaging and in
communication, have progressed to the point that it is now possible to acquire medical
images in digital form, archive them on computer systems, and display them in diagnostic
quality. The display monitor used to present the images can be at an adjacent or distant
location to the original point of acquisition. Indeed, there can be multiple monitors at multiple
locations, since once the master image file has been archived; it is only ever a copy of the
data that is transmitted for display.
The benefits of PACS are well documented and a table of benefits is included as an appendix
to this document.
Several standards have proved themselves useful in implementing a PACS, notably Digital
Imaging and Communications in Medicine (DICOM) and Health Level 7 (HL7). In a typical
radiology department, it is likely that a large number of steps are performed in the sequence
of events from the time that the patient is first registered in the department to the time that the
clinical report is issued. The required sequence is likely to be a process that has evolved over
many years, and it may no longer be the optimal process for a modern radiology department.
Installation of a PACS gives the opportunity to re-evaluate the workflow within the radiology
department. Rather than merely mimicking an existing, paper-based, system, a carefully
planned PACS implementation can encourage improved workflow, i.e. the more efficient flow
of information, images and patients through the department.
2.
As all trusts will be starting the process from a different point the following Road Map is a
guideline.
Identify Need for PACS
Review current processes and define process change (Modernisation Agency involvement)
Select Supplier/ System in conjunction with LSP including the process by which this happens
Implementation
On going maintenance / support
Page 7 of 45
3.
Lessons Learnt
3.1
Supplier Management
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Implementation is a joint task that involves a coordinated team effort. The suppliers are
experienced in the implementation of the PACS solution, but the NHS has the expertise of
business processes within the domain. It is in working together in one team utilising the skills
available that creates successful outcomes.
Working with the suppliers is not just an implementation activity, but also an on going
relationship through the provision of support over the life of the service contract.
3.2
Executive commitment is imperative for the success of the project, the CEO and board should
be fully briefed on the progress of the project. Finance and IT should also be represented on
the project board.
It is important to recognise that PACS is a clinical system that will be widely used and should
be managed as a clinical project with IT support. Clinical commitment and support to the
project from its conception is vital so that there is acceptance and ownership throughout the
clinical setting.
PACS is not solely a Radiology tool and will be utilised by many clinicians across the PACS
arena, a clinical champion within radiology and at least one from another department will help
the project.
Having clinicians involved in the decision making and the project significantly helps the
adoption of the system and supporting processes.
3.3
Planning
A network survey must be done, the bandwidth of both backbone and branches must
be assessed and any upgrading work undertaken. Advice on minimum network
requirements should be obtained from the PACS supplier. They may also be helpful
during the network survey process.
Ensure the Radiology Information system (RIS) can meet the requirements of a PACS
installation and address this as an urgent priority. Have a clear view as to how non
radiological (potentially non RIS entered studies) images will be incorporated into the
system.
A unique patient identifying number is vital to a Trust and Community wide PACS
system, e.g. NHS number or Hospital Registration number.
What needs replacing? For non DICOM equipment that will not be replaced how can
the images be sent to PACS? (You may need to provide space to accommodate an
image gateway computer and desk and network point and power socket)
Page 8 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Scan on demand where the PACS is introduced and from that point on film-based
patient records are scanned when a patient enters active care within a Trust.
Planned migration where the digitisation of images is started (using the active
records approach above) in advance of PACS being introduced, use a local RAID
store to create an initial archive.
Target group migration where groups of patient records (for example cancer
patients, children, etc) are scanned en masse into a PACS store.
Full migration where films are scanned in to a PACS store in large quantities.
The PACS NPfIT Team would be happy to discuss the various models with you, and share the
pros and cons of the approaches. Appendix A contains information on aspects of film
digitisers.
Page 9 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Typical Queries
The suppliers should provide answers to these questions and others appropriate to local
needs. If advice is sought or concerns raised these should be directed to NPfIT
Implementation Advisors throughout the Implementation phase.
What support will there be from the supplier at go live and for how long?
of training manual
Automatic upgrades
Local requests
Statutory requirements
Page 10 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Are there sufficient viewing workstations for imaging staff to view previous soft copy
images prior to X-ray? This can be done by record checking, in individual cases it
may be necessary to view the previous images.
5.
Project Planning
6.
6.1
The Radiology service improvement team (Associate Director, 4 National Managers and 4
National Clinical Leads) are part of the Modernisation Agency. Their role is to provide
expertise and advice on service improvement to clinical teams, Trusts and SHAs.
The National Framework for Radiology Service Improvement (July 2003) was developed in
partnership with the MA, DH and Professional bodies to ensure an integrated approach to
Radiology service improvement. It promotes a clinically lead approach which ensures all
aspects of Radiology Modernisation are aligned, including - Changes in workforce;
Equipment; Education; and IT strategies which includes PACS.
To support the above framework a Radiology Service Improvement toolkit is available. This
aims to provide a basis for multidisciplinary redesign, based on proven service improvement
methodology and learning from a number of pilot sites.
The National teams can provide support to any clinical team to ensure that service
improvement is integrated across the whole systems of care including the service redesign
opportunities that can be delivered as part of the implementation of PACS.
7.
System Testing
During implementation prepare some testing scenarios for the system, take them from real life
and test a combination of input events, ensure that the outputs are as expected.
e.g. Check:
Page 11 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Attempt to enter invalid data e.g. a name in a date field and evaluate the outcome.
Examinations are retrieved and images displayed within the required time
The supplier should be able to provide example test scripts, but you will need to adapt them
for local use and test your working practices as well as test the system. This could be a safe
test environment on your installed system.
Enquire of the supplier as to the availability of a test system environment. It may be possible
to perform tests on equivalent hardware and software prior to installation on site, or to carry
out the tests on a partitioned area of the system after installation. A test environment can be
a duplicate database on the installed system; it need not be a separate installation.
8.
Training Guidelines
Disparate groups of staff will require training to different levels. Level of access will depend on
the role of the individual across the Trust. Discussion with the supplier will help formulate the
training strategy.
Determine how many trainers are available and the number of available areas to train people.
Training ideally should happen as close to the go live as possible; to ensure staff retain the
information, and ideally a maximum of 8 trainees at a time, and 2 trainers should attend each
session.
Then take each group of staff and decide the length of time their training will take.
It is usually possible to do group training for most staff members, workload permitting, this
may require 1 to 1 sessions for consultant and more senior staff.
Ensure that the composition of the groups is carefully considered as the training session
should be relevant for the entire group, e.g. dont try to train nurses and radiographers at the
same time as their use of the system will be very different.
Ensure that people sign up for sessions as a free for all drop in session often means that
people arrive late or leave early which can disrupt the group.
Develop training guidelines for the users, ensuring that these are short and to the point, large
manuals are not easily read.
Some credit card size laminated guides are useful as people can keep them in their pockets
or attach them to the terminal for easy reference.
Allow for extra sessions to train people who were unable to attend their allocated session.
Users should not be assigned a PACS account and password until they have completed a
training session satisfactorily. Schedule training sessions as part of a staff members normal
working day to ensure maximum attendance.
Have trainer and trainee evaluation forms for the sessions to ensure that there is a record of
any difficulties people may have experienced or any policy decisions that need to be followed
up from the session.
If a member of staff has had issues during the training ensure that they are offered additional
training or extra help over the go live period. PACS training should be an integral part of junior
Doctors Induction Training
Identify keen users during the sessions as they will provide good support to other staff
members in their areas.
Allow users access to a training system once they have completed their session to practise
before go-live, better to have mistakes there than in the real system.
PACS Practical Experiences
Page 12 of 45
9.
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
The Output Based Specification (OBS) for the Integrated Care Records Service (now the
National Care Records Service) and the relevant technical information in section 115 - Digital
Imaging Including Specification for a Picture Archiving and Communications System (PACS)
Solution defines technical requirements and integration standards. The OBS can be found on
the
Department
of
Health
website
at
http://www.dh.gov.uk/assetRoot/04/0716/32/04071632.pdf
In addition the Project Initiation Document (PID) for PACS also references recommendations
for networking. See OBS available on www.dh.gov.uk
There should be real time interfaces between PAS, RIS and PACS this reduces the
requirements for patient demographics to be re-entered on different systems. The RIS/PACS
interface should pass the examination details automatically to the PACS
Details on technical aspects can be found in Appendix C.
10
Communication
Ensure that all staff are aware of the PACS implementation, through news letters
and/or lunch and learn sessions, encourage people to ask questions.
Projects that involve change often cause concern to staff and in particular in a PACS
implementation there are likely to be staff changes and some relocation of resources.
Make sure that these concerns are addressed.
The following lists some observations from sites that have installed PACS:
Plan implementation meetings on quieter days or parts of the day to ensure fewer
interruptions.
When implementing a PACS there are practical considerations to be taken into account
regarding the department layout that need to be thought through as part of the project.
Service re-design should incorporate these considerations.
Involve the estates department at the beginning of the planning process for a PACS
installations to ensure appropriate use of accommodation and facilities e.g. to assist with
planning equipment moves, air conditioning.
Health and Safety issues must be considered in department redesign and documentation to
assist with this is available from the local Estates department.
When looking at these practical designs there are three main areas to focus on: Radiologist
office/Reporting area; Radiographer zone; Computer Room. The Radiologists offices and the
reporting areas may be quite separate and may have quite different requirements. Please
see Appendix D
Consider whether the implementation approach is to be Big Bang or Phased. Each have
their specific advantages. Sites should determine which approach best suits their needs
Ensure that the Trust puts in enough funds to pay for what is needed, such as networking,
allowing for contingencies that become apparent once implementation is under way.
Ensure good communication with IT colleagues to explain the true implications to all
radiography and other clinical staff. PACS does not just 'plug and play'.
11
During the implementation phase the amount and type of resource will vary depending upon
the size, phase and scope of the project. You will require multi-skilled staff with a range of
competencies.
The following table documents some suggestions for the core skills that you will be looking for
along with some of the expected key roles. The supplier should be able to provide their views
PACS Practical Experiences
Page 13 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
on the particular skills that they see as critical to a successful implementation along with the
time commitment they see as appropriate.
Personnel
Project Manager
These personnel will require advice and support from others around them (e.g. IT, Training,
Supplier, clinical groups)
When looking at the Implementation Team, consider the cluster and SHA implementation
plans. Setting up an expert PACS Implementation Team at SHA level may be beneficial as it
is very likely that implementations through a SHA will be staggered. As the system roles out
you develop a core team of expertise that works at each site, utilising local expertise, and
then as the implementation matures, this core team can evolve to also provide system
support, training and maintenance.
12
Page 14 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
the formation of the PACS Project team. They should be responsible for facilitating the
provision of the following type of services:
System maintenance
Data Integrity
QA
Trouble shooting
Specific examples of tasks undertaken by people already in this role are documented below.
12.1
Ensuring that the PACS and RIS databases are updated and synchronised as soon
as possible after the resumption of normal service.
Ensuring that correct images for the exam are contained in the relevant folder.
Ensuring that empty orders do not occur e.g. pelvis/spine images not all in pelvis.
Correct any faults sent to PACS e.g. exams marked completed in error.
Keeping accurate and timely records with regard to all aspects of system etc.
12.2
Creating protocol for input of new doctors twice yearly, and dropping leaving doctors
from the system.
Page 15 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
12.3
Managing the printing of films for other hospitals (patient transfers), controlling access
rights for those carrying out the activity.
System demonstrations.
Liaising with other hospitals and departments re any service involving PACS.
13.
The significant proportion of communications both between and within departments is still
paper based and it is recognised that this will continue. However, the long term aim should
be the move to electronic based communications.
The reduction in paper is supported by electronic order communications and results reporting,
the electronic capture of all relevant and appropriate clinical information and the overall vision
of NCRS, of which PACS is a component.
Decisions about the migration of any existing analogue archive have to be made in the light of
the Trusts PACS wider role i.e. sending and receiving data from other PACS and the NCRS.
Patient demographic data also needs to be migrated with the amount of information migrated
being at least commensurate with the image data migrated.
14.
PACS can provide many benefits, some can be financially measured but many are aspects
that improve the quality of service and patient care, and indeed some improve the work
environment and the environment as a whole.
Each site will need to identify their expected benefits as a part of their business plan as the
type and volume of benefits achievable will depend upon local variances such as service
redesign , physical geography and services provided.
See appendix E for a table of example benefits.
Appendix E also includes an example from a site where the deployment of PACS has
improved services.
15.
Go-Live Period
The go-live date needs to be part of the implementation plan. Most clinical departments will
require between 6 12 weeks confirmation notice. When choosing a go live date consider
the timing of this in relation to workload (sometimes a go live over a weekend is preferable,
but it must be ensured that support staff are available either on site or on call) or reducing
workload from all areas (e.g. clinics) for a few days in advance is advisable, if appropriate.
Notices for patients and communications to all other staff and GPs are essential to explain
that a new system is being implemented.
The supplier should provide extra go live resources during this period and likewise the site
should provide extra staff. Extra supporting documentation / crib sheets should be made
available at workstations.
During this period it is important that you have a clear process for handling questions, issues
and general support calls, often a dedicated go live log is used. Typically the Project Manager
should be responsible for the escalation and resolution of the issues, while the System
Administrators will be key in actually resolving many of them during this time. A tier system
should be defined for the escalation of issues.
PACS Practical Experiences
Page 16 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Any deviation from the go-live date should be communicated across the Trust at the earliest
opportunity.
Page 17 of 45
16.
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Executive Summary
Introduction
Benefits delivered
Business risks
Technical risks/considerations
Business satisfaction
Recommendations
A post implementation review provides the opportunity to revisit what was done, and consider
any changes to processes that may be useful.
Page 18 of 45
17.
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Page 19 of 45
A.1
Film Digitisers
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Film digitisers perform the task of taking an image stored on film and converting that image
information into a digital data file suitable for storage on a computer. This file can
subsequently be stored, manipulated, compressed, transmitted and displayed like any image
file acquired to the PACS direct from an imaging modality.
The image resolution obtained after digitising a film depends on the scanner used. The
resolution used for a particular scan may also be selectable on the scanner. The ACR
(American College of Radiology) recommends a resolution of 2.51 1p/mm, 10 bits deep for
film digitisation for primary needs (American College of Radiology Standard for Digital Image
Data Management, 1998).
Film digitisers are built using one of three different technologies.
A.1.1 Camera
Light is shone through the film being digitised, and a digital camera captures the information.
This is a low-cost solution, but it is also a low-quality solution, and digitisers built around this
technology are probably not suitable for medical imaging work.
A.1.3 Laser
A very thin beam of laser light is shone through the film; the beam is scanned across and
down the film until the whole image area is covered. The light transmitted through the film is
collected by a photomultiplier tube, which turns the light energy into electrical signal which is
then digitised. It has the advantages over CCD of producing a sharper image, and of having a
greater dynamic range, but the ultimate resolution is comparable to CCD. It is the most
expensive of the three options.
Film digitisers will typically be attached to the PACS network in a similar manner to other
acquisition devices, and images acquired from film digitisers onto the PACS should be
managed in the same way. This will include the creation of an examination on PACS to send
the image data to. One difference is that no local storage will be required, since the original
film acts as its own data store. Care should be taken to ensure that when the examinations
are displayed or listed on the PACS, the examination date is the actual date of the original
examination and not the date that the examination was digitised.
A.2
Just as traditional processors require QA, film digitisers require regular checks to ensure that
they are performing adequately.
These checks should include:
This ensures that a change in the optical density of the film from one region on the film to
another produces an appropriate change in the pixel data value stored in the image data file.
Pixel values of particular areas in the image data file can be determined using the tools
available on most PACS workstations, and the optical density of the corresponding region of
the film can be measured with a densitometer.
Page 20 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
This ensures that regions within a film - or on different films - that have the same optical
density produce equal pixel data values in the image data file. Again, pixel values in the
image data file can be determined using a PACS workstation, and the films optical density
can be measured with a densitometer.
Spatial resolution.
This is a measure of the ability of the digitiser to detect small features in an image or to
differentiate between two closely-spaced, but separate, features. A test film containing images
of suitable test objects, e.g. line-pair test tools, can be scanned and the digital image
produced can be visually inspected.
Contrast resolution.
This is a measure of the ability of the digitiser to produce a change in pixel data values for
regions in the image that are of similar, but different, optical densities. The testing method is
similar to that for the test for linearity of response, above.
Geometric distortion.
This is a test of the ability of the digitiser to create digital images which retain the proportions
of the original image. In particular, all straight lines in the original image should remain straight
when viewing an image reconstructed from the digitised image data
Page 21 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Successful installation and implementation of a PACS system relies on good preparation and
planning. Plans are constructed by identifying the products required, the activities and
appropriate resources necessary to deliver them. Keep plans relevant, be aware of the
audience for the prepared set of plans and aim to provide an appropriate level of detail for
tasks and activities.
Time must be allowed for planning because it is a time consuming exercise. Planning for the
next stage should start towards the end of the current stage.
It is easier and more accurate to plan short stages than long ones. Plans should cover all
aspects of the project, giving everyone involved a common understanding of the work ahead.
Consider the following initial steps
Decide what activities should be done and by whom, All activities should be thought
through in advance and to a consistent level
Estimate how long the activities will take and agree tolerance levels for this plan
Calculate what the overall effort will cost, produce the budget from the cost of the
effort plus any materials and equipment that must be obtained
B.1
The key areas of the project plan have been designed to:
Achieve core RIS and Modality integrations early to enable a smooth plug and play core
PACS installation.
Allow for Theatre workstations to be installed over a holiday period, so as not to disrupt
services.
Install local workstations last so as to allow a build up of the digital archive before
softcopy reporting.
Deliver temporary CR installations during enabling works to allow for continuity of service.
Allow flexibility, as once the core system and interfaces are installed the remaining PACS
roll-out phases can be easily tailored.
B.2
Supplier commitment is vital to the success of the project. However, there may be more than
one supplier involved in the PACS project and the commitment must be from all the suppliers.
The Company commits to working with the Trust to Project Manage the PACS
implementation utilising the PRINCE 2 methodology.
The Company commits to this Project Manager attending on-site project meetings.
Should the Project Manager be absent from work a suitably trained and briefed
deputy will be appointed.
Page 22 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Full details of the Company Project Manager is given and so are details of all Company
personnel involved in delivering this project.
Third parties will be managed by the Companys Project Manager via agreements made
with these companies when a purchase order is raised for their required input.
Round table meetings with these vendors will be hosted by the Company, as
required, to ensure timely delivery of resources and manage the implementation
process.
Task Name
PACS Install
Contract signed
PACS room designated
Drawings for PACS room
Proposal drawings submitted
Draft Drawings supplied
Drawings Accepted
Delivery
Delivery methodology
Deliver PACS Site A
Deliver PACS Site B
Installation
Install core components Site A
Install core components Site B
Integrate Dicom modalities
Integrate non Dicom modalities
Mirror Broker
Remove temp broker
Test web functionality
Distribute Workstations
Test workstations
Installation Accepted
Training Program
System Admin
Web core training
Radiologists training
Training Acceptance
GO LIVE
Go live support
System Acceptance
Duration
169 days?
1 day?
1 day?
20 days
2 wks
2 wks
0 days
80 days?
1 day?
16 wks
16 wks
21 days?
2 wks
1 wk
5 days
5 days
5 days
1 day?
1 day?
1 day?
1 day?
0 days
15 days
5 days
5 days
5 days
0 days
0 days
5 days
0 days
Start
Mon 12/05/03
Thu 01/01/04
Mon 12/05/03
Tue 13/05/03
Tue 13/05/03
Tue 27/05/03
Mon 09/06/03
Fri 02/01/04
Fri 02/01/04
Fri 02/01/04
Fri 02/01/04
Fri 23/04/04
Fri 23/04/04
Fri 23/04/04
Fri 07/05/04
Fri 07/05/04
Fri 14/05/04
Fri 21/05/04
Fri 14/05/04
Mon 17/05/04
Tue 18/05/04
Tue 18/05/04
Wed 19/05/04
Wed 19/05/04
Wed 26/05/04
Wed 02/06/04
Tue 08/06/04
Tue 08/06/04
Tue 08/06/04
Tue 08/06/04
Finish
Thu 01/01/04
Thu 01/01/04
Mon 12/05/03
Mon 09/06/03
Mon 26/05/03
Mon 09/06/03
Mon 09/06/03
Thu 22/04/04
Fri 02/01/04
Thu 22/04/04
Thu 22/04/04
Fri 21/05/04
Thu 06/05/04
Thu 29/04/04
Thu 13/05/04
Thu 13/05/04
Thu 20/05/04
Fri 21/05/04
Fri 14/05/04
Mon 17/05/04
Tue 18/05/04
Tue 18/05/04
Tue 08/06/04
Tue 25/05/04
Tue 01/06/04
Tue 08/06/04
Tue 08/06/04
Tue 08/06/04
Mon 14/06/04
Tue 08/06/04
Qtr 1, 2004
Jan
Feb
Mar
Qtr 2, 2004
Apr
May
Q
Jun
18/05
08/0
08/0
08/0
Page 23 of 45
B.4
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Below are two detailed project plans from multi site installations. The level of detail is greater,
note the provision of temporary imaging solutions to facilitate continuation of service.
B.4.1 Example 1
ID
1
Task Name
Phase 2 install
Duration
80 days
Start
Tue 08/06/04
May '04
Finish
Mon 27/09/04
0 days
Tue 08/06/04
Tue 08/06/04
Order CR
10 wks
Tue 08/06/04
Mon 16/08/04
Order workstations
16 wks
Drawings
20 days
Tue 08/06/04
Proposal drawings CR
2 wks
Tue 08/06/04
Mon 21/06/04
2 wks
Tue 08/06/04
Mon 21/06/04
2 wks
Tue 22/06/04
Mon 05/07/04
Drawings Accepted
0 days
Mon 05/07/04
Mon 05/07/04
18 days
Tue 17/08/04
Thu 09/09/04
11
Temp install CR
12
refurb CR area
13
5 days
Tue 17/08/04
Mon 23/08/04
3 wks
Tue 17/08/04
Mon 06/09/04
Re-site CR
3 days
Tue 07/09/04
Thu 09/09/04
14
Acceptance test CR
0 days
Thu 09/09/04
15
Installation Workstations
21 days?
16
17
Install Workstations
18
Test workstations
19
Site 1
Tue 07/09/04
Mon 27/09/04
Tue 28/09/04
Mon 04/10/04
Tue 05/10/04
delivery of CR
1 day?
Fri 10/09/04
Fri 10/09/04
4 days
Mon 13/09/04
Thu 16/09/04
22
5 days
Fri 17/09/04
Thu 23/09/04
23
2 days
Fri 24/09/04
Mon 27/09/04
24
Configure cluster+training
5 days
Tue 28/09/04
Mon 04/10/04
25
Acceptance of install
1 day
Tue 05/10/04
Tue 05/10/04
26
5 days
27
0 days
47 days?
Wed 06/10/04
5 days
Tue 24/08/04
Mon 30/08/04
5 days
Tue 31/08/04
Mon 06/09/04
31
32
Training Acceptance
0 days
33
GO LIVE
1 day?
34
Go Live support
5 days
Task Name
PHASE 3
Duration
147 days
Start
Wed 16/06/04
Wed 06/10/04
0 days
Fri 29/10/04
Fri 29/10/04
Order CR
10 wks
Fri 29/10/04
Thu 06/01/05
4
5
16/06
Drawings
0 days
Wed 16/06/04
Wed 16/06/04
15 days
Fri 29/10/04
Thu 18/11/04
Oct '04
Predecessors
Fri 29/10/04
Thu 04/11/04
Site 3 CR
5 days
Fri 29/10/04
Thu 04/11/04
Site 4 CR
5 days
Fri 29/10/04
Thu 04/11/04
Site 5 CR
5 days
Fri 29/10/04
Thu 04/11/04
10
Site 6CR
5 days
Fri 29/10/04
Thu 04/11/04
11
10 days
Fri 05/11/04
Thu 18/11/04
6,7,8,9,10
12
0 days
Thu 18/11/04
Thu 18/11/04
11
14
Site 2
Fri 07/01/05
Wed 23/03/05
20 days?
Fri 07/01/05
Thu 03/02/05
15
Temp Install CR
2 days
Fri 07/01/05
Mon 10/01/05
3,4
16
5 days
Tue 11/01/05
Mon 17/01/05
15
17
Install CR
2 days
Tue 18/01/05
Wed 19/01/05
16
18
1 day?
Thu 20/01/05
Thu 20/01/05
17
19
Acceptance of install
0 days
Thu 20/01/05
Thu 20/01/05
18
20
Training
10 days
Fri 21/01/05
Thu 03/02/05
19
Thu 03/02/05
21
22
10 days
Fri 21/01/05
11 days
Fri 04/02/05
Fri 18/02/05
23
2 days
Fri 04/02/05
Mon 07/02/05
24
5 days
Tue 08/02/05
Mon 14/02/05
23
25
Install CR Solo
2 days
Tue 15/02/05
Wed 16/02/05
3,24
26
Configure cluster+training
2 days
Thu 17/02/05
Fri 18/02/05
25
27
Acceptance of Install
0 days
Fri 18/02/05
Fri 18/02/05
26
28
Site 4
12 days
Mon 21/02/05
Tue 08/03/05
3 days
Mon 21/02/05
Wed 23/02/05
27
30
5 days
Thu 24/02/05
Wed 02/03/05
29
31
Install CR Solo
2 days
Thu 03/03/05
Fri 04/03/05
30
32
2 days
Mon 07/03/05
Tue 08/03/05
31
33
Acceptance of install
0 days
Tue 08/03/05
Tue 08/03/05
32
Site 5
11 days
Wed 09/03/05
2 days
Wed 09/03/05
Thu 10/03/05
33
36
5 days
Fri 11/03/05
Thu 17/03/05
35
37
Install CR Solo
2 days
Fri 18/03/05
Mon 21/03/05
36
38
Tue 22/03/05
Wed 23/03/05
37
39
Acceptance of install
Wed 23/03/05
Wed 23/03/05
38
0 days
09/09
12/10
19/10
25
Nov '04
01 08
15
22
Dec '04
29 06 13
20
27
Jan '05
03 10
17
24
Feb '05
31 07
14
21
Mar '05
28 07
14
21
28
Ap
0
18/11
20/01
18/02
08/03
Wed 23/03/05
35
05/07
21
29
34
08/06
29/10
5 days
54 days?
25
Site 2 CR
Installation
N
18
Wed 27/10/04
13
Oct '04
04 11
Wed 20/10/04
Thu 21/10/04
27
Tue 19/10/04
Wed 20/10/04
20
Tue 19/10/04
Tue 19/10/04
Finish
Thu 06/01/05
Sep '04
30 06 13
23
Tue 12/10/04
30
ID
1
16
Wed 27/10/04
29
10 days
Aug '04
02 09
Tue 12/10/04
Tue 12/10/04
Tue 24/08/04
26
Tue 12/10/04
21
Training
19
Tue 05/10/04
Fri 10/09/04
20
28
12
Tue 05/10/04
1 wk
23 days?
Jul '04
28 05
Thu 09/09/04
Tue 07/09/04
3 wks
1 day?
21
Mon 05/07/04
Installation CR
14
Mon 27/09/04
Tue 08/06/04
10
Jun '04
31 07
Page 24 of 45
23/03
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
B.4.2 Example 2
ID
Task Name
Duration
July
Contract Discussions
Sign Contract
1 day
80 days
IMPAX
16 wks
ADC
12 wks
PAXPORTS
6 wks
HARDCOPY
6 wks
11
2 day s
12
4 wks
13
1 day
14
15
Testing
16
17
7 day s
3 day s
21
23
22/11
27/12
21/07
25/08
October
29/09
03/11
January
08/12
12/01
16/02
April
22/03
26/04
31/05
July
05/07
09/08
October
13/09
18/10
22/11
27/12
25/08
October
29/09
03/11
April
22/03
26/04
31/05
July
05/07
09/08
1 day
25
Installation
3 day s
26
3 day s
27
3 day s
28
3 day s
29
3 day s
Task Name
30
1 day
Duration
July
Acceptance and Sign Of f
1 day
32
Deliver to site A
33
34
35
Acceptance Tests
36
Install Reporting CT
37
38
Acceptance Tests
39
40
41
Acceptance Tests
42
43
44
Acceptance Tests
45
46
Deliver to site B
47
Install CT Reporting
48
49
Acceptance Tests
50
51
52
Acceptance Tests
53
54
Deliver to site C
55
56
57
Acceptance Tests
58
59
60
Acceptance Tests
61
62
63
Acceptance Tests
MILESTONE 3: CR IMPLEMENTATION
1 day
0.5 day s
1 day
1 day
0.5 day s
1 day
1 day
0.5 day s
1 day
1 day
0.5 day s
1 day
1 day
2 day s
1 day
0.5 day s
1 day
1 day
0.5 day s
1 day
1 day
2 day s
1 day
0.5 day s
1 day
1 day
0.5 day s
Duration
July
16/02
October
13/09
18/10
22/11
January
27/12
31/01
1 day
0.5 day s
1 day
1 day
25 days
1 day
66
1 day
67
68
2 day s
69
2 day s
70
2 day s
71
2 day s
72
3 day s
73
1 day
74
2 day s
75
Pre-Installation site C
2 day s
76
Installation site C
2 day s
77
78
January
08/12
12/01
1 day
65
84
October
13/09
18/10
3 day s
Deliv er to site
83
09/08
22 days
24
82
July
05/07
1 day
22
81
31/05
15 days
20
80
26/04
1 wk
79
April
22/03
1 wk
64
16/02
3 day s
19
ID
January
08/12
12/01
10 day s
18
31
October
29/09
03/11
10
ID
25/08
1 d ay
21/07
194.5 days
1 day
3 day s
1 day
30 days
5 d ays
5 day s
5 d ays
5 day s
Page 25 of 45
B.5
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
SENIOR MANAGEMENT
TEAM
SUPPLIER TEAM: Healthcare Director
TRUST Project Sponsor: Medical Director for
Clinical Services
Monthly Report
Issue Resolution
Issue Resolution
Issue Resolution
Monthly Report to
steering committee
Issue resolution
IMPLEMENTATION TEAM
SUPPLIER TEAM:
Project Manager
Informatics Account Manager
Regional PACS Specialist
Regional Service team leader
Lead Engineer
TRUST TEAM:
Project Manager
Implementation Radiographer
Report to
Implementation team
-Purchase
orders
-On-site
commitment
-Integration
-Acceptance
THIRD PARTIES
RIS Suppliers
PAS Suppliers
HIS Suppliers
Modality Suppliers
PM feeds
implementati
on team
Implementation Team
feeds Installation Team
INSTALLATION TEAM
INSTALLATION
TEAM
SUPPLIER TEAM:
Engineers
SUPPLIER TEAM
TEAM: (incl LSP and PACS Vendor)
Applications
Engineers Specialists
Applications Specialists
TRUST TEAM:
Project
TRUST Manager
TEAM:
Project Manager
PACS Practical Experiences
PM Manages
Third Party
Companies:
Page 26 of 45
C.1
Networking
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
The OBS states that The Contractor shall check that the Authority networks and connections
are satisfactory to deliver the performance described in Section 4.3 (Solution Requirements)
and the Contractor shall state whether any changes are required to Authority networks. The
Contractor shall state the minimum network and connections required to deliver the
performance described in section 4.3.
In addition The Contractor shall be required to warrant the performance of their system over
the network, or propose enhancements if the network is not adequate.
It should be noted that the NPfIT PACS Project Initiation Document (PID) suggests that A
robust LAN is essential. PACS must not be installed on a network less than 100Mbps
Ethernet.
The PID also recognises the dependency of N3 for the Delivery of Wide Area Network (WAN)
network infrastructure work to provide required PACS bandwidth and availability (which will
provide services for more than just community PACS). Image data volumes have been shared
with N3 to aid their capacity planning.
So in summary the supplier will typically undertake a survey of the local Area Network and
make recommendations. An example of one is available from the NPfIT if required.
C.2
Communication Standards
C.2.3 HL7
IHE (Integrating the Healthcare Enterprise) is a global initiative designed to advance the data
integration in healthcare. It aims to develop a framework to ease the integration of, and
information flow between various medical information systems, with the ultimate goal of
ensuring that all required clinical information is correct and readily available to the relevant
users. Currently, interfacing systems can be difficult due to the different standards and
implementation of those standards employed by such systems. IHE aims to define how
existing standards may be used in order to facilitate communications between computer
systems used in healthcare; initially, IHE will concentrate on DICOM and HL7 but mat extend
to other standards if necessary.
The OBS states that The Contractor shall ensure that the PACS service shall be fully
integrated with other systems within the Authority and must confirm that the IHE, DICOM and
HL7 standards are the basis for the integration with other systems. Also where appropriate
The Contractor shall migrate communications to HL7 v3.
Page 27 of 45
C.3
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Interfaces
When designing and implementing a PACS it is important to give detailed thought to storage,
management and acquisition of non-image data (e.g. patient demographic data, examination
details, clinic appointments, etc).
Much, if not all, of the non-image data required by a PACS is available on external systems
such as Radiology Information Systems (RIS), Patient Administration System (PAS) or
Hospital Information Systems (HIS). The standards described above should be used for the
sharing of this data and the sort of information required includes aspects of examinations on
RIS, current patient location and forthcoming appointments (HIS, PAS and RIS)
To allow for efficient communication between an external information system and a PACS, it
may be necessary to use an interface engine. An interface engine is a computer system
which sits between two (or more) information systems, and reformats the output from one
system into a form readable by the receiving system. In a PACS implementation, this interface
engine is generally referred to as a PACS Broker. It typically receives information on patient
demographics and examination bookings from a RIS and/or a HIS, and passes this data on to
the PACS, following appropriate reformatting by the broker. Data can also flow from the PACS
to an external system should the external system have the ability to use data from the PACS
(for example information from an imaging modality regarding the acquisition status of an
examination). The PACS broker may maintain its own database of information derived from
information acquired from the attached devices.
The advantages of integrating other hospital information systems with a PACS include:
A single point of entry for data means consistency, and avoids duplication of effort
Access to patient location information allows for filtered worklists. PACS can obtain
information on patient status and location from the HIS, and use this to present useful
worklists to radiologists and clinicians. For example, a list of examinations for all
patients on a particular ward can be created.
C.4
Digital Image
One of the key features of a PACS is its ability to store and transfer image data. This is a
digital representation of the original image, and all image data acquired onto the PACS must
be digital.
Many imaging modalities already produce data in digital form (for example, CT or MR) and
these modalities may be attached directly to the PACS (although it is possible that some
intermediate interfacing unit will be required). Other modalities generate image data as
analogue film (for example, traditional x-ray) or video display (e.g. older ultrasound scanners)
only and this analogue data must be converted to digital form before it can be sent to the
PACS.
Images produced on traditional film can be converted to digital form using a film digitiser (See
Appendix A2) and indeed video displays can use frame grabbers to be converted to digital
output.
In recent years, Computed Radiography (CR) and Direct Radiography (DR) have become
increasingly important for plain x-ray imaging. Both CR and DR, together with modalities such
as CT and MR, produce digital data.
Page 28 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Other imaging modalities will form the image by processes appropriate to that modality, but
however the image is formed, the end product is a computer file containing the image data.
The only exception to this is where computed radiography is used to print film, with the
creation of an image data file being a temporary step towards production of the film.
1760 pixels
Image height:
2140 pixels
Number of bits/pixel:
16 bits
Thus to store a single CR chest image requires 1760 x 2140 x 16 bits = 60262400 bits.
Assuming 8 bits per byte, 1024 bytes per kB and 1024 kB per MB, this calculates to 7.2 MB
per image. Lossless compression can typically reduce the storage requirements by about a
factor of 2.
In order to calculate the archive storage requirements for a PACS, the data on the typical
image sizes for each modality can be used. For each modality, multiply the typical image size
by the average number of images per exam, and multiply this figure by the number of
examinations performed in a year. This will give the annual storage requirements. This figure
can be modified according to the amount of compression to be used on the data.
Page 29 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
The storing of image data uses the DICOM standard. Most medical image acquisition devices
produce image data compatible with the DICOM standard. There may be occasions when
imaging acquisition devices that are not DICOM-compliant will be required to send images to
a PACS. It can be possible to acquire images onto the PACS by use of a DICOM gateway.
In a similar manner to which a PACS broker allows information flow between a PACS and
external information systems, a DICOM gateway can allow image data to flow from imaging
devices to the PACS.
Page 30 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Off-line archive. Should the near-line archive become full, a third line of storage can be
used. Space is freed in the near-line archive by removing archive media that become full, and
replacing them with blank media. The removed media can be stored on a shelf, and replaced
in the near-line archive device should the data contained upon it be required. Note that this
replacement will require manual insertion by PACS support staff, and it could be several hours
before the data becomes available. The removed media should be stored in a safe place, and
needs to be managed properly so that the disk or tape containing the required data can easily
be found.
Recent increases in the capacity of systems, together with price falls, are leading to a shift in
thinking away from the above definitions of storage (which are focussed on the ease of
accessibility of the data), to definitions based on the lifetime of the data within storage
classes. As disk-based systems increase in capacity, it becomes feasible to store several
months data on-line, with the complete archive being stored near-line in a tape or diskbased archive. Thus storage can be thought of as being in one of two categories: short-term
or long-term.
The most common types of hardware used to provide storage solutions are those using
magnetic and optical technologies. This can be further broken down into disk (e.g. RAID,
DVD, Magneto Optical Disk (MOD)), and tape (e.g. Advanced Intelligent Tape (AIT), Digital
Linear Tape (DLT), Linear Tape Open (LTO) Digital Audio Tape (DAT)) technologies.
The media used in archive storage are housed in a device known as a jukebox. A jukebox can
contain one of many types of media (CD-ROM, tape or disks). The jukebox moves the media
from its storage location, by means of a robotic mechanism or carousel, to a reading/writing
area; the time for this movement of disk to read is usually in the order of 10 30 seconds.
C.4.5.1
Networked Storage
Computer networks can be attached to two types of networked storage topologies, known as
Network Attached Storage (NAS) and Storage Area Network (SAN). These storage topologies
are becoming increasingly common in PACS.
Network Attached Storage (NAS)
In NAS, the storage device is usually a RAID attached directly to the network, below
illustrates the NAS attached to a LAN.
Page 31 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
This ensures that a change in the pixel data value in the image data file produces an
appropriate change in the optical density of the printed film.
Page 32 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
This ensures that regions in the image that have the same pixel value have the same optical
density when printed to film.
Spatial resolution.
This is a measure of the ability of the film printer to print small features in an image or to allow
two closely-spaced, but separate, features in an image to be visualised separately on a film.
Contrast resolution.
This is a measure of the ability of the film printer to produce a change in optical density for
regions in the image that are of similar, but different, pixel values.
Geometric distortion.
This is a test of the ability of the film printer to print films which retain the proportions of the
reconstructed image. In particular, all straight lines in the original image should remain
straight on the printed film.
Other hardcopy printing devices may be appropriate; these devices include inkjet printers,
thermographic printers and laser printers. These devices also require regular checks to
ensure that they are performing adequately, and these checks will be similar to those
described above for film printers.
C.5
Monitors
Guidance is often asked for on recommended workstations for image display. The information
below has been collated to assist people who are considering their requirements for PACS
workstations.
It is hard to be prescriptive as the types and numbers required will depend upon the source of
the images (e.g. CT, plain x-ray), local workflow and clinical process. Careful consideration
must also be given to the ergonomics and environmental conditions of the areas in which the
workstations are to be placed.
Workstations comprise a combination of base station (most often, a PC), software to allow the
display and manipulation of medical images from the PACS and a display device. This
guidance note concerns the display device component of workstations only.
The most important factor is that the display device should be fit for use, be available at
required clinical locations and maintained in appropriate condition. It should be the Suppliers
responsibility to work in conjunction with you to provide or recommend the appropriate
devices in the relevant locations to meet the clinical needs of the service that is being
provided. Note that specialist displays and/or workstations may also be required for remote
access to images, e.g. on-call consultants reporting from home. Where there is a monitor that
does not meet the required standard it is recommended that it is identified as 'Unsuitable for
PACS diagnostic use' and marked in an agreed way locally. Users should be told not to use
monitors so marked for diagnostic work.
C.5.2 Displays
The following documents actual experiences from sites that have implemented PACS
workstations and can be used as an indicative guide.
Displays purchased for diagnostic use are generally monochrome. This is because
monochrome displays can be manufactured to be significantly brighter than colour displays,
PACS Practical Experiences
Page 33 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
thus improving the contrast ratio and so the contrast resolution of the display. Typically a
contrast ratio of at least 400:1 is desirable for a diagnostic display.
Colour screens may be appropriate in less demanding situations (i.e. for image review only)
or when colour information is present in the original image. Note that as well as being less
bright, colour displays may also demonstrate reduced spatial resolution when compared to a
monochrome display.
A choice is available between traditional Cathode Ray Tube (CRT) displays and the new
Liquid Crystal Displays (LCD). For most purposes the image quality of the two devices is
comparable and other factors may sway the decision on which type of device to purchase
LCD flat-panel displays are lighter, take up less space and produce less heat when compared
to CRT displays, but may be more expensive. At the high end of the market (5 mega pixel
devices) CRT displays still have a small edge in quality compared to LCDs.
For reporting workstations: 2 or 3 mega pixel (2k or 3k) 17 or 19 portrait monitors are
typically used. (An example size seen is 2048 pixels x 1560 pixels). These displays are most
often used in pairs, to allow for comparison of two or more images at full resolution. 5 mega
pixels screens are seen for mammography.
Review / web workstations: SVGA quality, with web browser software adapted for access to
images and textual reports is typical. These are usually devices of around 1 mega pixel (1k)
display size.
It is important to have a high-quality video display card in the base workstation to drive the
display screens. Standard PC display cards will not be able to provide data of sufficient quality
and resolution to allow a diagnostic quality display to perform at its maximum capability.
Advice should be sought from the display vendor as to the availability of appropriate display
cards.
Further information on displays can be obtained from PACSnet (contact information can be
found at http://www.PACSnet.org.uk) who provide a free PACS technical service to the NHS.
C.5.2.1
It is essential to ensure that all workstations and screens used for diagnosis and review are
performing adequately for their designated tasks.
Tests that can be carried out on display monitors include:
Luminance.
Peak display brightness should be within specification the brightness should be measured at
several points on the screen, and all points should be within a specified range.
Contrast resolution.
Focus.
A visual inspection of a test image should be made to ensure that the image is adequately
sharp over the display area.
Geometric distortion.
A test image which includes straight lines and circles should be displayed. Ensure that
straight lines are straight to within defined limits, and similarly that circles are circular to within
defined limits.
Flicker.
The display should be judged for unacceptable amounts of flicker. Significant amounts of
flicker can result in user fatigue.
Dropouts.
Page 34 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Visually inspect the entire screen area for artefacts. CRT tubes may suffer from small areas
where dark spots are apparent, due to a lack of phosphor on the screen at this area. LCD
displays can have dark or light spots where individual crystals are malfunctioning
Investment of resources into performing QA checks must not be underestimated, remember
that maintaining records of test results in order to evaluate any deterioration in performance
over time is also important.
C.6
Web Browsers
As part of their product lines, most PACS vendors offer the possibility of using web browsers
to view images and clinical reports in addition to the use of dedicated PACS workstations. A
web browser is a standard piece of software most commonly used to display pages from the
World Wide Web, for example Netscape Navigator or Microsoft Internet Explorer. The use of
web browsers has several advantages, both for the purchaser and for the user:
Web browsers are a simple, robust technology. They have been under development for
many years, and, provided they can access the required data reliably, perform well.
Web browsers can run on relatively low specification computers, often on computers that
already exist within a healthcare institution.
Many users will already be familiar with web browsers through use of the World Wide
Web, and so it is possible that little additional training will be required.
Hospital I.T. support staff are likely to have familiarity with the use and installation of web
browsers.
However, although it is possible that a PACS web browser will run on a standard desktop
computer, as discussed above thought should be given to the display used to look at the
images. The standard monitor may not be of adequate quality for the viewing of PACS images
and it is important to consider the intended use of images displayed on a web browser.
Another point to consider is the functionality provided by the web browser for the display and
manipulation of images: although the features offered by web browsers have become
increasingly sophisticated in recent years, web browsers are still unlikely to match the
software available in a dedicated manipulation and viewing application.
In order for web browsers to be able to obtain the image data files required for the display of
images, it is usual for a PACS that supports web browsers to include a web server. This is a
computer that is responsible for the delivery of image data to those web browsers that request
it, and may be a machine separate from the main PACS server and image data store. The
server can also deliver the workstation software to the workstation and thus allow software
upgrades to be maintained centrally.
There may be concern regarding the security of using web browsers. Although standard web
browsers are used, of the same type as those used to access the World Wide Web, this does
not mean that everyone with access to the internet can view the data. It is possible to limit
access to particular computers or areas of the hospital network. In addition, it will be
necessary to type in a standard username and password before images can be displayed.
Page 35 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
D.1
The primary function is image viewing and one has to consider the following to comply with
Health and Safety issues and ensure diagnostic accuracy.
Workstation ergonomics
Take into account the needs of the individual; consider how tasks will be performed with
particular regard to Health & safety issues e.g. RSI and the need for regular breaks.
o
Seating
Environment
Temperature
Air conditioning needs to be considered in conjunction with the Estates Department
Noise Pollution
Acoustic screening can be effective in shared offices
Education
o
PACS users should be instructed in the most beneficial use of the equipment.
This training should cover the areas listed above, in particular, instruction on
Page 36 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
D.2
Radiographer Zone
Lack of space may be an issue reconsider your current workflow when positioning
monitors
Ambient lighting is important for image QA, and for aspects of Red Dot reporting
D.3
Ideally this should be sited as close to Radiology to quickly assist with urgent access e.g.
system restart required by the system engineer and PACS system Administrator
Air conditioning will be required. Many items of computer equipment are sensitive to
temperature and may have safety cut-outs that will operate at high temperatures or
may have components that will malfunction at high temperatures (e.g. disks in a RAID
storage device). It is important that the temperature in the computer room is
controlled and monitored.
PACS Administrator would be expected to have an office with sufficient space to allow for
independent access to multiple systems.
Page 37 of 45
Y
Y
Qualitative
Benefits
Quantitative
non-cash
releasing
cash
releasing
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Who benefits
Trust / SHA
Trust / SHA
Patient
Trust / SHA
Trust / SHA
Trust / SHA
Trust / SHA
Reduction in litigation
Trust / SHA
Trust / SHA
Trust / SHA
Environmental
Trust / SHA
Trust / SHA
Trust / SHA
Patient
Staff
Quicker results
Patient
Trust / SHA
Staff
Patient
Trust / SHA
Patient
Trust / SHA
Patient
Staff
Patient
Trust / SHA
Page 38 of 45
Patient
Staff
Patient
Trust / SHA
Patient
Trust / SHA
Patient
Trust / SHA
Patient
Trust / SHA
Trust / SHA
Staff
Patient
Patient
Trust / SHA
Patient
Trust / SHA
Benefits
cash
releasing
Qualitative
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Quantitative
non-cash
releasing
Who benefits
Patient
Trust / SHA
Staff
Patient
Trust / SHA
Staff
Patient
Trust / SHA
Trust / SHA
Page 39 of 45
Patient
Trust / SHA
Staff
Trust / SHA
Staff
Trust / SHA
Environment
Staff
Benefits
cash
releasing
Qualitative
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
Quantitative
non-cash
releasing
Who benefits
Trust / SHA
Staff
Patient
Staff
Staff
Trust / SHA
Trust / SHA
Trust / SHA
Trust / SHA
Trust / SHA
Page 40 of 45
E.1
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
With the opening of its new hospital in 2001 this Trust installed both a PACS (a computerised
x-ray archive system), CR (a facility to digitise standard x-rays) and various items of x-ray
equipment that produce digital images (CT Scanner, MRI, angioscope, fluoroscope). At the
same time the Trust installed a wide bandwidth network and improved monitors to enable
clinicians in wards and departments to view these x-rays.
A full benefits realisation appraisal has not been completed so this discussion is incomplete
and partially anecdotal.
The radiologist now has much speedier access to images and there has been
a reduction in the time between an inpatient or casualty patient being x-rayed
and his report being available.
Additionally the Trust has radiology services on more than one site. The
PACS system means that the radiologist does not need to be at the remote
site to report on the image again improving reporting times.
The digital image gives the radiologist the ability to manipulate that image, to
compare two or more images and to view a series of cross-sections as a
single moving image. This certainly helps the radiologist who would otherwise
have to hold the images in his mind and may result in more accurate
diagnosis.
Images are now available where the clinician requires them and when the
clinician requires them.
In the past the clinician has had to await delivery of the x-rays to the ward
and to rely on clerical procedures delivering x-rays to outpatients at the same
time as the patient. In both cases if the consultant needed access to historical
x-rays this resulted in further delay.
Now the clinician has immediate access to x-rays from any workstation.
Remote consultation
o
When one health professional seeks advice from another, this can now be
done interactively. This could be a radiologist seeking advice from a
colleague. They no longer need to meet for both to view the x-ray together
thus improving the speed with which a diagnostic report is issued.
Page 41 of 45
GP Patient admission
o
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
The digital nature of PACS will enable it to be included within the patients'
EPR. This will mean that the clinician will be able to find it alongside the
patients' other electronically held data again improving the delivery of
healthcare.
PACS is very popular with clinicians and improves their morale. Making their
job easier because x-rays are available where and when they need them to
facilitate efficiency and effectiveness.
Page 42 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
This section is a working draft and is based on the best available information. The detail of the
Business Case Templates may change as decisions on central funding and detailed local
contractual arrangements are put in place, but this does provide a way forward for addressing
the local service specification, costs, benefits, and implementation planning. It will be updated
to reflect process changes as they emerge.
F.1
Introduction
The process assumes a business case is required at individual NHS organisational level. It
can however be aggregated if a number of organisations want to work together. This may be
where local business needs are best met by a group of Trusts working together. Alternatively
an SHA may wish to proceed with all its Trusts as part of the same exercise.
Local Trusts will have to pay for elements of the implementation and the running costs over
the lifetime of the contract. Each Trust either acting individually or as part of a group will need
to understand and accept the financial consequences of their PACS implementation. The
process ensures that Trust specific figures will be available whatever consortium approach is
adopted.
The financial model envisages a mixture of capital investment and revenue. Decisions on
central capital funding for local PACS implementation are yet to be made.
The process consists of 3 elements:
A toolkit which is used to drive the detailed local specification and financial model.
A workshop(s) run by the central team to facilitate the completion of the templates.
The whole package is aimed at enabling NHS organisations to speedily proceed to PACS
implementation. It represents the minimum requirement consistent with good practice.
The Templates are based on the standard 5 case model as detailed in the Treasury Green
Book and the Department of Healths Capital Investment Instructions.
The process can therefore satisfy local requirements for strong governance on investment
decisions. It provides the necessary business justification for Board consideration and
approval to proceed.
The requirements of the detailed local PACS specification will be met through the Local
Service Provider. There will be no need to undertake any separate procurement activity.
Individual Clusters will provide information on how these arrangements will work in practice.
This means that an Outline Business Case is not required and this process produces in a
single stage the case for local approval.
Page 43 of 45
F.2
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
The aim is to provide an easy to use set of guidance for NHS Users. The written material
coupled with the workshops is intended to enable the rapid development of a business case
in house.
The templates cover the 5 sections of the standard model. Wherever possible they are pre
populated with information which is common to all locations. They contain guidance and
prompts to assist in the local customisation
F.3
The Toolkit
As described above this provides the framework within which the key data is captured and
manipulated to develop the Financial Case. The data is clearly defined and will be available
from sources within the Trust. Much of the data has already been collected within the context
of the Modalities surveys and the work on the Financial Templates. This information is
required for the Toolkit.
F.4
The Workshops
These support the use of the written and interactive material described above. There is a
common structure, which can be modified to meet the specific requirements of individual Trust
or groupings.
The process is aimed to assist the author of the business case and their attendance is critical.
That individual will have a different title according to the local approach. It may be the SHA or
Trust lead or both.
In addition a senior Radiology User is needed to lead on the local service specification. This
may be the Radiology Services Manager but once again it is for the local project to nominate.
A finance representative from each participating Trust will be needed to assist with elements
of the costed benefits and the financial template
Page 44 of 45
NPFIT-PRI-GMP-0001 V0.13
28 June 2004 Draft
There may be other interested parties such as the Senior Clinical Sponsor who wish to
attend. The above list is the suggested minimum and the detail of the workshop package and
attendees will be agreed as part of the Initial Contact.
F.4.1
Initial Contact
This can be by phone or meeting. The aim is to explain the process and agree how to
proceed. The discussion will identify:
How the generic process maps onto the local user requirement
The key players and local constituencies
Specific local issues, e.g. existing PACS contracts, PFI, immediate operational requirements
Funding flows
Agree timescales and attendees for workshop/s.
Workshop 1
The first workshop provides:
Overview of the whole process
Use of toolkit for local service specification
Development of the Cost Model
Identification and resolution of specific local issues
Workshop 2
The second workshop provides:
Validation of the service specification
Validation of cost model
Benefit and Risk appraisal
Development of Implementation Plan
Handling specific local issues
Workshop 3
The third workshop provides:
Review of all templates
Benefit realisation plan
Preparation for Approval, e.g. Board Summary
Post approval and National Programme issues.
In addition to the workshops a help line will be provided by the Central PACS team to assist
users with all elements of the Business Case Templates as required. Initially Mark Freeman
on 0113 280 6489
The PACS facilitators attached to each cluster are also available to provide support on
implementation and associated issues.
This suggested programme can be flexed and adapted to meet the specific requirements of
the Trust or group developing the PACS business case.
F.5
Summary
NHS Users wanting to arrange an Initial Contact should contact their local PACS Facilitator or
use the help line number provided. The latest documentation will then be sent and an Initial
contact arranged.
Page 45 of 45