Beruflich Dokumente
Kultur Dokumente
goods
without
consent.
If the material and goods delivered to site by the contractor has been paid by
the employer under Interim Certificate that issuance accordance to proviso of
clause 30.2, provided that the material and goods is not prematurely brought to
the site. After the materials and goods have been included in the Interim
certificate, the materials and goods had become the property of the employer.
The contactor has no right to remove the paid material and goods which are
belong to the employer without consent of the employer.
This clause is similar to Clause 20.0 in P.W.D 203A.
Example:
In a project, the contractor had ordered the Ceramic Wall Tiles deliver to site
which will use on nine month later accordance to working schedule submitted
by contractor. In this situation, the contractor will be not entitle payment for
the Ceramic Wall Tiles until the date near to commencement of Ceramic Wall
Tiles work because this had considered as the material and goods prematurely
brought to site.
was
stolen
by
other.
clause
under
is
peculiar
in
Clause
PAM
2006
(With
30.4.
Quantities).
Example:
In the contract, the Ceramic Floor Tiles has been delivered to site and has been
included in Interim Payment to contractor. However, the Ceramic Floor Tiles
have been found out that are the stolen goods from others, which the right of
titles of the goods is belong to the original owner. In this case, contractor had
made a false warranty on title because the employer unable to become the
rightful owner of the material and goods due to that is stolen goods from other
although the contractor paid to purchase it. In this case, the contractor should
pay for the employers loss or the employer can set off the amount of loss in
the next Interim Payment to the contractor.