Sie sind auf Seite 1von 4

BAUER Nimr LLC

Weekly Project QA/QC Update


Report No. : 005
Waste Management Area Ph 2 Permanent
Facility

Project Title
Client
Value of the Project:

BP Exploration (Epsilon) Ltd

Date:

Contract/Job No.
Client Representative

Project Start Date:

1-Nov-16

REP-BPXO-14-0727
Jacobs Engineering Group Inc.

Completion Date:

Anticipated Completion

Report For the Period From:

To:

25-Oct-16

1. CONCERNS
a

Manufacturing ITP for Transformer includng FAT and SAT procedure for the same

Required documents for equipments that arrived (drop arm barrier,pressure washer and submersible pump) for receiving inspection

Commissioning and preservation plan documents

Receiving inspection procedure. BAUER permanent Materials/equipment shall be endorsed to QA/QC personnel for internal inspection.

Lifting plan procedure and erection of structural steel method statement preparation.

2.

KEY EVENTS

a.

Material Receiving inspection for Split type AC units have been raised

Backfilling and compaction for weighbridge, vehicle wash bay and drop arm barrier have been inspected and approved by client.

Form work and reinforcement rebar installations for valve pits VP-1 and VP-2 have been inspected and approved by client.

2.1 Ongoing works:


a

Backfilling of clean washed sand and compaction of the same is ongoing for cess tank installations.

Excavation of cable trench for light poles on the southwest portion of the facility.

c.

Sealing of roof at the admin building.

preparation of AC foundation formworks.

3.

QC Staff
QA/QC Engineer (Muscat)
QA/QC Supervisor
QA/QC Inspector (Subcon)

5.

Required

Available

1
1

1
1
2

QC DOCUMENTS STATUS

QC
Document Description
Doc
um
Manufactuiring ITP
ents
Method Statement
Stat Data Sheets
us: RFI Raised

To be
Mobilized

Descipline

Status

EL CV ME
6
4
1
3

9
40 1

39 approved, 5 to
be signed

PROJECT STATUS
Item

Electrical
Civil
Mechanical
Instrumentation

6.

4.

QC STAFF (SubCon Included)

Scope

Unit

100
100
100
100

%
%
%
%

Completed Till date

Remarks

Update of Percentage complet


takenfrom Mr. Aravin

NCR STATUS
NCRs Issued By

Construction
Operation
Client
Internal Audit
External

Total Issued

Closed Till Date

Open Till Date

0
0
0
0
0

0
0
0
0
0

0
0
0
0
0

Personal: QA/QC Report Rev 0 22-Sep-2016

Remarks

BAUER Nimr LLC


7.

OTHERS
There are 8 nos. of Method statements for permit purposes as of this moment.

Prepared by: Joel M. Alcantara


Distribution : QHSE Regional Head/PD/PM

Note: To be Emailed to QA/QC / Project Management


on Thursday before 10.00 am.

Personal: QA/QC Report Rev 0 22-Sep-2016

BAUER Nimr LLC


1-Nov-16

Group Inc.

31-Oct-16

pection

al inspection.

lient.

Remarks

For permit purposes not included


9 Nos this week

emarks

age completed will be


vin

Personal: QA/QC Report Rev 0 22-Sep-2016

BAUER Nimr LLC

Personal: QA/QC Report Rev 0 22-Sep-2016

Das könnte Ihnen auch gefallen