DOCUMENT NO.

POLLACHI-COIMBAROTRE SECTION OF NH209


KNR-ST-VD-DC-06
Design of Substructure and Foundation - EJ
DESIGNED
CHECKED
TITLE:
Pier P42
KKK
MPB
Design Details of Pier Group, GP3 (EJ PIER) are presented in this REPORT.
P42 is the Critical Pier among this group of Piers.
Founding
S.No
Pier
FRL
GL
Height
Level
1
P3
334.955
324.512
320.512
14.443
2
P6
335.589
324.979
320.979
14.610
3
P9
335.964
324.831
320.831
15.133
4
P12
336.339
324.896
320.896
15.443
5
P15
336.714
325.278
321.278
15.436
6
P18
337.089
325.8855
321.8855
15.204
7
P21
337.952
325.794
321.794
16.158
8
P24
339.736
327.6855
323.6855
16.051
9
P27
341.34
330.417
326.417
14.923
10
P30
342.2015
331.835
327.835
14.367
11
P33
342.315
330.601
326.601
15.714
12
P36
341.967
329.92
325.92
16.047
13
P39
342.408
330.042
326.042
16.366
344.023
330.9715
326.9715
17.052
14
P42
15
P45
345.898
334.582
330.582
15.316
16
P48
347.564
337.22
333.22
14.344
17
P51
348.508
337.261
333.261
15.247
18
P54
348.6985
337.7895
333.7895
14.909
19
P57
348.142
337.744
333.744
14.398
17.052
Maximim height
P42
PROJECT:

DATE

30-Oct-16
SHEET