Beruflich Dokumente
Kultur Dokumente
Rajkumar A, Engineer
Western Regional Load Dispatch Center
India
WRLDC,POSOCO
RELIABILITY--DEFINITIONS
A measure of the ability of a system, generally
given as numerical indices, to deliver power to all
points of utilisation within acceptable standards
and in amounts desired. Power system reliability
(comprising generation and transmission &
distribution facilities) can be described by two
basic functional attributes: adequacy and security.
(Cigr definition)
Reliability is the probability of a device or a system
performing its function adequately, for the period
of time intended, under the operating conditions
intended. (IEEE PES definition)
10/29/2012
WRLDC,POSOCO
System Reliability
System
Adequacy
WRLDC,POSOCO
System
Security
10/29/2012
Adequacy
5
WRLDC,POSOCO
10/29/2012
Security
6
WRLDC,POSOCO
10/29/2012
Security
7
WRLDC,POSOCO
10/29/2012
1.
2.
3.
10/29/2012
WRLDC,POSOCO
10/29/2012
WRLDC,POSOCO
10/29/2012
WRLDC,POSOCO
10/29/2012
WRLDC,POSOCO
10/29/2012
13
10/29/2012
WRLDC,POSOCO
10/29/2012
WRLDC,POSOCO
10/29/2012
WRLDC,POSOCO
10/29/2012
10/29/2012
Load should be unserved in hours when the cost of serving it would exceed
Value Of Lost Load (VOLL). Put algebraically, outage makes sense so long as
VOLL (Outage Hours) < FA + (VA (Outage Hours)),
and solving this gives us the answer.
WRLDC,POSOCO
10/29/2012
10/29/2012
WRLDC,POSOCO
10/29/2012
WRLDC,POSOCO
10/29/2012
Generation planning
22
WRLDC,POSOCO
10/29/2012
Transmission planning
23
WRLDC,POSOCO
10/29/2012
WRLDC,POSOCO
10/29/2012
Section 2.4:
The following options may
strengthening of the transmission network.
be
considered
for
system. (whenever three or more circuits of the same voltage class are
envisaged between two sub stations, the next transmission voltage
should also be considered.)
10/29/2012
2.5
2.6
2.7
The evacuation system for sensitive power stations viz., Nuclear Power
stations, shall generally be planned so as to terminate it at large load
centers to facilitate islanding of the power station in case of contingency.
2.8
Where only two circuits are planned for evacuation of power from a
generating station, these should be ( as far as possible) two single circuit
lines instead of a double circuit line.
WRLDC,POSOCO
10/29/2012
2.9
2.10
WRLDC,POSOCO
10/29/2012
3.2
LOAD DEMANDS
3.2.1
The profile of annual and daily demands will be determined from past data.
These data will usually give the demand at grid supply points and for the
whole system identifying the annual and daily peak demand.
3.2.2
WRLDC,POSOCO
10/29/2012
The policy, standards and guidelines issued by the CEA for the
planning and design of the Transmission system
WRLDC,POSOCO
10/29/2012
o
o
o
Loss of supply
Prolonged operation of the system frequency below
and above specified limits.
Unacceptable high or low voltage
System instability
Unacceptable overloading of ISTS elements
WRLDC,POSOCO
10/29/2012
The
All
WRLDC,POSOCO
10/29/2012
Operating limits
32
Thermal limits
o
Voltage limits
o
o
Stability limits
o
WRLDC,POSOCO
10/29/2012
WRLDC,POSOCO
10/29/2012
Probability of failure
Expected frequency of failure
Expected number of voltage violations
Expected number of load curtailments
Expected load curtailed
Expected energy not supplied
Expected duration of load curtailed
WRLDC,POSOCO
10/29/2012
Reliability Indices(2)
35
10/29/2012
Reliability Indices(3)
36
4)
jx , y
kj
jx, y
kj
Dkj F j MWh
jx , y
10/29/2012
Distribution Reliability
37
Data Required
Failure rate, manual sectionalizing time, Outage duration of
each component connected in distribution system
Three primary terms
o
WRLDC,POSOCO
10/29/2012
10/29/2012
WRLDC,POSOCO
10/29/2012
40
WRLDC,POSOCO
10/29/2012
terminology
Hidden failures relays
WRLDC,POSOCO
10/29/2012
WRLDC,POSOCO
10/29/2012
WRLDC,POSOCO
10/29/2012
Lessons-Bottlenecks (1)
44
Absence of
Primary Response of Generators
Automatic Generation Control(AGC)
Full fledged Tie Line Control
Ancillary Services(Dynamic)
Decision Support Systems(online )
Robust Communication systems
Manual Control Instructions and Actions.
Line Loadability- lack of Dynamic Compensation
and control
Inadequate/lack of WAMS assisted tools
WRLDC,POSOCO
10/29/2012
Volume
Wide Floating Frequency
Inadequate commercial mechanism for
10/29/2012
Lessons-Inadequacies (3)
46
zone 3 settings
Dynamic Compensation
Dynamic Reserves
situations.
No Hotline Communication among Control Centers
WRLDC,POSOCO
10/29/2012
Thank You
47
WRLDC,POSOCO
10/29/2012