Beruflich Dokumente
Kultur Dokumente
Review area
Findings
Recommendations
Management
comments
Obligations
relating to
provision of
water
services,
licences,
planning and
registration.
Management
agrees with
the
recommendati
on that
continuous
engagement
and
cooperation is
needed to
ensure there is
harmony
between the
two levels of
Government
and sector
institutions,
and will
endeavour to
do so.
Management
agrees with
the
Review area
Findings
Recommendations
Management
comments
water
services,
licences,
planning and
registration.
recommendati
on that all
approvals
necessary for
the
commenceme
nt of a project
should be
obtained prior
to
commenceme
nt and the
conditions
therein
continuously
monitored.
Management
agrees with
the
Review area
Findings
Recommendations
Management
comments
l and waste
management
obligations.
Accounting,
financial and
tax
obligations.
recommendati
on and will
institute
measures
geared at
ensuring
regular energy
audits are
undertaken for
its facilities.
Management
agrees with
the
recommendati
on and has
commissioned
the services of
a tax
consultant who
is advising and
assisting in the
resolution of
this liability.
Tax
Head
Princip
al Tax
(Kshs
000)
Penalti
es
(Kshs
000)
Intere
st
(Kshs
000)
Total
Tax
(Kshs
000)
Corpo
ration
tax
202,971
40,594
84,588
328,153
376
572
948
5,556
5,556
75,596
13,505
56,152
145,253
VAT
PAYE
Withh
olding
Review area
Findings
Recommendations
Management
comments
tax
Total
278,94
3
60,227
140,7
40
479,910
Management
AWSB should seek in depth agrees with
expert clarity on this matter the
Review area
Findings
During our review of procurement of and payments to
contractors, we noted various instances where
contractors had indicated through correspondence to
AWSB that the contract sums with respect to their
respective contracts were exclusive of VAT. We also
noted that the bid documents indicated that prices
should be inclusive of all taxes while the agreement
with contractors was silent on this issue. We therefore
noted there was an issue in the interpretation of the
contractual documents.
One such contractor who had notified the Board
about exclusion of VAT in the contract sum was
Shanxi Geological Engineering Exploration Institute.
During the review, we noted that Shanxi Geological
Engineering Exploration Institute was awarded two
(2) contracts for water supply in Kiambu (Kshs
749,882,570) and in Muranga (521,015,817). In both
contracts, the contractor had written to the Board
citing that both contracts were awarded exclusive of
VAT.
Based on the contractors assertion vis-a-vis the
contractual documents, a task force was formed to
look into the issue and report on status of VAT on
Muranga and KiambuWater Supply contracts (Ref
AWSB/WaSSIP AF/Comp. 1/W-5/2013). The task force
recommended among other things that the Board
should settle the VAT as proposed by the contractor
or else appoint an adjudicator to resolve the issue.
Our review
From our review of the procurement documentation
Recommendations
in order to resolve the
same before making
payments on the same.
Management
comments
recommendati
on and will
seek further
advice from
procurement
experts.
Review area
Findings
(including contractual documents), we noted that
both agreements relating to this contractor indicated
the total contract sums without indicating whether
the same was inclusive or exclusive of VAT. Both
agreements also indicated that the agreement shall
prevail over all other contract documents such as the
letter of acceptance and the letter of bid among
other.
We also noted that the letter of bid did not state
whether the contract sum was inclusive of VAT or not
while the letter of acceptance from the contractor
stated that the contract sum was exclusive of VAT.
Further, the Bid Documents sent to the contractors
stated that all the prices shall be inclusive of taxes.
Analysis
Based on the fact that the bid documents obtained by
the contractor at the time of bidding stated that the
prices shall be inclusive of all taxes, it was clear to
the contractor that all the prices quoted would be
inclusive of taxes including VAT. Moreover, it was on
this basis that the Board conducted the evaluation
and selection of the best contractor, otherwise, the
contractors bid would have been non- compliant at
this stage.
The letter of acceptance issued by the contractor
purporting to exclude taxes from the contract sum
impliedly varied the terms of the bid documents. At
the point of receiving the letter of acceptance, the
Board should have considered seeking a clarification
from the contractor and if indeed the contractors
Recommendations
Management
comments
Review area
Findings
Recommendations
Management
comments
Management
agrees with
the
recommendati
on and will
open a Conflict
of Interest
Register for
Public
procurement
Review area
Findings
Recommendations
Management
comments
staff.
in a procurement process.
this purpose
Management
agrees with
the
recommendati
on and will
include this in
the evaluation
criteria in
future
procurements.
Review area
Findings
Recommendations
Management
comments
Employment
and labour
relations
obligations.
Management
agrees with
the
recommendati
on and will
commence the
registration
process
Lack of evidence of display of statement on
ASWB should display a
Management
employees rights
statement of employees rights agrees with
There was no evidence of a statement on employees in a conspicuous place.
the
rights displayed in a conspicuous place within the
recommendati
organisation. Section 15 of the Employment Act, 2007
on and will
requires the employer to informing employees of
draft and
their rights by displaying a statement of employees
display a
rights in a conspicuous place.
statement of
This implies that employees may not be fully aware of
employee
their rights due to the non-compliance.
rights.