Sie sind auf Seite 1von 43

A practical application of RCM principles at the

Cement Australia Railton plant


by
Dennis Knuckey Maintenance Manager &
Peter Johnson Maintenance Planner

CEMENT AUSTRALIA
Australian

Queensland

Cement

Cement &

P/L

Lime P/L

Cement supply & distribution

Cement & lime supply

in Tas, Vic & NSW

in Qld & NSW

Sales & marketing roles

Manufacturing in

in other states

Gladstone / Rockhampton Qld(1.7Mt)

Manufacturing in Kandos NSW(0.5Mt)


& Railton Tas (1.2Mt)
2

The Process we went


through
The trigger - the Asian crisis 1998 / cement imports 1999 / import parity / $15
challenge
Step 1 = Benchmarked current maintenance performance to
determine whats good
determine what can be improved
set a business target in $s
Step 2 = RCM trial process on no 5 Cement Mill system by Honeywell
Step 3 = find RCM type software and train in the use of for building Reliability Block Diagrams (RBDs) and for both Weibull analysis /
FMECA analysis (Failure Mode Effects and Criticality Analysis)

Step 4 = The actual project


3

STEP 1 = BENCHMARKING

Strategic Industries Research Foundation (Vic) (SIRF) contacted in mid 1998 to


perform a maintenance benchmark of the Railton site which they fed back to us in
November 1998
Their conclusions were -

Existing maintenance systems well defined and quite effective


However plant operating performance being achieved at above normal
maintenance expense
Possible savings in the order of $2.5 M which represents a reduction
from approx 4% ERV to 3% ERV (Equipment Replacement Value)
World best practice for a brand new, green field facility would approach
2.2% to2.5% ERV
Too many people maintaining
Too few resources planning

They recommended we adopt a Reliability Centred Maintenance approach


We set ourselves a target of $2M maintenance cost reduction p.a. within 2 years
Need to do so without adversely affecting annual production for business reasons
4

Step 2 = PILOT STUDY - NO 5 CEMENT MILL


Developed by Honeywell under the guidance of Craig Webb
Down loaded a 12 month period of breakdown data from our CMMS for all
machines in CM5 system and built a typical RBD diagram and showed us
how the FMECA process worked.
Conclusions were System availability was only 87% & 5 machines of the 28 machines in the
system were responsible for more than 80% of the failures
By reducing breakdowns by 50% the system availability would improve to
94%
50% reduction in breakdowns calculated to a direct maintenance savings of
approx $200k p.a
50% reduction in breakdowns would reduce the requirement to run the
smaller no 4 CM (60 tph c.f 130 tph) and save another $200k p.a.
He predicted that we would find this 20/80 rule in machines and in failure
modes throughout the plant and that our maintenance system was not aligned to
recurring failure modes. To test this we looked at breakdown work c.f planned
work from our CMMS.
5

Step 2 = PILOT STUDY - site wide planned /


unplanned work analysis
Planned v Breakdown
work orders

2000
1500
1000
500

-9
Ju 8
n98
Au
g98
O
ct
-9
D 8
ec
-9
Fe 8
b99
Ap
r-9
Ju 9
n99
Au
g99
O
ct
-9
D 9
ec
-9
9
Fe
b00
Ap
r-0
Ju 0
n0
Au 0
g00
O
ct
-0
D 0
ec
-0
0
Fe
b01
Ap
r-0
Ju 1
n0
Au 1
g01
O
ct
-0
D 1
ec
-0
Fe 1
b02

0
Ap
r

number of work orders

2500

Time
Breakdown events

Planned events

CONCLUSIONS:
1/. Planned w ork base w ork orders have decreased by approx. 250 per month
2/. Yet, unplanned w ork orders or events are static at approximately 230 per month
3/. Therefore, the site w ide MTBF is constant. I.e. the random failure rate has not changed
4/. Therefore the planned w ork IS NOT addressing the failures

Step 3 - software - AvSim & RCMCost by


Isograph, UK and represented in Australia by
ARMS Reliability Engineering

Step 3 - software - AvSim & RCMCost by


Isograph, UK and represented in Australia by
ARMS Reliability Engineering

Step 3 - software - AvSim & RCMCost by


Isograph, UK and represented in Australia by
ARMS Reliability Engineering

Lifetime costs simulated


over 10 years in this
example

Step 3 - software - AvSim & RCMCost by


Isograph, UK and represented in Australia by
ARMS Reliability Engineering

Typical Weibull
calculation from
failure data

10

"Bath tub curve" - Weibull

Failure rate f

Beta < 1

Beta = 1

Beta > 1

Random failure

Wear out failure

1
Infancy failure

Gamma

Time

11

Step 4 = The Actual Project

12

How will we do this ?

We have to align our maintenance strategies for poorly performing


machines to address actual failure modes that the machine is
experiencing
We have to challenge the maintenance strategy on machines that
perform well for probable over servicing
To do so, we need to determine which machines to investigate and
what specific failure modes these machines show.
By looking at what we currently do from our planned maintenance
system we can make choices to Delete / Add / Alter / existing pms so that the failure modes are addressed
Test the decision to change the maintenance choice using new Reliability
software

13

How will we do this ?

We have reasonable, historic work order data


The site has been broken up into 4 areas or missions Mining
Raw Milling
Clinkering
Cement / Despatch
We analysed 3 years breakdown work orders and for each major machine
within these 4 areas calculated Mean Time Between Failure (MTBF) and Mean Time To Repair (MTTR)
This enables us to calculate Machine Availability (A). Hence we can rate
machines by performance.
By using a pareto approach we will select the worst performing machines in
each area for FAILURE MODE analysis
We then check what our existing maintenance looks for and make the
necessary changes
14

Typical breakdown work order data for a single machine


M AJOR
M ACHINE NO.

WORK
ORDER NO.

WORK ORDER DESCRIPTION

EM PLOYEE
LABOUR
COST

WORK PERFORM ED

MACHINE NO. 1656 = MINE LIM ESTONE FEEDER


1 6 56

539328

CHECK BLOCKED FILTER ALARM IN HYD PUMP - NEW MINE

6 F G1PWM 23

1 6 56

543444

APRON FEEDER JAMMED

6 F G1BRH 22 10 1998 1 LIMESTONE FEEDER JAMMED CLEARED FEEDER AND

1 6 56

543444

APRON FEEDER JAMMED

6 F G1BRH 22 10 1998 2 ADJUSTED REGULATING VALVE TO CLEAR BLOCKAGE

1 6 56

544389

APRONFEEDER WONT RUN.

6 F G1PGM 20 11 1998 1 ADJUSTED PRESSURE TO MAX. 350BAR BUT COULD

1 6 56

544389

APRONFEEDER WONT RUN.

6 F G1PGM 20 11 1998 2 NOT MOVE FEEDER. ENDED UP DIGGING FEEDER

1 6 56

544389

APRONFEEDER WONT RUN.

6 F G1PGM 20 11 1998 3 OUT WITH EXCAVATOR

1 6 56

544389

APRONFEEDER WONT RUN.

6 E G1MRW 30 11 1998 1 ASSISTED FITTER UN-BLOCKING APRON FEEDER

1 6 56

554075

CHECK LOW TONNAGE OUTPUT FROM LIMESTONE FEEDER

6 E G1SKC 14

9 1999 1 CHECKED AND ALL OK ELECTRICALLY. SUSPECT FEED

1 6 56

554075

CHECK LOW TONNAGE OUTPUT FROM LIMESTONE FEEDER

6 E G1SKC 14

9 1999 2 CHUTE BLOCKAGE.

1 6 56

5 F G1PTM

4 2000 1 FOUND THAT LIMESTONE HAD JAMMED APRON FEEDER

3002870 LIMESTONE FEEDER JAMMED.

6 1998 1 CHECKED FILTER LOOKED OK CLEANED OUT ANYWAY

74.16
162.9

377.65
5.4
0
135.5

1 6 56

3002870 LIMESTONE FEEDER JAMMED.

5 F G1PTM

4 2000 2 ASKED QUARRY PERSONAL TO REMOVE LIMESTONE

1 6 56

3002870 LIMESTONE FEEDER JAMMED.

5 F G1PTM

4 2000 3 FEEDER.

1 6 56

3002379 NEW MINE APRON FEEDER ZSS TRIP

6 E G1DBC 12

4 2000 1 FEEDER JAMMED

1 6 56

3002379 NEW MINE APRON FEEDER ZSS TRIP

6 E G1DBC 12

4 2000 2 DUG OFF & ALL OK

1 6 56

3003861 1656 APRON FEEDER JAMMED

5 F G1BJB

5 2000 1 OPERATED APRON FEEDER MANUALLY, FEEDER STILL

135.57

1 6 56

3003861 1656 APRON FEEDER JAMMED

5 F G1BJB

5 2000 2 JAMMED, HOPPER HAD TO BE DUG OUT.

1 6 56

3003877 1656 LIMESTONE FEEDER JAMMED

6 F G1GB

5 2000 1 BOOSTED HYDRAULIC PRESSURE

130.39

1 6 56

3003290 LIMESTONE FEEDER TRIPPING ON LOW OIL PRESSURE

5 E G1GMB 29

8 2000 1 FITTER FOUND A BLOCKED VALVE

517.18

1 6 56

3003742 APRON FEEDER TRIPPING ON UNDERSPEED

5 E G1GMB 29

8 2000 1 VALVE FAULT,FITTER CALLED TO REPAI NOW OK.

188.16

1 6 56

3013353 CHECK MULTILIN ALARM ON 1656 LIMESTONE FEEDER

6 E G1SKC 22

1 2001 1 HOT ROOM CAUSED THERMISTER ALARM. RESET WHEN IT CO

1 6 56

3013353 CHECK MULTILIN ALARM ON 1656 LIMESTONE FEEDER

6 E G1SKC 22

1 2001 2 OLED DOWN.

1 6 56

200

541151

CHECK GREASE PUMP CUTTING OUT - NEW MINE

6 E G1DBC 12

8 1998 1 REPLACED EMPTY DRUM. ALL NOW OK.

1 6 56

200

541151

CHECK GREASE PUMP CUTTING OUT - NEW MINE

6 E G1DBC 12

8 1998 2 THE ALARMS FOR THIS NEED LOOKING AT. WHEN THE DRUM

1 6 56

200

541151

CHECK GREASE PUMP CUTTING OUT - NEW MINE

6 E G1DBC 12

8 1998 3 RUNS EMPTY THE PUMP DISABLES ITSELF AND THE ONLY

8 1998 4 ALARM IS CMD.LOCKED.

64.01
0
124.17

1 6 56

200

541151

CHECK GREASE PUMP CUTTING OUT - NEW MINE

6 E G1DBC 12

1 6 56

200

555498

CHECK 1656 GREASE PUMP

6 F G1PWM 1 10 1999 1 REPLACED M/T DRUM

1 6 56

200

555498

CHECK 1656 GREASE PUMP

6 F G1PWM 1 10 1999 2 PUMP TOOK 45MIN TO BUILDUP PRESSURE

1 6 56

200

3001423

MINE APRON FEEDER GREASE PUMP STOPPING

6 E G1DBC 29

2 2000 1 CHECKED BUT FOUND NOTHING

1 6 56

200

3001423

MINE APRON FEEDER GREASE PUMP STOPPING

6 E G1DBC 29

2 2000 2 NEED TO SEE IT IN OPERATION

1 6 56

200

3002888 RELIEF VALVE HOSE ON GREASE PUMP BROKEN -A/FEEDER

5 F G1BJB

4 2000 1 SHORTENED HOSE BY 25MM, FITTED 12.5 S/S TUBE

1 6 56

200

3002888 RELIEF VALVE HOSE ON GREASE PUMP BROKEN -A/FEEDER

5 F G1BJB

4 2000 2 INSIDE HOSE FOR COMPRESSION OLIVE TO SEAT ONTO,

1 6 56

200

3002888 RELIEF VALVE HOSE ON GREASE PUMP BROKEN -A/FEEDER

5 F G1BJB

4 2000 3 REFITTED HOSE - TESTED PUMP O.K.

1 6 56

200

3003878 LIMESTONE FEEDER GREASE PUMP NOT WORKING

6 F G1GB

1 6 56

200

3006989 LIMESTONE FEEDER GREASE PUMP CUT OUT

6 F G1PGM 17

7 2000 1 PUMP CUT OUT -BUILT UP PRESSURE BUT HAD'NT

1 6 56

200

3006989 LIMESTONE FEEDER GREASE PUMP CUT OUT

6 F G1PGM 17

7 2000 2 CHANGED OVER - CRACKED DISCHARGE LINES , PUT

1 6 56

200

3006989 LIMESTONE FEEDER GREASE PUMP CUT OUT

6 F G1PGM 17

7 2000 3 PUMP ON LOCAL AND TEST RAN, CHANGED OVER OK

1 6 56

200

3006989 LIMESTONE FEEDER GREASE PUMP CUT OUT

6 F G1PGM 17

7 2000 4 RAN FOR 10MIN CHANGING OVER BOTH WAYS OK

1 6 56

200

3008475 CHECK 1656 GREASE PUMP OUT ON O/L

6 E G1BJE 17

8 2000 1 REPLACED GREASE DRUM AND RESET PUMP.

638.56
321.37

129.17
0
106.14
0
175.45

5 2000 1 REPLACED EMPTY DRUM / PUMP THEN OK

123.94
46.66

1 6 56

200

3008476 CHECK 1656 GREASE PUMP FAULT

5 F G1PLB 17

8 2000 1 CHANGE OVER VALVE WAS STUCK, RELEASED PRESSURE

1 6 56

200

3008476 CHECK 1656 GREASE PUMP FAULT

5 F G1PLB 17

8 2000 2 & IT STARTED TO WORK AGAIN OK.

1 6 56

200

3008809 INSPECT GREASE LINE FAULT ON FEEDER GREASE PUMP

5 F G1BJB 26

8 2000 1 CHECKED GREASE PUMP SYSTEM - CHANGE OVER VALVE

1 6 56

200

3008809 INSPECT GREASE LINE FAULT ON FEEDER GREASE PUMP

5 F G1BJB 26

8 2000 2 STUCK IN ONE POSITION, BLED OFF PRESSURE THEN

1 6 56

200

3008809 INSPECT GREASE LINE FAULT ON FEEDER GREASE PUMP

5 F G1BJB 26

8 2000 3 RESTARTED.

1 6 56

200

3008622 HIGH DIFFERENTIAL PRESSURE ON PUMP.

6 E G1NPR

6 10 2000 1 RELEASED PRESSURE OUT OF GREASE LINES.

1 6 56

200

3008622 HIGH DIFFERENTIAL PRESSURE ON PUMP.

6 E G1NPR

6 10 2000 2 SYSTEM STARTED WORKING OK.

1 6 56

200

3010936 CHECK LIMESTONE FEEDER GREASE PUMP FAULT.

6 E G1SKC 10 10 2000 1 TOOK GREASE LINE OFF AND CHANGED OVER PRESSURE

1 6 56

200

3010936 CHECK LIMESTONE FEEDER GREASE PUMP FAULT.

6 E G1SKC 10 10 2000 2 SWITCH. RESET OK.

NO EVENTS

23

0
24.31

199.36

15

0
35.19
0
3715.24

MACHINE NO. 3030 = STACKER

PURCHASES COST

STORES COST

EMP. LABOUR COST

AVAILABILITY

MTTR

MTBF

OPERATING EST.HOURS

HOURS

% OF CUMULATIVE TOTAL
EVENTS

% OF TOTAL EVENTS

NO. OF B/DOWN OR
UNPLANNED WORK ORDERS

MACHINE DESCRIPTION

A Summary of Breakdown data for the Mine Section

109

32.15%

32.15%

539.595

4500

41

4.95

0.8929

59424.15

3107.51

16369.08

MACHINE NO. 1658 = MINE CRUSHER

53

15.63%

47.79%

665.23

4500

85

12.55

0.8712

56404.89

158039.71

13765.54

MACHINE NO. 1660 = MINE CRUSHER DISCHARGE CONVEYOR

49

14.45%

62.24%

215.785

4500

92

4.40

0.9542

15052.62

30437.71

14803.79

MACHINE NO. 1656 = MINE LIMESTONE FEEDER

23

6.78%

69.03%

45.095

4500

196

1.96

0.9901

3715.24

80.97

119.4

MACHINE NO. 3025 = STACKER FEED CONVEYOR

19

5.60%

74.63%

30.4

4500

237

1.60

0.9933

2216.94

962.3

95

MACHINE NO. 1675 = MINE TRUNK CONVEYOR

17

5.01%

79.65%

26.625

4500

265

1.57

0.9941

2246.95

1237.09

1067.42

MACHINE NO. 1657 = MINE LIMESTONE FEEDER SPIILAGE CONVEYOR

16

4.72%

84.37%

40.04

4500

281

2.50

0.9912

3207.34

160.35

1961.89

MACHINE NO. 3022 = ANALYSER INLET CONVEYOR

16

4.72%

89.09%

19.59

4500

281

1.22

0.9957

1466

1563.48

3757.92

MACHINE NO. 1661 = MINE CRUSHER DISCHARGE SPILLAGE CONVEYOR

10

2.95%

92.04%

28.27

4500

450

2.83

0.9938

2431.46

1500.22

128.2

MACHINE NO. 1682 = MINE TRANSFER CONVEYOR

1.77%

93.81%

14.28

4500

750

2.38

0.9968

1106.54

611.87

MACHINE NO. 1652 =MINE CRUSHER MAINTENANCE CRANE

1.18%

94.99%

6.02

4500

1125

1.51

0.9987

262.44

1780.2

MACHINE NO. 1680 = MINE TRANSFER TOWER

1.18%

96.17%

14.765

4500

1125

3.69

0.9967

927.68

312.76

1127.54

MACHINE NO. 1699 = MINE CRUSHER OTHER

0.88%

97.05%

2.93

4500

1500

0.98

0.9993

135.87

36

MACHINE NO. 3023 = CROSSBELT ANALYSER

0.88%

97.94%

10.9

4500

1500

3.63

0.9976

339.74

MACHINE NO. 1650 = MINE STRUCTURE

0.59%

98.53%

1.12

4500

2250

0.56

0.9998

36.2

MACHINE NO. 1655 = MINE LIMESTONE HOPPER

0.59%

99.12%

2.45

4500

2250

1.23

0.9995

118.17

14

MACHINE NO. 1662 = MINE CRUSHER DUST COLLECTOR

0.59%

99.71%

3.25

4500

2250

1.63

0.9993

151.35

470.89

MACHINE NO. 1663 = MINE CRUSHER AIR COMPRESSOR

0.29%

100.00%

4.32

4500

4500

4.32

0.9990

208.73

12.19

16

17

18

Forming Failure Mode data from the work order data for a single
machine - sheet 1

Empl $

MACHINE NO. 1656 = MINE LIMESTONE FEEDER

Str

1 6 56

0 139454 COMMISSION NEW T.P.HOUR INDICATOR - MINE

1 E G1TER

28

5 1998

1 JOB DONE BY INSTRUMENT DEPT.

1 6 56

0 539328 CHECK BLOCKED FILTER ALARM IN HYD PUMP - NEW MINE

6 F G1PWM 23

6 1998

1 CHECKED FILTER LOOKED OK CLEANED OUT ANYWAY

1 6 56

0 539544 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1PLB

14

7 1998

1 COMPLETED AS PER INSTRUCTION, NOTHING UNUSUALL

1 6 56

0 539964 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1BJM

27

7 1998

1 1656C GREASE PUMP IS CHANGING OVER AT LESS THAN

159.55

1 6 56

0 540491 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1IDS

10

8 1998

1 APRON FEEDER WAS JAMMED BUT ALL LOOKED OK

222.64

22.28

1 6 56 200 541151 CHECK GREASE PUMP CUTTING OUT - NEW MINE

6 E G1DBC

12

8 1998

1 REPLACED EMPTY DRUM. ALL NOW OK.

124.17

1 6 56

0 540995 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1BJB

25

8 1998

1 ONLY HAD SHORT AMOUNT OF TIME TO INSPECT APRON-

1 6 56

0 541931 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1JJL

14

9 1998

1 6 56

0 542380 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1BJB

28

9 1998

1 6 56

0 542874 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1BJB

12 10 1998

1 6 56

0 543444 APRON FEEDER JAMMED

6 F G1BRH

22 10 1998

1 LIMESTONE FEEDER JAMMED CLEARED FEEDER AND

1 6 56

0 543293 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1IRS

26 10 1998

1 CHECKED AS PER SCHEDULE O/K

138.28

1 6 56

0 541456 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1PGM

16 11 1998

1 CHECKED AS PER METHOD SHEET OK

102.32

29

1 6 56

0 544058 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1BJB

16 11 1998

1 CHECKED AS PER SCHEDULE. COULD NOT RUN APRON

100.96

1 6 56

0 544389 APRONFEEDER WONT RUN.

6 F G1PGM

20 11 1998

1 ADJUSTED PRESSURE TO MAX. 350BAR BUT COULD

377.65

1 6 56

0 544464 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1BJB

30 11 1998

1 INSPECTED AS PER SCHEDULE - FOUND SLIDE RAIL LUBE

391.1

1 6 56

0 544997 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1JH

14 12 1998

1 CLEANED HYDRAULIC POWER PACK UP AND SWEPT ROOM

421.88

1 6 56
1 6 56

0 547255 NEW MINE APRON FEEDER - TWO WEEKLY INSP


0 547520 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1GKH
7 F G1JJL

22
8

1 ONLY VISUAL INSPECTION CARRIED OUT DUE TO HOPPER


1 CHEKED ALL OKAY.APRON FEEDER FULL COULD TEST RUN

104.23
161.5

0
0

1 6 56

0 547984 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1GAW 22

3 1999

1 CHECKED AND OK

193.04

81.2

1 6 56

0 548409 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1JMH

4 1999

1 CHECKED AS PER METHOD 0128. FOUND THE APRON FEEDER

467.14

1 6 56

0 548863 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1BRH

19

4 1999

1 HAVE CHANGED GREASE DRUM ON 1656C PUMP.FITTED

375.97

1 6 56

0 550337 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1GAW 31

5 1999

1 ALL CHECKED AND OK

291.03

1 6 56

0 550751 REPAIR FEEDER ACCESS DOORS

1 F G1PWM

6 1999

1 TEMP REPAIR ONLY CHANGED TO M/SHUTDOWN W/O

102.83

10.18

1 6 56

0 550725 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1JJL

11

6 1999

1 CHECKED ALL OKAY.

105.62

35

1 6 56

0 551300 REPAIR GUARD AT HEAD END OF APRON FEEDER.

1 F G1DEJ

29

6 1999

1 WELDED LUGS BACK ONTO SIDE OF BIN TO BOLT GUARD TO

278.16

68.47

1 6 56

0 552211 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1GB

30

7 1999

1 CHECKED AS PER W/O----OK

258.41

1 6 56

0 553209 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1BRH

8 1999

1 HAVE INSPECTED HYDRAULICS AS REQUIRED.OK.

293.49

7.39

1 6 56

0 553634 NEW MINE APRON FEEDER - TWO WEEKLY INSP

7 F G1PGM

20

8 1999

1 HYDRAULIC POWERPACK AND LINES OK - SLIGHT LEAK ON

293.49

1 6 56

0 553792 CUT OFF REMAINS OF DAMAGED RIPPER BARS ON FLIGHTS 1 F G1PTM

20

8 1999

1 CUT OUT DAMAGE RIPPER BARS AND GRIND FLIGHTS

127.09

29.54

1 6 56

0 550751 REPAIR FEEDER ACCESS DOORS

1 F G1BJM

30

8 1999

1 REPAIRED ALL ACCESS DOORS TO LIMESTONE FEEDER.

308.49

30.53

1 6 56

0 554075 CHECK LOW TONNAGE OUTPUT FROM LIMESTONE FEEDER

6 E G1SKC

14

9 1999

1 CHECKED AND ALL OK ELECTRICALLY. SUSPECT FEED

1 6 56 200 555498 CHECK 1656 GREASE PUMP

6 F G1PWM

2 1999
3 1999

1 10 1999

6.2

74.16

28.03

1 CHECKED AS REQUIRED ALL OKAY

122.62

11.35

1 INSPECTED AS PER SCHEDULE. NO PROBLEMS FOUND ALL

286.81

1 INSPECTED AS PER SCHEDULE, ALL O.K.

101.68

7.7

162.9

1 REPLACED M/T DRUM

5.4

129.17

19

Forming Failure Mode data from the work order data for a single machine
- sheet 2

Com ponent Function

Functional Failure

Apron Feeder
Apron Feeder To provide motive pow er to f eeder

Failure Mode

Start date Fail date

Days run Op Hrs 6.3

Effects

Probable cause

Alarm

Blocked filter

1-Apr-98

23-Jun-98

83

519 S

Grease drum empty

Alarm

Empty grease drum

1-Apr-98 12-Aug-98

133

831 F

Feeder jamming

Feeder trips Rock jamming f eeder

1-Apr-98

204

1275 S

Feeder jamming

Feeder trips Rock jamming f eeder 22-Oct-98 20-Nov-98

TPH Indicator
Fails to provide motive pow er

Oil f ilter failure

7
7

Grease pump

7
Grease pump To provide adequate grease supply

Feeder jamming
Fails to supply grease at all

7
7
7
7
Apron Feeder To transport material to crusher at design rate Fails to transport material at all

22-Oct-98

7
7
7
Apron Feeder To transport material to crusher at design rate Fails to transport material at all

29

181 S

1-Apr-98 30-Nov-98

243

1519 S

High oil temp. Blocked cooler

1-Apr-98 14-Dec-98

257

1606 S

Spillage

1-Apr-98

23-Jun-98

83

519 S

30-Nov-98

Grease pump To provide adequate grease supply

Fails to supply adequate grease Change over valve failure No grease

Apron Feeder To provide hydraulic oil cooling

Fails to provide hydraulic oil cooli Oil cooler failure

7
7

Valve sticking

Bearing housing w edge

7
7
7

Grease drum empty

7
Apron Feeder To contain spillage

Fails to contain spillage

Access door failure

Door damaged

7
Apron Feeder

Guard repairs

7
Grease pump To provide adequate grease supply

Fails to supply adequate grease Change over valve failure No grease

Grease pump To provide adequate grease supply

Fails to supply adequate grease Grease line f ailure

Apron Feeder To transport material to crusher at design rate Fails to transport at design rate

Ripper bar f ailure

Apron Feeder To contain spillage

Access door failure

Fails to contain spillage

Valve sticking

6-Aug-99

249

1556 S

1-Apr-98 20-Aug-99

506

3163 S

Bars damaged

1-Apr-98 20-Aug-99

506

3163 S

Door damaged

23-Jun-98 30-Aug-99

433

2706 F

Grease spilla Loose f ittings


Spillage

Apron Feeder To transport material to crusher at design rate Fails to transport material at all

Feeder jamming

Feeder trips Rock jamming f eeder 20-Nov-98 14-Sep-99

298

1863 S

Grease pump To provide adequate grease supply

Grease drum empty

Alarm

415

2594 F

Fails to supply grease at all

Empty grease drum

12-Aug-98

1-Oct-99

20

Forming Failure Mode data from the work order data for a single machine sheet 3

Effects

Probable cause

Access door failure

Spillage

Door damaged

1-Apr-98 23-Jun-98

83

519 S

Access door failure

Spillage

Door damaged

23-Jun-98 30-Aug-99

433

2706 F

Apron feeder flight failure

Spillage

Bent / damaged

1-Apr-98 21-Dec-99

629

3931 F

Apron feeder flight failure

Spillage

Bent / damaged

21-Dec-99 13-Dec-00

358

2238 F

Skirt failure

Spillage

Wear / abrasion

1-Apr-98 21-Aug-00

873

5456 S

Skirt failure

Spillage

Wear / abrasion

Ripper bar f ailure


Ripper bar f ailure

Start date Fail date

Days run Op Hrs

6.25 RCM NO.

Failure Mode

21-Aug-00 23-Mar-01

214

1338 S

Bars damaged

1-Apr-98 20-Aug-99

506

3163 S

Bars damaged

20-Aug-99 21-Dec-99

123

769 F

1-Apr-98 22-Oct-98

204

1275 F

Feeder jamming

Feeder trips

Rock jamming feeder

Feeder jamming

Feeder trips

Rock jamming feeder

22-Oct-98 20-Nov-98

29

181 F

Feeder jamming

Feeder trips

Rock jamming feeder

20-Nov-98 14-Sep-99

298

1863 F

Feeder jamming

Feeder trips

Rock jamming feeder

14-Sep-99

7-Apr-00

206

1288 F

Feeder jamming

Feeder trips

Rock jamming feeder

7-Apr-00 12-Apr-00

31 F

Feeder jamming

Feeder trips

Rock jamming feeder

12-Apr-00

3-May-00

21

131 F

ETA BETA

CORRECTIVE

8.00 28.73

1656-11A2

1.34 38.26 3427.47 3 0.90 30.59 30

1656-11A3

1.34 44.90

1656-12A1

8.00 31.77 1784.76 2 0.60 30.59 30

Feeder trips

Rock jamming feeder

3-May-00

8-May-00

31 F

1656-12B1

Oil cooler failure

High oil temp.

Blocked cooler

1-Apr-98 14-Dec-98

257

1606 S

1656-21A1
1656-22A1

1.73 42.87

0.00

8.21 42.93

0.00

Alarm

Blocked filter

1-Apr-98 23-Jun-98

83

519 S

Valve failure

No oil flow

Blocked valve

1-Apr-98 13-Apr-00

743

4644 F

Valve failure

No oil flow

Blocked valve

13-Apr-00 29-Aug-00

138

Hydraulic pressure transducer


Hydraulic pump
Hydraulic pump

863 S

1656-22A2

29-Jan-01

1656-22A3

1-Jun-95

S
S

Hydraulic pump
Multilin f ailure

Alarm

Room temp. too high

1-Apr-98 21-Jan-01

Change over valve failure

No grease

Valve sticking

Change over valve failure

No grease

Valve sticking

30-Nov-98

Change over valve failure

No grease

Valve sticking

Change over valve failure

No grease

Valve sticking

Change over valve failure

No grease

Change over valve failure

1-Apr-98 30-Nov-98

1026

1656-22A4

6413 S

1656-31A1

243

1519 F

6-Aug-99

249

1556 F

6-Aug-99

17-Jul-00

346

2163 F

17-Jul-00

4-Aug-00

18

113 F

Valve sticking

4-Aug-00 17-Aug-00

13

81 F

No grease

Valve sticking

17-Aug-00 26-Aug-00

56 F

Change over valve failure

No grease

Valve sticking

26-Aug-00

6-Oct-00

41

256 F

Change over valve failure

No grease

Valve sticking

6-Oct-00 10-Oct-00

25 F

INSPECTIONS

1656-11A1

Feeder jamming
Oil filter failure

PREVENTIVE

1656-41A1

617

0.00 2 0.60 30.59 30

0.57 3.24 41.75 17.06

0.90 30.59 30
13.62 31.00

0.00
1.37 46.72

0.00

0.00 19.08 31.75

0.6 3.16 38.72 13.00

0.00 1
0.30 30.59 30

57.04 31.72

594

765.24 3

8.00 37.33

932.22 1

509.11 3 0.90 30.59 30


310.74 3

10.40 1 0.60 30.59 30

21

22

Mine Crusher Apron Feeder

85 t capacity haul trucks

400 tonnes capacity hopper

Matl into crusher


17 metres

Hydraulic drive
Average capacity = 200 t

Lubricated impact bars

Apron feeder

Coefficients of friction:
Steel on steel lubricated = 0.05
Steel on stell dry = 0.2
Steel on steel limiting friction = 0.3
Frictional drag:
Lubricated = 10 tonnes
Dry = 40 tonnes
Stalled = 60 tonnes

23

24

25

26

27

28

29

30

Documenting the optimising process

Maintenance Strategy DecisionTree


Select the failure mode and have its root cause known
Step 1

Are any of the current maintenance inspections, PM's or schedules aimed at the
failure mode?
If not then eliminate the existing maintenance strategies
If so is it aimed at root cause or does it need modifying?

Yes

Retain

Step 2

Of those remaining inspections, PM's or schedules tied to this machine are any
adding value to detecting failure modes? If not then eliminate.

Yes

Retain

Step 3

Can the failure mode be tolerated?


So what if it occurs?
Is the risk acceptable?

Yes

Run to failure

Step 4

Can the onset of the failure mode be detected?


Is there a potential failure condition I can detect?
Is the p-f interval long enough for response?

Yes

Specify a predictive maintenance task

Step 5

Can the failure mode be prevented from acting?


Can I predict a wear out age?
Will sufficient items last to wear out?

Yes

Specify a preventive maintenance task

Step 6

Can instrumentation pick up an alarm condition


Will I have time to repsond?

Yes

Install a condition monitoring system

Step 7

Is the failure mode hidden?


Will an operator know if it fails in normal operation?

Yes

Specify hidden failure finding task

Step 8

Select the best strategy


Does it meet your goals and objectives?

Yes

Implement

No

Change design - capital solution

31

Documenting the optimising process

As is costs

Optimised costs

GREASE PUMP

Maintenance strategy

1656-41A1 Change over valve failure


$482

594 Yes

Corrective

Yes

$146

6843 Yes

Preventive

Nil

$441

228 Yes

$0

Nil

50%

$241

Prepared to run to failure with new Woerner lube system

$0

Inspections

Nil

$0

Remove inspection schedules

On condition

Nil

$0

Capital expediture to replace grease pump which is unreliable & is causing

TOTAL $1,069

$241 TOTAL

$828 a large majority of jamming problems

1656-41A2 Grease line failure


$81

6843 Yes

$0

Nil

$132

228 Yes

$0
TOTAL

Nil

Corrective

Yes

Preventive

Nil

Inspections

Yes

On condition

Nil

50%

$50

20

$115

$0
$0

$213

$165 TOTAL

Keep as part of walk around inspection


Capital expediture to replace grease pump which is unreliable & is causing
$48 a large majority of jamming problems

1656-41B1 Grease drum empty


$523

1589 Yes

$0

Nil

$132

228 Yes

$0
TOTAL

Nil

Corrective

Yes

Preventive

Nil

Inspections

Yes

On condition

Nil

$656

50%

$188
$0

40 hrs

$172
$0
$360 TOTAL

New Woernersystem has its own supplementary reservoir of approx 8 litres capacity. Hence we can
schedule drum changes on alarm without stopping the plant.
Keep as part of a visual schedule check by Shane Dennis 2 weekly
Capital expediture to replace grease pump which is unreliable & is causing
$296 a large majority of jamming problems

1656-41B2 Grease pump failure


$0

Nil

Corrective

Nil

$0

$0

Nil

Preventive

Nil

$0

$119

3422 Yes

$0
TOTAL

Nil
$119

Inspections

Nil

$0

On condition

Nil

$0
$0 TOTAL

Prepared to run to failure as new system very reliable and well protected

Capital expediture to replace grease pump which is unreliable & is causing


$119 a large majority of jamming problems

32

Project control spreadsheet

Summary of Project Development YEM99-2004


Section

Cement
Mining
Raw milling
Clinkering

Total
machines to be
investigated
65
9
27
33

YEM 99-2004

134

Original YEM99-01

79

Models
completed

FMECA
ready

65
9
27
33

57
9
21
22

134
100.0%
79

109
81.3%
79

Review
completed
& initiated
37
4
16
9
66
49.3%
65

Completed

27
0
8
4
39
29.1%
49%

33

Project control spreadsheet


E L E C T R IC A L
AREA

LAB. & M AT.

F IT T IN G
HOURS

LAB. & M AT.

S E R V IC E S

HOURS

LAB. & M AT.

HOURS

LAB. & M AT. HOURS

$ 5 ,1 0 5

113

$ 1 3 ,5 3 7

278

$0

S a v i n g s t a r g e t f it t i n g = 1 6 % o f 2 5 0 0 h r s

R A W M IL L IN G

$ 2 7 ,7 2 2

616

$593

14

$0

S a v i n g s t a r g e t f it t i n g = 1 7 % o f 2 5 0 0 h r s

C L IN K E R IN G

$ 2 1 ,3 6 0

475

$0

S a v i n g s t a r g e t f it t i n g = 2 9 % o f 2 5 0 0 h r s

CEMENT

$ 3 5 ,9 2 8

798

$0

S a v i n g s t a r g e t f it t i n g = 3 8 % o f 2 5 0 0 h r s

F IX E D

$ 2 2 ,9 6 7

510

$ 1 1 3 ,0 8 2

2 ,5 1 3

M IN E

TOTALS

$ 1 4 ,1 3 0

$0

292

$0

$ 1 2 7 ,2 1 2

2 ,8 0 5

$ 1 ,0 4 2 ,7 1 4

5 ,1 9 9

M a c h in e s w ith L o w M e a n T im e B e tw e e n F a ilu r e - C U M U L A T IV E A N N U A L IS E D C O S T S A V IN G S
Y E M 9 9 -0 3
b y r e d u c in g fa ilu r e m o d e s
E L E C T R IC A L
AREA

LAB. & M AT.

F IT T IN G
HOURS

LAB. & M AT.

S E R V IC E S

HOURS

LAB. & M AT.

HOURS

M IN E

$ 2 3 ,3 1 9

104

$ 1 2 6 ,5 5 9

633

$ 3 ,3 1 9

19

R A W M IL L IN G

$ 1 3 ,7 7 7

61

$ 2 3 3 ,3 4 0

1 ,1 6 7

$ 1 3 ,7 7 7

79

$ 1 ,2 1 5

$ 1 2 1 ,1 1 3

606

$ 1 ,2 1 5

$ 3 4 ,6 4 0

154

$ 4 5 2 ,7 8 0

2 ,2 6 4

$ 1 7 ,6 6 0

101

$ 7 2 ,9 5 1

324

$ 9 3 3 ,7 9 2

4 ,6 6 9

$ 3 5 ,9 7 1

206

C L IN K E R IN G
CEMENT
NON AREA

TOTALS

T o ta l H ig h M T B F s a v in g s =
T o ta l L o w M T B F s a v in g s =

$ 1 2 7 ,2 1 2
$ 1 ,0 4 2 ,7 1 4

T o ta l s a v in g s =
T o ta l m a n h o u rs =

$ 1 ,1 6 9 ,9 2 6
8 ,0 0 3

34

Project control spreadsheet

Description

Base Year
YEM99 - 01

YEM02

YEM03

YED2003

Note: Anything over 1% is highly significant

Unavailability Unavailability Unavailability Unavailability

Mining
MACHINE NO. 1655 = MINE LIMESTONE HOPPER
MACHINE NO. 1656 = MINE LIMESTONE FEEDER
MACHINE NO. 1657 = MINE LIMESTONE FEEDER SPIILAGE CONVEYOR
MACHINE NO. 1658 = MINE CRUSHER
MACHINE NO. 1660 = MINE CRUSHER DISCHARGE CONVEYOR
MACHINE NO. 1661 = MINE CRUSHER DISCHARGE SPILLAGE CONVEYOR
MACHINE NO. 1662 = MINE CRUSHER DUST COLLECTOR
MACHINE NO. 1663 = MINE CRUSHER AIR COMPRESSOR
MACHINE NO. 1675 = MINE TRUNK CONVEYOR
MACHINE NO. 1680 = MINE TRANSFER TOWER
MACHINE NO. 1682 = MINE TRANSFER CONVEYOR
MACHINE NO. 1683 = MINE TRANSFER DUST COLLECTOR
MACHINE NO. 1698 = MINE MCC
MACHINE NO. 3022 = ANALYSER INLET CONVEYOR
MACHINE NO. 3023 = CROSSBELT ANALYSER
MACHINE NO. 3025 = STACKER FEED CONVEYOR
MACHINE NO. 3030 = STACKER

54.80%
0.10%
8.93%
1.37%
26.26%
7.51%
0.62%
0.17%
0.04%
1.11%
0.41%
0.31%
0.00%
0.00%
0.97%
0.13%
1.49%
10.30%

44.47%
0.31%
4.53%
0.56%
30.79%
2.96%
0.09%
0.00%
0.02%
1.20%
0.04%
0.35%
0.00%
0.00%
0.54%
0.13%
0.14%
4.27%

34.33%
0.11%
3.13%
4.05%
11.17%
7.96%
0.45%
0.00%
0.00%
0.70%
0.00%
0.00%
0.00%
0.00%
0.78%
0.27%
0.00%
6.46%

33.50% Improved 39%


1.80%
1.01%
Lube system upgraded
0.53%
20.17%
Broken shafts
4.03%
0.00%
0.30%
0.00%
0.20%
Tail end zero speed
0.00%
0.08%
0.08%
0.19%
1.36%
0.44%
0.56%
3.00%
Improved but need more

35

Project control spreadsheet


Description

Base Year
YEM99 - 01

YEM02

YEM03

YED2003

Note: Anything over 1% is highly s

Unavailability Unavailability Unavailability Unavailability

CM5
MAJOR MACHINE 6100 = C.M.5. BUILDING
MAJOR MACHINE 6105 = C.M.5. DRIVE MOTOR
MAJOR MACHINE 6112 = C.M.5. MAIN GEARBOX
MAJOR MACHINE 6115 - C.M.5. AUXILLARY DRIVE
MAJOR MACHINE 6122 = C.M.5. BALL MILL
MAJOR MACHINE 6125 = CM5 SCHENCK MULTICONT CONTROLLER
MAJOR MACHINE 6130 = C.M.5. CLINKER BIN
MAJOR MACHINE 6132 = C.M.5. GYPSUM BIN
MAJOR MACHINE 6133 = C.M.5. LIMESTONE BIN
MAJOR MACHINE 6140 = C.M.5. CLINKER WEIGHFEEDER
MAJOR MACHINE 6141 = C.M.5. LIMESTONE WEIGHFEEDER
MAJOR MACHINE 6142 = CM5 GYPSUM WEIGHFEEDER
MAJOR MACHINE 6143 - C.M.5. LIMESTONE CONVEYOR
MAJOR MACHINE 6144 = C.M.5. MILL FEED CONVEYOR
MAJOR MACHINE 6146 = C.M.5. BUCKET ELEVATOR
MAJOR MACHINE 6150 = C.M.5. SEPERATOR
MAJOR MACHINE 6158 = CM5 DUST CYCLONE
MAJOR MACHINE 6159 = C.M.5. DUST CYCLONE FAN
MAJOR MACHINE 6160 = C.M.5. LURGI PROCESS FILTER
MAJOR MACHINE 6161 = C.M.5. LURGI FILTER EXHAUST FAN
MAJOR MACHINE 6165 = C.M.5. IBAU PUMP & DOME VALVES
MAJOR MACHINE 6166 = C.M.5. TWO WAY VALVES
MAJOR MACHINE 6167 = C.M.5. COMPRESSOR
MAJOR MACHINE 6170 = C.M.5. ANCILLARY DUST COLLECTOR
MAJOR MACHINE 6198 = MCC61

10.46%

11.23%

1.87%

0.07%
0.17%
0.02%
2.23%
1.51%
0.00%
0.09%
0.02%
0.00%
0.34%
0.08%
0.00%
0.00%
0.30%
1.50%
0.33%
0.00%
0.04%
0.65%
1.20%
1.67%
0.05%
0.12%
0.05%
0.00%

0.04%
0.10%
0.21%
0.20%
4.89%
0.00%
0.22%
0.00%
0.00%
0.39%
0.13%
0.00%
0.00%
0.16%
2.70%
0.19%
0.00%
0.02%
0.51%
0.05%
1.33%
0.01%
0.00%
0.06%
0.00%

0.02%
0.19%
0.00%
0.01%
0.10%
0.00%
0.05%
0.00%
0.00%
0.16%
0.00%
0.00%
0.03%
0.17%
0.24%
0.35%
0.00%
0.00%
0.09%
0.09%
0.33%
0.00%
0.02%
0.00%
0.00%

4.90% Improved 53%


0.03%
0.05%
0.00%
0.00%
0.12%
0.00%
0.06%
0.00%
0.00%
0.81%
0.24%
0.00%
0.03%
0.07%
1.07%
0.55%
0.00%
0.07%
0.06%
0.03%
1.24%
0.00%
0.32%
0.00%
0.14%

Belts -Local supplied belts

Grit return dust. Feed chu


Belt failure caused this
Replaced rotor Jan 2003

Holed front blast plate


Impeller / NDE brg
Includes Dome valves

36

Project control spreadsheet


Description

Base Year
YEM99 - 01

YEM02

YEM03

YED2003

Unavailability Unavailability Unavailability Unavailability

Z and Z1 Silos
MAJOR MACHINE 6816 = Z. SILO
MAJOR MACHINE 6820 = Z. SILO DUST COLLECTOR
MAJOR MACHINE 6825 = Z. SILO AERATION
MAJOR MACHINE 6830 = IBAU PUMP
MAJOR MACHINE 6840 = LOADING HOSES Z & Z1 SILO
MAJOR MACHINE 6845 = Z.SILO DISCH. AIRSLIDE TO PUMP 6830
MAJOR MACHINE 6850 = DUST COLLECTOR ON PUMP 6830
MAJOR MACHINE 6860 = IBAU PUMP
MAJOR MACHINE 6875 = Z SILO DISCHARGE A/SLIDE TO PUMP 6860
MAJOR MACHINE 6877 = CEMENT LINES Z & Z1 SILOS
MAJOR MACHINE 6878 = CONTROL PLC & COMPUTER
MAJOR MACHINE 6880 = DUST COLLECTOR FOR PUMP 6860
MAJOR MACHINE 6885 = Z1 SILO
MAJOR MACHINE 6886 = Z1 SILO ROOF D/COLLECTOR
MAJOR MACHINE 6887 = Z1 SILO AERATION & CONT.AIR
MAJOR MACHINE 6888 = Z1 SILO IBAU PUMP
MAJOR MACHINE 6889 = Z1 SILO DISCH. AIRSLIDE TO PUMP 6888
MAJOR MACHINE 6890 = Z1 DUST COLLECTOR ON PUMP 6888
MAJOR MACHINE 6891 = Z1 IBAU PUMP
MAJOR MACHINE 6892 = Z1 DISCH.AIRSLIDE TO PUMP 6891
MAJOR MACHINE 6893 = DUST COLLECTOR ON PUMP 6891
MAJOR MACHINE 6894 = Z1 SILO VENT FAN
MAJOR MACHINE 6895 = Z1 CONTROL PLC & COMPUTER
MAJOR MACHINE 6896 = ROAD TRUCK SYSTEM
MAJOR MACHINE 6898 = MCC68

20.49%

33.99%

12.62%

0.45%
0.13%
1.94%
2.91%
2.34%
0.70%
0.04%
3.90%
0.10%
2.02%
1.82%
0.40%
0.26%
0.01%
0.45%
0.71%
0.41%
0.19%
1.53%
0.04%
0.01%
0.00%
0.62%
0.00%
0.00%

0.63%
0.87%
0.00%
2.10%
2.76%
1.46%
0.21%
11.86%
0.76%
1.54%
0.17%
0.05%
1.06%
0.37%
0.95%
1.09%
0.08%
0.20%
8.24%
0.10%
0.09%
0.00%
0.05%
0.00%
0.00%

0.01%
0.00%
0.00%
0.47%
0.40%
0.12%
0.00%
0.02%
0.00%
0.00%
0.00%
0.00%
0.18%
6.00%
0.00%
1.33%
0.00%
0.00%
0.52%
0.00%
0.00%
0.00%
0.00%
3.55%
0.00%

7.90% Improved by 61%


0.58%
0.00%
0.00%
4.93%
0.01%
0.01%
0.00%
0.00%
0.01%
0.00%
0.24%
0.34%
0.09%
0.02%
0.00%
0.31%
0.85%
0.00%
0.01%
0.00%
0.40%
0.00%
0.04%
0.02%
0.00%

Significant impr. Due to m

Significant impr. Due to m

Fixed. Was throwing belts

37

Project control spreadsheet


Description

Base Year
YEM99 - 01
Unavailability

Rail Bulk
MAJOR MACHINE 6740 = S. SILO
MAJOR MACHINE 6745 = S. SILO DUST COLLECTOR
MAJOR MACHINE 6748 = S SILO AERATION SYSTEM
MAJOR MACHINE 6749 = T SILO AERATION SYSTEM
MAJOR MACHINE 6752 = CONTROL AIR COMPRESSOR
MAJOR MACHINE 6755 = S. SILO DISCH. AIRSLIDES
MAJOR MACHINE 6756 = S. SILO LOADING CHUTES
MAJOR MACHINE 6757 = T. SILO DISCH. AIRSLIDES
MAJOR MACHINE 6758 = T. SILO LOADING CHUTES
MAJOR MACHINE 6760 = T. SILO
MAJOR MACHINE 6761 = S SILO LOADING CHUTE VIBRATORS
MAJOR MACHINE 6763 = T SILO LOADING CHUTE VIBRATORS
MAJOR MACHINE 6765 = T. SILO DUST COLLECTOR
MAJOR MACHINE 6770 = S. SILO TRAIN LOADING D/COLLECTOR
MAJOR MACHINE 6772 = T. SILO TRAIN LOADING D/COLLECTOR
MAJOR MACHINE 6776 = S. SILO WEIGHBRIDGE
MAJOR MACHINE 6778 = T. SILO WEIGHBRIDGE
MAJOR MACHINE 6796 = MCC67
MAJOR MACHINE 6797 = WAGON DOOR HYD. POWER PACK
MAJOR MACHINE 6798 = WAGON I.D. & SUPERVISORY SYSTEM

YEM02

YEM03

YED2003

Unavailability Unavailability Unavailability

14.80%

14.69%

19.61%

12.62%

0.80%
0.21%
0.12%
0.00%
0.01%
1.07%
3.39%
0.36%
2.47%
0.80%
0.00%
0.00%
0.14%
1.40%
0.42%
2.33%
0.69%
0.30%
0.10%
0.21%

0.09%
0.06%
0.00%
0.06%
0.05%
1.97%
5.07%
0.38%
3.81%
0.00%
0.00%
0.00%
0.02%
0.63%
0.47%
0.18%
0.56%
0.00%
0.04%
1.28%

2.31%
0.00%
0.00%
0.08%
0.00%
3.39%
4.33%
1.26%
2.97%
0.59%
0.00%
0.00%
0.09%
0.83%
3.68%
0.07%
0.00%
0.00%
0.00%
0.02%

0.09%
0.03%
0.00%
0.01%
0.00%
0.13%
3.69%
2.88%
1.44%
0.29%
0.00%
0.00%
0.04%
1.37%
1.03%
0.07%
0.09%
1.09%
0.07%
0.28%

38

What went well

Original data collection of breakdown work orders enabling the quick analysis by
pareto to identify machines with low or high MTBF.
For the first time we have machine availability measures across the entire site.
Sorting and filtering data to produce the Failure Mode information needed to
populate both AvSim and RCMCost software models.
The development of the optimising spreadsheets which capture the actual As Is
costs and the simulated future Optimised costs and the proposed maintenance
strategy changes.
Using AvSim and RCMCost software models to assist in the justification of Capital
Expenditure where this was the chosen strategy.
Using RCMCost field data set numbers to
link model spare parts, Weibull data sets and spreadsheet identification of
failure modes.
to link to future failure work orders as the failure mode for each specific
machine. This will speed up the process of linking work orders to machines to
specific failure modes.
Using a controlled structure to trap costs and project progress for upward
reporting of project savings and major changes to existing plant.
Cost reduction, increased availability and reduced operational costs.
39

What went not so well

Work order data quality - estimate only 70% accurate


Recorded history of work done - from nothing to volumes
Stores issues not reported on the work order
Use of the wrong work order in transactions
Multiple use of work orders
People changing spare parts specs resulting in downstream failures
I.T data corruption - not a clear understanding of what was
needed
Stores parts issues at machine level and not component level
Cultural issues - quick or bandaid fixes, addressing effects and not
root cause
Many mistakes because we didnt properly understand the software many phone calls to Jason and Stuart
40

16th July, 2002


Mine Crusher Apron Feeder Lube System Upgrade
ER no. ACH580
Recommendations

That the existing lubrication system be replaced with a Woerner lubrication


system. These are very reliable and have the ability to self diagnose faults and
alarm accordingly. There are 3 existing applications at Railton using Woerner
systems no.4 kiln girth gear, no.4 cement mill girth gear and the kiln clinker
cooler grate. The estimated capital cost is $40,150.
That some improved management of the crushing system occurs to try and
prevent the hopper stopping because of being at low level e.g if trucking problems
occur reset the TPH aim to suit the operating conditions.

Benefits

Reduced maintenance costs for the lube system (50% of $1,600) = $ 800 p.a
Reduced hired excavator costs for unblocking (50%of $1,500) = $ 750 p.a
Reduced operations overtime
$23,000 p.a
$24,550 p.a
Total savings

41

Using AvSim to aid capital justification


Reliability information
Mine system

Mine system availability based on YEM99 01 data A= 40.55%


Eliminating 50% of apron feeder failures A=43.1%
Eliminating most failures A=46.3%

Apron feeder
Availability based on YEM01 data A=86.3%
Eliminating 50% of faults A=92.9%
Eliminating most faults A=97.4%

Maintenance savings
Eliminating 50% of faults will realise
Maintenance savings of $ 800 p.a.
Hired excavator savings of $750 p.a.
Operational overtime of $23,000 p.a calculated by
Driving failure mode of the lube system = Changeover valve

failure
MTBF = 594 hours with MTTR = 30 hours
Estimated total operating hours per year = 2,700 hours
Estimated failure per year = 2,700 / 594 = 5 failures
Hours lost per year due to failure = 30 x 5 = 150 hours
6% gain in availability of 2,700 hrs also = 150 hours
50% represents 75 hours lost / year
Cost = 7 operators x 75 hours x $45 /hour = $ 23,000 p.a

42

The end

43

Das könnte Ihnen auch gefallen