Beruflich Dokumente
Kultur Dokumente
HUSSAIN F
21909203011
21909203028
MAHESH R
21909203308
BACHELOR OF TECHNOLOGY
IN
CHEMICAL ENGINEERING
BONAFIDE CERTIFICATE
Certified that this project report SEPARATION OF CO2 FROM
SYNTHESIS GAS USING MDEA ABSORBER IN AMMONIA
MANUFACTURE is the bonafide work of Philip Bernstein Saynik,
Hussain F, Mahesh R who carried out the project work under my
supervision.
Signature
Signature
Dr. R. Parthiban
Mr. C. Muthuraj
PROFESSOR AND
SUPERVISOR
ASSISTANT PROFESSOR
INTERNAL EXAMINER
EXTERNAL EXAMINER
Date:
Date:
ACKNOWLEDGEMENT
ABSTRACT
TABLE OF CONTENTS
4
CHAPTER NO.
TITLE
PAGE NO.
ABSTRACT
1.
2.
3.
4.
iv
INTRODUCTION
1.1
1.2
Revamp
1.3
Post-revamp
PROCESS IN MFL
2.1
Ammonia
2.2
Urea
2.3
Utilities
3.2
3.3
3.4
Kelloggs Process
10
3.5
Habers Process
10
3.6
11
Introduction
13
4.2
14
15
16
Reforming Section
17
19
20
22
4.4
24
4.5
Shift Conversion of CO
27
28
29
4.6
CO2 Removal
30
4.7
Methanation
33
4.8
35
4.9
Refrigeration
38
4.3
5.
6.
Introduction
39
5.2
40
5.3
40
5.4
45
5.5
46
MATERIAL BALANCE
6.1
49
6.2
50
6.3
55
6.4
7.
9.
10.
57
ENERGY BALANCE
7.1
8.
58
EQUIPMENT DESIGN
8.1
59
8.2
71
8.3
78
89
9.2
89
9.3
90
9.4
91
CONCLUSION
BIBLIOGRAPHY
1. INTRODUCTION
1.1. About Madras Fertilizer Limited
MADRAS FERTILIZERS LIMITED (MFL) is a Central Public
Sector Undertaking situated at Manali near Chennai in Tamil Nadu, South
India. MFL is an ISO-9001-2000 and ISO-14001-2004 certified company.
MFL was incorporated in December 1966 initially as a joint venture
between the Government of India and Amoco India Corporation of USA
with equity share capital contribution of 51% and 49% respectively. Now
the Government of India holds 67.55% of shares and National Iranian Oil
Corporation (NIOC) has 32.34% shares.
The MFL plant consists of production plants: ammonia, urea in
single streams and NPK in three streams, viz. NPK A train, B train and C
train. Utilities Plant is the service plant supplying treated water, cooling
water, off-site steam, instrument air, captive power and emergency power.
On November 1, 1971, MFL commenced commercial production of
ammonia, urea and NPK complex. The feedstock for ammonia is naphtha
and it is being supplied by the neighbouring M/s Chennai Petroleum
Corporation Limited (CPCL)
The MFL plant has been in operation for the last 40 years. The
proposals for revamping and modernization of MFL plant were sent to the
Government of India for approval which was approved at an estimated
8
11
2. PROCESS IN MFL
2.1 Ammonia
Ammonia, a chemical compound of nitrogen and hydrogen is
produced using naphtha, steam and air. Feedstock naphtha is the source of
hydrogen and atmospheric air is the source of nitrogen.
Naphtha is desulphurized in two stages and the hydrocarbon is
reformed together with steam and air to raw synthesis gas in the reforming
section. The reforming section consists of pre-reformer, primary reformer
and secondary reformer. Air is introduced into the secondary reformer.
Reformed gas containing H2, N2, CO and CO2 and minute amount of
unreformed methane (CH4) is sent to the CO shift conversion section
where CO is converted into CO2 in two steps. CO2 is absorbed using
methyl di-ethanol amine.
MDEA is removed in the CO2 removal section and the CO2 is sent
to the urea plant as one of the raw materials for its production. The
remaining CO and CO2 from the process gas are converted to CH 4 in the
methanator. The processed synthesis gas is compressed and sent to the
catalyst converters (S-200 and S-50) where ammonia is produced by the
catalytic action. Synthesized ammonia is separated and sent to urea plant
as raw material and the remaining quantity is refrigerated and stored in
cylindrical storage tanks.
12
2.2 Urea
Urea is produced by the action of ammonia with carbon-di-oxide
(obtained from ammonia plant) in stainless steel lined reactors at 215-220
kg/cm2 gauge pressure, using the technology of UTIs Total Heat Recycle
Process. The high efficiency reactor has conversion of about 76% per
pass. After flashing and decomposition at medium pressure, additional
CO2 is injected into the medium pressure system followed by flashing and
decomposition at low pressure and then concentration of urea solution at
vacuum. Further concentration takes place in the prilling tower.
Here the hot urea solution is sprayed down in a 210 cylindrical
concrete prilling tower, counter current to a stream of cold air with a free
fall height of prills for 170. The urea solidifies into small urea prills. The
prills are then passed through a fluidized bed cooler (Prills Cooling
System) to reduce the temperature and fines thereby improving the quality
of the product. The entire off gas is absorbed in a bubble cap tray absorber
and then recycled to the reactors. The chloride-free effluent is treated in a
Hydrolyser Stripper and the contents are recycled fully. The treated water
is used for demister washing. The product is sent though a system of
conveyors and elevators to bagging streams. There it is bagged and
shipped as urea product.
13
2.3 Utilities
MFL receives water from Panjetti Well-fields & Tamaraipakkam
though the Chennai Metropolitan Water Supply & Sewerage Board
(CMWSSB), which also supplies Secondary Treated Sewage Water. Water
requirement is around 3.5 IMGD. Tamil Nadu Electricity Board is the
source of electrical power supply.
2.3.1 Tertiary Treatment Plant
After experiencing acute water shortage, MFL commissioned
Tertiary Treatment Plant (630 Nm3/h Capacity) for treating the Secondary
Treated Sewage Water supplied by CMWSSB in September 1992. Tertiary
treatment of the secondary treated domestic sewage is done in two steps at
MFLs sewage reuse facility. They are Biological and Chemical treatment.
The biological treatment employs the conventional activated sludge
process with surface aerators. The chemical treatment involves the water
treatment step and finally breakpoint chlorination which kills micro
organisms and removes the last traces of ammoniacal nitrogen. The
tertiary treated water is pumped for further desalination to the Reverse
Osmosis Plant. The TTP receives Sewage Water to the tune of about 71%
of the total water requirement of plant thereby contributing to save the
precious ground water.
14
15
18
(1)
(2)
CO2 + H2 CO + H2O Q
(3)
24
for (1) and (2) is to be supplied continuously for the reaction to proceed
on.
The reactions take place in three steps, in the pre reformer and the
two reformers, the primary reformer and the secondary reformer. Heat is
required for the reaction in the pre reformer as the net reaction is slightly
endothermic. The necessary heat of reaction for the two reformers is quite
different. In the primary reformer, heat is supplied indirectly by firing. In
the secondary reformer the heat is supplied as reaction heat by mixing air
into the gas. The burning gas provides heat for the rest of the reforming.
The reforming taking place in the primary reformer is adjusted in such a
way that the air supplying the reaction heat in the secondary reformer will
give the required hydrogen to nitrogen ratio of 3 : 1 at the outlet from the
methanator.
It is desirable to reduce the methane content in the raw synthesis
gas to maximize the production of hydrogen and to keep the level of inert
gases in the synthesis gas low. The methane content in the raw gas is
governed by the equilibrium of the reforming reaction (2) and by the
approach to this equilibrium obtained in practice. The equilibrium for
reaction (2) is so that higher temperature, more steam and lower pressure
results in lower methane content. On the other hand, by raising the
reforming pressure, a considerable saving in the power consumption for
synthesis gas compression can be obtained and the equipment can be
25
26
poisoning, no regeneration will work. The gas leaves the tubes and enters
the refractory-lined cold collector though the bottom hairpins and hot
collectors. At the tube outlet the process gas has a temperature of about
800C. The methane concentration is about 9.5% by volume (dry basis) at
outlet.
When passing the catalyst in the tube, the following reactions take place:
CH4 + H2O CO + 3H2 Q
(2)
CO + H2O CO2 + H2 + Q
(3)
28
Fuel gas from the primary HDS and purge gas from the synthesis
section are mixed and preheated to 200C in the steam fired fuel gas
preheater. The remaining fuel being raw naphtha is vaporized and heated
to 200C in the steam fired naphtha fuel preheater before being sent to the
primary reformer burners. The flue gas from each radiant chamber is
collected in the flue gas collector of the flue gas heat recovery section
where the sensible heat of the flue gas is utilized, in consecutive order,
for:
1. Preheating of process feed
2. Preheating of process air
3. HP steam superheating
4. Combustion air preheating
The heat recovery section brings down the temperature of the flue gas to
about 175C. After the heat recovery section the flue gas fan leads the gas
to the stack.
4.3.3 Secondary Reforming
Preheated air at 550C is mixed into the partly reformed gas and
reacts in the upper empty space of the secondary reformer. The reaction
here is mainly a combustion resulting in a temperature rise. From the
empty space the gas passes the catalyst bed in the lower part of the
reformer where the reforming reaction is completed with simultaneous
29
cooling of the gas. The outlet temperature will be about 970C and the
methane concentration approximately 0.3% by volume (dry basis).
The exit gas from the secondary reformer contains about 14 mol %
CO and 10 mol % CO2. Consequently there is a theoretical risk of carbon
formation according to the Boudouard reaction
2CO CO2 + C (as soot)
When the gas is cooled at the actual operating conditions the carbon
formation can only take place at a temperature below 720C in the
primary reformer and below 766C in the secondary reformer, because of
the equilibrium conditions. The lower limit for the reaction is 650C as the
reaction rate becomes too slow at lower temperature. Consequently, it is
important to pass the temperature range from 766C to 650C reasonably
quickly, and also contact between gas and hot metallic surfaces is to be
avoided.
The cooling of the process gas is carried out in the waste heat
boiler, where the exchanged heat is used for producing saturated high
pressure steam at 45 kg/cm2 g being needed in the ammonia plant. The
boiler is designed to obtain the rapid cooling, but very high flux is to be
avoided, as it may cause film boiling on the steam side which in turn
would decrease the heat transfer coefficient significantly.
30
31
Mol formula
Volume Percentage
Hydrogen
H2
52.86
Carbon monoxide
CO
14.40
Carbon dioxide
CO2
10.15
Nitrogen
N2
22.02
Argon
Ar
.27
Methane
CH4
.30
32
The reacted gas will contain only about 0.12 % CO by volume (dry
basis). The reacted part of the CO increases the H 2 yield with
simultaneous formation of CO2 which is more easily removable. A further
reduction of the CO content in the process gas is takes place in the
selectoxo unit, where CO reacts with O2 (from air) to form CO2. The CO2
is then removed in the CO2 removal unit leaving less than 50 ppm by
volume (dry basis) of CO2 in the gas.
Even small amounts of CO and CO2 left are severe poisons to the
ammonia synthesis catalyst and should therefore be removed down to a
concentration of few ppms. This is done in the methanator where reverse
of the reforming reaction will take place resulting in the formation of
methane at the expense of hydrogen.
CO + 3H2 CH4 + H2O + heat
CO2 + 4H2 CH4 + 2H2O + heat
In the ammonia synthesis loop the inerts Ar + CH 4 will be built up
to a level depending on how much gas is purged from the loop. The
purpose of this is to keep the methane concentration reasonably low as
nothing can be done to decrease the content of the other inert gas, Argon.
33
The shift reaction taking place in the converters will proceed only
when process gas comes in contact with a catalyst.
CO + H2O CO2 + H2 + heat
The equilibrium is favoured by lower temperature and more water
while reaction rate will be higher at higher temperatures. More water may
give an apparently lower reaction rate due to the larger total volume
resulting in a shorter contact time. This means that for each catalyst there
will be an optimum temperature. Depending on the activity and the
quantity, this will give optimum conversion. As the reaction results in a
temperature rise, the outlet gas will be at an unfavourable equilibrium if
removal of heat has not taken place before the conversion is finished.
Thus, the conversion is performed in three steps. The first step takes
place in the primary CO converter, where a copper promoted
iron/chromium- based catalyst is installed. The inlet temperature is 360C
and of the reaction takes place here, causing a temperature rise of 73C.
The second step is taking place in two converters, the LT guard vessel and
the secondary CO converter. Between the converters the process gas is
cooled in 2nd HHP BPW pre heater.
36
(1)
piperazine). In the CO2 absorber the CO2 is removed from the gas by
counter current absorption in two stages. In the lower part (bulk absorber)
of the absorber, flash- regenerated (semi-lean) solution is used for CO 2
removal. In the upper part stripper regenerated (lean) solution is used for
final CO2 removal. At the outlet of the absorber the CO 2 content in the gas
has been reduced to less than 500 vol. ppm on the dry basis. The solution
which enters the absorber at 50C (stripped solution) and 75C (flash
solution) is heated to 85C by the exothermic absorption reactions.
High interfacial areas between gas and liquid are provided by
2 CS, IMTP (Intaloz Metal Tower Packing) or cascade mini rings loaded
in 2 beds in the bulk absorber and by 1 CS IMTP or cascade mini rings
loaded in 3 beds lean absorber, respectively. To prevent losses of
scrubbing solution by entrainment in the purified gas, the top of the
column is provided with 3 bubble cap trays which are fed with
approximately 900-1300 kg/hr boiler feed water. The energy in the rich
solution leaving the bottom of the absorber is utilized in a hydraulic
turbine, which together with the steam turbine servers as driver for the
flashed solution main pump, thereby reducing the total steam consumption
of the process. The flash regeneration of the rich solution is performed in
two stages. In the HP flash drum the main part of the dissolved inert
components are liberated at a pressure of 6.2 kg/cm2 g. The flash gas is
used in the secondary HDS preheater. The LP flash drum is equipped with
the packing, 2 SS and CS pall rings and 2 bubble cap trays in the top.
38
4.7 Methanation
39
base. As the reaction takes place at much lower temperature than those
prevailing in the reformers, the catalyst must be very active at lower
temperatures, whereas the performance of the catalyst at higher temp is of
minor interest.
Catalyst is very sensitive to sulphur, arsenic and chlorine
compounds. Steam without hydrogen will oxidize the catalyst and should
therefore not be used in heating, cooling or pursuing. Furthermore, it
should not be exposed to condensing steam as it will disintegrate the
catalyst. It is activated simply by heating it up with gas it should normally
treat. The content of CO and CO2 in the gas used for activation should be
as low as possible preferably close to specific gas.
The adiabatic temperature rise is about 75C per mole % CO and
60C per mole % CO2. The methanation reaction starts at a temperature of
about 240C, but in order to ensure a high reaction rate and a sufficiently
low content of CO and CO2 in the effluent gas, the operating temperature
would be from 290C to 350C , depending on the catalyst activity and the
gas composition . The methanator catalyst should not be exposed to
catalyst temperature above 450C for long periods of time.
42
gas, as water and CO2 gets dissolved in the liquid ammonia. When
entering the ammonia loop, the make-up synthesis gas is saturated with
water vapour and contains traces of carbon monoxide and carbon dioxide
(leakage from methanator). The water vapour concentration in the makeup gas is in the range 400-450 ppm, depending on the operating pressure
of the loop. The water is removed by absorption in the condensed
ammonia. Any tracer of carbon dioxide in the make-up gas reacts both
with gaseous and liquid ammonia, forming ammonia carbamate
NH3 + CO2 NH2-COO-NH4
The formed carbamate is dissolved in the condensed ammonia. The
carbon monoxide is only slightly soluble in ammonia and will pass with
reticulating gas to the ammonia converter where it is hydrogenated to
water and methane (methanation). As water deactivates the ammonia
synthesis catalyst, the carbon monoxide in the makeup synthesis gas
should be kept as low as possible.
The converters are radical type converters with gas flowing though
the catalyst beds in radical direction. S-200 converter, contains two
catalyst beds, an inter bed heat exchanger and a feed effluent heat
exchanger in the bottom. The converter contains Topsoe type KMIR
catalyst. The nominal diameters of the catalyst granules are 1.5mm to
3mm. Catalytic activity of the small particles are very high and the special
44
45
solution has an amine component. Mostly used solutions were MonoEthanol Amine (MEA), Di-Ethanol Amine (DEA), etc. Present day most
preferred solution in alkanol amines processes is activated Methyl DiEthanol amine (a-MDEA).
Activated MDEA process for CO2 removal is a physical/chemical
absorption process. It behaves as a physical absorption process at higher
partial pressure of CO2 and as a chemical absorption process at low CO2
partial process. The bulk of the solution can be regenerated by simply
flashing, leading to very low energy consumption.
5.2. Various CO2 Removal Processes
CO2 removal is a significant step in ammonia production process
with respect to investment and energy consumption and due to fast
increasing energy cost, the CO2 removal processes are being continuously
improved. As a result of this the requirement of energy has been reduced
from 36000 Kcal/kmole of CO2 removed to about 9500 Kcal/kmole of
CO2 removed. CO2 can be removed by scrubbing the gas under pressure
with various solvents.
5.3 Solvents Used for CO2 Removal by Absorption
Following the shift conversion of CO with steam to oxygen and
hydrogen, the CO must be removed from the hydrogen and nitrogen.
47
Carbon dioxide can be removed by scrubbing the gas under pressure with
various solvents. Processes for CO2 removal include;
1. Hot Potassium Carbonate Benfield Process or Catacard
2. Water
3. Methyl Di-Ethanol Amine
4. Sulfinal Sulfolane
5. Fluro solvent propylene carbonate
6. Rectisol refrigerated methanol
7. Vetrocoke (arsenical)
8. Tri-Ethanol Amine
9. Selexol Di-Methyl Ether of polyethylene glycon
10. Alkaline potassium N-methyl amine propionate
11. Purison N-methyl pyrrolidone
Water Scrubbing:
This steam was used widely, has not remained competitive. A large
quantity of water is required to dissolve the carbon dioxide and special
design is needed to avoid excessive loss of nitrogen and hydrogen. Power
48
49
50
Straight Solution
Single Stage
100
500
300
100
100
100
500
16,000
32,000
29,000
9,500
6,000
Selexol
Vetrocoke Glycine
100
Double Stage
Benfield
99.95
MEA UOP-IV
99.5
MEA UOP-II
99.4
19,000
25,000
CO2 Purity
36,000
Parameters
a- MDEA
99.95 98.5
CO2 slip in
product gas,
ppm
Energy
required
51
52
usually become the overriding factor and the net CO 2 pickup will begin to
decrease.
Circulation Rate:
As is the case for primary and secondary amines, when the
circulation rate is increased for any given column, the CO 2 pickup will
increase. This usually holds true for MDEA in a column of fixed diameter
even though the liquid residence time on a tray will decrease with
increased circulation.
Steam Stripping Rate:
For any given situation, as the steam stripping rate is increased, a
leaner amine will be produced which will result in a higher CO2 pickup.
54
CO2 Gas
CO2 Stripper
Semi-Lean Solution
Purified Process Gas
LP Flash Drum
Lean Solution
CO2 Absorber
Semi-Lean Solution
HP Flash Drum
Heat Exchanger
Process Gas
Lean Solution
6 MATERIAL BALANCE
6.1 Overall Material Balance
Ammonia Production
1050 MT/Day
43759 Kg/hr
Molecular Weight
17.0306 Kg/Kmole
43759/17.0306
2568.905 Kmole/hr
2568.9053/2
3853.358 Kmole/hr
536.544 Ton
Moles of N2 required
2568.905/2
1284.453 Kmole/hr
Steam Required
93687 Kg/hr
56
(data)
(data)
Lean Solution
Process Gas
Flow Rate = 164714 Nm3/hr
Liquid Outlet
Flow Rate = 2168.8 ton/hr
57
Inlets:
Streams
Kg/hr
Process Gas
Nm3/hr
Ton/hr
164714
335.734
Semi-Lean Solution
1712219
1712.219
Lean Solution
269600
269.6
794
0.794
2318.347
= 2.03828537 kg/m3
Process Gas flow rate
= 164714 Nm3/hr
= ( 164714 2.0382837 ) kg/hr
= 335734.1364 kg/hr
= 335.734 ton/hr
58
Mol. Wt (MWi)
Nm3/hr
moles/hr
Mole Fraction ( xi )
xi*MWi
Hydrogen
95432
4257.6961
0.5794
1.1588
Nitrogen
28
31625
1410.9485
0.1920
5.3760
Carbon Monoxide
28
64
2.8554
0.0004
0.0109
Carbon Dioxide
44
34780
1551.7088
0.2112
9.2908
39.94
381
16.9983
0.0023
0.0924
Methane
16
426
19.0060
0.0026
0.0414
Water
18
2006
89.4976
0.0122
0.2192
164714
7348.7106
1.0000
16.1894
Argon
59
Outlets:
Streams
Purified Gas
Liquid Outlet
Nm3/hr
Tons/hr
127994
149.547
Kg/hr
2168800
2168.8
Total
2318.347
= 1.152831656 kg/m3
Purified gas flow rate
= 127994 Nm3/hr
= ( 127994 1.152831656 )
= 149547.1364 kg/hr
= 149.547 tons/hr
60
Mol. Wt (MWi)
Nm3/hr
moles/hr
Mole Frac ( xi )
xi*MWi
Hydrogen
94921
4234.897832
0.7416
1.48321015
Nitrogen
28
31539
1407.111627
0.2464
6.899479663
Carbon Monoxide
28
64
2.855358258
0.0005
0.014000656
Carbon Dioxide
44
64
2.855358258
0.0005
0.022001031
39.94
380
16.95368966
0.0030
0.118577433
Methane
16
424
18.91674846
0.0033
0.053002484
Water
18
602
26.85821362
0.0047
0.084660218
127994
5710.448827
1.0000
8.674931637
Argon
61
Lean Solution
Flow Rate = 269600 kg/hr
Inlets:
62
Streams
Kg/hr
292300
Nm3/hr
Ton/hr
292.300
292.300
Outlets:
Streams
Kg/hr
Lean Solution
269600
22685
Nm3/hr
269.600
17697
22.685
292.285
= 22685.384 kg/hr
= 22.685 ton/hr
Ton/hr
195463 Nm3/hr
63
1.8811 Kg/m3
(195463 1.8811)
368025.758 Kg/hr
368.026 Ton/hr
175332 Kg/hr
175.332 Ton/hr
Cold Fluid
Inlet Liquid Flow Rate
7. ENERGY BALANCE
7.1. Energy Balance of Heat Exchanger
Cold Fluid (Water) Details
Flow Rate
175332 Kg/hr
64
Inlet Temperature
40C
Outlet Temperature
80C
J
4185 Kg.K
Specific Heat
368025.758 Kg/hr
Inlet Temperature
127C
Outlet Temperature
93C
J
2345.63 Kg.K
Specific Heat
m C
T h
=
=
m C
T c
=
=
29350.577 MJ/hr
(175332 4185 ( 8040 ))
29350.577 MJ/hr
8. EQUIPMENT DESIGN
8.1 Design of CO2 Absorber
Design of Bottom Section ( Bulk Absorber )
65
Flow
Rate
of
Lean
Solution
1982613 kg/hr
137897.7812 kg/hr
Density of MDEA
1070 kg/m3
25.9 kg/cm2 g
2.03828537 kg/m3
25.7 kg/cm2 g
1.152831656 kg/m3
1.595558513 kg/m3
Average Density ()
66
L
G
g
l
1982613
( 137897.7812
) 1.595558513
1070
14.37741045 0.00149117618
L
G
g
l
0.555194493
0.52
From this value of K4, the mass velocity per unit square meter can be
calculated used the relation given below,
13.1 V Fp L
L
v ( L v )
0.1
* 2
w
K4
13.1F p L / L
Vw*
0.1
13.1 59 0.001 / 1070
Vw*
2.144042635 Kg/m2.s
Vw*
1/ 2
K 4 v L v
Mass Velocity / m ,
67
0.1
1/ 2
Column Diameter , D
137897.7812/3600
2.144042635
17.86575444 m2
4 17.86575444
3.1416
68
4.768462431 m
NTU Calculation
X1 = ?
Y1 =
0.214901
X2 = 0.025
Y2 =
0.0257
36498.748
20490.18 =
20490.18 kmol/hr
36498.74816 kmol/hr
Y1 Y2
X1 X 2
0.214901 0.0257
X 1 0.025
X1
0.131216315
0.8x
X
0.8 1 X
Y
1 Y
69
When X1 = 0.131216315,
Y1e
1 Y1e =
Y1e
0.131216315
0.8 1 0.131216315
0.102288664
Y2 e
1 Y2 e =
0.025
0.8 1 0.025
When X2 = 0.025,
Y2e
0.019900498
Y1 Y2
NTU =
Y1 Y1e Y2 Y2e / ln
Y1 Y1e
Y2 Y2e
0.214901 0.257
NTU
NTU =
5.254088288
HTU Calculation
HTU =
Q
K ga P
56929895.86 Kg/m2.hr.Pa
70
Kga
25.9 kg/cm2 g
360325 Pa
32.87 Kg/m3.hr.Pa
HTU =
=
56929895.86
32.87 3603325
4.8067 m
Hb
NTU HTU
5.254088288 4.8067
25.25478 m
Flow
Rate
of
Lean
Solution
269600 + 794
270394 kg/hr
58958.19635 kg/hr
71
Density of MDEA
1070 kg/m3
25.9 kg/cm2 g
2.03828537 kg/m3
25.7 kg/cm2 g
1.152831656 kg/m3
1.595558513 kg/m3
Average Density ()
L
G
g
l
270394
58958.19635
1.595558513
1070
4.586198641 0.00149117618
0.177099502
72
L
G
g
l
1.3
From this value of K4, the mass velocity per unit square meter can be
calculated used the relation given below,
13.1 V Fp L
L
v ( L v )
0.1
* 2
w
K4
*
w
Vw*
1/ 2
K 4 v L v
13.1F p L / L
0.1
13.1 134 0.001 / 1070
0.1
1/ 2
*
Mass Velocity / m2, Vw =
2.249453542 Kg/m2.s
58958.19635/3600
2.249453542
7.280557903 m2
73
Column Diameter ,D
4 7.280557903
3.1416
3.044037619 m
NTU Calculation
X1 = ?
Y1 =
0.0257
X2 = 0
Y2 =
0.0005
3760.51 kmol/hr
5816.08 kmol/hr
Y1 Y2
X1 X 2
5816.08
3760.51
0.0257 - 0.0005
X1
X1
0.016293595
0.8x
X
0.8 1 X
L
G
Y
1 Y
When X1 = 0.016293595,
Y1e
1 Y1e =
Y1e
0.016293595
0.8 1 0.016293595
0.012992537
74
When X2 = 0,
Y2 e
1 Y2 e =
Y2e
0
0.8 1 0
Y1 Y2
NTU =
Y1 Y1e Y2 Y2e / ln
Y1 Y1e
Y2 Y2e
0.0257 0.0005
NTU =
NTU =
6.678740962
HTU Calculation
HTU =
Q
K ga P
24340376.98 Kg/m2.hr.Pa
25.7 kg/cm2 g
358325 Pa
75
Kga
HTU =
=
21.38 Kg/m3.hr.Pa
24340376.98
21.38 358325
3.1772 m
Ht
Total Height of Absorber
NTU HTU
6.678740962 3.1772
21.21959 m
Hb + Ht
25.25478 + 21.21959
46.4744 m
76
Design Summary:
The Absorption Column for the absorption of CO2 using the MDEA
solvent was designed and the following design details were found,
Bottom Absorber Diameter
4.768462 m
25.25478 m
3.04404 m
21.21959 m
Total Height
46.47440 m
77
= 292300 kg/hr
= 269600 kg/hr
= 22700 kg/hr
Formula
Mole %
Mole/hr
Kg/hr
Carbon Di-Oxide
CO2
5.58
276.91
12183.91
C5H13NO2
37
1836.12
218682.05
Piperazine
C4H10N2
148.87
12823.47
Water
H2O
54.42
2700.59
48610.57
Methyl Di-Ethanol
Amine
= 98 C
= 371 K
Pressure
= 1.39 atm.
= 140841.75 Pa
Formula
Mole %
Mole/hr
Kg/hr
Carbon Di-Oxide
CO2
0.47
18.99
835.76
78
Methyl Di-Ethanol
C5H13NO2
45.07
1836.12
218682.05
Piperazine
C4H10N2
3.65
148.87
12823.47
Water
H2O
50.81
2069.93
37258.72
Amine
= 113 C
= 386 K
= 12183.91 Kg/hr
= 835.76 Kg/hr
= 12183.91 835.76
= 11348.15 Kg/hr
0.5
( )
Where,
G
= 22700/3600
= 6.3056 Kg/sec
G
= Density of Gas
=
140841.75 25.5466
8314.51369.15
Kg/m3
= 1.172264689 Kg/m3
l
= Density of Liquid
= 1035 Kg/m3
L
G
g
l
74.89 1.1723
= 6.3056 1035
= 0.3997
Value of gas mass flux G is got from General Pressure Drop Correlations
in Rule of Thumbs for Chemical Engineers 4 Ed ( Pg. No. 101,102 )
80
= 1.2197
6.3056
1.128
1.12197
= 2.57 m
0.5
0.19
0.21
[ ] [ ]
20
0.2
Where,
A = Size of packing = 90mm
81
HETP=
HETP=
90 10
3 0.19
30 10
20
] [
1.8375 10
0.2
4 0.21
0.07129 m
NTU =
1
x y1
ln 1 2
1
x1 y1
Where,
x2
x1
y1
= Henrys Constant
= 888.58 Kmole/hr
4073.91
3
= 888.58 3.47 10
= 0.001309926
1
0.00470
NTU = 10.00131 ln ( 10.00131 ) 0.05580 +0.00131
= 2.47625476
Height of Overall Gas Transfer Unit (HOG)
HOG
1
1
1
ln
= HETP
1
0.00131
1
ln
= 0.07129 0.00131
= 8.18592
Column Height
Total Height = HOG NTU
= 8.18592 2.47625476
83
= 20.123 m
Giving 0.45m allowance for disengegment of vapours at top and liquid at
bottom
Total Height = 21.023 m.
Design Summary:
The Stripper Column for the stripping of CO2 from MDEA solution was
designed. The following design details were found,
Diameter of the Stripping Column
2.57 m
21.023 m
Units
Fluid
Shell Side
Tube Side
Water
Process Gas
Inlet Temperature
40
127
Outlet Temperature
80
93
Specific Heat
KJ
Kg.K
4.185
2.345
84
Thermal Conductivity
W
m.K
0.65439
0.03419
Viscosity
Pa.s
4.664 104
1.599 105
Density
Kg
m3
983.2
1.8811
Fouling Coefficient
W
m 2 C
500
3500
( mCpT )h
( 102.22942345.6334)
29350.5768106 J/hr
8152938 J/sec
To find LMTD
Tc1
40C
Tc2
80C
Th1
127C
Th2
93C
T1
53C
T2
47C
85
LMTD
T1 T2
T1
ln
T
2
49.939942C
53 47
53
ln
47
49.939942C
86
Uo
W
2
300 m C
UoATLMTD
Q
U o TLMTD
8152938
300 49.9399
84.1142 m2
Assume,
Outer diameter of inner tubes
20 mm
16 mm
Length of tubes
4.83 m
Do L
0.02 4.83
0.3036
87
No of tubes, NT
88.1142
0.3036
277 tubes
0.023 Re
0.8
Pr
0.33
0.14
where,
Re
Reynolds Number =
DiV
Cp
Prandtl Number
W
0.03419 m.K
KJ
2.34563 Kg.K
1.59910-5 Pa.s
Kg
3
1.8811 m
Cp
Pr
88
Di 2
4
0.016 2
4
2.01143 10-4 m2
5.5727 10-2 m2
Kg
2
6.6211853 m .s
Linear Velocity
m
3.51984012 s
Reynolds Number
18349.83
2345.63 1.599 10 5
0.03419
1.097
Mass Velocity
Prandtl Number
0.023 18349.83
hi
W
2
4744.67773 m C
89
1.0974
0.016
0.8
0.33
0.03419
j h Re Pr
1/ 3
where,
Re
Reynolds Number =
DiV
Cp
Prandtl Number
W
0.65439 m.K
KJ
4.185 Kg.K
Kg
3
983.2 m
Cp
Pr
90
Bundle Diameter
Here ki
Bundle Diameter
Shell Diameter
Tube Pitch
Baffle Spacing
=
=
0.249,
N
Do T
ki
2.207
1
277
0.020
0.249
0.48012 m
0.48012 + 0.068
0.54812 m
1.25 20
25 mm
0.54812
5
0.10962 m
2.207
2
Ds 2
N T Do
4
4
-
0.148983 m2
91
Kg
2
326.9057 m .s
Linear Velocity
m
0.3325 s
Reynolds Number
9953.6621
4185 4.664 10 4
0.65439
2.98275
0.023
1. 1
2
pt2 0.917 d o
do
0.014201 m
hs De
k
j h Re Pr
hs
W
2
1518.5680 m C
Mass Velocity
Prandtl Number
jh Factor
Equivalent dia, De
92
1/ 3
0.33
0.65439
1
U
1
1
ho hod
1
1
= 1518.568 500
do
di
d o ln
2k w
do 1 do 1
d i hid d i hi
0.02
1
0.016 0.02 1 0.02
2 45
0.016 3500 0.016 4744.677
0.02 ln
W
2
300.4177 m C
4f
L 2
v
D
Where,
f
Diameter
4 0.00396
416.27 Pa
0.416 kPa
4.83
983.2 0.3325 2
0.020
L ut
8 jf
di 2
jf
di
Where,
94
From the Tube-side friction factor chart, the value of jf has been found to
be 0.04
0.020
2
900.525 Pa
0.9 kPa
Design Summary:
The Shell and Tube Heat Exchanger for the cooling of process gas was
designed and the following design details were found,
Design Specifications
Value
16 mm
20 mm
4.83 m
No. of Tubes
277
95
Shell Diameter
0.54812 m
Bundle Diameter
0.4812 m
W
2
300.4177 m C
0.418 kPa
0.900 kPa
3. Urea
4. Carbonate
5. Carbon dioxide in non-ventilated area.
9.2. Handling Hazardous Materials
In general it should be emphasized that operates should minimize all
physical contact with the chemicals handled in this plant by considering
the following rules:
1. Keep chemicals within closed containers at all times.
2. Utilize proper protective clothing and equipment if the chemicals
cannot be kept within closed containers.
9.3. Safety in Use of Pressurized Vessels
All vessels should be completely drained, depressurized, purged and
vented before opening and/or attending for inspection on maintenance.
From an environmental, atmospheric aspect, vessels should preferably be
drained to another vessel before opening. If this cannot the accomplished,
the next most desirable procedure is to drain vessels to drums. If drained,
full precaution should be taken to prevent sledge, atmospheric
contamination and excessive flashing in the sewers. Vessels should be
depressurized back to process if possible.
97
98
99
At all times operators and other personnel within the plant should
be fully clothed with long trousers, long-sleeved shirts, hats, safety glasses
and safety shoes.
In order to decrease the possibility of hazardous contacts with
chemicals, operators should be compelled to wear suitable goggles where
applicable.
Small liquid anhydrous NH3 and Liquid ammonia leaks from drain
or vent valves or packing around valves can go unnoticed and can cause
eye injuries.
the safety and first aid equipment, response teams should be set up to
assist workers when they are in danger.
10. CONCLUSION:
In this project, a study of the manufacture of ammonia by Haldor
Topsoe Process was done. A detailed study was done on the MDEA
section where CO2 is absorbed from the process gas because CO2 acts as a
catalytic poison to the ammonia synthesis and Separation of CO 2 from
Synthesis gas using MDEA Absorber was done. Structural packing gives
the following advantages by increased capacity for exiting towers,
reduced CO2 content in product gas, and decreased reboiler heat duty,
greater mass transfer and hydraulic capabilities, twice the surface area per
unit volume and lower pressure drop.
101
11. BIBLIOGRAPHY
1. Robert E. Treybal, Mass Transfer Operations, 3rd Ed., McGraw-Hill
Book Company, 1981
2. McCabe W.L., Smith J.C. and Harriott P., "Unit operations of
Chemical Engineering", 7th Ed., McGraw-Hill, 2004
3. D. Q. Kern, Process Heat Transfer", Tata McGraw Hill Publishing
Co., New Delhi, 1990
4. Madras Fertilizers Plant Process Manual
5. R.K. Sinnott, Coulson & Richardsons Chemical Engineering Series
Volume 6, Chemical Engineering Design , 4th Edition, Elsevier
Butterworth-Heinemann, 2005
102
103