Beruflich Dokumente
Kultur Dokumente
mobilization of any marine equipment; and, therefore, did not impact shipping traffic or
sensitive marine life. Also, a lengthy permitting process was avoided. A 1,600-ft-long bore
was used at this river crossing with approximately a 26-in.-hole diameter. The cables were
bundled and pulled back directly through the bore in one single operation.
HDD was also used to construct a 600-ft-long portion of the alignment that is adjacent to the
toe of the 20-ft-high, I-93 highway embankment, and beneath an I-93 on-ramp embankment.
A curved horizontal alignment was used for this section. Using HDD for this section
eliminated impacts on vehicular traffic on the highway and on-ramp, and avoided the need to
pass under a structure owned by an adjacent property owner. These two applications of HDD
avoided the need for permitting and right-of-way acquisitions processes, which enabled
construction to be completed in significantly less time than would have been required by
trenching methods.
Interceptor Relief Project Constructed by Microtunneling
Microtunneling methods were used to install 3,000 lf of new 66-in.-dia sewer and 4,700 lf of
36-in.-dia sewer in Chelsea, MA. The project is one component of the Massachusetts Water
Resources Authority's Combined Sewer Overflow Facilities Plan, and will improve overall
water quality in Chelsea Creek and Boston Harbor.
Haley & Aldrich completed a combined geotechnical and hazardous materials site
investigation that identified the presence of contaminated soil and groundwater along the
sewer alignment. Alternative construction methods were evaluated including cut-and-cover,
soft ground tunneling, pipe jacking, and microtunneling. Microtunneling was selected
primarily to avoid surface disruption and impacts to adjacent businesses that would have
occurred with trench construction. The sewer alignments pass through industrialized
reclaimed land along Chelsea Creek. Soil types encountered included organic soils, estuarine
fine sands and silts, marine deposits, and glacial soils. Inverts are below groundwater level
and range from 15 to 28 ft below ground surface. In addition to the trenchless design, Haley &
Aldrich provided construction management and hazardous materials management services.
As new population growth necessitates expansion of transportation, energy, and water-related
infrastructure; and the demands for new telecommunications technologies drive the expansion
of underground cable and fiber optic networks, construction technologies must keep pace.
HDD and microtunneling are moving trenchless engineering and construction options
forward.