Beruflich Dokumente
Kultur Dokumente
200
4
CONTENTS
Sl.No.
CHAPTERS
PAGE NOS.
1.
BOILER
2.
3.
14
4.
23
5.
27
6.
36
7.
47
8.
50
9.
53
10.
55
11.
61
12.
68
13.
SH / RH ATTEMPERATION SYSTEM
73
14.
76
15.
81
16.
83
17.
89
18.
STEAM GENERATION
95
19.
103
20.
HOT START UP
126
BOILER
INTRODUCTION :
The Boilers of 210 MW Units in TTPS are of conventional Single Drum,
Natural Circulation, Radiant, Dry Bottom, Balanced Draft and Re Heat Type. The
Steaming capacity of the Boiler is 700 T / Hr., designed for full Load Oil Firing or
Coal Firing, depending upon the availability of Fuel. During Startup, when the
Furnace will be comparatively cold, Light Oil (High Speed Diesel Oil) will be used
and can be changed over to Heavy Oil Firing and subsequently to Coal Firing as
the Furnace temperature and Steam flow through the Boiler increases. The heat
released in the Furnace is received by the Water / Steam / Air to the maximum
extent to have a Boiler Efficiency of the order of 86 %. The Boiler consists of the
Furnace, Drum, Down Comers, Water Wall, Super Heaters, Re Heaters,
Economiser, Air Pre Heaters, Bottom Ash Hopper and the connected auxiliary
equipments for injecting Coal / Oil to the Furnace and for extracting the
combustion products.
The Natural Circulation in the Boiler Water Walls is based on the Thermo
Siphon principles. As the Heat input to the Furnace increases, the water
temperature near the surface of the tube increases and reaches saturation
temperature. At this point a change from liquid to vapour occurs locally. But since
bulk of the water does not reach Saturation temperature, the steam bubbles collapse
giving up their Latent Heat to raise the temperature of the bubbles do not collapse.
This condition is known as the Nucleate Boiling. The Circulation system in this
Boiler is designed to ensure the Nucleate Boiling for all anticipated operating
conditions. One more design criterion is the acceptable percentage steam by
volume or the corresponding percentage Steam By Weight (SBW) through out the
fluid flow path. The SBW is the circulation number which is the ratio of the
quantity of the mixture flowing through the circuit to the quantity of steam
produced in the circuit, which will be normally around 6 to 8 .
The circulation is achieved by the density difference between the column of
water in the Down Comer and the column of water and steam mixture in the
Furnace Walls.
TECHNICAL SPECIFICATIONS :
1. TYPE :
2. FUEL :
a. Bituminous :
Designed Coal
Worst Coal
Fixed Carbon
Volatile Matter
Moisture
Ash
Grindability
HHV
33 %
28.5 %
15 %
23.5 %
45 HGI
5000 Kcal / Kg.
40.5 %
33 %
7.5 %
19 %
55 HGI
5960 Kcal / Kg
GCV
85.5 %
11.05 %
2.5 %
0.5 %
10,200 Kcal / Kg.
Type
a) Stage I
b) Stage II
c) Stage III
LTSH
Platen S.H
Final S.H
Heating Surface in M2
6360
1006
1037
5. RE HEATER :
Type
Pendent
Control
Burner Tilt.
6. ECONOMISER :
Type
No. of Stages
5690 M2
Continuous Finned
One
Type
No. Off
2 per Boiler
Heating Surface
19100 M2 (each).
a. Burners
b. Coal Burners
:
:
c. Oil Burners
d. Ignitors
9. MILLS :
a.
b.
c.
d.
Type
No. Off
System
Basic Capacity
e. Motor
:
:
:
:
:
BOILER AUXILIARIES
A. FANS :
Sl.
Duty
No.
1.
F.D
2.
P.A
3.
I.D
Type
Axial
Reaction
API 20 / 11
Radial
ND FV 20 b
Axial
Impulse
AN 25 e 6
Medium Design
Motor
No. off /
Quantity Pressure Temp.
Boiler
KW rpm
0
M3 / Sec. mmWCL
C
2
150
495
40
1100 1480
2
67.5
940
40
900
1480
220
420
140
1700
990
B. SOOT BLOWERS :
Sl.No.
1.
2.
3.
Zone
Type
Furnace
Quantity /
Boiler
56
Medium
Steam
20
Steam
Steam
Make
Dresser
Type
1759 WA
1749 WA
1749 WA
1538 VX
Set
Pressure
ksc (g)
158.2
161
162.4
141.5
Reliving
Capacity
T / Hr.
159
193
195
87.0
1739 WD
1739 WD
1775 WA
1785 WA
1785 WA
1785 WA
144.5
143.8
33.0
33.4
33.8
34.1
87.0
86.0
100.0
130.3
131.6
133.0
1705 RWD
30.6
115
C. SAFETY VALVES :
Sl.
No.
Location
1.
Drum
2.
Super Heater
(Electromatic
Valve)
3.
Re Heater (CRH)
4.
Re Heater (HRH)
Relief
Purpose of this system is to Feed Water of specified quality to the Boiler and
its related parts to the required level at the time of filling the Boiler with Boiler
Feed Pump before Unit light up or Hydraulic test.
FEED WATER SYSTEM DESCRIPTION :
The Feed water system consists of the following:
i)
ii)
iii)
iv)
v)
This includes filling of water to the full level of Water Wall, Economiser and
to the normal level of Drum. This is for the purpose of Unit light up.
2) FILLING ALL PARTS OF BOILER :
This includes filling of water to the full level of Water Wall, Economiser,
Drum, Super Heaters and Main Steam Piping up to MSSV. This is for the purpose
of Boiler Hydraulic Test.
In both the above cases, filling is done by Boiler Feed Pump after providing
required chemicals (i.e Hydrazine and Ammonia ) in the Deaerator.
Regular feeding of water to Hot Well of the Turbine Condenser (i.e. Make
up Water) is done with Hot Well Make Up Pump, while Unit is in service.
FLOW PATH OF FEED WATER SYSTEM :
The flow path of Feed Water system starts from DM Water Storage Tank
(DMWST) and travels as follows.
i)
DM water at DMWST is pumped to CST to the required level with DM
Water Make up Pump.
ii)
DM Water from CST pumped to Hot Well to the required level through Hot
Well Make up Pump.
iii)
iv)
(in M3) :
-----------------------------------------------------Sl.No.
Location
Total Volume to be
Volume to filled
Volume filled for unit
for Hydraulic
Light up
Test.
- - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1.
Drum
37.20
11.53
37.20
2.
Water Wall
126.30
126.30
126.30
3.
Super heaters
97.18
-97.18
4.
Re-heaters
48.10
--5.
Economiser
25.17
25.17
25.17
6.
MS piping
12.05
-12.05
------------------------------------------------------Total
346.00
163.00
297.90
------------------------------------------------------2) TECHNICAL DETAILS OF PUMPS AND TANKS :
i)
Pumps :
:
:
:
:
:
Make
Type
Quantity
Delivery head
Temp. of Fluid
Motor Capacity
:
:
:
:
:
:
BHEL / Hydrabad
200 KHI
7330 L / Min.
1830 MLC.
164.2 0C
4000 KW
PUMP
CAPACITY OF PUMP
HEAD
CAPACITY
SPEED
:
:
:
:
100 T / HR.
30 MWC.
15 KW
1480 RPM
MOTOR
MAKE
KW
RPM
AMPS
PHASE
VOLTAGE
FREQUENCY
ii)
:
:
:
:
:
:
:
UNIT I & II
UNIT III
NGEF
15
1460
28
3
415
50 Hz
KIRLOSKAR
18.5
1470
32
3
415
50 Hz
Tanks :
:
:
:
:
1No./ Unit
500 M3 (each tank)
9000 mm
8250 mm
:
:
:
:
1No. / Unit
350 M3
7.5 M
8.5 M
Conductivity
pH
Silica
:
:
:
0.3 mho / cm
6.5 7.0
Not traceable.
16. FW System :
Isolate main Isolation Valve from FW line to Attemperation Headers.
Isolation Valves of Feed Control Valves (both FCV-2 & FCV-1 / 7) are kept
Open.
FCV-2 (1No.) and FCV-1 / 7 (2Nos.) Control Valves are in closed condition.
E-2 (Eco. Inlet Isolation Valve) valve Open.
Economiser Recirculation Valves Open.
17. All sampling line valves of Steam and Water open.
6. Raise the Boiler Pressure slowly to 135 ksc and keep it for 5 Minutes.
7. After 5 Minutes, slowly reduce the Pressure to 70 ksc for inspecting the Boiler.
8. After completion of Hydraulic Test Drum Pressure may be gradually lowered to
about 5 ksc suitably after stopping Boiler Feed Pump.
9. Boiler Line Up for Light Up After Hydraulic Test :
a) Open all the air vents (SH, Eco. & Drum) at 2ksc.
b) Open SHH drains and Master valve to IBD for draining the Super Heaters.
c) Bring the drum level to normal value by opening EBD valves.
d) Open all the sampling line valves at Economiser and drum floor (CBD,SH&SS)
e) Inform Boiler Maintenance crew to release the Safety Valves gagging, if any.
f) Open ERV Isolation Valve.
g) Open Phosphate Dozing Isolation Valve at Drum Level.
h) Open Economiser RC Valves.
i) Open Start Up Vent Hand Valves.
Note : One Number Boiler Fill Pump is available at D.M Plant for Unit I, II & III
and its Specifications are as below :
PUMP :
Make
Rated Capacity
Shut off Head
Speed
Pump Efficiency
Power Input to the Pump
:
:
:
:
:
:
:
:
:
:
:
:
:
Crompton Greaves
3 Induction Motor.
415 10 Volt.
1490 rpm.
260 A.
160 KW.
95.3 %
MOTOR :
Make
Type
Voltage
Speed
Current
Rated Capacity
Efficiency
There are provisions for filling the Deaerator and Boiler (through bottom
Water Wall Drains and Super Heater Drains) for Units I, II & III by using Boiler
Fill Pump. Boiler Fill Pump LT Breaker is available at Unit III Heat Exchanger
Switch Gear Room.
The main objective of this system is for lighting up the boiler and flame
support to main fuel up to and below 120MW.
SYSTEM DESCRIPTION :
1) HIGH SPEED DIESEL OIL SYSTEM :
HSD firing is normally carried out only during cold light up periods. It is
also advisable to use HSD till Furnace temperature is increased to a limit above
which HFO can be easily & freely fired. It will take at least one hour for the above
temperature rise and hence, HFO change over is being carried out only after one
hour of Boiler lighting up. During this period, only one pair of Guns in AB
elevation is to be cut in to service. It is the routine practice to cut in AB 1 to 3
Guns for the first hour and AB 2 & 4 Guns are cut in additions in the next
hour, so that warming up of the Boiler will be uniform and slow.
HSD contains minimum Sulphur contents (almost 0.5%) and HFO contains
almost 1 to 3%, hence it will be better to cut in SCAPH before lighting up the
Boiler to avoid cold end corrosion of APHs.
HSD is being transported from IOC at Nellai through Oil Tankers. Oil is
transferred to HSD Storage Tank of capacity 1176 KL through 2x100 % duty HSD
Oil Decanting Pumps. Each Pump can deliver 50 M3 / Hr. oil.
HSD Pumps are Screw Pumps. There are 2 x 100 % duty HSD Pumps to
deliver HSD to one stage. There are two Strainers at the suction side of the Pumps.
Any strainer can be used for any Pumps. Pump discharge pressure is being
controlled by a pneumatic RC valve at Pumps discharge. In the firing floor HSD
line is provided with a Trip Valve and a flow Control Valve. Bypass Valve to flow
Control Valve is also provided for the purpose of manual operation in case of
failure of pneumatic control of PCV.
The Controlled Oil is then allowed to go through all the Guns in AB
elevation through Hydra motor valve and NRV.
Since this HSD is costlier than HFO, the duration of HSD firing is restricted
to about one hour only.
HFO is brought to TTPS either through roads or by rails. There are 2x100%
duty Transfer Pumps at oil and Decanting Pump House to transfer the receipt HFO
to HFO Tanks at TTPS.
There are 2 Nos. HFO Tanks of 13,598 KL capacity each. As the hot oil
circulation is being done continuously, the HFO Tank temperature is maintaining
around 80 0C so as to restrict the firing of oil in the Oil Tank itself, it is the routine
practice in TTPS to cut out the HFO heating only if the Tank temperature exceeds
85 0C and HFO heating is cut in to service if the HFO Tank temperature has fallen
down below 75 0C.
There are three numbers of oil temperature gauges at local in each HFO
Tank at 120 o apart.
There are Two Nos. of drains in each HFO Tank (provided 120 o apart) so
that the water is being let out periodically. Usually this draining is being carried
out once a week.
Auxiliary PRDS steam is utilized for the following purposes at FOPH and
decanting pump house.
a) For steam coil heating inside the HFO tank.
b) Steam coil heating in the bottom of HFO tank but at the Normal, Take off
point of HFO to the Common Suction Header to the Pumps.
c) HFO Heaters.
d) HFO Tankers heating while decanting the LSHS (Low Sulphur High Stock oil).
Apart from that, electrical space heaters at various locations in HFO Pump
suction lines, FOPH lines, HFO lines after Pumps and HFO return lines are
provided to keep up the temperature so that easy flow of HFO may be ensured.
Each Tank receiver oil from Decanting Pump House at its top. Isolation
Valve is provided to completely isolate the receipt of oil from Decanting Pump
House. Similarly each Unit RC lines are also connected at the top of the HFO
Tank.
The oil delivery from HFO Tank to Pump is taken at two levels in HFO
Tank. The normal source level is somewhat at higher elevation when compared to
that of emergency source delivery point. The normal source of delivery line
contains steam heating provision where as the emergency lines do not.
Two numbers of normal and emergency take off points connect two numbers
of HFO receipt line. Normally one number receipt line is made through to all
Units HFO Pumps suction.
The construction of HFO Strainers and HFO Pumps are just like that of HSD
Pump except the following :
a) One LDO line is connected well before the Strainers of the HFO scheme so as
to release Strainers choke up in case of LSHs handiling. This LDO Isolation
Valve is being normally kept closed during HFO handling.
b) Pumps
Numbers
Discharge
Pr. (ksc)
Capacity
LPH
HSD
4 (Stage I & II )
22.5
205
HFO
22.5
1140
c)
HFO Tank
LDO Tank
Capacity :
13598 KL
Capacity :
1176 KL
Height
15.33 M
Height
11.6 M
Dia
35 M
Dia
12 M
Vertical Tank
Vertical Tank
c) Steam Heaters are available in HFO system to ensure easy flow and for having
better atomization.
e) RC at Burner location is available in case of HFO system.
f) Fine Filters are available at 18 M Level.
III.
OPERATION :
A)
HSD Tank :
a) Isolation Valve to Pumps from the Tank Open
b) Isolation Valves of RC Valves at HSD Tank Open
c) Tank Vent Open
2)
Pump Side :
a) One Strainer is in service, the other one is standby.
b) Suction valves of both the Pumps are open.
c) Discharge valves of both the Pumps open
d) Isolation Valves of Pneumatic Control Valve (RC valve) Fully Open.
Its Bypass Valve Fully closed.
e) Pumps are primed up.
f) Strainers are also primed up.
3)
18 Metre Side :
a) Trip valve is made through.
b) PCV is made through. Ensure the closure of PCV Bypass Valve.
c) Atomizing air pressure is adequate.
d) All LMS (Local Maintenance Switches) in AB elevation are in
Remote position.
e) All limit switches of AB elevation HSD lines and air atomizing lines
are being made through.
f) Ensure the closure of all HMVS.
NOTE:
For starting any HSD Pump, Tank side and FOPH side clearances
only are essential. The 18 M side LINE-UPS should be
followed up
by the 18 M Operator during Pre-Light up checks.
During this period, the Light Oil pressure will lower due to the consumption
of oil by Guns. Hence Boiler Operator will keep up the elevation Light Oil
header pressure by properly operating the Light Oil PCV.
10.Boiler Operator cuts in the Light Oil Guns of AB-2 & 4 after an hour.
11.Boiler Operator cuts in any two Guns in CD Elevation (HFO Guns) and then
only cuts out of AB Guns (LDO firing) while changing over to HFO.
B)
Pre Checks :
1) Short RC Valve Full Open
2) Strainers Fully Isolated & Its Vents Open
3) Trip Valve is made through
4) Long RC Valve is made through
5) HFO Control Valve is made through Its Bypass Valve is closed.
6) AB, CD & EF Elevations Isolation Valves both at inlet and outlet Open.
7) All limit switches of healthy HFO Guns Open full.
8) All HFO HMVS closed.
9) All scavenge HMVS closed.
10) All LMS Remote.
11) Atomizing steam is available.
CHARGING HFO AT 18 M LEVEL :
1)
2)
3)
4)
5)
HYDROMETER VALVE
RETURN OIL
FSSS
PERMISSIVE
AIR
PR. LOW TRIP
PS
SCANNING
VALVE
FSD
PS
OIL
GUN
HOSE
LO
TANK
1000 T
AIR
PCV 12
SERVICE
AIR
PCV 8
FLOW METER
STRAINER
STRAINER
LO PUMPS
175 L/m
23.3 Kg/Cm2
LO
PCV 10
LOTV
FSSS PERMISIVE
PS
OTHER
ELEVATIONS
AB ETC IGNITOR
PRV 11
STRAINER
18M LEVEL
FOPH
OM LEVEL
12500T
PCV 6
RC
RETURN OIL
UNIT I
INTER
CONNECTION WITH
OTHER UNITS
STRAINER
OTHER UNITS
HO PUMPS
1100 L/Min
22 Kg/Cm2
TEMP.
STEAM TRAP
OTHER
ELEVATION
FLOW
METER
HOTV
STRAINER
FCV 3
AB Etc
FROM PRDS
PCV 7
TCV 7
FROM
PRDS
FO
TANK 2
12500 T
INLET
VALVE
TO ATMOS.
HOSE
SCAVANGE
VALVE
OIL GUN
S-39
TCV-7
TO DRAIN
S-44
FO-38
FO-36
FO-36
FO-43
S-36
FO-37
HOTV
FO-37
TO BURNERS
S-36
FO-38
PCV-6
FO-37
FO-37
FO-17
FO-48
FO-36
FO-36
FORV
FO-43
FO-17
FO-57
FUEL OIL
RETURN
TO CONDENSATE HEADER
This system is designed to supply the Support and Guide Bearings with a
bath of continuously cleaned oil at the proper viscosity. Circulation of the oil is by
means of a motor driven pump through an external filtering system.
The driving force for turning the rotor is applied at its periphery. A pin rack
mounted on the rotor shell is engaged by a pinion attached to the low speed shaft
of a power driven speed reducer or gear motor.
(e) ROTOR SEALS :
Seals are provided at both ends of air pre heater to minimize leakage
between the air side and gas side of the pre heater. The hot and cold end radial
seals are attached to each diaphragm of rotor and are set at specified clearance
from the sector plates which separate the air and gas streams.
The seals provided at rotor post are set to operate with minimum clearance
with respect to horizontal sealing surface of center section.
Bypass seals provide sealing between the periphery of the rotor and sealing
surface of the connecting plate and preheating housing.
Axial seals are provided vertically in the rotor shell in line with radial seals.
(f)
CLEANING DEVICE :
27 V I ( T ) 72
:
:
:
2. AUXILIARY DRIVE :
Air motor
:
Coupling
:
Solenoid valve
:
Pressure switch
:
Rotor Support Bearing:
Guide Bearing
:
:
:
:
:
:
:
:
:
:
Allroyd or Radicon.
Lovejoy L095
1200 kg / Hr / Device at 17.6 ksc.
4. CLEANING DEVICE :
Motor
Reducer
Coupling
Steam consumption
PROCEDURE :
The operating procedure is as follows :
PRECHECKS :
OPERATION :
8. Start main A.C. APH motor, Air motor will stop on Auto. Watch the no load
current.
9. Ensure normalcy of APH main motor and air motors standby condition. Then
keep main motor in service.
10.APH shall be stopped while making the Unit for Shutdown, when the FG
temperature outlet comes below 120 0C.
11.After stopping APH main drive, the Guide Bearing and Support Bearing and
Support Bearing LOPs shall be stopped 2 to 3 Hrs after the stopping of APH.
EMERGENCIES DURING OPERATION :
I.
II.
Fire in APH : Incase of fire in APH, reduce the unit load and look for fire
quenching by external agencies or by means of APH fire pump.
III.
CONSTRUCTIONAL DETAILS :
The Fan consists of the following Sub Assemblies :
1) Suction Chamber.
2) Inlet Vane Control.
3) Impeller.
4) Outlet Guide Assembly.
5) Diffuser.
6) Bearings.
7) Flexible Coupling.
1) SUCTION CHAMBER :
The Suction Chamber is of welded sheet steel construction and is split
horizontally for easy assembly and dismantling. A man hole is provided in the
Suction Chamber for checking up the Inlet of the Fan.
2) INLET VANE CONTROL :
The Axial Inlet Vane Control Assembly of the Fan consists of a number of
Aerofoil Inlet Vanes fixed to individual shafts which are connected by means of
Angular Joints to a Central Ring. The Ring is guided by a set of Roller and Spring
Assemblies. A Control Lever is connected to the Ring which can be operated by
an electric servo motor or a Pneumatic Power Cylinder. The Inlet Vane Control
Assembly is split to facilitate handling and dismantling.
3) IMPELLER :
The Impeller body is welded sheet steel construction, with welded on, non
profiled solid blades. The Impeller is dynamically balanced. It is bolted to the
flange welded on to the hollow shaft. The Impeller casing is of undivided type but
the conical connection piece connected to the casing is split horizontally such that
the top half can be removed for removal of the Impeller. A peep hole is provided
in the casing for checking the wear on Impeller. The Impeller is supported in
between the bearings.
4) OUTLET GUIDE ASSEMBLY :
The outlet guides are fixed in between the core of the diffuser and the
casing. These guide vanes serve to direct the flow axially and to stabilise the drift
flow caused in the Impeller. The Outlet blades for fans handling dust laden gases
are of removable type from outside. During operation of the fan itself these blades
can be replaced one by one.
5) DIFFUSER :
Diffuser of the fan is of welded sheet steel construction with a core inside.
The core of the diffuser houses the inner bearing which is supported by all the
outlet blades. The core of the diffuser is provided with a man hole with access
from diffuser casing so that the bearing can be checked even during the operation
of the fan. For fans handling Hot Gases the diffuser cores are insulated inside.
The lubrication pipes as well as the thermometer for the inner bearing are brought
outside through the core for easy access.
6) BEARINGS :
The Bearings are self aligning roller type. The flanged bearing on the
impeller side is the fixed bearing and the outer bearing is the expansion bearing.
Both bearings are grease lubricated and the lubrication point is available on
diffuser casing for inner bearing. A grease quantity control ring is provided in each
bearing to discharge the surplus amount of grease. For controlling the Bearing
Temperature a contact Tele Thermometer is provided in the bearing. The
contacts are to be set to 80 0C for signaling and to 90 0C for stopping the main
Motor.
The Cooling pipe for cooling the inner bearing is provided for fans handling
gases above 70 0C.
7) FLEXIBLE COUPLING :
Coupling between the motor and fan is flexible pin type with rubber bush
inserts.
TECHNICAL DATAS OF ID FANS :
Number of Fans / Unit
Type
:
Capacity
Total Head
Speed
Fan Drive coupling
Medium Handled
Temperature of medium
Specific weight of medium
Motor Rating
:
2
Axial / Impulse Type AN 25 e6
:
220 M3 / Sec.
:
430 mmWCL.
:
980 rpm
:
Pin Type Flexible Coupling
:
Flue gas
:
150 0C
:
0.807 Kg / M3
:
1700 KW
OPERATION DETAILS :
PRE-START CHECKS :
ii)
Ensure that water has been filled in the seal trough, Bottom Ash Hopper
and water is filled up in the mixing boxes of all ash hoppers.
Ensure the full opening of all the gas dampers other than the suction and
discharge dampers of the two ID fans.
Ensure that there is no work permit pending in the ID fans, ESP or in the
furnace and APH.
ii)
iii) Ensure that Fan protections and interlocks have been checked and found
O.K. (This is normally done when the Fan is being started after a long
Shutdown / Overhaul)
iv) Check the Remote operation of the Suction and Discharge Dampers and
also the IGV.
v)
Ensure electrical supply from 6.6KV Switch Gear. Also ensure that all
related relays are in reset condition.
Suction Dampers (GD-22, 23, 24 & 25 for Unit I & II ; GD-220 & 221
for Unit III ) closed.
ii)
Discharge Dampers (GD-12 &13 for Unit I & II ; GD- 204 & 205 for
UnitIII ) closed.
STARTING PROCEDURE :
After the completion of the pre-start checks and after ensuring the
availability of all permissive, ID Fan is started from remote as follows :
i)
ii)
iii) Ensure the opening of the ID Fan Stator Cooling Water Valve.
iv) Load the fan gradually so as to maintain a furnace pressure of 5 to
10 mmWCL.
Post Start Checks (by Local Operator) :
i)
ii)
The second ID Fan is normally brought into service as and when the Unit is
synchronized. One ID Fan is enough to maintain the Furnace pressure within the
normal limit of 5 to 10 mmWCL when Oil Guns are in service in two elevations
and two milling systems are in service. When further loading of the Furnace is
required, the second ID Fan is started as per the same procedure as that of the first
Fan. Once both the ID Fans are brought into service, the loading of both the Fans
are matched and put on Auto.
SHUTDOWN PROCEDURE:
i)
Reduce Unit load gradually by cutting out the milling systems one by
one.
ii)
iii) When the load reduction is gradual, the Furnace pressure master control
takes care of the Furnace pressure automatically. But if there is large
variation, the master control is thrown to Manual mode due to the high
deviation between the set pressure and actual pressure. In such case, the
Operator takes the master on Manual and reduces the loading of the ID
Fans and normalizes the Furnace pressure.
iv) At < 20 MW load, the Unit is tripped by actuating Turbine Trip. This in
turn actuates the MFT (Master Fuel Trip) and trips the Boiler. All Boiler
side equipments trip, leaving the following in service.
-
Both ID Fans.
Both FD Fans.
Both APHs with their LOPs.
AC Scanner Air Fan
PA Fan LOPs.
v)If the Boiler is to be Boxed Up, the MSSVs at Boiler end are closed after
the Baring Gear starting. Both the ID Fans and FD Fans are stopped after
purging the Boiler followed by a Boiler trip. To stop the ID Fans.
- Fan is unloaded by reducing the load gradually.
- Once the Control Vane is minimum, the Fan is switched OFF.
- The Suction and Discharge Dampers close on Auto. Complete
closure of the same is ensured from the Local Operator / from the
Control Desk.
- Ensure the closing of ID Fan Stator Cooling Water Valve.
If the Boiler Maintenance personnel require the cooling of Furnace / Boiler
passes / ESP fields for taking up maintenance work, one set of ID Fan and FD Fan
is kept in service as long as required by them and then switched OFF.
EMERGENCIES :
ii)
iii) Lube Oil pressure low ( < 1.5 ksc for 120 Sec).
iv) Motor Bearing Temperature > 80 0C (70 0C Annunciation )
v)
GD22
GD4
GD2
APH-A
WIND BOX
GD13
GD11
GD5A
PLTN
FURNACE
SUPER
FINAL
CON
SH
SH
RH
CHIMNEY
ECO
HEATER
GD5B
ID FAN-B
ESP-B
GD6
GD-1
WIND BOX
GD25
GD3
GD12
APH-B
GD10
GD8
GD26
AD 15
AD 17
AD 20A
AD 20
AD 34
AD 155
FROM ECO
TO MILL F
GD 192
APH A
AD 40
GD 194
ESP A
GD 198
AD 3
AD 6
FD FAN A
GD 199
ESP B
GD 206
GD 220
GD 207
ID FAN A
GD 204
GD 202
AD 22
AD 28
AD 8
GD 196
TO WIND
BOX (LEFT)
SCAPH A
HOT
TO MILL B
TO MILL D
TO WIND
BOX (RIGHT)
SCAPH B
AD 39
AD 7
TO MILL E
GD 193
FROM ECO
AD 27
APH B
AD 9
AD 45
AD 33
CHIMNEY
AD 5
COLD
AIR
TO MILL A
AIR
BUS
BUS
TO MILL C
GD 222
AD 1
AD 4
FD FAN B
GD 200
GD 195
AD 2
AD 21A
GD 201
AD 156
GD 223
GD 197
ESP C
ESP D
GD 221
PA FAN B
FILTER
AD 16
FROM
ATMOS
V DAMPER
TO SCANNERS
TO MILLS
FILTER
GD 205
ID FAN B
GD 209
AD 21
AD 18
GD 203
GD 208
TO IGNITORS
There are 2 Nos. of Forced Draft Fans per Boiler and located at Ground
Floor. The Technical Datas of the FD Fans incorporated in both the stages are
provided below:
---------------------------------------------------------------------------------------------------Sl.No.
PARTICULARS
FAN DATA
---------------------------------------------------------------------------------------------------1.
Fan Type & Size
-Axial Reactio Type API20/ 11
2.
Fan Orientation
-Horizontal
3.
Medium Handled
-Atmospheric Air
4.
Location
-Ground Level
5.
No. of Fans / Boiler
-Two
6.
Fan Design Rating
i. Capacity
-150 M3 / Sec
ii. Total Head Developed
-485 mm WCL
iii. Temperature of medium
-40 0C
iv. Specific Weight of medium
-1.089 Kg / M3
v. Speed
-1480 rpm
7.
Fan Reserve
i. Flow
-29.3 %
ii. Pressure
-44.8 %
8.
Fan Drive Coupling
-Coupling with Intermediate
Shaft.
9.
10.
11.
Drive Motor
i. Manufacturer
ii. Frame Size
iii. Rating
iv. Voltage
v. Frequency
vi. Phase
vii. Speed
Fan Weight
Lubricating Equipment
i. Fan (Forced Lub Oil system)
ii.
12.
---------
BHEL Hardwar
AC 142 36 H4 A
1100 KW
6.6 KV
50 Hz
3
1480 rpm
7000 Kg
--
70 LPM
M/s. Metal Weld - Drg.
0-56-910-00116
5 LPM
Tecalenut
Pitch Control
---
The part of the setting mechanism being inside the Diffuser core is
accessible through mounting holes.
BEARINGS :
Coupling Side
An Oil Hydraulic servo motor flanged to the impeller and rotating with it
adjusts the blades during operation. This results in a closed flux of force between
adjusting forces and oil pressure, so that no forces are released to the outside
(bearings, housing, foundation). The servo motor consists of piston, cylinder, and
control devices.
During adjustment of the blades, the translational movement of the servo
motor piston is turned into rotation via the adjusting levers of the pivoted blade
shafts so that the blades can be set at different angles.
The restoring moments of the blades are produced by the rotating blades.
They are counter balanced by the oil pressure in the servo motor.
Weights at the blade shafts partly compensate the restoring moment. These
weights produce a moment opposed to the restoring moment of the blades so that
the adjusting devices are relieved.
The Oil Hydraulic servo motor can be connected to any control or
regulating system. It can also be adjusted by hand. The movement of the non
rotating control slide in the servo motor to initiate the blade adjustment requires
only small forces of a few Kilo Pounds.
OPERATING PROCEDURE :
After ensuring that the final permissive available for starting the FD Fan can
be started both at local through LPB or from UCB
Start the FD Fan by pressing the start button and see that the ammeter
reaches the starting current. Let the current reduces to no load reading
within 8 to 10 Seconds.
Ensure the opening AD-3 or AD-4 on Auto (or) Local opened it.
Open IGV gradually and see that the discharge pressure and Secondary Air
Flow indicators show increase in their readings. Establish slightly more air
flow than the minimum Air Flow required for Purging (i.e 240 T / Hr 30%
of MCR). Suitable loading of ID Fan should be done to keep up the Furnace
Draft.
Purging :
Purging is nothing but the scavenging of the Boiler with the minimum air to
avoid accumulation of unburned fuel and explosion possibilities, which has to be
necessarily be carried out before every light up and after a Boiler trip out. Purging
is started after ensuring that the following permissive are available and carried out
for 5 Minutes.
Permissive for Purging are:
1) Any one ID / FD set is in service with > 30 % Air Flow
2) Drum Level Normal
3) No Boiler Trip Persists
4) Burner Tilt Horizontal
5) No Mills Running
6) No Feeder Running
7) LOTV Close
8) HOTV Close
9) All HMVS Close
10) All Scanners No Flame
11) All HAGs Close
12) Both PA Fans Stop.
4) Stopping Procedures :
While stopping the FD Fans when the Unit is in tripped condition, the
following procedure is to be adopted.
Reduce the IGV loading gradually for one Fan and see that the Air Flow
drops.
If required load the other FD Fan to maintain the required Air Flow.
Reduce the IGV to minimum and stop the Fan
Ensure the Closure of Discharge Damper on Auto (or) Close it Local.
Similarly, the same procedure is to be adopted to stop the second FD Fan
also. After stopping the HT Breakers to be racked out and DC kept OFF if not
required to be brought back into service immediately. Whenever operating FD
Fans & ID Fans are to be adjusted either Manual or on Auto.
5) Alarms & Tripping conditions One FD Fan Trip
Both FD Fans Trip
1. When One ID Fan trips, the corresponding FD Fan will trip. (Tripping of
One FD Fan leads to tripping of Mills leaving top 3 Mills ).
2. When Both ID Fan Trips, Both the FD Fans will Trip which leads to Unit
Trip.
3.
(a) Bearing Temperature Very High at 80 0C (Annunciation 70 0C ) for
Motor.
(b) Bearing Temperature Very High at 90 0C (Annunciation 80 0C ) for
Fan.
When one FD fan trips, the Secondary Air Flow, Wind Box to Furnace DP,
Furnace pressure etc. go down and become insufficient and thus creating
emergency. In that case, the following procedure to be adopted.
Increase the loading of the other FD Fan in service to the maximum
permitted level.
Maintain the Furnace pressure by adjusting ID Fan loading.
Adjust the SADC control at control desk so as to maintain the Furnace to
Wind Box DP.
Bring the IGV of the tripped FD fan to the minimum position.
Check with on which protection the Fan has tripped and what annunciation
has appeared on the Panel.
Check with Switch Gear operator which relay has acted.
On findings from the above it is to be intimated to the concerned
Maintenance Staff.
When both FD Fans trip, the Unit gets tripped if in service. When Fans
alone are running, tripping of both FD Fans lead to highly negative pressure in the
Furnace which can be corrected by suitably adjusting the ID Fans loading.
While starting a FD Fan after completion of Line Clearance / Over Hauling the
procedure to be adopted is as follows.
Ensure that all other systems in a Unit are available with all Clearances.
APHS and ID Fans are maintaining the Furnace Pressure.
Check for FD Fans permissive.
Control Oil pressure adequate.
IGV Minimum.
ID Fans Running.
Discharge Damper Close.
L.O pressure Adequate
Ensure that the HT Breaker is racked in and DC kept ON.
Ensure that the bearing temperature Gauge is fixed in their position.
Start FD Fan at local.
Check for any abnormal noise and vibration at no load.
If normal Fan to be loaded gradually and trial run conditions to be observed at
various loadings.
Check all the available parameters at various loadings
Ensuring the normal performances, the Fan to be stopped after reducing the
IGV to minimum and to be kept ready for service.
Generally whenever a disturbance is experienced in the Secondary Air Flow
System it mainly affects the flame condition and Furnace Draft and thus creating a
total instability. Hence when such disturbances occur the parameter like Furnace
Draft, Wind Box to Furnace DP are to be immediately adjusted so that a perfect
flame condition is being maintained with or without the support of Oil Gun. This
can be achieved by adjusting ID Fan, FD Fan Vane Control and SADC Control
etc., and better Unit conditions can be established. It will be better to have oil
support at less than 120 MW.
TO PA FAN - A
AIR MOTOR
STATION AIR
AD-155
FD FAN-A
AIR
AERO FOIL
AD8
PRE
AD-3
AD-6
HEATER - A
FROM ATMOSPHERE
AD-1
WIND BOX
AD-158
FURNACE
AD-5
AD10
WIND BOX
FD FAN-B
AD-159
AERO FOIL
AIR
AD9
AD-7
AD-4
FROM ATMOSPHERE
PRE
HEATER - B
AD-156
AID MOTOR
STATION
AIR FROM
COMPRESSOR
AD-2
MAIN DRIVE
TO PA FAN - B
MAIN
STEAM
PRDS SYSTEM
SAFETY
VALVE
V2-16
(R)
(L)
TO EJECTOR
V2-17
V2-18
ATTEMPERATION
TO GLAND STEAM
HDR
PRDS-PCV
FROM FEED
PUMP
V2-19
TO
DEAERATOR
VALVES AT
13.5 MT
TO
OHS
TCV
TCV
BYPASS
DEAERATOR
DIVERSION
TO
IC
:
:
:
:
:
:
:
:
:
:
:
:
3450 M3 / HR.
200 MMWC
50 0C
1.014 KG / M3
2920 RPM
ON CAPACITY
ON TOTAL PRESSURE
:
:
20 %
18 %
:
:
:
CAPACITY
TOTAL PRESSURE
MEDIUM TEMPERATURE
MEDIUM DENSITY
SPEED
FAN RESERVE :
SHAFT
DRIVE MOTOR :
:
:
PROCEDURE :
Scanner Air Fans can be started only from UCB (Unit Control Board). Its
operation comes under Furnace Safe Guard Supervisory System (FSSS) control,
control switches and indicating lamps are provided in UCB at FSSS console.
Provisions are not made to start the Scanner Air Fans from local, in order to avoid
many unnecessary emergencies due to mal operation. It is a vital system without
scanners air fan system the unit should not run more than 10 Minutes.
a) STARTING :
Scanner Air Fans A.C and D.C can be started manually by depressing the
respective start push button in FSSS console. Normally A.C Scanner Air Fan
started initially when Boiler light up activities is started. It develops a discharge
pressure of 350 mm WCL. Auto start to standby Scanner Air Fan will occur only
when the running Scanner Air Fan trips.
b) STOPPING :
AC / DC Scanner Air Fans can be stopped manually by depressing the
respective push button in FSSS console.
Normally Scanner Air Fans are stopped when the RH metal temperature
dropped down to about 40 0C after a Boiler Trip out.
:
:
:
:
:
:
:
:
:
:
:
15300 M3 / HR.
680 mmWCL
50 0C
1.09 Kg / M3
2960 rpm
:
:
:
25 %
10 %
IMPELLER MOUNTED DIRECTLY ON
MOTOR
FAN RESERVE :
ON CAPACITY
ON TOTAL PRESSURE
FAN DRIVE COUPLING
SHAFT
DRIVE MOTOR :
MAKE / FRAME SIZE :
TYPE
:
SQUIRREL CAGE
RATING
:
60 HP , 415 V , 3 , 50 HZ
OPERATION PROCEDURE :
Seal Air Fans can be started either from Unit Control Board or from Local.
After starting the Fan , discharge damper is opened gradually and Seal Air pressure
is maintained 200 mm WCL above Primary Air Header pressure.
a) STARTING :
Seal Air Fan A/B can be started manually by pressing the respective start
push button in console.
b) STOPPING :
Seal Air Fan A/B can be stopped manually by pressing the respective push
button in console after stopping PA Fans.
c. ALARMS :
i.
Seal Air Fan filter Differential Pressure (DP) high alarm persists when the
DP goes over 55 mmWCL. So immediately the standby filter will be put
into service in parallel and the chocked filter will be isolated, cleaned and
kept as standby.
ii.
Seal Oil Air Fan discharge pressure low alarm persists when the pressure
reduces to 1000 mmWCL. The standby Seal Air Fan will be started
automatically.
iii.
Seal air to corresponding Mill DP low alarm persists when the DP reduces to
125 mmWCL and the corresponding Mill will be tripped.
An Inlet Guide Vane unit is arranged on the suction side. The Axial
Inlet Vane control assembly of the Fan consists of a number of aerofoil inlet vanes
fixed to individual shafts which are connected by means of angular joints to a
central ring. The ring is guided to the rotating position by a set of roller
assemblies. A control lever is connected to the ring which can be operated by an
electric servo-motor or a pneumatic power cylinder.
(ii)
ROTOR :
(iii)
HOUSING :
BEARINGS :
FLEXIBLE COUPLING :
Coupling between the motor and fan is normally of flexible pin type
with rubber bush inserts.
(vi)
SHAFT SEAL :
A two part labyrinth seal, seals off the fan spiral casing at the shaft
passage.
Lub oil system for cooling and lubrication of fan bearing consists of one pair
of Pumps, Filters and Coolers, one each being standby. The system is fitted with
thermometers, pressure gauges and pressure switches. Lub oil system control
panel is located in the ESP from where the L.O. system can be operated in Remote.
Three pressure switches provided in the lub oil header before bearing are set at 3.5,
2.5 and 1.5 ksc. for alarm, auto change over and protection of the fan respectively.
TECHNICAL DETAILS OF PA FANS :
Number of Fan / Unit
Type
Capacity
Total Head Developed
Speed
Fan Drive Coupling
Medium Handled
Temperature of Medium
Specific Weight of Medium
Motor Rating
:
:
:
:
:
:
:
:
:
:
2
Single Suction Radial Type NDFV 20 b
67.5 m3 / Sec.
940 mmWC.
1480 RPM.
Pin Type Flexible Coupling.
Atmospheric Air
40 0C
1.089 kg / m3
900 KW
PRE-START CHECKS:
1. Ensure that there is no pending Work Permit in the PA Fans, Air Heater, PA
Ducts, Mills, Furnace and Flue Gas Ducts.
2. Ensure the man holes are closed.
3. Check that Air Pre Heater Inlet and Outlet Dampers are open.
4. APH, ID Fan & FD Fan are in service before taking any PA Fan into service.
5. Ensure that air circuit is made through atleast in one Mill to the Furnace, by
opening Cold Air Gate and Damper and the Mill Discharge Valves.
6. Check the oil level in the Lub Oil tank and bearing housing.
7. Ensure the cooling water flow through the cooler and bearing housing.
8. Check the availability of the instruments to measure the flow, pressure, and
temperature of the PA Fan and its lub oil system.
9. Check the opening & closing of the Suction / Discharge Dampers (AD-155,
AD-156, AD-17 & AD-18). Keep it closed before starting the PA Fan.
Ensure that the vane position is in minimum.
10.Ensure that the Local Push Button is in released position.
11.Check the operation of vane control from UCB.
12.By simulation checks confirm all the protections and interlock functions
properly. Especially when the PA Fan is started after long Shut Down, all
the protections must be checked.
PA FAN LUB OIL SYSTEM :
Line up and taking into service :
1. Ensure oil level in the tank. Level should be between the maximum and
minimum marks in the oil tank gauge glass.
2. Ensure the Suction and Discharge Valves of Lub Oil Pump are kept fully
opened.
3. Commission the Lub Oil Coolers and ensure water flow through it.
4. The Lub Oil Filters may be made through.
5. Check for full opening of the needle valve before bearing in Lub Oil line.
6. The Lub Oil Pump may be started from Manual or Auto from the Lub Oil
Pump Control Panel located in ESP Control Room. There is a selector switch
consisting of two positions 1. Manual 2. Auto.
7. Ensure the power supply and control supply to the control panel.
8. Ensure Local Push Buttons for the Pumps are released.
9. Ensure the pressure switches and temperature gauges are intact.
Start any one Lub Oil Pump manually from control panel putting the selector
switch in manual position and observe the Lub Oil pressure low annunciation in
the control panel gets reset. Check that there is no oil leak in the system.
After resetting the Lub Oil pressure low annunciation the selector switch
may be turned to Auto.
Now trip the running Lub Oil Pump and observe that standby pump starts on
Auto. The Lub Oil Pump starts on Auto when the Lub Oil pressure drops to
2.5ksc., annunciation will appear in the panel window. Thus any one of the Pumps
may be kept in service.
Ensure adequate oil flow to the bearing by seeing the return oil flow in the view
glass.
a) Normal working pressure of Lub Oil inlet is 3.5 ksc to 5.0 ksc.
b) Normal working pressure of Cooling Water inlet is 2.2 ksc.
c) Differential pressure across filter should be less than 0.3 ksc.,
normally the DP will be 0.1 ksc.
PA FAN START PERMISSIVE:
1. Primary Air Fan Suction / Discharge Dampers (AD-155, AD-156, AD-17 &
AD-18) closed.
2. Inlet Guide Vane at minimum.
3. Lub oil pressure to the Motor & Fan bearings adequate.
4. No master fuel trip relay is actuated.
5. PA Fan stopped condition is established.
6. PA Fan tripped indication should not exist.
7. All the Cold Air Dampers to the Mills should be less than 5 % open.
Note:
Before starting any PA fan select any one Seal Air Fan should be put into
service keeping Suction & Discharge Dampers in open condition.
POST START CHECKS:
1. Note the starting current of the motor.
2. Check the opening of the Suction / Discharge Damper on interlock or
open the Damper by switching ON from UCB control desk.
3. Immediately after the Suction / Discharge Damper is opened load the Fan
slightly by opening the inlet guide vane up to required P.A Header
Pressure.
4. Check the Fan and the motor for smooth running.
5. Check the bearings for proper lubrication, and monitor regularly the
bearing temperatures.
6. Maintain the PA header pressure at 800 mmWCL by suitable loading of
the PA Fan, for taking Mills into service.
PA FAN TRIP INTERLOCKS:
1. When one PA Fan trips, the running Bottom Mills will trip, leaving Top three
Mills in service. .
2. When both PA Fans trip, all the Mills will trip on PA Header pressure very low,
less than 450 mmWCL.
3. When the Boiler trips, both PA Fans will trip on MFT protection.
4. When any one of the PA Fans trip, the Suction / Discharge Dampers will close
automatically.
5. The Suction / Discharge Dampers of both PA Fans will close, when both PA
Fans trip.
The following procedure may be carried out to stop any one PA Fan to attend
any breakdown maintenance.
1. Reduce the generation by keeping two Mills and oil guns in two elevations
in service.
2. The Oil Guns should be put into service when the Unit generation is reduced
to below 120 MW.
3. Maintain the SH and RH temperatures above 510 0C. So that the Turbine
Expansions are within the limit.
4. To maintain the SH and RH temperatures, close the SH and RH spray
valves.
5. After stopping all the Mills except two Mills and all the Guns in two
Elevations (AB and CD) got proven then stop the particular PA Fan.
6. Maintain the PA header pressure at 800 mmWCL by increasing the vane
control of the running PA Fan.
7. If it is unable to maintain the PA header pressure within the limits (around
550 to 600 mmWCL) then stop another Mill by running one Mill only.
8. The LOPs of the stopped PA Fan can be stopped after the Motor & Fan
bearing temperatures (DE and NDE) are reduced to below 40 0C.
TO COLD PA BUS
PA FAN - A
AD 17
AIR
AD 21
PRE
AD 21A
FROM FD FAN A
DISCHARGE
AD 155
HEATER - A
AD 15
AIR MOTOR
MAIN DRIVE
TO HOT PA BUS
STATION AIR
AD 19
AD 157
MAIN DRIVE
TO HOT PA BUS
AIR MOTOR
PA FAN - B
AIR
FROM FD FAN B
DISCHARGE
PRE
AD 20
AD 20A
AD 18
AD 156
HEATER - B
AD 16
TO COLD PA BUS
There are six numbers of Coal Bunkers for each Unit with an individual
storage capacity of 680 Tones. They are filled by either of the two Traveling
Trippers, through Conveyors 25A or 25 B. Raw Coal Bunkers normally have one
day storage for full load operation of their respective Units. The Coal Handling
Plant does the filling operation. A 36 chain operated coal valve is provided in the
Bunker Discharge pipe to the RC feeder
RAW COAL FEEDERS :
The Raw Coal Feeders are volumatric type is set to supply 33.8 Tonnes/Hr
of Coal to Pulveriser per Hr. while operating on a 415 V ; 3 phase ; 50 Hz Power
Supply.
COAL PULVERISERS :
Six numbers of Bowl Mills of the type XRP-763 is provided for each Unit.
The capacity of the pulveriser is 33.8 T / Hr. for a Primary Air supply of 52 T / Hr.
at 800 mmWCL.
The pulveriser consists of essentially a grinding chamber with a classifier
mounted above it. The grinding chamber has 3 No. of rolls placed 120 apart on a
rotating bowl, in which centrifugal force is utilized to move the coal delivered by
the Raw Coal Feeder, outward against the Grinding Ring (or Bull Ring). Rolls
revolving on journals that are attached to the Mill-Housing pulverise the coal
sufficiently to enable the air stream to pass through the pulveriser to pick it up.
Heavy springs acting through the journal saddles provide the necessary
pressure between the grinding surface and the coal. The rollers do not touch the
Grinding Rings, even when the pulveriser is empty. The tramp iron and foreign
material are discharged through a suitable spout.
The Air and Coal mixture passes upward in to the classifier with its deflector
blades where the direction of the flow is changed abruptly causing the coarser
particles to be returned to the bowl for further grinding. The fine particles
remaining in suspension leaves the classifier and pass through the coal piping to
the Coal nozzles. When the Mill is unloaded intentionally or due to a foreign
material or due to coal choking, Mill motor current low alarm is provided to
the operator. Each Bowl Mill supplies an entire Elevation of Coal nozzles, through
4 No. of Mill discharge valves. The Mill discharge valves are connected to coal
pipes, which deliver Coal + Air mixture to all the four corners of an Elevation.
PULVERISER DATA
TYPE OF PULVERISER
SIZE
763 XRP
M / S. BHEL, HARDWAR.
MESH
INDEX 55 HGI AND A
MOISTURE OF NOT MORE
8 %.
MOTOR
TYPE
AD 13168 H 6A
COUPLING
BEARINGS
COOLING SYSTEM
LUBRICATING
WORM SHAFT,
SHAFT BEARINGS &
VERTICAL SHAFT BEARINGS. OIL
IS COOLED BY CIRCULATING
WATER INSIDE THE CUBE BUNDLES
IMMERSED IN THE OIL BATH.
COOLING
KSC
WAER SURFACES
OF
COAL PIPES :
The coal pipes carry the coal + air mixture to all the four corners of the
Boiler Furnace from the Mills. Each coal pipe is connected to the respective Mill
discharge valve. The coal piping are connected at places by means of Grooved and
Sleeve type pipe couplings. These pipe couplings are specially designed to achieve
quick assembly and to automatically allow for contraction, expansion, and to some
extent translation of the coal pipes. Orifice plates are installed in the vertical run
of the coal piping leaving the pulveriser discharge valves, to compensate for unequal resistance to flow due to different length of piping to the Coal Nozzles.
COAL BUNKERS :
When filling the Bunker with coal, first close the Feeder inlet coal valve to
minimise the filling pressure on the Feeder to avoid compaction of the coal at the
Feeder inlet. This precaution is unnecessary if the Bunker is refilled while atleast
2.4 to 3 Meters. (8 10 Feet) of coal remain in it.
RAW COAL FEEDERS :
I) START UP AFTER A CLEAN SHUT DOWN :
1.
2.
3.
4.
5.
6.
7.
8.
Ensure all the Line Clear and Permission etc., in the pulveriser
system are cancelled.
Keep the corresponding mill in service with necessary FSSS
interlocks.
Open the Bunker Discharge Gate and Feeder Inlet Gate slowly.
Open the seal air connection butterfly valve.
Energise the Feeder controls at the power cabinet in the Relay
Panel Room adjacent to UCB and observe Feeder off green indication.
Open Cold Air Gate and Cold Air Damper to control Mill
Outlet Temperature.
Open Hot Air Gate.
Open Hot Air Damper and allow a Primary Air Flow of 52 T /
Hr in the Mill.
9.
Feeder.
R.C Feeder got tripped with no coal flow by closing the Bunker Gate and
Feeder Gate.
Close the Hot Air Damper, Hot Air Gate and Cold Air Damper.
Ensure all the Line Clear and Permission etc., in the pulveriser system
are cancelled.
2.
Keep the corresponding Mill in service with necessary FSSS
interlocks.
3.
Open the Bunker Discharge Gate and Feeder Inlet Gate slowly.
4.
Open the seal air connection butterfly valve.
5.
Energise the Feeder controls at the power cabinet in the Relay Panel
Room adjacent to UCB and observe Feeder off green indication.
6.
Open Cold Air Gate.
7.
Open Hot Air Gate.
8.
Open Hot Air Damper and allow a Primary Air Flow of 52 T / Hr in
the Mill.
9.
When the Mill O/L temperature of 75 0C is reached start the Feeder.
10.
Maintain the Mill outlet temperature of 65 0C for high volatile coals
and 820C for low volatile coals by operating the Cold Air Damper.
11.
Slowly raise the Feeder speed as per the Boiler requirement while
maintaining 52 T / Hr of Primary Air at a Mill outlet temperature,
depending upon the Volatile Matter of the Coal.
IV) NORMAL SHUT DOWN PROCEDURE :
1.
2.
3.
MILL OPERATION :
Normal start up procedure :-
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
Check that all Permission and Line Clear in the milling system are
cancelled. Check lubrication with reference to proper level and cleanliness
of lubricants.
Check sufficient Raw Coal in the Raw Coal Bunker.
Check for proper operation of Mill Discharges Valves, Hot Air Shut
Off Gate, Hot Air Damper and Cold Air Damper and Seal Air System.
Check that all Classifier Vanes are open to the same extent.
Check that no Boiler trip conditions exist.
Check sufficient ignition energy is available in the Furnace.
Check that all Mill Discharge Valves are in open condition.
Check that all Seal Air Valves to Mill are open and Seal Air supply
present at adequate pressure.
Check the cooling water line is open and cooling water supply present
at the Mill Oil Coolers.
Check that tramp Iron Spout Valve is open.
Check that Raw Coal Bunker Outlet Gate and / or Inlet Gate to Feeder
is /are open.
Check that Cold Air Gate is open.
Check that adequate Primary Air pressure is available in the Hot Air
Header (i.e), 800 mmWCL.
Ensure 6.6 KV supplies to the motor are available with necessary
protection and interlocks.
Start the Mill from the UCB, FSSS Panel.
After the Mill has been started, check up the return oil flow from the
upper bearing through the flow sight provided. This should be observed
within 8 to 15 Minutes after the Mill start up.
Raw Coal Feeder must be started only after the Mill has been started
and warmed up.
During the initial period and load picking up of the Mill check that
sufficient ignition energy is available in the Furnace till pulverised fuel
from each Mill attains self sustained condition.
Check all bearing and oil temperatures.
Check for Mill rejects, quantity and quality.
Check for any abnormal sound.
Check for any air or pulverized fuel leakage.
Check for Fuel fineness at routine intervals and adjust the classifier
vanes accordingly.
1.
2.
3.
Close the Mill Hot Air Damper and Hot Air Gate and open Cold Air
Damper to maintain 100 % Air Flow.
Continue feeding coal till the Mill outlet temperature reaches 50 0C then
stop the Feeder.
Run the Mill for another few minutes till it becomes empty and then shut
down the Mill.
4.
1.
2.
3.
4.
After an emergency trip, the Mills that were in service will be hot and
contain a considerable amount of partially pulverised coal. The Hot Coal should
be removed from the Mills one by one by taking them in to service quickly. So the
following procedures are to be followed.
1.
2.
3.
4.
5.
6.
7.
8.
The two most common indications of a fire in the milling system are
A high or rapidly increasing Mill outlet temperature without other cause.
I.
II.
Closing Hot Air Gate will frequently extinguish the fire, but if the Mill
temperature continues to rise
a. Cool the Mill by admitting water.
III.
After the Mill outlet temperature has dropped and all signs of fire are gone
a. Shut off the water being admitted to the system.
b. Stop the Feeder.
Run the Mill for several minutes to completely purge the system and to
reduce the possibility of an accumulation of water.
IV.
If it becomes obvious from peeling paint and change in colour that a fire
exists completely throughout the Mill and Fuel piping and the preceding
methods of comparing the Fire have been ineffective.
a. Clear all personnel from the area surrounding the Mill and its
associated Feeder and Fuel piping.
b. Shut Off the Feeder and allow the Mill to clear itself of Fuel.
c. Maintain a flow of Cold Air through the Mill until all evidence of
fire has disappeared and the Mill is Cold.
d. Shut Down and Isolate the Mill.
The Fuel Firing equipment consists of four Wind Box Assemblies located in
the Furnace Corners.
Each Wind Box Assembly is divided in its height into number of Sections or
Compartments. The Coal compartments (Fuel Air compartment) contain a Coal
nozzle. The top, bottom and intermediate compartments are used for admission of
Secondary Air (Intermediate Air compartments), Combustion Air (Secondary Air)
is admitted to the Intermediate Air compartments and each Fuel compartment
(around the Fuel Nozzle) through sets of louvre Dampers, each set of Dampers is
operated by a Damper Drive Cylinder located at the side of the Wind Box. The
drive cylinders at each elevation are operated either remote manually or
automatically by the Secondary Air Damper Control System in conjunction with
the Furnace Safeguard Supervisory System.
Some of the (Auxiliary) Intermediate Air Compartments between Coal
Nozzles contain a Retractable Oil Gun. Retractable High Energy Arc (HEA)
Ignitors are located adjacent to the Retractable Oil Guns. These Ignitors directly
light up the Oil Guns. Optical Flame Scanners are inserted in Flame Scanner
Guide Pipe Assemblies in the Auxiliary Air compartments. The Scanners sense the
visible light given off by the flame and then prove the flame.
COAL BURNERS:
In a tangentially fired Boiler, four tall Wind Box (combustion air boxes) are
arranged, one at each Corner of the Furnace. The Coal Burners or Coal Nozzle are
located at different levels or Elevations of the Wind Box. The number of Coal
Nozzle Elevations is equivalent to the number of Coal Mills. The same Elevation
of Coal Nozzles of 4 Corners is fed from a Single Mill.
The Coal Nozzles are sandwiched between Air Nozzles or Air
compartments. That is Air Nozzles are arranged between Coal Nozzles, as one
below the Bottom Coal Nozzle and one above the Top Coal Nozzle.
The Coal Fuel and Combustion Air streams from these nozzles or
compartments are directed tangential to an imaginary circle at the center of the
Furnace. This creates a turbulent vortex motion of the Fuel, Air and Hot Gases,
which promotes mixing, ignition energy availability, combustion efficiency.
The Air Nozzles in between Coal Nozzles are termed as Auxiliary Air
Nozzles and the Top most and Bottom most Air Nozzles as End Air Nozzles.
The Coal Nozzles Elevations are designated as A,B,C,D,E,F from Bottom to
Top. The Bottom End Air Bozzles as AA and the Top End Air Nozzles as FF.
The adjacent Coal Nozzles like AB, BC, CD, DE & EF from Bottom to Top
designate the Auxiliary Air Nozzles.
The four Furnace Corners are designed as 1,2,3 and 4 in clockwise direction
looking from top and counting Front Water Wall Left Corner as 1.
Each pair of Coal Nozzle Elevations is served by one elevation of Oil
Burners located in the in between Auxiliary Air Nozzles. In this Boiler with
6 Mills or 6 Elevations Coal Nozzles, there are 12 Oil Guns arranged in
3 Elevations at Auxiliary Air Nozzles AB, CD & EF .
BURNER TILT MECHANISM :
The Air and Fuel Nozzles are vertically adjustable by means of movable
nozzle tips, which can be tilted upward or downward through a total angle of 60 o.
This movement is effected through connecting rods and tilting mechanism in
each Wind Box compartment, all of which are connected to a drive unit at each
corner operated by automatic control. Provision is given in UCB to know the
position of nozzle tips during operation. The tilt drive units in all four corners
operated in unison so that all nozzles have identical tilt positions.
WINDBOX DAMPERS :
Wind Box Compartment Damper positioning affects the air distribution as follows:
Opening up the FuelAirDampers or closing down the Auxiliary Air
Dampers increases the Air Flow around the Fuel Nozzle. Closing down the FuelAir Dampers and opening the Auxiliary Air Dampers decrease the Air Flow
directly around the fuel stream.
The Wind Box Compartment Dampers are operated by the Secondary Air
Damper Control system in conjunction with the Furnace Safeguard Supervisory
System. When an Automatic Control System provides modulation of the Auxiliary
Air Dampers as required maintaining a preset Wind Box to Furnace Differential
Pressure.
OPERATING PROCEDURE :
I ) WIND BOX :
1
After taking ID Fan and FD Fan into service maintain a 30 40 % of Total
Air Flow and purge the Furnace.
2
3
Open all the Elevations of Auxiliary and End Air Dampers to have a uniform
and thorough purging across the Furnace volume.
4
5
Maintain a Furnace to Wind Box Differential Pressure of 40 mmWCL for a
Boiler load up to 30 % by opening the Auxiliary Air Dampers.
6
7
Open the associated Oil Elevation Auxiliary Air Damper when Oil Guns are
taken in to service.
8
9
Open the Oil Elevation Air Dampers as a function of oil header pressure.
10
11
All the Coal-Air Dampers normally are closed, when the corresponding Coal
Mill is not in service.
12
13
Open the Coal Air Dampers after the associated Feeder is started and open
the Coal-Air Dampers as a function of Feeder speed.
14
For a Boiler load above 30 % , Furnace to Wind Box Differential Pressure
should be maintained at 100 mmWCL ,by operating Auxiliary Air Dampers
accordingly.
15
16
Total Air Flow should be increased for maintaining the Furnace to Wind Box
Differential Pressure when the firing rate is increased.
17
18
Keep the Bottom End Air Damper to a fixed pre-determined position, to
reduce unburned coal dust fall out.
19
When the Coal-Air Dampers are fully open, further Damper adjustments
should be made, if necessary , with the Auxiliary Air Dampers only.
20
21
Close the Coal-Air Dampers when the corresponding Coal Mill is stopped.
22
23
When changing Damper positioning an entire elevation should be treated
simultaneously (i.e.) Damper positioning at the same elevation should always be
identical in all Wind Boxes.
24
The Oil Elevation Dampers modulate as a function of oil header pressure
when put on Auto mode.
25
26
The Coal Elevation Dampers modulate as function of Feeder speed when put
on Auto mode.
27
28
The Auxiliary Air Dampers modulate as a function of Furnace to Wind Box
Differential Pressure according to the Boiler load, when put on Auto mode.
29
30
All the Auxiliary Air Dampers maintain their status quo upon a Boiler trip
and will open fully when both FD Fans are off, under Auto mode of operation.
31
II) BURNER TILT :
32
Ensure minimum instrument air pressure of 5 6 ksc for the Burner Tilt
mechanism.
33
34
Always have the tilt mechanism on Master Control, which tilts all the
Burners in all the corners.
35
36
Tilt the Burner either upwards or downwards so that the steam temperatures
are maintained at 540 0C for any combination of firing elevations.
37
38
Exercise it manually through full range, minimum once in a shift, to ease the
mechanism.
39
40
Set the RH Steam temperature at 540 0C for keeping the Burner Tilt master
on Auto mode.
SH / RH ATTEMPERATION SYSTEM
The purpose of the SH / RH Attemperation system is to maintain the Boiler
outlet SH / RH Temperature well within the permissive limits.
SYSTEM DESCRIPTION :
The metal temperature at all sections in the Super Heater and Re-heater and
also in the Turbine should be maintained with in the permissible values.
Attemperation by Feed Water injection is used to limit the temperatures to steam at
Boiler outlet. The design margin in temperature control may get deviated and may
result in higher outlet temperature control due to slag formation in Water Wall,
high excess air, low feed water temperature, low load operations, and top tier Mills
in service. The cause has to be identified and action taken to keep the SH and RH
temperature at 540 0C, at Boiler outlet always.
Wall Blower operation and Burner Tilt adjustment are also made in addition
to adjust temperature control. Temperature control by feed water injection has to
be initiated as a final measure. For SH steam temperature control, the required
quantity of feed water is injected at the SH connection links between LTSH and
Platen SH through a nozzle. Normally spray type De-Super Heaters are provided
with renewable liners to protect the main Super Heater shell from erosion of spray
water and thermal shock. Since they are placed before Platen Super Heater, the
water particles entry to Turbine is remote.
For Re-Heater temperature control Burner tilting is carried out. Re-Heater
spray injection is carried out as a last resort at the Cold Re-Heat pipe before
entering the Re-Heater coils.
A Control Valve in an automatic control drive unit regulates the flow of
spray water quantity supplied to the De-Super Heaters for Main Steam and RH
steam temperature control of 100 % stand by Spray Control Valve is provided for
RH & SH temperature control. Both of the main and stand by Spray Control Valve
are provided with electrical Isolation Valve at the upstream side and hand valve at
the down stream end.
For SH / RH Attemperation system of the Boiler is of Direct Spray Type &
which consists of the following components.
1. Electrically operated main inlet block valve for both SH and RH Attemperator
Heaters.
2. Spray water limbs for SH Attemperation 4 Nos.
3. Spray water limbs for RH Attemperation 4 Nos.
4. Pneumatically operated Block Valve to RH Attemperation main inlet.
5. The Spray water required for the Attemperation taken from the Feed Water inlet
to the Boiler, through the electrically operated Attemperation Valve E 13 and
further distributed to SH / RH Attemperation through the electrically /
pneumatically operated Isolation Valves. Spray water enters through this limbs
to the Super Heater Header No:10th outlet, for SH temperature control and at the
CRH header for RH temperature control.
PROCEDURE :
SH TEMPERATURE CONTROL :
SH / RH ATTEMPERATION
SHH 11
RHH2
HRH
HRH
DESH
STEAM FOR
SHH 10
RHH1
SOOT BLOWING
S56
S30
S37
S33
S32
S55
DESH
S36
S27
S28
DESH
S54
S39
TO
DRAIN
S43
S29
CRH
INLET
S31
R44
R21
S49
R23
R29
R28
R16
R30
R24
FROM BFP
R45
R19
R25
E13
TO
DRAIN
DISCHARGE
R36
R17
R20
R22
R37
CRH
INLET
Cone Cyclones
Electrostatic Precipitators
Scrubbers
Fabric Filters
:
:
:
:
85 %
99 %
99.7 %
99.9 %
ELECTROSTATIC PRECIPITATOR :
The Technical Superiority of Electrostatic Precipitator lies in low pressure drop,
High Efficiency for small particle size and relatively easy removal of the collected
particles.
The four different steps are,
1.
2.
3.
4.
PRINCIPLE OF OPERATION :
A.C Input is applied to the Main Transformer through the load windings of the
two Transducers. The Control Windings are connected in series and the Control
Current is provided by a Thyristor Bridge Circuit. The Thyristor Bridge is driven by a
pulses generated by an Electronic Pulse Generator which in turn is controllable by
Electronic Control System. Basically transducer is employed as a variable impedance
device which controls the input applied to the Main Transformer. If the Main A.C is
applied, with Zero Excitation to the Transducer Control winding, the Transducer
impedance will be high compared to the reflect load impedance on the Primary of the
Main Transformer and the HV Output from the set will be low. As the Control Current
is gradually increased, the impedance of the Transducer falls, thus enabling application
of increased A.C Voltage to the Main Transformer. Control Current to the Transducer
is in turn under the Control of a Thyristor Bridge. The Controller Output regulates the
conduction angle of the Silicon Control Rectifier (SCR) Bridge via the driver
regulating the set output.
Note : The Electrostatic Precipitator need not be cut in to service while the Boiler is
under Oil Firing.
TECHNICAL DATA
DESIGN CONDITIONS :
a)
12,96,000 M3 / Hr.
b)
Temperature
140 0C
c)
Dust Consentration
33 gm / M3
d)
- 200 mm WCL
e)
5 Nos.
f)
98.5 %
g)
15 mm WCL
h)
Treatment Time
13.68 Seconds.
i)
Velocity of Gas at
Electrode Zone
1.053 M / Sec.
39 Nos.
:
:
:
:
5616
9M
400 mm
109.44 M2 / M3 / Sec.
:
:
:
:
:
:
:
36
1368
21888
7879 M
125 mm
A. COLLECTING ELECTRODE :
a)
b)
c)
d)
e)
f)
A. EMITTING ELECTRODE :
a)
b)
c)
d)
e)
f)
g)
Type
Size
No. of Electrodes in the Frame
forming in one Row
No. of Electrodes in each Field
Total No. of Electrodes per Boiler
Total Length of Electrode per Field
Plate / Wire Spacing
:
:
d) Drive
b) Rapper Size
c) Frequency of Rap
d) Drive
:
:
:
D. HOPPERS :
a)
b)
c)
d)
Type
No. of Hoppers
Capacity
Heating
e) Baffling Arrangement
:
:
:
:
:
Pyramidal
40 (2 / Field )
8 Hours Storage.
Electrical Heating Provided to
the Bottom of the Hopper.
2 Sets of Reflector Plates for
each of the Hopper underneath
the Collecting Plate to prevent
gas sneakage.
E. RECTIFIER :
a) Rating
b) No. of Rectifiers
c) Type
:
:
:
d) Location
F. MOTORS :
:
:
G. HEATING ELEMENTS :
240 KW
16 KW
64 KW
The balance quantity of fly ash is separated at ESP fields and collected in the
ESP Hoppers located at down side of fields. There are 48 Nos of ESP Hoppers for
each Unit. The Fly Ash so collected is sent to mixing chambers at its bottom and ash
slurry is formed. Ash in all the Hoppers above the mixing chambers is collected by
water jet.
The ash slurry from BAH Economizer Hoppers, APH Hoppers, ESP Hoppers
and Chimney Hoppers are sent to ash slurry sump by gravity and by forcing through
water jets.
Diversion sluice gates just before ash slurry sumps are provided to divert ash
slurry into any ash slurry sumps in particular stage. Normally unit basis drawl of ash
slurry is being carried out.
LP line water make up is provided at ash slurry sump for clearing deposits in
the grate and diluting purpose. HP line water make up through water jets near the
suction line of ash slurry pumps is provided to clear the ash choke up, diluting ash
slurry and to pickup slurry sump level speedily if necessary.
Great provision is made in the sump to restrict the flow of larger size ash blocks
into the suction of ash slurry pumps.
Each stage Ash Handling Pump House has two numbers of Ash Slurry Sumps
and each Sump is being connected with two streams of Ash Disposal System. So each
stage has four streams of Ash Disposal System are called A,B,C,D streams.
Each stream has three number of Ash Slurry Pumps connected in series and the
suction line of first pump is connected with Ash Slurry Sump through two suction
valves. One is electrically operated Isolation and the other is Manual Isolation Valve.
The suction line sucks the ash slurry from Ash Slurry Sump and sent to Ash
Slurry Pump No. 1 (say A1 for A stream) where the discharge pressure is 4.5 ksc.
The pressurised ash slurry goes to the suction of next pump (say A2) and the ash slurry
pressure is raised to 9.0 ksc. The discharge from second pump is sent to the suction of
third pump and the final discharge pressure of ash slurry is around 13.5ksc.
In the discharge side there is a discharge valve (Manual). In the down stream
side of the discharge valve the following valves are being connected.
1) One number ash slurry drain valve which is connected to common header drain
pipe. Similarly every stream discharge lines drains are connected to this drain
header. This drain header runs over to ash slurry sumps. Stop valves are also
provided at ends of drain header over the sump.
2) Flushing line from Flushing Water Pump is also connected at the down stream
side of ash slurry pump discharge valve through NRV.
The LP water and HP water are supplied to the system through LP and HP water
pumps respectively. Flushing of ash slurry discharge line being done after stopping
the ash slurry pump to avoid ash slurry choking in the discharge line. For this purpose
two numbers of Flushing Pumps are provided for each stage. Water sealing is provided
for ash slurry pump glands by means of Seal Water Pumps.
For all the above water pumps water is fed from Ash Water Tank. Auxiliary
cooling water return line from the individual unit normally feeds the corresponding
Units Ash Water Tank. Over Head Tank water make up can also be made if in the
case of any emergency of low water level in ash water tank. No isolation provision is
made in the ACW return line and the entire water is to be collected in the Ash Water
Tank.
PROCEDURE :
OPERATING INSTRUCTIONS :
PRE CHECKS
1) Ensure the opening of following valves
All ESP hopper valves
All Economizer hopper valves
All APH hopper valves
Chimney hopper valves
Mixing chamber isolation valves at various location
ACW line to seal trough
ACW line to BAH nozzles
HP line to BAH nozzles
Clinker grinders seal valve
LP valves to ash slurry sumps
Seal water line valves to ash slurry pumps
All feed gates in BAH
Nozzles at various location made through
2) Ash water tank is filled up.
3) OHT line isolation valve to seal water pumps is opened and start one seal
water pump per each unit and opened its delivery valve.
4) Open the suction valves of one number HP Water pump and one number of LP
Water pump in each Unit.
Crack open the discharge valve of HP / LP water pump (to be started).
Start HP water pump and then open its discharge valve full gradually.
Similarly start LP water pump also.
5) Ensure that seal water is available for ash slurry pumps by opening the
individual valves.
6) Ensure the filling up of
Seal trough
BAH
AH mixing chute chambers of ash hoppers at various locations.
7) Start both the clinker Grinders and check for the correct direction of rotation.
8) Start both the scrapper feeders.
9) Open all the four feed gates at the Bottom ash hoppers.
Note : Starting of scrapper feeder, clinker grinder and opening of feed gates are
to be done just before the starting of the very first mill.
10) Ensure all nozzles at various locations are working all right.
11) If required manual isolation valves in HP or LP lines may be opened to dilute
the ash slurry where it tends to block the drain channel.
12) STARTING OF ASH SLURRY PUMPS
Ash slurry pumps discharge valve should be in closed condition.
Ash slurry discharge drain valve is to be kept in full closure position.
Ash slurry discharge flushing valve also be closed fully.
Manual isolation suction valve to ash slurry pump is in OPEN condition.
Rack in the Breakers of THREE ash slurry pumps in that particular
stream.
Release the local push button.
Reset the flags in the panel.
Open the inlet electrical valve.
Ensure the avilability of seal water to both the pumps.
In case of any blockage at the suction line of the pump the running pump
may not consume normal load current. This is the correct indication of nonloading of pump. Hence to release the blockage the LP/HP water spray in the ash
slurry sumps is opened. Normally LP water make up is being opened for the
dilution and ash slurry sump level make up.
STOPPING OF ASH DISPOSAL SYSTEM.
1.
2.
3.
4.
5.
6.
e) Keep Flushing end Isolation Valve slight open (2 to 3 turn), Start the
Flushing Water Pump and then open the discharge valve gradually. (The
pressure around 13.5 ksc).
16. Ensure the closure of Ash Slurry Pumps Discharge Valve and Ash Slurry Drain
Valve.
17. Gradually open the Isolation Valve in the flushing water line that connects the
ash disposal line in which ash slurry is completely drained.
Note :
If the disposal line ash slurry is not completely drained after the stopping of the
pumps, then water content in the ash slurry inside the higher level disposal line
may pass into Ash Slurry Sump, due to its gravity and passing in the discharge
valve. But ash content in the discharge line will stay in the pipe itself, which may
cause choking of the pipes. Hence it is the routine practice to drain the slurry
immediately after stopping of the pump, the flushing operation is followed.
If it is required to back wash the Ash Slurry Pumps the same also can done by
keeping its suction valves open and admitting flushing water through the Pumps
Discharge Valve. During this operation slightly opening of Discharge Valve only is
enough.
18. Flushing operation is normally being carried out for about 20 Minutes.
19. The close FW Isolation Valve and then stop Flushing Water Pump after closing
its Discharge Valve.
20. Close the delivery valve of seal water line and stop the Seal Water Pump.
IMPORTANT NOTE :
Never start ASH SLURRY PUMPS if
Ash Slurry Sump level is inadequate
No sealing is given to Pumps
Adequate dilution of Ash Slurry is available.
Never stop the Ash Slurry Pumps before closing the discharge valve.
Never leave Ash Slurry in the ash disposal line.
1) To provide necessary space for separation of steam from a mixture of steam &
water.
2) To house the equipment needed for purification of steam after separation from
water.
3) To provide a water storage for preventing the starvation of tubes.
Wet steam entering the drum from the riser tubes and furnace walls is collected
in a compartment called separating chamber. From here the steam is led through two
rows of Turbo-separators consisting a primary stage and secondary stage.
From the secondary stage of Turbo separators the steam flows uniformly and
with relatively low velocity upward to the series of screen dryers, extending in layers
across the length of the Drum. These screens perform the final stage of separation.
The fitting and alignment of Drum internals are very important for its efficient
performance.
SUPER HEATER:
The details of 4 basic sections of Super Heater is as follows:
SL.NO.
SECTION
LOCATION
1.
PLATEN
2.
PENDANT
3.
HORIZONTAL
4.
Steam Cooled
Wall & Roof.
STEAM FLOW :
Saturated, dry steam from the steam drum flows as follows:
1) Steam cooled wall roof tubes.
2) Steam cooled side wall tubes.
3) Extended steam cooled side wall tubes.
4) Front steam cooled wall tubes.
5) Steam cooled root and rear wall tubes.
Temperature
in oC
341
345
350
SHH-4
SHH-5
SHH-6
SHH-7
SHH-8
SHH-9
SHH-10
355
360
370
380
400
430
Pressure
in ksc
146.5 Steam cooled roof tubes-I pass
146.0
---do
--- II pass
145.5 Steam cooled side wall tubes
(L&R)
145.0
---do
-----144.5 Steam cooled side wall tubes.
144.0
143.5
143.0
142.5 Super heater horizontal (Lower)
142.5 Super heater horizontal (Upper)
De-Super Heaters
SHH-11
SHH-12
SHH-13
SHH-14
427
515
530
540
142.0
141.5
141.0
140.0
Final
super
heater
Super heated steam from the pendant super heater outlet header goes to the
H.P.Turbine via main steam lines.
After passing through the high pressure stages of Turbine, steam is returned to
the Re-Heater via Cold Re-Heat lines. The Re-Heat De-Super Heaters are located in
the Cold Re Heat header. Re-Heat steam flow through the unit is as follows.
1) Front Pedant Re-Heater.
2) Rear Pendant Re-Heater.
After being re-heated to the required temperature the re-heated steam is returned
to the low pressure section of the turbine via the HOT REHEAT LINE.
The main purpose of re-heating is to increase the dryness fraction of steam
passing through the later stages of turbine.
During all startups, care must be taken not to overheat the super heater or Reheater elements. The firing rate must be controlled and exit gas temperature must be
below 540 0C.
Safety valves are also provided in the main steam lines and HRH / CRH lines to
expel out maximum quantity of steam while Boiler pressure exceeds the
predetermined design value.
An Electrometric Relief Valve (ERV) also provided in the main steam line
which has the setting below the minimum Super heaters safety valves setting. This
valve can also be operated manually at any pressure.
The 14Nos. of safety valve set pressure details are given below.
---- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Sl.
Safety Valve
Set Pressure
Reviving
No
Location
in ksc (g)
Capacity
(in T/Hr)
----------------------------------------------------1
Drum LHS-B1
158.2
159.0
2
,,
RHS-B2
161.0
193.0
3
,,
RHS-B13
162.4
195.0
----------------------------------------------------4
MSL RHS S 1
143.8
86.0
5
MSL RHS S 53
144.5
87.0
6
MSL ERV
141.3
87.0
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -7
CRH LHS
33.0
100.0
8
CRH LHS
33.4
130.3
9
CRH RHS
33.8
131.6
10
CRH RHS
34.1
133.0
----------------------------------------------------11
HRH LHS
30.6
115.0
----------------------------------------------------12
Soot blower Line
38.0
-----------------------------------------------------13
PRDS Line
18.0
-----------------------------------------------------14
CBD expansion tank
7.8
-- -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - MAIN PARAMETERS :
1) Steam generation
2) Feed water supply
3) Drum steam pressure
4) Main steam temperature
:
:
:
:
700 T / Hr.
715 T / Hr.
147 to 150 ksc
540 0C
:
:
:
:
:
:
137 ksc
580 T / Hr.
26 ksc
332 0C
24.5 ksc
540 0C
STEAM QUALITY :
-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Pressure in ksc
--------------------------------------------< 40 ksc
40 to 100
100 and above
------------------------------------------------------Sodium mg /Kg < 60
< 15
< 10
Na
- - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Silica mg /Kg
--< 25
< 20
Si02
-----------------------------------------------------Conductivity
-------< 40 50 s/cm
PROCEDURE :
The horizontal super heater sections and steam cooled walls are completely
drained by opening the super heater header drains and Eco., Drum & SH vents before
lighting up. Super heater header drains are closed at a drum pressure of 5 to 7 ksc.
Close Eco., Drum & SH air vents when they begin to steam.
1) SH start up vents are opened immediately after lighting up and closed after
synchronization.
SH start up vents are closed if HP / LP Bypass system is brought into service.
The above vents are again opened during Turbine rolling as HP / LP Bypass station is
closed.
STEAM GENERATION
A Boiler services the purpose of generating steam at a required Pressure and
Temperature (137 ksc & 540 0C in case of a 210 MW Unit) which is utilised in driving
the Turbine for Electrical Energy Generation in Generator.
SYSTEM DESCRIPTION :
The steam generator used in a 210 MW unit is described as follow
a) NATURAL CIRCULATION :
The flow of water from the drum through the down corners followed by the
rising of water in the water walls and the rising of the steam up to the drum all occur
naturally and no external pumping is carried out. The natural circulation takes place
due to the density difference between the steam and water in the water wall tubes as
the operating pressure (137 KSC) is well below the critical pressure.
b) BALANCED DRAUGHT :
A combination of both forced draught and induced draught fans are used, there
by maintaining a furnace pressure of 5 to 10 mm WCL inside the furnace.
c) WATER COOLED FURNACE:
The furnace walls are made up of water wall tubes, which serves dual purpose
of steam generation as well as cooling the furnace.
d) TANGENTIAL CORNER FIRED:
The fuel (both oil and coal) is injected into the furnace from the corners and the
nozzles are so designed as to direct the fuel tangential to the imaginary fire ball, thus
giving a swiveling action to the fire ball, resulting in effective heat transfer.
e) DRY BOTTOM:
The maximum furnace temperature is well below the ash fusion temperature
and hence the ash from the furnace falls as dry ash.
In addition to the above definitions, the boiler used in a 210 MW is of two pass,
single drum, radiant superheat and reheat type with regenerative air pre-heater.
PROCEDURE :
1) COLD START UP :
2) HOT RESTART:
Normally the casing metal temperature of HPT is more than 350 C in case of HOT
start.
Open SH drains and air vents if the pressure has reduced considerably
although this will cause further pressure reduction.
If the re-start is immediately done after a tripping, the drains and vents
should not be opened.
Cut in HFO guns in CD elevation (in case of immediate hot start) or LDO
guns in AB elevation (in case of delayed hot start). The decision can be made
depending upon the flue gas temperature at APH O/L. Then change over to
HFO guns in CD elevation and cut out LDO guns in AB elevation. Cut in
HFO guns in AB elevation if required.
Start mill D and feeder D and raise the steam parameters such that the
steam temperature is 50 C higher than the HPT casing temperature.
The loading of the Boiler is done gradually so that the unit load is raised to 210 MW is
50 to 55 Minutes time.
The starting of the fans and other auxiliaries is done in same way as cold start up.
3)
Note: 1) If the Boiler is to be Shut Down for a long period like overhauling, the
Bunkers have to be emptied. Hence the feeding to the Bunkers is stopped well in
advance after maintaining the Bunker levels such that the Mills can trip in the
following sequence.
ii) If the Shut Down is for a short duration, the Feeders can alone be emptied by
closing the Bunker Gates, if required by MP maintenance.
Gradually reduce Boiler load and hence the Unit load. The drop in the
saturated steam should not exceed 83 0C per Hour.
Cut out the top most Feeder ( E & F as the case may be ). Admit the
Cold air to the Mill for a while to cool the Mill. Trip the Mill if the Mills O /
L temperature is around 50 0C.
Cut out Feeder A and Mill A as per procedure. Close main SH / RH
Attemperation Valve to avoid abrupt drop of MS & HRH temperature.
Cut in Oil Guns in CD Elevation. ( If the temperature drop is drastic due
to problem in spray lines, EF Elevation Guns may be cut into service).
Cut out Feeder B and Mill B.
Cut out Feeder C and Mill C.
Finally cut out Feeder D and Mill D.
The Unit is now on Oil Guns alone. Usually the Unit is Tripped using
Turbine Trip switch.
MFT is actuated. The Oil Guns Trip. PA Fans and Seal Air Fan Trip. All
Oil Trip Valves close.
4)
BOXING UP THE BOILER (to facilitate Hot restart after a short duration)
Normally all the Boiler side drains are opened out after the tripping of the
Unit for long Shut Downs to avoid trapping of water resulting from
condensation of the steam, which may cause hammering while charging
during start up. The opening of the drains is also ensured during the pre-start
checks for light-up.
6)
ROUTINE OPERATIONS
Operate APH Soot Blowing in all the three Shifts by drawing steam from
10 Header.
Charge CBD Expander if CBDs Silica value drops below 0.2 PPM.
Cut out CBD Expander and raise CBD valve opening whenever Silica
value raises above 0.4 PPM.
th
The main duty of a boiler operator is to maintain these parameters within normal
limits.
Action
Check
2.
Open
3.
Close
4.
Open
5.
Open
5.a
Close
6.
Close
Remarks
7.
8.
Close
9.
Close
Open
11.
Open
Open
Close
Close
Close
Open
Open
Open
Open
21. Seal Oil filter inlet / outlet valve (A.B) SO-15 Close
/ SO-17 and SO-16 / SO-18
22. DPR and POR inlet valve SO-20
Open
Open
Open
Open
Open
Close
Close
Check
Check
Establish
OPERATING INSTRUCTIONS :
Sl.
Description
No.
1. Discharge valve of AC / DC seal oil pumps
SO-7 SO-10.
Action
Remarks
Close
2.
Observe
the
performa
nce of
the pump
3.
Open
Watch load current of
gradually AC seal oil pump
and then
keep it
full open.
4.
Throttle
Open
5.
Open
To maintain load
current of SOP about
18-20 A
fully
6.
Open gradually.
Charge by air
releasing.
7.
Check
Check should be
below 0.5 ksc.
8.
Open
gradually
9.
Full
Open
11.
Open
Check D.P 0.6 to 0.8
gradually ksc
and keep
it full
open
Check
Conform any
overflow to Hydraulic
Seal Tank.
Check
Check
Close
Throttle
16. Charge S.O coolers (A, B) on oil side SO12 / SO-81 and SO-14 / SO-83
Open
Admit
Open
Open
Switched
ON.
Place it
in locked
position
Bring it
to 5 ksc.
Observe
for auto
start.
Bring it
to normal
pr.12 ksc
Stop
In
service
Open
Throttle
Open
Bring it
to 6.5 ksc
Observe
for auto
start
Bring it
to normal
pressure
12 ksc.
Stop
So header pressure to
be maintained around
12 ksc.
Seal oil system is in service with injector and AC / DC Seal Oil Pumps on
AUTO stand by.
Action
Inservice
2.
Check up
3.
Kept in
position
4.
5.
Close
6.
Close
7.
Close
8.
Close
Remarks
Close
Close
11.
Open
Open
Open
Open
Open
Open
Close
Open
Open
Carbon di Oxide
admitted
21. Pressure of Carbon di Oxide gas admitted Adjust to Read from GPG 1
3 ksc
pressure gauge
22. Collect samples
Analyse
Action
Remarks
Close
2.
3.
Open
4.
Open
5.
Select
the scale
of H2 in
CO2
Check up
purity &
pressure
6.
Close
Purity 97 % pressure
0.5 ksc
7.
Build up
to 3.5 ksc
8.
Open
9.
Open
Open
11.
Open
Gas analyzer in
service
Action
Remarks
Close
2.
Close
3.
Carbon di Oxide
is admitted
4.
Open
Hydrogen pressure
reduced to 0.2 ksc
5.
Connect
- ed to
generator
vent
6.
Check up
purity &
pressure
Description
Action
Remarks
1.
Close
2.
3.
Open
4.
Open
5.
Select the
2%
scale of
Carbon di
Oxide in Air.
T.G set
C.W Pump to condenser
Bottom Ash Hopper &
Sealing trough
Drum level
All peep holes & man
holes in boiler
Soot blower (Wall
blowers, long retract
and APH soot blower)
Soot blower PRS valve
pneumatic valve and
isolation valves
Isolation valve to
impulse safety valve
Both Air Pre Heaters
A/B
Both ID fans A / B
Both FD fans A / B
Action
Remarks
3 Nos. in Service
2 Nos. in Service
2 Nos. in service
on barring gear
3 Nos. in service
Filled up
with header
pressure 7.5 ksc.
with header
pressure 7.5ksc.
Check up over
flow
Normal
Closed
Check that all blowers are
retracted
Closed
Opened
In Service
In Service
In Service
Check and placed in 0
position (50 %)
Cleaned and made ready for
operation
Check for availability
In Service
Check fuses, Supply switch to
be kept ON
Lined up
If SCAPH avails
charge (Unit III)
Opened
37. Economiser
Recirculation valves
(2 Nos.)
Open
Opened
Fully Opened
Closed Condition
Opened
Opened by 5 turns
Opened
At 18 M & 52 M
Closed
Closed
At 18 M
Fully closed
Closed
Kept opened
Lined up
In Service
BOILER LIGHTING UP
38. Purge ready Condition
39. Purge ready Indication
40. Purge complete
Indication
41. Ignitor trip valve and
Warm Up oil trip valve
42. Warm Up oil firming
for AB elevation
43. AB elevation Ignitors
Check
Available in FSSS console.
Push to purge is depressed
After 5 minutes purge
complete indication will come
in FSSS console.
Open
Selected in FSSS console
Cut in
Check flame
Check
locally ( 18 M )
The same has to
be changed over
to other pair after
30 min.
If the flame is
smoky adjust the
oil pr. or wind box
to furnace D.P.
At 18 M.
52 M
18 M
V2 31 (L&R) Unit
I & II
V2 7 (L&R) Unit
III slightly open
for warming up
Action
Remarks
Establish
service
Admitted
Close
Close
> 540 mm of
Hg
Open
Open
Open
Open
Check
Open steam
purity less
than 1 ppm
Open
about 20 %
valve
Close
Close
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Action
Remarks
Check
Check > 600
mm Hg.
Opened
Check
Observe
Close
Open
Open
Open
20 % Open
Open
Open
Open
(DW38,DW 4)
(Unit I&II)
Open
(DW 38 )
(Unit I & II)
Open DW 39
Unit I & II
DW 40 (Unit I
& II) Open
In service
Check Zero
Check
Reset
21. TLR
Reset
Open
gradually
Opened 80 %
Observe
Open
gradually
Observe the
recorder
Check
Action
Open partially
Remarks
To maintain steam pr.
Close
Close
Close
Close
Check
Check
Open
Rotate gradually
anticlockwise
direction
Partially open
TURBINE ROLLING
11.
Open speed
control gear
further by one or
two turns
Check
Close and
observe
Sl.
Description
No.
1. AS 16 steam admission valve to
flange and stud heating scheme
2. AS 51 drain of steam header
3. AS 30, 31, 32, 33, 34 and AS 35
drain from flange and stud heating
jackets
4. AS 18 flange heating valve
5.
6.
7.
Action
Remarks
Open
Open
Open
Crack
open
AS 19 stud heating valve
Crack
open
AS 50 isolating valve (Electrically Open
operated)
partially
AS 40 drain of flange and stud
Open
heating system
partially
6.
AS 50 isolating valve
(Electrically operated)
AS 41 drain of flange and stud
heating system
7.
Action
Remarks
Open
Open
Open
Crack
open
Crack
open
Open
partially
Open
partially
1.
Admit cooling
water to oil coolers
2.
By pass valves
V2 7 & V2 8 (Unit I & II)
V2 9 & V2 10 (Unit III)
Turbine speed at 1200 rpm
3.
4.
5.
6.
7.
To be brought into
service
To be maintained around
42 0C from 500 rpm to
3000 rpm and also on
load.
Rates of speed raise 50
rpm per minute.
Flow meters to be
brought to service
position.
To be brought into
service
Open such that
Turbine speed
increases and
attains 3000 rpm
Full open
Full open
Observe
Description
Close gradually
Action
Remarks
1.
Check
2.
Gradually
open full
3.
4.
5.
6.
7.
8.
9.
Synchronising switch
10.
11.
12.
13.
14.
15.
16.
Conformation to be
obtained from OD /
Switch yard for proper
closing.
Switch ON Confirmationto be
obtained from 6.6 kv
operator
Auto /
Manual
Press to
Generator terminal
close
voltage will built up to 14
with in 20 sec.
Turned
Manual position, observe
clockwise the Bus and Generation
voltage
Raise /
Frequency of Grid & T.G
Lower
set
Raise /
Observe check
Lower
synchronism lamp
Close
Synchro scope rotation in
clockwise direction
slowly while
synchronizing.
Pick up
load
Switched
ON
Fully open
Switched
1) Start up vent to be
closed by Boiler
confirmation.
2) All drains to flash tank
& MSL drains to
atmosphere to be closed
17.
Fans
Field flashing supply
ON
Switch
OFF
Action
5 to 10 MW
2.
3.
Steam
parameters
4.
5.
6.
10 MW for 10
minutes
Observe
7.
Unit Auxiliary
Transformers
Cut in.
8.
Drip Pump
Cut in.
9.
Start Second
Boiler Feed
pump.
11. H.P.Heaters
Charge.
Remarks
Preforably two heavy oil elevations in
service
Watch expansions vibrations and other
parameters
Main Steam Pressure 30 ksc & Temp.
350 0C ; Temp. before IPT 320 0C
Thermal Expansion- 10 mm from front
pedestal
Prepare PA fans, Seal Air Fans & Mills
Water side.
Warming up.
15. H.P.Heaters
Steam side.
Charge
Increase the
Load to 180
MW.
HOT START UP
Sl.
Description
No.
1. Lubricating oil system /
Governing oil system
2. T.G set rotor either on Barring
gear / Counting down
3.
Auxiliary Cooling Water
Action
In service
Check
In service
4.
In service
5.
Condensate Pump
In service
6.
In service
7.
In service
8.
9.
3 pump out of 4
pumps in service with
Tower fans.
3 pump out of 4
pumps in service.
Two out of three
pumps in service
One out of three to be
kept in service
Two out of 3 kept in
service.
With in limits
More than 540
mm of Hg
In service
Check
Check
Boiler trip-oil
elevation trip coal
feeder drip resets.
Remarks
Check
Check
Observe
Check
25.
26.
27.
28.
29.
30.
31.
Check
Maintain at 6 ksc
by suitably
adjusting HP and
LP by pass
If exceeds 360 0C HP
by pass will get
closed.
rate.
33. Bring the speeder gear position
to zero and then open the
speeder gear to 8 mm
34. ESV (L&R) and IV (L&R)
Resetting the
Turbine
Open manually by
20 mm for ESVs
and 5 to 10 mm
for IVs by the
Hand arrestors
Open by 2 to 3
turns
Check
Check
Release fully
Close suitably the LP by pass The T.G set may
valves (and open HP by pass roll and if it rolls
valves if required)
continue, roll the
machine
Move anticlockwise slowly, Watch forth
till such a time the speed
opening of IVs &
picks up then close HP
ESVs and then
bypass valves
CVs
Check
If not switch off
manually
Open
Open
In service
Watch over
expansion,
bearing temp. and
vibration.
Open ES 6 for
Deaerator
pressure
Check the specific
system
45. Lub oil coolers
Open partially
Resistivity for
normal value
>500
Soak the Turbine
at 1000 rpm for
10 min.
Open fully
Confirm the closing of the
same from OD / Switch Yard
Check
Switch on
To be switched on
by OD / 6.6 KV
Check vibration &
bearing temp.
SYNCHRONISE
53. Synchronise
atmosphere.
54. All drains to flash
tank and MSL
drains
55. Stator Water
secondary system
56. Hydrogen Coolers
Booster Pump
common O/L valve
57. LP by pass
Fully close
Put into service
Fully open
Close fully
Close fully watching the
exhaust hood temp.
should be below 50 0C
By varying Speeder Gear Depending up on the Boiler
control
parameters and Turbine
parameters
Description
Action
Remarks
No.
1. Initial load
5 to 10 MW
2.
3.
Steam parameter
4.
All Drains to
Flash Tank &
MSL Drains to
atmosphere.
Differential
Expansion
Close
Metal Temp.
difference
between inner
and outer casing
of HPT.
Load on the TG
Set
Maintain
5.
6.
7.
8.
50 MW for 10
Minutes
Check & observe
Maintain within
limits
- 0.6 to + 4.00 mm ( HP )
- 1.5 to +3.00 mm ( IP )
-2.5 to + 4.5 mm ( LP )
Within 35 0C
Increase to 30
Prepare Seal Air Fans, PA Fans and
MW in a period of Mills for put into service
10 minutes
Observe
Observe
Increase to 70
MW
nd
Tripped on Auto.
According to drum level