CONTENTS

CONTENTS

PAGE NO.

BILL OF QUANTITIES
PREAMBLES & METHOD OF MEASUREMENT

PN/1-21

PRELIMINARIES & GENERAL REQUIREMENTS

BQ/P/1-8

Bill No.1 ENABLING WORKS


1.1

Excavation & Earthworks

BQ/1/1/1-4

1.2

Excavation Support & Protection

BQ/1/2/1-2

1.3

Piling

BQ/1/3/1-4

1.4

Dewatering

BQ/1/4/1-3

SUMMARY

BQ/MS/1-1

DAYWORK SCHEDULE

BQ/DW/1-6

November 2016

Residential Building, Marina -Res 012


Enabling Works Package

PRELIMINARIES & GENERAL REQUIREMENTS


Description

Qty

Unit

Rate

Amount

PRELIMINARIES & GENERAL REQUIREMENTS


Restrictions
Access to and possession or use of the Site
A

The contractor shall allow for mobilization on site

Item

The contractor shall allow for de-mobilization from the site


on completion of works

Item

The contractor shall allow for the requirement of clauses


42.1 of Tender and Contract Conditions

Item

Item

Item

Item

Item

Item

Limitations of working space


D

The working space on Site is subject to the reasonable


limitations imposed by the Engineer
Limitations of working hours

The contractor shall allow for the requirement of clauses


45.1 of Tender and Contract Conditions
Contractor's Administrative Arrangements
Site administration

The Contractor shall provide sufficient staff and equipment to


perform the administrative duties in executing the Contract
Supervision

The whole of the works shall be under the full time


supervision of the Contractor. The Contractor shall liaise and
coordinate with all other persons as necessary, including Sub
Contractors
Security

The Contractor shall protect the Site from unauthorized entry


and shall control his labor force to prevent nuisance or
trespass onto adjacent property

To Collection QR

November 2016

BQ/P/1

Residential Building, Marina -Res 012


Enabling Works Package

PRELIMINARIES & GENERAL REQUIREMENTS


Description

Qty

Unit

Item

Item

Item

Item

Item

Rate

Amount

Security against fire


A

The Contractor shall take all necessary precautions against


fire as required by the insurance company insuring the
Works, the Department of Civil Defence and the Engineer
Safety, health and welfare of workpeople

The Contractor, and all persons employed by him on Site,


shall comply with all Acts, Orders, Laws and Regulations
concerning the safety, health or welfare of workpeople
First Aid

The Contractor shall provide and maintain first aid stations in


all areas where work in progress, complete with all first aid
equipment. At each first aid station the names of the
Contractor's staff that are trained to render first aid shall be
displayed
Messing and welfare facilities

The Contractor shall provide and maintain adequate messing


facilities; sufficient sanitary facilities in workmen
accommodation areas, at messing facilities and in areas
where work is in progress for his own and Sub Contractors'
workmen. Facilities shall comply with government regulations
Transport of workpeople

The Contractor shall make all necessary arrangements for


the transport of his own, and his sub-contractors', employees
for the duration of the Works

To Collection QR

November 2016

BQ/P/2

Residential Building, Marina -Res 012


Enabling Works Package

PRELIMINARIES & GENERAL REQUIREMENTS


Description

Qty

Unit

Item

Item

Rate

Amount

Constructional Plant
Small plant and tools
A

Provide small plant and tools


Scaffolding

The Contractor shall allow for providing and maintaining


scaffolding for the use of his own and Subcontractor's
operatives
Cranes and lifting plant

Establishment

Item

Maintenance

Item

Removal and making good the Site

Item

Plant
F

Establishment

Item

Maintenance

Item

Removal and making good the Site

Item

Employer's and the Engineer's Facilities


Temporary office accommodation for the exclusive use of the
Engineer and the Employer and his representatives including
all furnishings, fittings, parking areas and related facilities as
mentioned in the Specifications
I

Establishment

Item

Maintenance

Item

Removal and making good the Site

Item

Services for the exclusive use of the Engineer and the


Employer and his representatives
L

Telephone and telefax

Item

Internet - high speed

Item

Monthly progress reports and progress photographs as


specified

Item

To Collection QR

November 2016

BQ/P/3

Residential Building, Marina -Res 012


Enabling Works Package

PRELIMINARIES & GENERAL REQUIREMENTS


Description

Qty

Unit

Item

The Contractor shall arrange for the provision of


uninterrupted electrical power supply to the Consultants'
offices as required by the Engineer

Item

The Contractor shall arrange for the provision of


uninterrupted water supply to the Consultants' offices as
required by the Engineer

Item

Rate

Amount

Equipment
A

Provide instruments and protective clothing as required


by the Engineer and the Employer and his representatives
Utility connections

Contractor's facilities
Buildings including offices, compounds, stores, mess rooms
D

Establishment

Item

Maintenance

Item

Removal and making good the Site

Item

Sign Board
The Contractor shall provide sign board all in accordance with
drawings and Municipality requirement and to Engineer's
approval
G

Erect project sign board

Item

Maintain project sign board

Item

Allow for handing over to Main Contractor in good condition

Item

Temporary Fencing
The Contractor shall provide fencing all in accordance with
drawings and Municipality requirement and to Engineer's
approval
J

Erect fencing and security gates

Item

Obtaining authority permit for whole of the fence

Item

Maintain fencing ( all four sides)

Item

Allow for handing over to Main Contractor in good condition

Item

To Collection QR

November 2016

BQ/P/4

Residential Building, Marina -Res 012


Enabling Works Package

PRELIMINARIES & GENERAL REQUIREMENTS


Description

Qty

Unit

Item

Item

Rate

Amount

Lighting and power for the works


A

The Contractor shall supply lighting and power for the


works
Water for the works

The Contractor shall supply clean water for the works


Temporary Works
Traffic diversions

Provide all temporary works, traffic control signals, signs,


marking and lighting required throughout the Site

Item

Co-ordination with service authorities

Item

Item

Item

Item

Item

Item

Item

Sundry Items
Testing of materials
E

Provide all testing, and assistance as specified in the


Contract
Testing of the works

Provide for testing all in accordance with local regulations


and as per the Contract
Protecting the works from inclement weather

Allow for protecting the works from inclement weather


Drawings

Allow for providing shop drawings & As-built drawings


Guarantees and warranties

The Contractor shall provide all guarantees and warranties


and hand over to the Engineer on completion
Quality Assurance and Quality Control

The Contractor shall ensure the proper adoption of QA/QC


procedures

To Collection QR

November 2016

BQ/P/5

Residential Building, Marina -Res 012


Enabling Works Package

PRELIMINARIES & GENERAL REQUIREMENTS


Description

Qty

Unit

Item

Item

Item

Item

Item

Rate

Amount

Removing rubbish, protective casings and coverings


and cleaning the works at completion
A

The Contractor shall remove rubbish at regular intervals,


provide protective casings and coverings and clean the
works at completion
Traffic regulations

The Contractor shall comply with all traffic regulations


and shall liaise with the police and other authorities with
jurisdiction over traffic movement
Maintenance of public and private roads

The Contractor shall maintain all public and private roads


Control of noise and pollution

The Contractor shall ensure that excessive noise and


pollution does not occur during the execution of the Works
Statutory obligations

The Contractor shall comply with all statutory obligations


Co-ordinations with Local Authority for payment of fees
Performance Security / Insurances

Performance security as per Clause 10.1

Item

Third party insurance

Item

Workmen compensation insurance

Item

Plant and machinery insurance

Item

Professional Indemnity insurance as specified

Item

Item

Item

Item

Conditions of Contract
K

The Contractor to list below and price for all costs associated
with compliance with the Conditions of Contract and not
covered elsewhere otherwise; FIDIC 1987 & Project
Specifications
Specifications

The Contractor to list below and price for all costs associated
with compliance with the Specifications and not covered
elsewhere otherwise; QCS 2014
Regulations
The Contractor will abide by all regulations pertaining to
building projects in Lusail as issued by Lusail Real Estate
Development Company (LREDC); A. Construction Regulations, B.
Guidelines for Contractors, Health Safety & Environmental, HSE
Manual and will liaise with the LREDC authority on all related
matters

To Collection QR

November 2016

BQ/P/6

Residential Building, Marina -Res 012


Enabling Works Package

PRELIMINARIES & GENERAL REQUIREMENTS


Description

Qty

Unit

Rate

Amount

Works by Other Contractors


A

Allow for co-coordinating with other contractors for the


execution of their works.

Item

Obtaining permits, NOCs and approval from the relevant


authorities including its fees

Item

Generally
C

The Contractor shall list and price below, the items and
quantities of addition or deduction for any Bill of Quantity
Item(s) and or any omitted items that in his opinion are
necessary for the full and satisfactory completion of the work
as described in the Specifications or shown on the Drawings
and for which either expressed or implied provision is
required and which are not covered by the items or the rates
in the Bill of Quantities. Any such items not listed below shall
be deemed to be included.
(i)

(ii)

(iii)

(iv)

(v)

To Collection QR

November 2016

BQ/P/7

Residential Building, Marina -Res 012


Enabling Works Package

PRELIMINARIES & GENERAL REQUIREMENTS


Description

Qty

Unit

Rate

Amount

COLLECTION
Page No BQ/P/1
Page No BQ/P/2
Page No BQ/P/3
Page No BQ/P/4
Page No BQ/P/5
Page No BQ/P/6
Page No BQ/P/7
PRELIMINARIES & GENERAL REQUIREMENTS

Carried To Summary QR

November 2016

BQ/P/8

Residential Building, Marina -Res 012


Enabling Works Package

EXCAVATION & EARTHWORKS


Description

Qty

Unit

Rate

Amount

EXCAVATION & EARTHWORKS


GENERAL NOTES
The following General Notes are applicable to Excavation and
Earthworks included within this Bill of Quantities. The
information provided in these notes shall be deemed to have
been incorporated into the construction methodology, and in
the construction unit rates/total rates as and where the
information may be considered applicable to the construction
work items indicated herein

Note

The unit rates and total rates for excavation are to include for
excavating in any material including solid rock and removal of
material by any means necessary (except by blasting) and in
accordance with the general specifications and local regulation

Note

For a detailed description of materials, workmanship,


construction method statements, construction works
sequencing, and special requirements for the special
Substructure Construction Works, refer to the Design
Engineers' detailed drawings, the design specifications,
geotechnical report, and other related documents

Note

Notwithstanding the measurement rules of the 'Standard


Method of Measurement of Building Works' for the State of
Qatar relating to excavation depth ranges, excavation has not
been measured in accordance with the rules included therein
but have been described and measured in depth ranges as
considered suitable for the nature of the deep excavations and
bulk excavations of this project

Note

All quantities for excavation have been measured net

Note

All quantities for excavation have been measured net with no


allowance for working space. Should working space be
required it shall be determined by the contractor and all
associated costs shall be allowed for in the unit rates/total
rates

Note

Keeping excavations free from 'General Surface Water' and


'Ground Water' (water incursion into excavations occurring at
level of water table [static or rising]) is included in Bill of
Quantities Section "DEWATERING"

Note

The unit rates and total rates for excavation are to include for
generally upholding sides of excavations. Special excavation
shoring support for excavations and associated works is
included in Bill of Quantities Section "EXCAVATION SUPPORT
AND PROTECTION

Note

To Collection QR

November 2016

BQ/1/1/1

Residential Building, Marina -Res 012


Enabling Works Package

EXCAVATION & EARTHWORKS


Description

Qty

Unit

Rate

Amount

GENERAL NOTES (Cont'd)


The unit rates and total rates for excavation are to include, as
required, for grading, levelling, ramming and compaction of
surfaces exposed by excavations for the purpose of preparing
surfaces for subsequent works

Note

The unit rates and total rates for excavation are to include for
bulking of excavated materials

Note

The unit rates and total rates for excavation are to include for
double or multiple handling, staging and phasing of
excavations, staging platforms, and the like

Note

SITE PREPARATION
The Contractor shall allow for all costs associated with the
removal and disposal off-site of surplus debris, vegetation,
abandoned utilities, disused buildings and structures, the like
(Contractor's Responsibility)
Site Clearance
A

generally; over entire site area approximately 4720m2

Item

Item

Item

45,423

m3

Protection
B

Protect existing servises, road and adjacent building


structure and make good damaged areas
TEMPORARY WORKS
Temporary Excavation Works for Bulk Excavations

temporary ramps; construction, adaptation, maintenance


and removal on completion of associated works
EXCAVATION
Excavation; in all materials including rock
Bulk excavation; level 0.00 to level -12.25; commencing at
0.00 level

generally

To Collection QR

November 2016

BQ/1/1/2

Residential Building, Marina -Res 012


Enabling Works Package

EXCAVATION & EARTHWORKS


Description

Qty

Unit

m3

75

m3

70

m3

294

m3

187

m3

34

m3

46,089

m3

Rate

Amount

Pit excavation; level -12.25 to level -12.45; commencing


at -12.25 level
A

generally
Pit excavation; level -12.25 to level -13.05; commencing
at -12.25 level

generally
Pit excavation; level -12.25 to level -13.25; commencing
at -12.25 level

generally
Pit excavation; level -12.25 to level -13.45; commencing
at -12.25 level

generally
Pit excavation; level -12.25 to level -14.30; commencing
at -12.25 level

generally
Pit excavation; level -12.25 to level -15.15; commencing
at -12.25 level

generally
DISPOSAL
Disposal of excavated material

off site

To Collection QR

November 2016

BQ/1/1/3

Residential Building, Marina -Res 012


Enabling Works Package

EXCAVATION & EARTHWORKS


Description

Qty

Unit

Rate

Amount

COLLECTION
Page No BQ/1/1/1
Page No BQ/1/1/2
Page No BQ/1/1/3
EXCAVATION & EARTHWORKS

Carried To Summary QR

November 2016

BQ/1/1/4

Residential Building, Marina -Res 012


Enabling Works Package

EXCAVATION SUPPORT & PROTECTION


Description

Qty

Unit

Rate

Amount

EXCAVATION SUPPORT & PROTECTION


GENERAL NOTES
The following General Notes are applicable to Excavation
Support and Protection included within this Bill of Quantities.
The information provided in these notes shall be deemed to
have been incorporated into the construction methodology,
and in the construction unit rates/total rates as and where the
information may be considered applicable to the construction
work items indicated herein

Note

Temporary shoring designed by the Contractor; Allow for


design, construction and completion of suitable temporary
shoring system

Note

Tenderers to note that complete shoring system shall be


Contactor's Design Liability.

Note

Rates shall include for mobilization, demobilization, all


equipment and staff, excavation and disposal, supply and
installation of reinforcement as required considering the
special conditions of site works, tie back anchors (where
required), concrete, formwork, as specified and all that is
required for the satisfactory completion and performance of
the shoring system in accordance with applicable BS codes
and local authority requirements; all to the satisfaction of the
Engineer

Note

Dimensions shown in the drawings are indicative only. Final


dimensions are depend upon the final design drawings by the
contractor

Note

Shoring system including design, obtaining NOCs and


approvals all as per Drawings and Specifications

Note

To Collection QR

November 2016

BQ/1/2/1

Residential Building, Marina -Res 012


Enabling Works Package

EXCAVATION SUPPORT & PROTECTION


Description

Qty

Unit

247

247

Rate

Amount

CONTIGIOUS PILE SHORING SYSTEM


Piling works; excavation, pile boring, in-situ concrete, high
yield bar reinforcement; including (as required by piling
method) drilling mud, temporary bracings, pile shoes, pile
splices, temporary or permanent linings, disposal of excavated
material off site
Contiguous Pile Shoring System; excavation / boring
commencing at existing reduced ground level at approximately
.-0.80 QND
A

900mm diameter
CAPPING BEAM
Capping beam; including excavation, disposal of excavated
materials, concrete, reinforcement, formwork and all
other requirements as determined by construction method
Capping beam

900 mm wide x 600 mm deep

To Collection QR

November 2016

BQ/1/2/2

Residential Building, Marina -Res 012


Enabling Works Package

EXCAVATION SUPPORT & PROTECTION


Description

Qty

Unit

Rate

Amount

COLLECTION
Page No BQ/1/2/1
Page No BQ/1/2/2
EXCAVATION SUPPORT & PROTECTION

Carried To Summary QR

November 2016

BQ/1/2/3

Residential Building, Marina -Res 012


Enabling Works Package

PILING
Description

Qty

Unit

Rate

Amount

PILING
GENERAL NOTES
The following General Notes are applicable to Piling Works
included within this Bill of Quantities. The information provided
in these notes shall be deemed to have been incorporated into
the construction methodology, and in the construction unit
rates/total rates as and where the information may be
considered applicable to the construction work items indicated
herein

Note

This section shall include all works required for completion of


the Piling Works for the project. Notwithstanding what is
included in descriptions, the unit rates/total rates shall be
deemed to include everything necessary for the works

Note

IN-SITU BORED PILES


Piling works; excavation, pile boring, disposal of excavated
material; including (as required by piling method) drilling;
temporary bracings; concrete pile head and reinforcement
projection with protective sheathing; pile casings, pile shoes,
pile splices; temporary or permanent linings; removal of all
waste materials
Trial Test Piles
A

800mm diameter

no

Working Piles
B

1000mm diameter; 40m socketed length; ref P1

30

no

800mm diameter; 36m socketed length; ref P2

20

no

800mm diameter; 30m socketed length; ref P3

80

no

800mm diameter; 26m socketed length; ref P4

85

no

1000mm diameter; 30m socketed length; ref P5

57

no

To Collection QR

November 2016

BQ/1/3/1

Residential Building, Marina -Res 012


Enabling Works Package

PILING
Description

Qty

Unit

no

Rate

Amount

Static load testing of piles; in accordance with the specified


Pile Testing procedures
Trial Test Piles
A

800mm diameter
Working Piles (1% of total piles)

800mm diameter

no

1000mm diameter

no

no

Sonic integrity testing of piles; in accordance with the


specified Pile Testing procedures
Trial Test Piles
D

800mm diameter
Working Piles

800mm diameter

185

no

1000mm diameter

87

no

no

Dynamic load testing of piles; in accordance with the specified


Pile Testing procedures
Trial Test Piles
G

800mm diameter
Working Piles (5% of total piles)

800mm diameter

no

1000mm diameter

no

no

Sonic core testing of piles; in accordance with the specified


Pile Testing procedures
Trial Test Piles
J

800mm diameter
Working Piles (5% of total piles)

800mm diameter

no

1000mm diameter

no

To Collection QR

November 2016

BQ/1/3/2

Residential Building, Marina -Res 012


Enabling Works Package

PILING
Description

Qty

Unit

Rate

Amount

Trimming pile heads to cut-off level; including trimming


concrete, reinforcement, removing temporary protection,
protection of rebar's, prepare surfaces of pile heads
and reinforced bars to receive raft slab
Working Piles
A

800mm diameter

185

no

1000mm diameter

87

no

Pile head treatment; Non-shrink grout with epoxy resin; all as


per specifications
Working Piles
C

900 mm diameter

185

no

1200 mm diameter

87

no

To Collection QR

November 2016

BQ/1/3/3

Residential Building, Marina -Res 012


Enabling Works Package

PILING
Description

Qty

Unit

Rate

Amount

COLLECTION
Page No BQ/1/3/1
Page No BQ/1/3/2
Page No BQ/1/3/3
PILING

Carried To Summary QR

November 2016

BQ/1/3/4

Residential Building, Marina -Res 012


Enabling Works Package

DEWATERING
Description

Qty

Unit

Rate

Amount

DEWATERING
GENERAL NOTES
The following General Notes are applicable to Dewatering
included within this Bill of Quantities. The information provided
in these notes shall be deemed to have been incorporated into
the construction methodology, and in the construction unit
rates/total rates as and where the information may be
considered applicable to the construction work items indicated
herein

Note

This section includes for the installation, maintenance and


completion and handover of dewatering works during this
contract to keep excavations and permanent construction works
from general surface water and ground water (percolating and
subsoil water below existing ground level). Notwithstanding
what is included in the descriptions, the unit rates/total rates
shall be deemed to include everything necessary for the works

Note

DEWATERING SYSTEMS
Surface Water
Keeping excavations free from general surface water;
including temporary drains, grading, dykes, and the like;
removal by gravity drains and pumping
A

generally

Item

Subsurface Water
Keeping excavations free from sub-surface water (percolating
water and sub-soil water); site dewatering system; including
wells, casings, suction hoses, electric submersible pumps,
electrical power, diesel consumption, perforated pipe,
excavation and earthworks, filling for trenches and boreholes;
all works to be carried out by an approved dewatring
subcontractor
B

complete dewatering system as required; design, supply &


installation of site dewatering system

Item

operation and maintenance of dewatering system for the


duration of the enabling works

Item

allow for assigning/ novation of the dewatering contractor to


the main contractor (to be appointed) or as advised by the
Engineer (The liability of the dewatering shall be with the
enabling contractor until the dewatering works are taken
over by the main contractor)

Item

Maintain dewatering system upon completion of the Enabling


Contract to commencement of Main Works Contract
(PROVISIONAL)

120

days

Generally
D

To Collection QR

November 2016

BQ/1/4/1

Residential Building, Marina -Res 012


Enabling Works Package

DEWATERING
Description

Qty

Unit

Rate

Amount

Testing and Field Verification


Pre-installation works
A

test borings

Item

field survey to identify and fix plot limits, benchmarks and


related items; by approved/licensed company

Item

Item

Monitoring performance of dewatering system


C

monitoring and reporting

To Collection QR

November 2016

BQ/1/4/2

Residential Building, Marina -Res 012


Enabling Works Package

DEWATERING
Description

Qty

Unit

Rate

Amount

COLLECTION
Page No BQ/1/4/1
Page No BQ/1/4/2
DEWATERING

Carried To Summary QR

November 2016

BQ/1/4/3

Residential Building, Marina -Res 012


Enabling Works Package

MAIN SUMMARY
BILL NO

DESCRIPTION

AMOUNT QR

MAIN SUMMARY (ALTERNATIVE)


Bill No. P
Bill No.1

PRELIMINARIES & GENERAL REQUIREMENTS


ENABLING WORKS

1.1

Excavation & Earthworks

1.2

Excavation Support & Protection

1.3

Piling

1.4

Dewatering

SUB- TOTAL
Adjustment Item (if any)
Add* / Delete*

* - Tender to Specify

TOTAL CARRIED TO FORM OF TENDER

Amount in Words : (QAR)

November 2016

BQ/MS/1

Residential Building, Marina -Res 012


Enabling Works Package

MAIN SUMMARY
MAIN SUMMARY (ALTERNATIVE)
PRELIMINARIES
ENABLING WORKS (ALTERNATIVE)

SUB- TOTAL
Adjustment Item (if any)
Add* / Delete*

* - Tender to Specify

TOTAL CARRIED TO FORM OF TENDER

Amount in Words : (QAR)

November 2016

BQ/MS/2

Residential Building, Marina -Res 012


Enabling Works Package

MAIN SUMMARY

November 2016

BQ/MS/3

Residential Building, Marina -Res 012


Enabling Works Package

DAYWORK SCHDULE

PROPOSED 3B+G+15 TYPICAL FLOORS


RESIDENTIAL BUILDING ON PLOT MARINA-RES 012, LUSAIL CITY, QATAR
DAYWORK SCHEDULE (RATE ONLY)
A

Generally
Dayworks will be administered strictly in accordance with the Conditions of Contract, Clause 52 (4).
The Contractor will be paid for dayworks carried out during the course of the Contract while other operations
are in progress at the rates set down in this Schedule. Profit and overheads are not to be included in the
actual rates but stated as percentage addition in the item provided for same at the end of the Labour,
Material and Plant Sections of this Schedule of Rates.
The basic Rates to be inserted in the Daywork Schedules shall be the Rates which the Contractor has used
in determining his Unit Rates inserted elsewhere in this tender and Contract document.
Time engaged in the actual works only will be allowed. In the event of labour or plant having to be brought to
the Site specially for the item of daywork then a reasonable allowance may be made for traveling time is to
be agreed before the Daywork item is executed.

Rates for Labour


The daywork rates quoted for labour are to be the inclusive NETT amounts payable including for use
and waste of hand tools and of all ordinary non-mechanical plant, stagings, scaffoldings, tarpaulins, use of
electric light and water for the Works, etc. and all special inducements for working in Doha. The rates
shall also be deemed to include the extra cost of public holidays other holidays with pay, medical costs,
bonus, sick leave, termination indemnity pay and the like. Unless specifically authorized in writing by the
Engineer, non-productive overtime or special rates for overtime will not be admissible. The cost of all
supervisory staff including engineers, foremen, clerks, storemen, etc., is to be included in the percentage
addition for profit and overheads.

Rates for Materials


Materials used on daywork shall be as specified for the Works. The rates are to include delivery to the Site.
Should materials be required for use on dayworks which are not included in the Schedule, the lowest
current Nett market prices shall apply, plus a reasonable allowance for collecting, loading and
off loading and transporting to the Works.

Rates for Plant Hire


Plant hire rates shall include for the cost of maintaining in proper working order, attendance in starting up
and shutting down, refueling and all fuel and power, oils grease and cleaning materials, replacement and/or
sharpening of tools, provision of tools and all other ancillary items including consumable spares. Idle
time in maintenance or traveling to the Site will not be allowed.
Drivers and attendants shall be charged for at the rates as laid down for labour.

This entire Bill is PROVISIONAL and the cost of the items will be paid to the Contractor only if expended.

November 2016

BQ/DW/1

Residential Building, Marina -Res 012


Enabling Works Package

DAYWORK SCHDULE

PROPOSED 3B+G+15 TYPICAL FLOORS


RESIDENTIAL BUILDING ON PLOT MARINA-RES 012, LUSAIL CITY, QATAR
DAYWORK SCHEDULE (RATE ONLY)
ITEM
NO.

ITEM DESCRIPTION

UNIT

RATE
(QAR)

BILL NO. 3 - DAYWORK SCHEDULE (RATE ONLY), cont'd.


LABOUR
A

Chargehand craftsman

hour

Ganger

hour

Carpenter

hour

Fitter (not on plant maintenance)

hour

Bar bender / steel fixer

hour

Mechanic & Electrician


F1

Skilled

hour

F2

Unskilled

hour

Plumber & Drainlayer

hour

Light Duty Driver / Plant Operator

hour

Heavy Duty Driver / Plant Operator

hour

Attendant

hour

Labourer

hour

Semi-skilled labourer

hour

Scaffolders

hour

Welders

hour

Additions for Profit & Overheads

November 2016

BQ/DW/2

Residential Building, Marina -Res 012


Enabling Works Package

DAYWORK SCHDULE

PROPOSED 3B+G+15 TYPICAL FLOORS


RESIDENTIAL BUILDING ON PLOT MARINA-RES 012, LUSAIL CITY, QATAR
DAYWORK SCHEDULE (RATE ONLY)
ITEM
NO.

ITEM DESCRIPTION

UNIT

RATE
(QAR)

BILL NO. 3 - DAYWORK SCHEDULE (RATE ONLY), cont'd.


MATERIALS DELIVERED TO SITE
A

Building Sand

m3

Aggregate (to pass 29 mm)

m3

Portland cement

tonne

Sulphate resisting cement

tonne

Ready mix concrete Grade 40

High yield steel reinforcement bars (all sizes)


GR460, BS 4449-97

Softwood for carpentry (any size)

m3

Shuttering

m2

8" uPVC Drainage pipe

Water

litre

Diesel

litre

m3
tonne

Addition for Profit & Overheads

November 2016

BQ/DW/3

Residential Building, Marina -Res 012


Enabling Works Package

DAYWORK SCHDULE

PROPOSED 3B+G+15 TYPICAL FLOORS


RESIDENTIAL BUILDING ON PLOT MARINA-RES 012, LUSAIL CITY, QATAR
DAYWORK SCHEDULE (RATE ONLY)
ITEM
NO.

ITEM DESCRIPTION

UNIT

RATE
(QAR)

BILL NO. 3 - DAYWORK SCHEDULE (RATE ONLY), cont'd.


PLANT ON SITE
A

Motor lorry, 5 tonne

hour

Pick-up, 2 tonne

hour

Pick up truck up to 3 T capacity

hour

Concrete mixer 10/7

hour

Dumper, 2 tons

hour

Concrete vibrator

hour

Soil compactor 2 -5 cwt.

hour

Compressor, 130-180 cu.ft/min

hour

Mobile crane, 5 T

hour

Generator, 75 KVA

hour

Small water pump

hour

Dewatering pump

day

Bulldozer upto 100 H.P.

hour

Bulldozer from 100 - 200 H.P.

hour

Crawler loader with bucket capacity less than 2 m3

hour

Crawler loader with bucket capacity 2 m3 or greater

hour

Wheeled loader with bucket capacity less than 2 m3

hour

Addition for Profit & Overheads

November 2016

BQ/DW/4

Residential Building, Marina -Res 012


Enabling Works Package

DAYWORK SCHDULE

PROPOSED 3B+G+15 TYPICAL FLOORS


RESIDENTIAL BUILDING ON PLOT MARINA-RES 012, LUSAIL CITY, QATAR
DAYWORK SCHEDULE (RATE ONLY)
ITEM
NO.

ITEM DESCRIPTION

UNIT

RATE
(QAR)

BILL NO. 3 - DAYWORK SCHEDULE (RATE ONLY), cont'd.


PLANT ON SITE, cont'd.
A

Self propelled vibrating roller 10T

hour

Self propelled vibrating trench roller 10T

hour

Wheeled offset excavator with backhoe and shovel


(JCB type)

hour

Water bowser with pump and spray bar (capacity


5000 gal)

hour

Tipper truck less than 15 T capacity

hour

Tipper truck 15 T or greater capacity

hour

Low sided truck less than 6 T capacity

hour

Low sided truck 6 T or greater capacity with lifting


arm (Hiab)

hour

Four wheel drive pick up or station wagon

hour

Concrete transit tipper truck 6 m3 capacity

hour

Mobile concrete mixer 0.5 m3

hour

Mobile concrete mixer 5 m3

hour

Four wheel driver dumper 1 m3 capacity

hour

Mobile generator and welding set 25 KVA or


larger complete with all accessories

hour

Sub-Total
Addition for Profit & Overheads

November 2016

BQ/DW/5

Residential Building, Marina -Res 012


Enabling Works Package

DAYWORK SCHDULE

PROPOSED 3B+G+15 TYPICAL FLOORS


RESIDENTIAL BUILDING ON PLOT MARINA-RES 012, LUSAIL CITY, QATAR
DAYWORK SCHEDULE (RATE ONLY)
ITEM
NO.

ITEM DESCRIPTION

UNIT

RATE
(QAR)

BILL NO. 3 - DAYWORK SCHEDULE (RATE ONLY), cont'd.


PLANT ON SITE, cont'd.
A

Lorry mounted crane up to 25 Tonne capacity

hour

Concrete pump complete (capacity 50 m3/h) *

hour

Mobile generator 250 KVA

hour

Mobile floodlight sea with generator

hour

Gas cutting set with all accessories

hour

Diesel driven 2'' vibrating poker unit

hour

Air compressor any size, together with pneumatic


breaker tools

hour

Dewatering pump with 200 m length of 150 dia. hose

hour

Piling rig for bored piles and all required equipment

week

3'' portable pump and hoses

hour

6'' portable pump and hoses

hour

Vibratory hammer/extractor hydraulic cent.


force - 16 tonne

week

Vibratory hammer/extractor hydraulic cent.


force - 59 tonne

week

Vibratory hammer/extractor hydraulic cent.


force - 200 tonne

week

* to be inserted by the Tenderer


Addition for Profit & Overheads

November 2016

BQ/DW/6

Residential Building, Marina -Res 012


Enabling Works Package