Beruflich Dokumente
Kultur Dokumente
CAPM & PMBOK are registered trademarks of the Project Management Institute, Inc.
Objectives
After completing this
lesson, you will be able
to:
Project Time Management includes processes required to manage timely completion of the project.
Project Time Management is primarily concerned with developing a realistic project schedule and controlling changes
to the schedule.
!
4
Schedule management plan defines how schedule contingencies will be reported and assessed.
Identifying
Activities
Estimating
Time and
Resources
Sequencing
Activities
Time and resources for each of the identified activities will be estimated.
Project Schedule
Project schedule assigns a duration to the project activities
and the activities are sequenced in a logical order.
!
6
Although project management plan is different from project schedule, it is more comprehensive and
contains various project related plans, like risk management plan, cost management plan, etc.
Copyright 2014, Simplilearn, All rights reserved.
Gantt Chart
Gantt chart is a type of bar chart that displays the start and end dates for project activities and the overall project
schedule. They can also show logical task relationships and indicate the task completion as percent.
Exam Tips
7
Create tasks and work with the Gantt chart. This will make answering Gantt chart based questions
easy and fun.
Copyright 2014, Simplilearn, All rights reserved.
Gantt ChartRelationships
Project activities are related to each other. The relationships among project activities can be classified as follows:
Finish to Start
Start to Start
Start
Activity A
Finish
Activity B
Start
Finish
Finish to Finish
Start to Finish
FinishtotoStart
Start
Finish
Start to Start
Start
Finish to Finish
Start
Activity A
Activity B
Finish
Finish
Start to Finish
FinishtotoStart
Start
Finish
Start to Start
Start
Finish to Finish
Start
Activity A
Activity B
Finish
Finish
Start to Finish
10
!
11
Finish to Start is the most commonly used relationship type and Start to Finish is the least used.
Copyright 2014, Simplilearn, All rights reserved.
Gantt ChartDependencies
Dependency suggests that the project activities are interdependent. Dependencies can be classified as follows:
Classification 1
Mandatory
Dependencies
These dependencies are inherent in the nature of the work and these cannot be passed by.
Example: The foundation of a civil structure must be laid before working on pillars and slabs.
Discretionary
Dependencies
These dependencies are based on the preference of the team and can be changed if required.
Example: Painting activities can be started only after all the electrical and plumbing is done.
Classification 2
12
External
Dependencies
These dependencies involve external entity that may impact the project.
Example: Approval by a government authority for the structural design of a building.
Internal
Dependencies
Network Diagram
Network diagram is used to plot the activity dependencies. Project activities are represented in the form of a network.
Network diagrams can be drawn in one of the following two ways:
13
Network DiagramExample
Given below is an Activity on Node network diagram:
Start
!
14
Finish
Hammock activities are used to show a comprehensive summary activity, which can be used for control and
reporting purposes.
Copyright 2014, Simplilearn, All rights reserved.
Key Terms
Given below are the key terms used in Project Time Management:
Leads and Lags
A successor activity is said to have a lead, when it can start before the predecessor.
Example: Activity B can start 2 days before the finish of activity A.
A successor activity is said to have a lag, when it needs to be delayed with respect to the predecessor.
Example: Activity B can start 2 days AFTER the finish of activity A.
Rolling Wave Planning
Rolling wave planning is an iterative planning technique in which the work to be accomplished in the near term
is planned in detail, while the work in the future is planned at a higher level. It is a form of progressive
elaboration.
Analogous Estimating
This estimating is based on previous projects (or activities) data. E.g., if the last 5 similar projects took 6 months,
this one will also take 6 months.
15
This uses a mathematical model to calculate projected times for an activity based on historical records from the
previous projects and other information.
Effort
Effort is the total amount of work required to complete the activity.
Duration
Duration is the calendar (elapsed) time required to complete an activity.
Example: An activity requires 10 people to work for 5 days; total effort is 50 person days, and duration is 5 days.
16
17
Project charter
Schedule management
plan
Organizational process
assets
Legend
Input
Output
Expert judgment
Meetings
Analytical techniques
18
Define Activities
Define Activities is the process of identifying the specific actions to be performed to produce the project deliverables.
[2] It belongs to the Planning Process Group.
Define Activities
Activity list
Milestone list
Activity attributes
Legend
Input
Output
Tools & Techniques
Planning Process
19
Decomposition
Expert Judgement
Sequence Activities
Sequence Activities is the process of identifying and documenting relationships among the project activities. [3] It
belongs to the Planning Process Group.
Activity list
Activity attributes
Milestone list
Schedule management
plan
Organizational process
assets
Project documents
updates
Sequence Activities
Enterprise environmental
factors
Project schedule network
diagrams
Legend
Input
Output
Tools & Techniques
Planning Process
20
Precedence diagramming
method (PDM)
Dependency
determination
Risk register
Activity cost estimates
Activity list
Resource calendars
Activity resource
requirements
Activity attributes
Enterprise environmental
factors
Organizational process
assets
Activity resource
requirements
Resource breakdown
structure
Legend
Input
Output
Tools & Techniques
Planning Process
21
Expert judgment
Alternatives analysis
Bottom-up estimating
Project documents
updates
Published estimating
data
Project management
software
Copyright 2014, Simplilearn, All rights reserved.
Resource calendars
Risk register
Project scope statement
Activity list
Activity attributes
Resource breakdown
structure
Activity resource
requirements
Organizational process
assets
Legend
Input
Output
Tools & Techniques
Planning Process
22
Project documents
updates
Enterprise environmental
factors
Activity duration
estimates
Expert judgment
Analogous estimating
Three-point estimating
Reserve analysis
Parametric estimating
Copyright 2014, Simplilearn, All rights reserved.
23
Jan, the EVP of the manufacturing division, has commissioned Jack to lead a project initiative in her
area of responsibility because of his attention to detail. Jack is working with his team to estimate
activity durations so they can map out the schedule for the project. After a successful decomposition
process of the scope statement of work, Jack is confident in his teams ability to capture the true work
effort that needs to be estimated and scheduled. In reviewing the activities to be estimated, Jack
realizes a large number of the activities could benefit from some historical data and the use of
mathematical parameters. This minimizes his estimating risk for 60% of the activities. For the
remaining activities, the team is able to research past practices and industry standards to come up
with a range of estimates for the durations. What approach are Jack and his team likely to take to
determine their estimates?
Business ScenarioSolution
A
Jack and team have decided to use parametric estimation technique for the large number of activities
and for the remaining activities decided to use three-point estimate, which is also known as PERT.
24
Develop Schedule
Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule
constraints to create the project schedule. [6] It belongs to the Planning Process Group.
PROJECT TIME MANAGEMENT
Risk register
Schedule management
plan
Activity list
Activity attributes
Resource calendars
Project schedule
Schedule baseline
Develop Schedule
Organizational process
assets
Enterprise environmental
factors
Activity resource
requirements
Resource breakdown
structure
Project calendars
Project documents
updates
Schedule data
Legend
Input
Output
Tools & Techniques
Planning Process
25
Schedule network
analysis
Resource optimization
techniques
Modeling techniques
Schedule compression
Scheduling tool
Copyright 2014, Simplilearn, All rights reserved.
Critical Path
Method
Critical Chain
Method
What-If
Scenario Analysis
Resource Optimization They arrive at the optimal utilization of the resources used on a project.
Techniques
26
Pessimistic (P) estimate refers to the duration an activity would take in the worst case scenario.
Most likely (M) estimate refers to the duration an activity would take in a realistic scenario.
Optimistic (O) estimate represents the duration an activity would take in the best case scenario.
() = (P+4M+O)/6
() = (P-O)/6
^2
PERTExample
The values of expected deviation and standard deviation can be applied to derive useful information about the likely
range for values.
!
28
PERT allows to plan based on the intended level of confidence in the outcome and determine buffers
accordingly.
Copyright 2014, Simplilearn, All rights reserved.
Float, also called slack is calculated in a network diagram. The three types of float are as follows:
29
The slack of activities on the critical path is zero (0) as the activities on critical path cannot be delayed.
Copyright 2014, Simplilearn, All rights reserved.
Calculation of Float
Steps to calculate float are as follows:
Before the start of exam, please make a note of the total float formula.
Exam Tips
30
ES
EF
each activity is known as early start (ES) and the end time is
known as early finish (EF).
Forward
Pass
Float
Backward
Pass
LS
LF
The end date is called the late finish (LF) and start date is
Total Float = Late Start Early Start or Late Finish Early Finish
31
Critical PathExample
Given below is the calculation of a critical path:
3
Start
6
Activity 2
Float = 0
14
Activity 4
Float = 0
14
Activity 1
Float = 0
32
14
18
Activity 5
Float = 0
14
7
Activity 3
Float = 7
Activity
Duration
Activity 1
Activity 2
Activity 3
Activity 4
Start, 1, 2, 4, 5, End
18
Activity 5
Start, 1, 3, 5, End
11
10
Paths
18
End
14
Duration
Schedule Compression
Schedule compression is done to see if the desired completion date can be met and what will have to change to meet
that date. The two techniques of schedule compression are as follows:
Fast Tracking
Crashing
33
Linear Activities
B
Parallel Activities
B
A
34
Crashing
Increasing resources on critical path activities while making cost and schedule tradeoffs to
determine how to obtain the greatest amount of schedule compression for the least
incremental cost while maintaining project scope.
35
Schedule CompressionExample
The table summarizes the project activity details. Which activity would you crash to reduce the project
time by 1 day?
Activity
A
36
Original
Duration
(in Days)
Crash
Duration
(in Days)
Time
Savings
Original
Cost in
Dollars
Crash Cost
Extra Cost
Crash Cost
per Day
10
10,000
12,000
2,000
1,000
14
10
14,000
24,000
10,000
2,500
15,000
17,000
2,000
2,000
12,000
18,000
6,000
3,000
Adds risks
Increases management time for the project manager
Crash
Adds costs
Increases management time for the project manager
Reduce scope
Fast track
Cut quality
Resource reallocation
37
What-If Scenario
Analysis
In this method, the following questions are asked to produce a realistic schedule:
What if a particular scenario changed on the project?
Would that produce a shorter schedule?
Monte Carlo
Analysis
Resource
Optimization
Technique
Critical Chain
Method
38
Control Schedule
Control schedule is the process of monitoring the status of the project to update project progress and manage changes
to the schedule baseline. [8] It is part of the monitoring and controlling process group.
Work performance
information
Schedule data
Project calendar
Schedule forecasts
Organizational process
assets updates
Control Schedule
Change requests
Organizational process
assets
Legend
Input
Output
Tools & Techniques
Monitoring & Controlling
39
Performance reviews
Resource optimization
techniques
Modeling techniques
Scheduling tool
Schedule compression
Project management
software
Copyright 2014, Simplilearn, All rights reserved.
40
In one of Janices project team meetings, her team is reporting the status of their assigned activities
defined on the project schedule. About halfway through the process, a problem with the schedule
starts to unveil itself, as several activities are behind schedule. After all activities for this phase of the
project are reported, the overall schedule is determined to be progressing at about a 75% productivity
rate. Janice has to figure out how she can get the schedule back on track. How can Janice go about
solving this schedule problem?
Business ScenarioSolution
41
To aid in the decision making process, Janice needs to schedule a follow-up meeting with her team to
evaluate the impact of this delay to the triple constraint. The delivery of the scope, budget, along with
the quality expectations, resource availability and limitations and risk factors have to be evaluated, so
that she can present a strategy for correcting the projects schedule delay to the Project Sponsor. Due
to the teams assessment, Janice can make the decision to add additional resources to the scheduled
activities on the critical path. Before crashing the critical path, the team can identify a series of
sequenced activities that could be re-arranged and completed in parallel to free up more resources that
could be re-allocated to the critical path activities. By utilizing these schedule compression techniques,
Janice will be able to decrease the lag time of her project by increasing the projects productivity rate to
95%.
Quiz
42
QUIZ
1
Your customer wants your project to be completed 10 days earlier than planned. You believe that you
can meet the target by overlapping the project activities. What is the approach that you plan to use?
a.
Concurrent Engineering
b. Crashing
43
c.
Resource Leveling
d.
Fast Tracking
QUIZ
1
Your customer wants your project to be completed 10 days earlier than planned. You believe that you
can meet the target by overlapping the project activities. What is the approach that you plan to use?
a.
Concurrent Engineering
b. Crashing
c.
Resource Leveling
d.
Fast Tracking
Answer: d.
Explanation: Overlapping of activities implies taking activities that would otherwise be executed
sequentially and executing them by introducing parallelism. This is referred to as fast tracking.
44
QUIZ
2
You are managing a project to build a multi-story complex in your city. You are waiting for the
clearance to start construction of a building. A dependency that originates outside of the project is
called _______________
a.
External Dependency
b. Mandatory Dependency
45
c.
Discretionary dependency
d.
Internal Dependency
QUIZ
2
You are managing a project to build a multi-story complex in your city. You are waiting for the
clearance to start construction of a building. A dependency that originates outside of the project is
called _______________
a.
External Dependency
b. Mandatory Dependency
c.
Discretionary dependency
d.
Internal Dependency
Answer: a.
Explanation: This is an example of an external dependency that involves relationships between the project
and non-project activities which are outside the control of a project manager.
46
QUIZ
3
Which of the following is the best action to take to complete a project one week ahead of schedule?
a.
Inform customer that critical path does not allow early completion
b. Motivate the team to work hard and check the status, next month
47
c.
Meet the team and look for options for crashing or fast tracking the critical path
d.
QUIZ
3
Which of the following is the best action to take to complete a project one week ahead of schedule?
a.
Inform customer that critical path does not allow early completion
b. Motivate the team to work hard and check the status, next month
c.
Meet the team and look for options for crashing or fast tracking the critical path
d.
Answer: c.
Explanation: You should first seek to understand what the best course of action is, before going ahead.
Also, when it comes to schedule compression, crashing and fast tracking are the two main options. The
project sponsor would approve any actions after your team develops them.
48
QUIZ
4
A project team is working on the network diagram of a project and wants to determine the float of a
project activity. Which of the following is the correct formula?
a.
49
c.
d.
QUIZ
4
A project team is working on the network diagram of a project and wants to determine the float of a
project activity. Which of the following is the correct formula?
a.
d.
Answer: b.
Explanation: Float is calculated by subtracting either the Early Finish (EF) from the Late Finish (LF), or the
Early Start (ES) from the Late Start (LS), i.e., Float for an activity = LS-ES or LF-EF.
50
The project manager, along with his team, has defined the dependencies among the activities and
estimated their durations and the resources required to work on them. He is now in the process of
creating the project schedule. All of the following tools and techniques will assist him in creating the
project schedule, except ____________
QUIZ
5
a.
Resource leveling
b. Schedule compression
51
c.
d.
Reserve analysis
The project manager, along with his team, has defined the dependencies among the activities and
estimated their durations and the resources required to work on them. He is now in the process of
creating the project schedule. All of the following tools and techniques will assist him in creating the
project schedule, except ____________
QUIZ
5
a.
Resource leveling
b. Schedule compression
c.
d.
Reserve analysis
Answer: d.
Explanation: All of the above stated options are tools and techniques for the develop schedule process
except reserve analysis, which is a tool and technique for estimate activity durations.
52
QUIZ
6
a.
Hanger
b. Hammock
53
c.
Float
d.
Milestone
QUIZ
6
a.
Hanger
b. Hammock
c.
Float
d.
Milestone
Answer: b.
Explanation: Hammock is a summary activity that represents a group of related activities.
54
Summary
Here is a quick recap of
what was covered in
this lesson:
Project time management includes the processes required to manage the timely
completion of the project
A project schedule defines the start and end dates of the project and the project
activities. These activities are assigned a duration and sequenced in a logical order
Gantt charts and network diagrams are used to identify project activities, and determine
the relationships and dependencies between them. Gantt chart displays the start and
end dates of project activities, the overall project schedule, and the logical task
Schedule network analysis technique generates project schedule based on the estimates
of time and resource requirements
55
Thank You
CAPM & PMBOK are registered trademarks of the Project Management Institute, Inc.
56
References
[1] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 145.
[2] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 149.
[3] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 153.
[4] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 160.
[5] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 172.
[6] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 172.
[7] Definitions taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body
of Knowledge, (PMBOK Guide) Fifth Edition, Project Management Institute, Inc., 2013.
[8] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 185.
57