TESTING AND
COMMISSIONING OF
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR
BANKS, EMDBS, SMDBs,
ESMDBs & VFD PANELS)
TABLE OF CONTENTS
Item Description
1.0 Scope.
2.0 References.
3.0 Access / Egress
4.0 Health &Safety Hazards
4.1 Safety Rules during Testing.
4.2 Safety Lighting.
4.3 Task Lighting
4.4 Emergency Arrangements.
4.5 Risk and Controls.
5.0 Abbreviations and Definitions.
6.0 Roles/Responsibilities/Competence.
7.0 Testing and Commissioning Procedures.
7.1 Attachment 1- Method of Commissioning:
8.0 Training.
9.0 Working Hours.
10.0Manpower Requirement and Supervision.
11.0Test Instruments Requirements.
12.0Requirements.
12.1General Requirements.
13.0Personnel Equipment.
14.0Supporting Information.
15.0Distribution
16.0Other information
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
17.0Attachments
17.1Method of Commissioning : MDBs, MCCs, EMDBs & Capacitor Banks
17.2Method of Commissioning : SMDBs, ESMDBs &DBs.
17.3Method of Commissioning: VFD Panels.
17.4Calibration Certificates.
17.5Risk Assessment.
17.6Test Reports.
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
1.0
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
SCOPE
This Procedure Covers the Testing and Commissioning of Electrical Panels in the DUCAB HV & EHV
Facility. The MDBs, EMDBs and Capacitor banks are installed at the LV rooms, while MCC Panels are at
VCV Tower roof, CCV Tower roof, EHV Test lab electrical room , Chiller plant area and mechanical plant
room. EMCCs are located at VCV Tower roof, CCV Tower roof and Administration office first Floor.
ESMDBs are installed at Factory area and VCV Tower electrical room (Ground floor). SMDBs and DBs are
installed at all areas in the project as indicated on the service drawings. This procedure will also ensure
proper workmanship and conforms to Contract documents, manufacturers instructions and standards.
2.0
REFERENCES
2.1
2.2
2.3
2.4
3.0
Approved MACAIR Shop Drawings for Power layout. (Ref: Ducab KB644/SD- 00107, 00108,
00161-00170, 00174-00176, 00187-00199, 00203, 01027,01324,01325 & 01485).
MACAIR Project Quality Plan.
MACAIR Safety Manual
Manufacturers recommendations.
ACCESS /EGRESS
The Commissioning of the System will commence only when Main Contractor clearance is given for
access to conduct the Testing and Commissioning.
4.0
4.2
Safety Lighting
Safety Lights will be used in case of power failure ensuring good illumination at the working area to
aid evacuation if necessary.
4.3
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
Task Lighting
Adequate lighting shall be provided to ensure good illumination at the working area.
4.4
Emergency Arrangements
4.4.1
General: Site Safety procedures will be followed and in case of any emergency, Safety
Officer will administer the emergency arrangements as per the system, stop work and
report to nearest Assembly Point, etc.
Safety Officer Name : Mr. Reghupathy, (Con # 0559262923)
4.4.2
Fire Precautions: No significant fire risks associated with this activity but general fire
precaution measures will be taken.
Communication: Via mobile phones issued to all engineers.
4.4.3
4.5
5.0
6.0
ROLES/RESPONSIBILTY /COMPETENCE
6.1
PM - will have the overall responsibility of the Project for execution, quality and safety, maintain
the planning and progress and coordination with Main Contractor.
6.2
PE - will be responsible for day to day activities in the Site for System Testing and Commissioning,
report preparation and demonstration of System Commissioning.
6.3
6.4
SO - will be responsible for Health and Safety aspects in the Site in line with Main Contractor
Safety requirements.
6.5
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
QA/QC - will oversee the quality requirements and quality control measures for the Project.
8.0
9.0
7.1
7.2
7.3
7.4
7.5
Calibration Certificates.
7.6
Risk Assessment.
7.7
Test Reports.
TRAINING
8.1
Engineers who will conduct the Commissioning shall have the experience in System
Commissioning.
8.2
Tool Box talks will provide general training and awareness for each activity and also undergo
further training by the Quality Assurance Department.
WORKING HOURS
Site Normal Working Hours.
10.0
11.0
11.1
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
Test Instruments
11.1.1 Megger.
11.1.2 High Pot Tester.
11.1.3 Torque wrench
11.1.4 Multimeter
11.2
Calibration
11.2.1 All Instruments used shall carry current calibration certificates. Calibration periods for all
instruments are recommended by the manufacturer and are in line with the requirements
of the Commissioning Specialist Association.
11.2.2 Certificates shall be available for presentation prior to commencement of commissioning.
12.0
REQUIREMENTS
12.1
General Requirements
Before commencing commissioning works, the following information /items will be made available.
12.1.1 System is fully installed and pre-tested.
12.1.2 All equipment are available at site.
13.0
PERSONNEL EQUIPMENT
13.1
14.0
15.0
16.0
All Commissioning Engineers and Technicians shall have the necessary Personnel Protective
Equipment such as Safety Shoes and Helmet.
SUPPORTING DOCUMENTATION
14.1
14.2
14.3
DISTRIBUTION
15.1
Main Contractor
15.2
Consultant.
15.3
15.4
OTHER INFORMATION
17.0
ATTACHMENTS
17.1
17.2
17.3
17.4
17.5
Calibration Certificates.
17.6
Risk Assessment.
17.7
Test Reports.
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
ATTACHMENT 17.1
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
ATTACHMENT 17.2
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
ATTACHMENT 17.3
10
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
ATTACHMENT 17.4
11
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
ATTACHMENT 17.5
Calibration Certificate
12
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
ATTACHMENT 17.6
Risk Assessment
13
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011
ATTACHMENT 17.7
Test Reports
14
CONTRACTOR:
MACAIR /
DOC.NO:MSREV:
DATE : 03/02/2011