PRE IMPLEMENTATION STEPS:

1) Confirm NetBackup catalog backup completed successfully 10am 11/02 Joe Guo
2) Confirm OpsCenter database backup is taken before the upgrade 10am 11/02 Joe
Guo
3) Confirm all backup server backups completed successfully 11am 11/02 Joe Guo
4) Disable OpsCenter data collection for master cxdappp23 11am 11/02 Joe Guo
6) Deactivate all backup policies 11am 11/02 Joe Guo
7) Deactivate all the SLP policies 11am 11/02 Joe Guo
IMPLEMENTATION PLAN:
1) Stop NetBackup services on 11:30am 11/02 Joe Guo
2) Upgrade Opscenter to 7.6.1.2 12pm 11/02 Joe Guo
3) Upgrade NetBackup master to 7.6.1.2 1pm 11/02 Joe Guo
4) Upgrade media servers kurarcp3 and lyrarcp1 to 7.6.1.2 3pm 11/02 Joe Guo
5) Upgrade Netbackup appliances to 7.6.1.2(2.6.1.2) 10am 12/02 Joe Guo
6) Start up all NetBackup services 4pm 12/02 Joe Guo
POST IMPLEMENTATION TEST STEPS:
Technical Verification by Fujitsu (TVT)
1) Activate NetBackup policies 4pm 12/02 Joe Guo
2) Activate NetBackup SLP policies 4pm 12/02 Joe Guo
3) Enable OpsCenter data collection for master cxdappp23 4pm 12/02 Joe Guo
4) Kick off another catalog backup 5pm 12/02 Joe Guo
Post Verification Test ( PVT, by customer)
1) Confirm OpsCenter GUI can be brought up 4pm 11/02 Joe Guo
2) Test backup from each site 11/02 - 12/02

PRE IMPLEMENTATION STEPS: (show dates, timelines and owner for each task)
1) Prepare Netbackup 7.6.1.2 install Set on PRDUTIL5 ( Netbackup UNIX Master Ser
ver ) 08/02/2016 Joe Guo from backup team
2) Power on DR master DRPRDUTIL5, 8/02/2016 Unix team
IMPLEMENTATION PLAN: (show dates, timelines and owner for each task)
1) Upgrade Netbackup DR Master Server DRPRDUTIL5 to patch 7.6.1.2 - 08/02/2016 J
oe Guo from backup team
2) Upgrade Master Servers PRDUTIL5 to patch 7.6.1.2 - 09/2/2016 Joe Guo from bac
kup team
3) Upgrade Netbackup Media server PRDUTIL3, PRDUTIL4 to Patch 7.6.1.2 - 09/2 - 1
0/2 Joe Guo from backup team
POST IMPLEMENTATION TEST STEPS: (show dates, timelines and owner for each task)
Technical Verification by Fujitsu (TVT): (show dates, timelines and owner for ea
ch task)
1)Check install Logs for any errors. 08/2/2016 - 10/2/2016 Joe Guo from backup t
eam
2)Shutdown DR master DRPRDUTIL5, 10/02/2016 Unix team
Post Verification Test ( PVT, by customer): (show dates, timelines and owner for
each task)
1)Check backup Status of upgraded servers next days to confirm backups are runni
ng fine. 08/2/2016 - 11/2/2016 Joe Guo from backup team