Beruflich Dokumente
Kultur Dokumente
IDBC-RH-KPCRR-C00001
Danan W/Dudi G.
Donal S.
Christiawan
DNW/DG
DS
CHR
DNW/DG
MR
CHR
DG
MR
CHR
DG
MR
CHR
Rev. date
Description
Prepared by
Checked by
Approved by
Rev.
Contract No:
C-3208020
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 2 of 18
Section
Description
All
All
Sect-1
Sect-4
C
Sect-5
D
0
Sect-9
Sect-6
Secr-7
Sect-8
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 3 of 18
Table of Contents
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
INTRODUCTION .....
1.1. General..............
1.2. Plan Summary.................
1.3. Reference...............
1.4. Definition...............
1.5. Abbreviations...............
SCOPE ..
PROJECT OVERVIEW ..
3.1. EPC5 and Components.................
3.2. Work Scope for EPC5................
OBJECTIVES AND STRATEGIES ..
4.1. Objectives....................
4.2. Strategies.................
4.4. Unique Project Challenges....................
PROJECT CONSTRUCTABILITY MILESTONES ...............
RESPONSIBILITIES ...
CONSTRUCTABILITY PLAN PROCEDURES..........
7.1. Plan Updates...................
7.2. Constructability Review..................
7.3. Team Composition & Organization..................
7.4. Basis Review...................
7.5. Issues Resolution Procedure................
7.6. Constructability Status Reporting .....
HUMAN FACTORS IN PROJECT ..
8.1. General.....................
8.2. Objective...................
8.3. Strategies.....................
LESSONS LEARNED & FEEDBACK ....
ATTACHMENT
ATTACHMENT 1 : CONSTRUCTABILITY CHECK LIST
ATTACHMENT 2 : TYPICAL REVIEW OF COORDINATING DOCUMENTS
ATTACHMENT 3 : CONSTRUCTABILITY ACTION ITEM LIST FORM
IDBC-RH-KPCRR-C000001-Rev 0
4
4
4
4
5
5
6
7
7
7
8
8
8
9
10
11
13
13
13
13
14
14
15
16
16
16
16
18
18
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 4 of 18
1. INTRODUCTION
1.1. General
This plan focus on the optimum use of construction knowledge and experience in
planning, design, procurement and field operations to achieve the overall project
objectives. The basis of constructability study is that experienced construction personnel
need to be involved with the project from the earliest stages to ensure that the
construction focus and their experience can properly influence MCL, planners, and
designers, as well as material suppliers. Additionally, it is intended to foster continuous
inter-group communication and cross training as well as providing a structured
mechanism to incorporate Constructability Lessons Learned from previous projects into
design of this project.
1.2. Plan Summary
Constructability Plan is prepared as a basis for developing Constructability program and
describes process implementation of program during execution of the project. This plan
will guide the team to define the constructability Action Item List for majority work to
ensure the work is capable to construct. A Constructability Action Item List is used to
capture, assign and steward high impact and/or urgent Constructability issue to closure.
The Action Item List was developed from earlier stages of EPC5 project and it will be
maintained with high visibility within the project, include assigned responsibilities and due
dates, and be monitored with status reported in the monthly Project Plan Report.
The Constructability Action Item List shall be then used in a series of meetings or
interviews with key discipline leads, as well as COMPANY personnel. This approach
helps to foster continual intergroup and inter-function communication. Additionally, this
approach provides a structured mechanism to incorporate constructability lessons
learned from previous projects.
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 5 of 18
1.4. Definition
Constructability
Constructability Program
Constructability Plan
Constructability action item list is used to manage findings that warrant focused
attention.
1.5. Abbreviation
Term
CFF
EPC1
EPC5
FEED
PPE
Definition
Central Field Facilities
Production Processing Facilities EPC Work Scope
Infrastructure Facilities EPC Work Scope
Front End Engineering and Design
Personal Protective Equipment
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 6 of 18
2. SCOPE
In order to provide a structured process for incorporating construction knowledge in the
project that will enhance project safety, quality, cost, and risk management objectives, an
Action Item List approach will be used.
In this approach, a comprehensive Checklist List will be maintained based on eight key
areas of construction execution, which are:
Schedule
Modularization
Specification
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 7 of 18
3. PROJECT OVERVIEW
3.1. EPC5 and Components
The Banyu Urip Project EPC5 is the Infrastructure Facilities (IF) contract package in the
Cepu area, the Project located in East Java, Indonesia.
EPC5 Infrastructure Facilities will include offices, warehouse, maintenance shop, living
quarters, clinic and other support facilities, as well as river water intake, fly-over, pipeline
and water storage basin.
3.2. Work Scope for EPC5
Emergency helipad
Fire fighting system (F&G detection, deluge, foam, fire distribution, fixed monitor,
portable equipment, etc)
CATV and cabling for telecommunications, security system, paging system, etc
Fly-Over
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 8 of 18
Enhance quality
4.2. Strategies
The following strategies will be adopted:
The Constructability Road Map and Action Item List will be used to guide
constructability effort
Optimize the use of standard elements, modules and preassembly, and lift
equipment
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 9 of 18
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 10 of 18
Milestone
Date
Status
Approval
Open
Approval
Open
Approval
Open
Achievement
Sept 4, 2012
Open
Achievement
Open
Deliverable
Open
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 11 of 18
6. RESPONSIBILITIES
RH will appoint an experienced Construction Coordinator to lead and coordinate all the
constructability activities throughout all phases of the Work. The Construction
Coordinator will provide construction knowledge, experience and engineering input
throughout all phase of work.
Constructability and Human Factor in Design and Construction Coordinator requirement
is below:
a) Overall experience of 15-20 years.
b) Engineering design background with 3-5 years in human factors/ergonomics
and/risk management.
c) HAZOP and /or human factors planning and facilitation experience.
d) Knowledge of construction safety policies, processes and work practice for
major project construction.
The responsibilities of the Construction Coordinator shall include, but are not limited to:
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 12 of 18
Ensure the appropriate lessons learned from previous projects are taken into
consideration.
Ensure the activities are carried out in compliance with local laws and
regulations.
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 13 of 18
Chair or nominate a deputy for each Constructability Review and ensure that
persons with the correct expertise participate.
Ensure that actions resulting from the Constructability Reviews are assigned to
relevant disciplines/ personnel. Construction Coordinator shall be responsible for
ensuring that assigned actions are adequately addressed and closed-out.
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 14 of 18
Project Manager
CHRISTIAWAN
Constructability
Coordinator
HERU AGUSTINO
HSE
Manager
ANDRI B
Engineering
Manager
YENNY K
Project Control
Manager
SUDARNO
HSE
Engineer
TEGUH
Lead Discipline
Engineers
ALL LEADS
Project Control
Engineer
AGUNG A
Construction
Manager
DUDI G
Construction
Engineers
DANAN W
Procurement
Manager
HERRY P
Procurement
Engineers
WENDI S
General
Superintendents
BUDIONO/SAPTONO
Constructability
Team
Superintendents
ALL SI
System Completion
Manager
TRIHANGGARA
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 15 of 18
is prepared.
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 16 of 18
Minimize the number and severity of injures, illness and loss incidents
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 17 of 18
Stairs, ramps, ladders (Stairways, ladders and ramps are means of moving safely
from one elevation to another), the stairways upward angle is between 30 and 40
degrees, ramp angle between 7 and 15 degrees, ladders angle between 75 and
85 degrees.
Handrail
- Hand rails must be provided for stairways with more than three steps
- A single tier handrail is installed on the wall side of the stairs and a double tier
on the top area
c) Working environment
Lighting
Thermal environment
Ventilation
Weather protection
d) Equipment
Consider all factors to enhancing the operability and maintainability of equipment
include: moving to and work space, display and control, manual handling, status
identification, communication and environmental condition.
e) Emergency Response
Develop emergency plan to manage and counter the risks and take action to build the
necessary capabilities needed to implement such plans. Common preparedness
measures include:
IDBC-RH-KPCRR-C000001-Rev 0
BANYU URIP
PROJECT
EPC5
Alarm system
Evacuation routes
MPI: Unclassified
IDBC-RH-KPCRR-C00001
Aug. 13, 2012
Rev. 0
Page 18 of 18
10. ATTACHMENT
Attachment 1 - CONSTRUCTABILITY CHECK LIST
Attachment 2 - TYPICAL REVIEW OF COORDINATING DOCUMENTS
Attachment 3 CONSTRUCTABILITY ACTION ITEM LIST FORM
IDBC-RH-KPCRR-C000001-Rev 0
ATTACHMENT-1
CONSTRUCTABILITY CHECKLIST
Page 1 of 5
SCHEDULE
1)
2)
3)
4)
Does schedule account for recruitment and training for local work force?
5)
6)
Does the overlap between commissioning and start-up allow for the
minimization of hot work? (e.g. does the schedule identify and minimize time
period when construction must work in an area with live lines, or
commissioned hydrocarbon lines, or hot electrical lines?)
7)
8)
Has the critical path analysis been done on the schedule? What are the
critical activities? What is planned to manage them?
B.
DESIGN
1)
Are any large items of equipment requiring special attention being designed
for transport and lift?
2)
What is design strategy to minimize the level of risk during construction and
commissioning?
3)
Review drawings for Temporary Facilities, Lay down areas and fabrication.
IDBC-RH-KPCRR-C000001-Rev D
Page 2 of 5
4)
5)
C.
2)
Security consideration
3)
Are there adequate areas for lifting operations for big vessel, column,
incinerator?
4)
D.
Are roads wide enough and bridges suitable for cranes to get in and out?
Is there any contaminated land on the new work site? If so have the
problems associated with this been quantified?
IDBC-RH-KPCRR-C000001-Rev D
Page 3 of 5
2)
Will construction involve workers coming into contact with lead, asbestos,
PCBs or radioactive substances or entering areas potentially contaminated
with unexploded ordnance?
3)
What is the plan for disposal of construction and start-up wastes? Are any
considered hazardous?
4)
Are there climatic problems due to heat, humidity, wind, flooding, sand,
erosion or darkness?
E.
5)
How will liquid and solid waste be disposed of during the construction?
6)
7)
8)
9)
10)
SPECIFICATIONS
1)
Are
material
procurement
specifications
consistent
with
construction
drawings?
F.
2)
3)
Will parts of systems be turned over to operations early? Will design take
turnover plan into account? For tie ins to existing facilities does design
address tie in strategy and operations shutdown philosophy?
2)
IDBC-RH-KPCRR-C000001-Rev D
Page 4 of 5
3)
4)
Are there any large, heavy, special or complex items of equipment requiring
special attention?
5)
Is there a strategy for unit(s) becoming operational whilst other units are
being constructed?
6)
Will the installation of some equipment need to be delayed until after major
lifting operations are complete?
G.
7)
8)
Are there any existing buildings/ structures on the work site where the new
facility is to be built?
2)
3)
Are there any special requirements for construction on the work site?
4)
5)
6)
7)
8)
9)
10)
IDBC-RH-KPCRR-C000001-Rev D
Page 5 of 5
H.
2)
Managing cultural differences among the MCL, RH, Government and joint
operations will prove to be challenging.
3)
4)
5)
IDBC-RH-KPCRR-C000001-Rev D
ATTACHMENT-2
TYPICAL REVIEW OF COORDINATOIN DOCUMENTS
Page 1 of 7
Proposed Checks
Documents to be
Reviewed
1
Plot Plan
Excavation
1.1
IF layout
1.2
1.3
Alternative recommendations
1.4
1.5
1.6
Future maintenance
1.7
1.8
Laydown areas
1.9
Rigging access
2.1
Access
2.2
2.3
2.4
2.5
Disposal
2.6
IDBC-RH-KPCRR-C000001-Rev D
2.7
Excavation levels
2.8
Muck-out routes
Page 2 of 7
2.9
Backfill access
Underground drawings
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
Civil/Structural/Building/
5.1
Building Services
5.2
5.3
IDBC-RH-KPCRR-C000001-Rev D
Page 3 of 7
5.4
5.5
5.6
5.7
5.8
5.9
5.10 Ensure duct banks are not too deep (max +/-0.75
m depth)
5.11 Ensure building internal finish is to meet
specification
5.12 Ensure HVAC is not clashing with other utility
5.13 Check interfaces of services: electrical and
instrument equipment and cable entries/
penetrations
5.14 Service ducts in buildings adequate for
installation
5.15 Pouring concrete in high temperature need to
add temperature-lowering additive to reach
optimum cement hydration process
5.16 Large concrete pours in preference to multiple
small pour Permanent access to reduce
scaffolding
5.17 HVAC specification for materials and testing
5.18 HVAC plant room layout
IDBC-RH-KPCRR-C000001-Rev D
Page 4 of 7
Piping
6.1
6.2
6.3
6.4
6.5
Clashes check
6.6
6.7
6.8
6.9
Page 5 of 7
Electrical
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
Page 6 of 7
and method
7.13 Check that schedule for lighting design is early
enough to allow use during construction and for
the dressing out of vessels on the ground
7.14 Size cable trays for additions due to design
development during construction
Instruments
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
Page 7 of 7
9.1
9.2
9.3
9.4
9.5
9.6
9.7
9.8
9.9
IDBC-RH-KPCRR-C000001-Rev D
ATTACHMENT-3
CONSTRUCTABILITY ACTION ITEM LIST FORM
No.
ITEM DESCRIPTION
SAVING OR POTENCIAL
AVOIDED COST
STATUS KEY:
A
N/A
C
R
: Accepted
; Not aplicable in this project
: Under Consideration
: Rejected
SCHEDULE
IMPACT +/-
DATE
BENEFITS
FOLLOW
UP
COMPLETION RESPONSIBLE
DATE
PERSONS