Beruflich Dokumente
Kultur Dokumente
Pre-tensioning process
Unlike those of post-tensioned concrete, the tendons of pretensioned concrete elements generally form straight lines
between end-anchorages. Where "profiled" or "harped"
tendons are required, one or more intermediate deviators are
located between the ends of the tendon to hold the tendon to the
desired non-linear alignment during tensioning. Such deviators
usually act against substantial forces, and hence require a robust
casting bed foundation system. Straight tendons are typically
used in "linear" precast elements such as shallow beams, hollowcore planks and slabs, whereas profiled tendons are more
commonly found in deeper precast bridge beams and girders.
Pre-tensioned concrete is most commonly used for the fabrication
of structural beams, floor slabs, hollow-core
planks, balconies, lintels, driven piles, water tanks and
concrete pipes.
Bonded post-tensioning
Unbonded slab post-tensioning. Installed strands and edgeanchors are visible, along with prefabricated coiled strands for the
next pour
Improved crack-control
In the presence of concrete cracking, bonded tendons respond
similarly to conventional reinforcement (rebar). With the
tendons fixed to the concrete at each side of the crack, greater
crack-expansion resistance is offered than with unbonded
tendons, allowing many design codes to specify reduced
reinforcement requirements for unbonded post-tensioning
proved fire performance
The absence of strain redistribution in bonded tendons may
limit the impact that any localised overheating has on the
overall structure. As a result, bonded structures may display a
higher capacity to resist fire conditions than unbonded ones.
Ability to be prefabricated
Unbonded tendons can be readily prefabricated off-site
complete with end-anchorages, facilitating faster installation
during construction. Additional lead time may need to be
allowed for this fabrication process.
Double-layer encapsulation
Prestressing tendons requiring permanent monitoring and/or
force adjustment, such as stay-cables and re-stressable dam
anchors, will typically employ double-layer corrosion
protection. Such tendons are composed of individual strands,
grease-coated and sleeved, collected into a strand-bundle and
Anchorage protection
In all post-tensioned installations, protection of the endanchorages against corrosion is essential, and critically so for
unbonded systems
The force which is used to stretch the wire to the required length
must be available all the time as prestressing force if the steel is
to be prevented from contracting. Contraction of steel wire occurs
due to several causes, effecting reduction in the prestress. This
reduction in the prestressing force is called loss in prestress. In a
prestressed concrete beam, the loss is due to the following:
a) Elastic shortening
b) Shrinkage of concrete
c) Creep of concrete
d) Frictional loss
e) Relaxation of steel
f) Anchorage take-up
a) Elastic Shortening:
When the prestress is transmitted to the concrete member, there
is contraction due to prestress. This contraction causes a loss of
steel.
at the ends
at the centre,
Average stress=
In the post tensioned beams several cables are provided. The
cables are stretched in succession. When a cable is stretched, this
cable suffers no loss, but the cable stretched before suffers a loss
Creep strain =
x Elastic strain
Elastic strain =
is the stress in concrete at the level of steel.
Loss in prestress = creep strain x
Relaxation loss (
0
0.6
35
0.7
70
0.8
90
is the characteristic strength of steel.
If
dF=
Frictional loss due to wobble effect is calculated as
dF = KFds
where K is coefficient of wave effect.
Therefore, total frictional loss = dF =
or
if F is the prestress at a distance S subtending an angle
Value of
Material in Contact
For steel and concrete
For steel and steel
For steel and lead
0.55
0.30
0.25
Loss of force = F Fx
Frictional loss can be reduced by adapting the following
measures:
1.
2.
3.
4.
5.
1.
elastic shortening
2.
shrinkage of concrete
3.
creep of concrete
4.
relaxation of steel
if jacketing stress is treated as the initial stress, effective stress is
jacketing stress minus all losses. Since in most cases frictional
loss and the anchorage take-up can be compensated by
overstressing, total loss is due to elastic shortening, shrinkage of
concrete, creep of concrete and relaxation of steel. Total losses for
pre-tensioned and post-tensioned beams are as follows:
Loss due to
Pre-tensioning
Post-tensioning
1. Elastic shortening
3
1
2. Creep of concrete
6
5
3. Shrinkage of concrete
7
6
4. Creep of steel
2
3
Total
18%
15%
Loss can be expressed as percentage or in terms of stress or in
terms of total deformation or in terms of strain.
What is prestressed concrete? How is it used?
Before getting into prestressed concrete, let us go back to the
basics first.
We all know that concrete is strong in compression and weak in
tension. This is reason for providing reinforcement (in the form of
steel bars) to resist tension/tensile force acting on
beams/columns/slabs etcetera.
RC structures under service load undergoes deflection causing the
bottom of the beam (tensile zone) to elongate, causing cracks.
Generally, steel bars are provided to limit the crack widths and
resist the tensile force which the concrete lacks.
Here, the rebar acts as passive reinforcement. Rebars (steel
reinforcement) provided at the bottom of the bar, does not carry
How it is used?
This is where prestressing comes into action. The principle behind
prestressed concrete is that compressive stresses induced by
high-strength steel tendons in a concrete member before loads
are applied will balance the tensile stresses imposed in the
member during service.
Simply, Permanent pre-compression is produced in the areas
subjected to tension using high tensile strength steel wires or
alloys. Now, a portion of tensile stress is counteracted, thereby
reducing the cross-sectional area of steel reinforcement.
As as result, the concrete does not crack because the prestressing has reduced the tensile stress in the section below
cracking stress. hence concrete is treated as a elastic material.
Now, the concrete is said to have two compressive force:
1. Internal prestressing force
2. External forces (Dead load, Live load etc.)
These two forces must counteract each other.
Then the tendon tries to shrink back to the original length, but
resisted by the bond between the concrete thereby inducing
compressive force in it.
Uses:
Longer spans
Unique designs: irregular shapes
Shorter construction cycles
Cost reduction
Shorter floor-to-floor heights
Superior structural performance
University of Luzon
Perez Blvd., Dagupan City
Submitted to:
Engr. Mandy Casaclang
Submitted by:
Babylon, Carl Cedrick
Chua, Harvin
Doctor, Justine Patrick
Manlangit, Mark Christian