Sie sind auf Seite 1von 17

IN-PROCESS INSPECTION REPORT

CENTERLINE MARKING & CHECKING

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-A


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Has the cleaning and levelling of the site been done?

Has the demarcation of the plot and marking of the


actual boundaries been done? (As per Drawing)

Are the grid pillars set out?

Has the check for right angle been done?

Are the locations of footings on the specified grid lines


as per drawing?

Has the allowance for the excavation of footing


shuttering been provided?

Has the marking of structural members been properly


supervised?

Is the reinforecement and shuttering provided as per


marking?

Has the centre line distance between columns and the


verticality been checked?

Yes

NA

Remarks

No. of column and column orientation compare with


Architectural & Structural Drawings
Manual excavation at last one foot of the footing
depth.
Pit bottom compact with the wracker
Check the bore well location while marking the footing
mat
Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Supervisor)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


CENTERLINE MARKING & CHECKING

Prepared By:
(Site Supervisor)

Format No: QA-03-A


Issue No: 01
Revision No: 00

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


FOOTING

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-B


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Are the latest "Good for construction"drawings


available with control seal

Are the required number of cement bags available on


site?

Have the Mixer machine & vibrators been checked


before start of the concrete?

Is the necessary shuttering and reinforcement


complete and in place?

Is the dimensional accuracy of shuttering material


correct? (length, Breath, Hight)

Is the test report of cement and steel available at site


office?

Has the diameter and spacing of reinforcement been


checked? (Footing Mat, Column)

Is the concrete been properly compacted with a


vibrator or manually?

*Are the markings on the column dowels done and a


line dori being used to maintain correct concrete level?

10

Check the cover block thickness as per drawing.

11

Measurement Box used for concret mix preparation

Yes

NA

Remarks

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Supervisor)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


COLUMN CONCRETING

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-C


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Are the required number of cement bags available on


site?

Have the Mixer machine & vibrators been checked


before start of the concrete?

Is the dimensional accuracy of shuttering material


correct?

Has markings been made on the column dowels for


concrete level?

Is the test report of cement and steel available at site


office?

Has the aggregate been checked?

Has the diameter and spacing of reinforcement been


checked as per Drawing?

Has the vertically of property supported column box


been checked?

Is the concrete been properly compacted with a


vibrator or manually?

10

Is the concrete been properly compacted with a


vibrator or manually?

11

Has deshuttering been done carefully without


damaging the concrete surface after 24 hours

12

Measurement Box used for concrete mix preparation

13

Is concrete pouring level mark available for all columns


as per drawing.

Yes

NA

Remarks

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Engineer)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


COLUMN CONCRETING

Prepared By:
(Site Engineer)

Format No: QA-03-C


Issue No: 01
Revision No: 00

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


PLINTH BEAM

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-D


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Is the necessary shuttering and reinforcement


completed and in place?

Has the shuttering material been properly aligned


using appropriate equipment?

Has the diameter and spacing of reinforcement been


checked?

Check Cover Block fixing is in propoer size

Yes

NA

Remarks

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Supervisor)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


ROOF
Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-E


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Are the latest Good for Construction drawings


available with control seal?

Is the area prepared for starting reinforcement


(shuttering complete, cleaned, oiled, and taped)?

Has the required barricading and safety measured


been taken?

Is the area to be reinforced compatible with the


drawings that are provided?

Are the required tools available at site to ensure


correct work?

Is the reinforcement free from mud, grease and other


forms of contamination?

Is the overlapping ensured and the laps are


staggered?

Are the dowels for column, beams and slab in place


and checked for proper length?

Are the required hooks fixing and is the chair height for
the upper layer of reinforcement correct?

10

Is the reinforcement done ae per specification and


drawing?

11

Are cover blocks provided and fixed in a systematically


correct manner and as per specifications?

12

Have beam and column joints checked for sufficient


cover blocks?

13

Has adequqte lap lengths been provided for all the


column bars?

14

Centering gaps covered with G.I Sheets.

15

Ensure all beam bottoms and all slab bottom are in


same level

16

Check with elevation darwing if any extra centering or


steel work required.

Yes

NA

Remarks

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Supervisor)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


ROOF

Prepared By:
(Site Supervisor)

Format No: QA-03-E


Issue No: 01
Revision No: 00

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


CEILING PLASTERING

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-F


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Is the concrete surface hacked?

Are button marks plased at appropriate intervals?

Is the electrical conducting works completed?

Is the kind of finishing required been achived?

Normal sponge finish?

Use measuring box for mortor mixing

Write curing date in the wall surface

Yes

NA

Remarks

check right angle (squareness) for the beam plastering

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Supervisor)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


BRICK WORK

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-G


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Are there any specific requirements of the client?

Has signature of the Client obtained

Is the brickwork checked in vertical and horizontal


directions?

Has the check for diagonals & dimensions been done


as per drawing?

Has the thickness for joints been done?

Has the brick work being erected to give specifications


to plum and in line?

Are the bricks soaked in water before laying

Check the location of door & Windows opening as per


drawing

Yes

NA

Remarks

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Engineer)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


INTERNAL PLASTERING

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-H


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Is the concrete surface beam/column hacked?

Are button marks plased at appropriate intervals?

Has the GI mesh been nailed between all RCC &


masonry members?

Are the openings of doors frames fixed at the same


level?

Is the electrical conducting works completed (pipe


laying & Box fixing?

Is the PHE piping works in toilets & kitchen


completed?

Is the height of switch boxes fixed correctly?

Use measuring box for mortor mixing

Are the windows corner are to the right angles, beam


& column?

10

Check loft bottom are at same level?

11

Cut the plaster surface properly for skirting

Yes

NA

Remarks

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Engineer)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


EXTERNAL PLASTERING

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-I


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Is the concrete surface beam/column hacked?

Are button marks plased at appropriate intervals?

Has the GI mesh been nailed between all RCC &


masonry members?

Has the scaffolding arrangement been made?

Is the plaster in proper line & verticality?

Is the wall being plastered to given specifications, to


plumb and even?

Is plastering done above & below platforms and


sunshades?

Are the switch boxes in position and properly finished?

Is the plaster surface cut properly for skirting?

10

Has the kind of finishing required been achieved?

Yes

NA

Remarks

- Normal Sponge finish


- Rough finish
- Smooth even finish
Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Engineer)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


EXTERNAL PLASTERING

Prepared By:
(Site Engineer)

Format No: QA-03-I


Issue No: 01
Revision No: 00

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


WALL TILES

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-J


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Are the joints properly aligned?

No hollow sound on the tile when tapped?

Have the edges been checked for straightness?

Are all the laid floor tiles properly covered?

Has the grouting been done?

Is the tiles surface plumb?

Have the setting of joints been done only after a


minimum of 24 hours?

check the tiles laying pattern with the client work order
if any change requested?

Check the Tiles brand & Size requested?

10

Check proper cutting of tiles at water pipe line out


lets?

Yes

NA

Remarks

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Engineer)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


FLOOR TILES

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-K


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Has slop been provided wherever required?

Has the laying procedure been followed?

Have the joints been cleaned to remove loos mortar?

Are the joints properly aligned?

No hollow sound on the tile when tapped?

Is the finished floor level?

Are all the laid floor tiles properly covered?

Has it been ensured that grouting is only done after 24


hours of laying of tiles?

Yes

NA

Remarks

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Engineer)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


GRANITE / MARBLE WORK

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-L


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Have the joints been cleaned to remove loose mortar?

Are the joints properly aligned?

Is work carried out to plump and horizontally to line?

Is the finished floor level?

Are all the laid floor tiles properly covered?

Has it been ensured that grouting is only done after


24hrs of laying of tiles?

Yes

NA

Remarks

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Supervisor)

Reviewed By:
(Project Manager)

IN-PROCESS INSPECTION REPORT


PAINTING

Project Code & Name:

Report. No / Date:

Location:

Stage of Inspection:

Site Engineer Name:

Floor No / Flat No:

Format No: QA-03-M


Issue No: 01
Revision No: 00

Project Manager Name:


S.No

Description

Is the primer application done?

Has the putty been applied after the 1st coat has
completely dried?

Have all undulation been covered using putty?

Has the dust from the surface been thoroughly wiped


off after sanding the puttied surface?

Has it been ensured that the final coat of paint is


applied and finished with roller?

Has it been ensured that the first coat is applied after


6 hours or more of first coat?

Yes

NA

Remarks

Draw / Write note on part being inspected & Mark the Actual readings

Prepared By:
(Site Engineer)

Reviewed By:
(Project Manager)

Das könnte Ihnen auch gefallen