Beruflich Dokumente
Kultur Dokumente
Chapter 2: Transformer
2.1 Rationale
Winding Construction
Moisture Removal
Process
Bushing Connections
Oil Filling
Installing Protection
System
Fig 3.1 Block Diagram
D2
4
4.44 D 2 B m f
E is proportional to D2.
Therefore, voltage per turn is increased with increase in diameter of
transformer core. Again if voltage across the winding of transformer is V. Then V =
eN, where N is the number of turns in winding.
If V is constant, e is inversely proportional to N. And hence, D 2 is inversely
proportional to N. So, diameter of the core is increased, the number of turns in the
transformer winding reduced. Reduction of number of turns, reduction in height of the
4
core legs in-spite of reduction of core legs height increased in core diameter, results
increase in overall diameter of magnetic core of transformer. This increased steel
weight ultimately leads to increased core losses in transformer. Increased diameter of
the core leads to increase in the main diameter on the winding. In spite of increased
diameter of the winding turns, reduced number of turns in the windings, leads to less
copper loss in transformer. So, we go on increasing diameter of the transformer core,
losses in the transformer core will be increased but at the same time, load loss or
copper loss in transformer is reduced. On the other hand, if diameter of the core is
decreased, the weight of the steel in the core is reduced; which leads to less core loss
of transformer, but in the same time, this leads to increase in number of turns in the
winding, means increase in copper weight, which leads to extra copper loss in
transformer. So, diameter of the core must be optimized during designing of
transformer core, considering both the aspects.
The maximum flux density of CRGO steel is about 1.9 Tesla. Means the steel
becomes saturated at the flux density 1.9 Tesla. One important criteria for the design
of transformer core, is that, it must not be saturated during the transformers normal
operation mode. Voltages of transformer depend upon its total magnetizing flux. Total
magnetizing flux through core is nothing but the product of flux density and cross
sectional area of the core. Hence, flux density of a core can be controlled by adjusting
the cross sectional area of the core during its design.
assembly of these blocks in such a successive manner as per their size from core
central line, that it gives an optimum circular shape of the cross-section. Such typical
cross-section is shown in the figure below. Oil ducts are needed for cooling the core.
Cooling ducts are necessary because hot-spot temperature may rise dangerously high
and their number depends on the core diameter and materials that get used for core. In
addition to that, clamp plates made of steel are needed on either sides of the core to
clamp the lamination. The steel sheet lamination blocks, oil ducts, and clamping
plates; all should lie within the peripheral of optimum core circle.
The net sectional area is calculated from the dimensions of various packets and
allowance is made for the space lost between lamination (known as stacking factor)
for which steel sheet of 0.28 mm thickness with insulation coating is approximately
0.96. Area is also deducted for oil ducts. The ratio of net cross sectional area of core
to the gross cross - sectional area inside the imaginary peripheral circle is known as
Utilization factor of transformer core. Increasing numbers of steps improve the
Utilization factor but at the same time, it increases manufacturing cost. Optimum
numbers of steps are between 6 (for smaller diameter) to 15 (larger diameter).
During core manufacturing in factory some factors are taken into consideration,
1.
2.
Higher reliability.
3.
4.
in the winding itself. The stranded conductor is also more flexible than a solid conductor of
similar size, aiding manufacture.
The windings of signal transformers minimize leakage inductance and stray
capacitance to improve high-frequency response. Coils are split into sections, and those
sections interleaved between the sections of the other winding.
Power-frequency transformers may have taps at intermediate points on the winding,
usually on the higher voltage winding side, for voltage adjustment. Taps may be manually
reconnected, or a manual or automatic switch may be provided for changing taps. Automatic
on-load tap changers are used in electric power transmission or distribution, on equipment
such as arc furnace transformers, or for automatic voltage regulators for sensitive loads.
Audio-frequency transformers, used for the distribution of audio to public address
loudspeakers, have taps to allow adjustment of impedance to each speaker. A center-tapped
transformer is often used in the output stage of an audio power amplifier in a push-pull
circuit. Modulation transformers in AM transmitters are very similar.
Dry-type transformer winding insulation systems can be either of standard openwound 'dip-and-bake' construction or of higher quality designs that include vacuum pressure
impregnation (VPI), vacuum pressure encapsulation (VPE), and cast coil encapsulation
processes.
.
Fig6.1 Core View
10
Insulation of cotton is wrapped on the limbs of core and then firstly lv and
then hv winding is overlapped together. After that assembly the core frame is
fixed.
The core assembly is then kept under oven at 90C for moisture removal for 23hrs.
11
After moisture removal, the core and coil assembly is put into the tank by
crane.
After the whole process oil is filled in the tank after connecting the bushing
connections and placed the lid of the tank.
12
After painting has been completed the protection box is attached to the
transformer.
Type tests
2.
Routine tests
3.
Special tests
Pre-commissioning tests
2.
3.
Emergency tests
2.
3.
4.
5.
6.
7.
8.
9.
2.
3.
4.
5.
6.
7.
8.
9.
Oil pressure test on transformer to check against leakages past joints and gaskets.
That means Routine tests of transformer include all the type tests except temperature rise and
vacuum tests. The oil pressure test on transformer to check against leakages past joints and
gaskets is included.
Dielectric tests.
2.
3.
Short-circuit test.
4.
5.
6.
7.
Transformer winding resistance measurement is carried out to calculate the I2R losses and to
calculate winding temperature at the end of a temperature rise test. It is carried out as a type
15
test as well as routine test. It is also done at site to ensure healthiness of a transformer that is
to check loose connections, broken strands of conductor, high contact resistance in tap
changers, high voltage leads and bushings etc.
There are different methods for measuring of transformer winding, likewise
this method of measurement of winding resistance, the test current is injected to the winding
and corresponding voltage drop across the winding is measured.
By applying simple Ohm's law i.e. Rx = V I, one can easily determine the value of
resistance.
Procedure of Current Voltage Method of Measurement of Winding Resistance:
1.
2.
3.
4.
Voltmeter leads shall be independent of the current leads to protect it from high
voltages which may occur during switching on and off the current circuit.
5.
The readings shall be taken after the current and voltage have reached steady state
values. In some cases this may take several minutes depending upon the winding
impedance.
6.
The test current shall not exceed 15% of the rated current of the winding. Large
values may cause inaccuracy by heating the winding and thereby changing its resistance.
7.
For expressing resistance, the corresponding temperature of the winding at the time of
measurement must be mentioned along with resistance value. As we said earlier that
after remaining in switch off condition for 3 to 4 hours, the winding temperature would
16
become equal to oil temperature. The oil temperature at the time of testing is taken as the
average of top oil and bottom oil temperatures of transformer.
1.
For star connected three phase winding, the resistance per phase would be half of
measured resistance between two line terminals of the transformer.
2.
For delta connected three phase winding, the resistance per phase would be 0.67 times
of measured resistance between two line terminals of the transformer.
3.
17
18
milli-ohms range) can be accurately measured by Kelvin bridge method whereas for higher
All other steps to be taken during transformer winding resistance measurement in these
methods are similar to that of current voltage method of measurement of winding resistance
of transformer, except the measuring technique of resistance.
19
20
2.
3.
Then apply single phase 230 V AC supply across one of the HV winding
terminals and neutral terminal.
4.
5.
In case of auto transformer, magnetic balance test of transformer should be repeated for LV
winding also.
There are three limbs side by side in a core of transformer. One phase winding is wound in
one limb. The voltage induced in different phases depends upon the respective position of the
limb in the core. The voltage induced in different phases of transformer in respect to neutral
terminals given in the table below.
Left
Side Central
Phase
Phase
Right
Side
Phase
AN
BN
CN
230V
180V
50V
115V
230V
115V
50V
180V
230V
In three phase transformer, it is essential to carry out a vector group test of transformer.
Proper vector grouping in a transformer is an essential criteria for parallel operation of
transformers.
There are several internal connections of three phase transformer are available in
market. These several connections give various magnitudes and phase of the secondary
voltage; the magnitude can be adjusted for parallel operation by suitable choice of turn ratio,
but the phase divergence cannot be compensated. So we have to choose those transformer for
parallel operation whose phase sequence and phase divergence are same. All the transformers
with same vector ground have same phase sequence and phase divergence between primary
and secondary. So before procuring one electrical power transformer, one should ensure the
vector group of the transformer, whether it will be matched with his or her existing system or
not. The vector group test of transformer confirms his or her requirements.
The vector group of transformer is an essential property for successful parallel
operation of transformers. Hence every electrical power transformer must undergo through
vector group test of transformer at factory site for ensuring the customer specified vector
group of transformer. The phase sequence or the order in which the phases reach their
maximum positive voltages, must be identical for two paralleled transformers. Otherwise,
during the cycle, each pair of phases will be short circuited. The several secondary
connections are available in respect of various primary three phase connection in a the three
phase transformer. So for same primary applied three phase voltage there may be different
three phase secondary voltages with various magnitudes and phases for different internal
connection of the transformer. Let's have a discussion in detail by example for better
understanding.
We know that, the primary and secondary coils on any one limb have induced emfs
that are in time-phase. Let's consider two transformers of same number primary turns and the
primary windings are connected in star. The secondary number of turns per phase in both
transformers are also same. But the first transformer has star connected secondary and other
transformer has delta connected secondary. If same voltages are applied in primary of both
transformers, the secondary induced emf in each phase will be in same time-phase with that
of respective primary phase, as because the the primary and secondary coils of same phase
are wound on the same limb in the core of transformer. In first transformer, as the secondary
22
is star connected, the secondary line voltage is 3 times of induced voltage per secondary
phase coil. But in case of second transformer, where secondary is delta connected, the line
voltage is equal to induced voltage per secondary phase coil. If we go through the vector
diagram of secondary line voltages of both transformer, we will easily find that there will be a
clear 30o angular difference between the line voltages of these transformers. Now, if we try to
run these transformers in parallel then there will be a circulating current flows between the
transformers as because there is a phase angle difference between their secondary line
voltages. This phase difference can not be compensated. Thus two sets of connections giving
secondary voltages with a phase displacement can not be intended for parallel operation of
transformers.
The following table gives the connections for which from the view point of phase
sequence and angular divergences, transformer can be operated parallel. According to their
vector relation, all three phase transformers are divided into different vector group of
transformer. All electrical power transformers of a particular vector group can easily be
operated in parallel if they fulfill other condition for parallel operation of transformers.
Group Connection
Yy0
Connection
Dd0
0
(0o)
23
Yd1
Dy1
Yy6
Dd6
Yd11
Dy11
1
( 30o)
6
( 180o)
11
( - 30o)
24
2.
3.
4.
Measure voltages between terminals 2U-1N, 2V-1N, 2W-1N, that means voltages
between each LV terminal and HV neutral.
5.
For YNd11 transformer, we will find, 2U-1N > 2V-1N > 2W-1N 2V-1W > 2V-1V or 2W-1W .
The vector group test of transformer for other group can also be done in similar way.
25
Insulation resistance test of transformer is essential type test. This test is carried out to ensure
the healthiness of overall insulation system of an electrical power transformer.
First disconnect all the line and neutral terminals of the transformer.
2.
3.
4.
Dielectric tests of transformer is one kind of insulation test. This test is performed to
ensure the expected over all insulation strength of transformer. There are several test
performed to ensure the required quality of transformer insulation, dielectric test is one of
26
them. Dielectric tests of transformer is performed in two different steps, first one called
Separate source voltage withstand test of transformer, where a single phase power frequency
voltage of prescribed level, is applied on transformer winding under test for 60 seconds while
the other windings and tank are connected to the earth and it is observed that whether any
failure of insulation occurs or not during the test. Second one is induced voltage test of
Transformer where, three phase voltage, twice of rated secondary voltage is applied to the
secondary winding for 60 second by keeping the primary of the transformer open circuited.
The frequency of the applied voltage should be double of power frequency too. Here also if
no failure of insulation, the test is successful. In addition to dielectric tests of transformer
there are other type test for checking insulation of transformer, such as lightning impulse test,
switching impulse test and partial discharge test.
DVDF (Double voltage and double frequency) test is popular test conducted on the
Transformer before it is commissioned. In this test double the rated voltage and double the
rated frequency is applied to the Transformer under test and observed for its withstand
capability usually for 1 min. Double voltage is applied to test the Transformer withstand
capability for higher voltages which are sometimes occur in the form of lightning surges and
faults on the transformer. But, practically, no transformer is subjected to double the rated
frequency as the frequency variations are not allowed beyond 0.5% by the power supply grid
controlling authority. In such a case, is it essential to test the transformer at 200% i.e. double
the rated frequency conditions?
When alternating electrical source is applied to the primary winding of the
transformer, it draws magnetizing current which produces alternating flux in the core of the
transformer. This flux links both primary and secondary windings and due its alternating
nature EMF is induced across both windings and Erms can be deduced by the equation.
Erms= 4.44mfN volts
Where
As per the above equation, when double the rated voltage is applied while testing
the transformer, without doubling the frequency, the maximum amount of flux linked will
also be doubled as the number of turns is always constant for a particular design. This causes
the abnormal heating of core of the Transformer under test and the magnetizing properties of
the core are disturbed permanently. Hence, to avoid this abnormal heating of the Transformer
27
due to increase in flux, applied frequency will also be doubled along with applied voltage to
test the high voltage with stand capability of the Transformer. Thus the test is named as
Double Voltage Double Frequency test.
28
The transformer oil is filled in the vessel of the testing device. Two standardcompliant test electrodes with a typical clearance of 2.5 mm are surrounded by the
dielectric oil.
An instant after ignition of the arc, the test voltage is switched off automatically by
the testing device. Ultra fast switch off is highly desirable, as the carbonisation due to the
electric arc must be limited to keep the additional pollution as low as possible.
The transformer oil testing device measures and reports the root mean square value of
the breakdown voltage.
After the transformer oil test is completed, the insulation oil is stirred automatically
and the test sequence is performed repeatedly: typically 5 repetitions, depending on the
standard.
29
2.
3.
efficiency of transformer. The power required for these open circuit test and short
circuit test on transformer is equal to the power loss occurring in the transformer.
30
The ammeter reading gives the no load current Ie. As no load current Ie is quite small
compared to rated current of the transformer, the voltage drops due to this current that can be
taken as negligible. Since, voltmeter reading V1 can be considered equal to secondary
induced voltage of the transformer, the input power during test is indicated by watt-meter
reading. As the transformer is open circuited, there is no output, hence the input power here
consists of core losses in transformer and copper loss in transformer during no load condition.
But as said earlier, the no load current in the transformer is quite small compared to full load
current, so copper loss due to the small no load current can be neglected. Hence, the
wattmeter reading can be taken as equal to core losses in transformer. Let us consider
wattmeter reading is Po.
Therefore,
if
shunt
branch
reactance
of
transformer
is
X m,
These values are referred to the LV side of transformer as because the test is conduced
on LV side of transformer. These values could easily be referred to HV side by multiplying
these values with square of transformation ratio.
Therefore it is seen that the open circuit test on transformer is used to determine core losses
in transformer and parameters of shunt branch of the equivalent circuit of transformer.
31
The connection diagram for short circuit test on transformer is shown in the figure. A
voltmeter, wattmeter, and an ammeter are connected in HV side of the transformer as shown.
The voltage at rated frequency is applied to that HV side with the help of a variac of variable
ratio auto transformer.
The LV side of the transformer is short circuited. Now with the help of variac applied
voltage is slowly increased until the ammeter gives reading equal to the rated current of the
HV side. After reaching at rated current of HV side, all three instruments reading (Voltmeter,
Ammeter and Watt-meter readings) are recorded. The ammeter reading gives the primary
equivalent of full load current I L. As the voltage applied for full load current in short circuit
test on transformer is quite small compared to the rated primary voltage of the transformer,
the core losses in transformer can be taken as negligible here.
Lets say, voltmeter reading is Vsc. The input power during test is indicated by wattmeter reading. As the transformer is short circuited, there is no output; hence the input power
here consists of copper losses in transformer. Since, the applied voltage V sc is short circuit
voltage in the transformer and hence it is quite small compared to rated voltage, so core loss
due to the small applied voltage can be neglected. Hence the wattmeter reading can be taken
as equal to copper losses in transformer. Let us consider wattmeter reading is Psc.
32
These values are referred to the HV side of transformer as because the test is
conduced on HV side of transformer. These values could easily be referred to LV side by
dividing these values with square of transformation ratio.
Therefore it is seen that the short circuit test on transformer is used to determine
copper loss in transformer at full load and parameters of approximate equivalent circuit of
transformer.
33
prevent oil sludge and sediment to enter into main tank from conservator. Generally silica gel
breather fixing pipe enters into the conservator from top. If it enters from bottom, it should be
projected well above the level of oil inside the conservator. This arrangement ensure that oil
does not enter the silica gel breather even at highest operating level.
One float,
2.
3.
An indicating dial.
Lets explain the construction of magnetic oil gauge or MOG from its dial parts. The dial of
this device has scale from empty to full. It has some intermediate divisions such as 1/4, 1/1,
3/4. The prescribed oil level at either 30C or 35C ambient temperature may also be
indicated on the dial. A mercury switch and bevel gear is fixed with pointer. When pointer
35
rotates, the alignment of mercury switch also changes according to the angle of rotation of the
pointer. All oil immersed distribution and electrical power transformers are provided with
expansion vessel which is known as conservator of transformer. This vessel takes care of oil
expansion due to temperature rise. When transformer insulating oil is expanded, the oil level
in the conservator tank goes up.
Again when oil volume is reduced due to fall in oil temperature, the oil level in the
conservator goes down. But it is essential to maintain a minimum oil level in the conservator
tank of transformer even at lowest possible temperature. All large electrical power
transformers are therefore provided with a magnetic oil level indicator or magnetic oil gauge.
In conventional conservator tank, a light weight hollow ball or drum floats on the transformer
insulating oil. The float arm is attached with bevel gear as we already explained during the
discussion on the construction of magnetic oil gauge. Naturally the position of the float goes
up and down depending upon the oil level in the conservator and consequently the alignment
of float arm changes. Consequently, the bevel gear rotates. This movement of bevel gear is
transmitted to the pointer outside the conservator, as this pointer is magnetically coupled with
the bevel gear. The pointer of magnetic oil level indicator is also incorporated with a mercury
switch. So it is need not say, when oil level in the conservator goes up and down, the pointer
moves on the MOG dial to indicate the actual level of transformer insulating oil in
conservator tank. As the alignment of mercury switch changes along with the pointer, this
36
switch closes and actuates an audible alarm when pointer reaches near empty position on the
dial of magnetic oil gauge. This event alerts us for topping up oil in electrical power
transformer.
8.4 Radiator
When an electrical transformer is loaded, the current starts flowing through its windings.
Due to this flowing of electric current, heat is produced in the windings, this heat ultimately
rises the temperature of transformer oil. We know that the rating of any electrical equipment
depends upon its allowable temperature rise limit. Hence, if the temperature rise of the
transformer insulating oil is controlled, the capacity or rating of transformer can be extended
up to significant range. The radiator of transformer accelerates the cooling rate of
transformer. Thus, it plays a vital role in increasing loading capacity of an electrical
transformer.This is basic function of radiator of an electrical power transformer.
37
The working principle of radiator is very simple. It just increases the surface area for
dissipating heat of the oil. In case of electrical power transformer, due to the transport
limitation, this units are sent separately and assembled at site with transformer main
body. At the time of dispatching, the flings of radiator are blanketed by gasket and
blanketing plates. The radiator valves on the main tank are also blanketed by gasket and
blanketing plates.
Conclusion
I have get through an idea how transformers are being manufactured in S.J. transformers
during the time of summer training. I have seen the core construction, winding construction
and other accessories that are required to manufacture distribution transformers. It has
improved my theoretical concept of transformer. The training also helped me to understand about
manufacturing of transformer more.
38
39