Beruflich Dokumente
Kultur Dokumente
DEVELOPERS EXPERIENCE
Presentation by Brian Caffyn
Chairman UPC Renewables Group
17 November 2014
List of Content
Sidrap 70MW
Sidrap Regency,
South Sulawesi
Start Construction:
End 2015/Early 2016
Samas 50MW
Bantul Regency, Daerah
Istimewa Yogyakarta
Start Construction: 2016
Samas 50MW Wind Farm as the First Large Scale Wind Farm Project Signed
PPA
Samas 50MW PPA was signed during the launching of 35,000MW Program by President of Republic
of Indonesia, Joko Widodo at Bantul, Yogyakarta on May 4th 2015
UPC is working with local partner Binatek Energi Terbarukan to develop the Samas 50MW wind farm
on the coast near Yogyakarta
UPC has spent 3 years in development of the project (including gathering wind data) before the
signing of PPA
UPC and PLN has worked together for more than 1 year to complete the standardized and bankable
wind PPA which will be used for every wind projects in Indonesia
PPA negotiation is concluded and determined by the banks and lawyers as bankable
Turbine selection remains open
Transmission line length of app. 25km and substation to be built by the project company to PLN
technical requirements
Wind resource is Class 3-4, diurnal (10AM to 8 PM) and seasonal (higher in the dry season)
Financing will be more challenging due to lack of Govt Support Guarantee
Wind Turbine will be Class 3 on a tall tower due to higher wind speeds at height
Bantul,
Yogyakarta
Construction
, Engineering
Land re-enforcement is required
and Logistics
due to sandy soil and seismic conditions
The design needs to withstand
earthquake which occurred occasionally
in the region
No major transportation issues found but
cost higher than expected
Materials locally available
Purchase
Price/Tariff
Financing
Starting and building any business in
Indonesia is time consuming,
complicated and expensive
Pioneer wind project concerns
financing entities
Need a multinational lead lending
institution (esp with no Givt support
letter)
10
Sidrap 70MW Wind Farm is the 2nd UPC Project That Has Signed PPA
with PLN
Sidrap 70MW PPA is signed during during Econex event in Jakarta on August 19th 2015
The PPA negotiation is relatively quick because UPC and PLN is using the template from Samas PPA
UPC has gathered the wind data for Sidrap site from Jan 2013 and now has 5 MET towers
established and has used extensive SODAR campaigns
Currently proposing 2.5MW per turbine utility scale turbines
Transmission line length of app. 8km and substation to be built by the project company to PLN
technical requirements
Wind resource is Class II/III, and seasonal (higher in the dry season)
PPA negotiation is concluded
Sale and purchase agreements for land are 100% complete. Certification in process.
Access and logistics planning highly advanced
Early works contracts have started and geotech progressing currently on all WTG location.
Bank debt mandate signed and in due diligence, 3rd party bank advisors working
Expected Financial Close in March 2016
Targeting early 2017 Commercial Operations Date
Turbine supply agreement agreed
Other Construction Contractor selected and in final contract negotiations
11
JAKARTA
Sidrap, South
Sulawesi
12
Construction
, Engineering
and Logistics
Purchase
Price/Tariff
Financing
Starting and building any business in
Indonesia is time consuming,
complicated and expensive
Low risk tolerance for new projects
Local funding is almost impossible
14
THANK YOU
Thank You
For Your Interest In
Clean Renewable Wind Energy
15
Contacts:
Brian Caffyn
President Director
PT UPC Renewables Indonesia
Pusat Niaga Duta Mas Fatmawati
Blok C1 No.02 - 03, Jl. R. S. Fatmawati No.39
Jakarta 12150
Indonesia
CELL
Email:
Web Site:
16
16