Beruflich Dokumente
Kultur Dokumente
Consultation Paper
(Second Round)
December 2006
461911-1
Purpose
1.
2.
3.
Submissions
4.
5.
6.
7.
8.
461911-1
Description
Electricity Act 1992
Electricity Commission
Electricity Governance Rules 2003
Submissions received
9.
Distributors
Transmission
/ System Operation
Consumers
Contact Energy
Genesis Energy
Meridian Energy
Vector
Transpower
Comalco
MEUG
461911-1
Key Issue
Commissions Response
Ordering of clauses
Key Issue
Commissions Response
confusing reference to each side of the grid
interface. In addition, the wording has been
changed to clarify that each asset owner is
required to provide duplicate protection for its
assets only.
Busbar protection
11.
12.
13.
The grid owners existing standard for 220 kV busbar protection systems
would not have been fully compliant with this requirement, although would
arguably be compliant with the current duplicate protection rule. The grid
owners standard 220 kV busbar protection consists of:
14.
461911-1
check zone protection (where circuits can be changed over from one
bus to another).
Check zone protection is used on double, triple, and ring buses where
circuits are able to be changed over from one bus to another (and
therefore changed over from one protected zone to another). Although
check zone protection has the same probability of fault detection as the
single main unit protection, it does not function as a second form of main
protection. Rather, its function is to improve the stability of the busbar
protection system by providing a two-out-of-two operation to trip a bus
zone. In the event that either the grid owners single main unit protection
fails or the check zone protection fails, the grid owners back up protection
must operate to clear a bus fault.
15.
The Commission does not intend to recommend that the grid owner should
be required to invest unnecessarily to duplicate its main unit protection on
all grid 220 kV busbars where the grid owners back up protection can
satisfactorily clear busbar faults if the main busbar unit protection fails.
16.
17.
18.
461911-1
(b)
ii.
(a)
(b)
(c)
4.4.1
461911-1
4.4.1.2
4.4.3
4.4.4
4.4.3.1
4.4.3.2
4.4.5
4.4.6
4.4.73
461911-1
iii.
General requirements
The asset owner must design, test and maintain all main
protection systems at voltages of 220 kV ac or above to
conform to electricity industry standards and practices as they
are reasonably and ordinarily applied by a skilled and
experienced asset owner to current installations at voltages of
220 kV or above in the New Zealand context.
2.
Test blocks
Either test blocks or both test switches and test
terminals must be provided;
2.2
2.3
3.
3.2
461911-1
3.3
3.4
3.5
3.6
3.6.2
3.7
3.8
Protection signalling
Where protection signalling is used, main 1 protection
must use a signal channel over an independent bearer
on a different route from that used for main 2
protection; and
3.9
Segregation of cabling
Main 1 protection cabling must be segregated from
main 2 protection cabling in a manner that minimises
the risk of common mode failure of main 1 and 2
protection and minimises the number of connections in
any protection circuit.
461911-1
Existing equipment
Despite rule1 and 3 of this Appendix:
4.1
Current transformers
A current transformer commissioned prior to [date to be
inserted1], is not required to comply with the
requirements of rule 3.5 until the current transformer is
replaced;
4.2
4.3
Cabling
Cabling commissioned prior to [date to be inserted1], if
not designed to be segregated, is not required to
comply with the segregation requirements of rule 3.9
until the cabling is replaced.
iv.
To be the date on which these proposed rule amendments come into effect.
The term circuit-breaker is not used elsewhere in the Rules. It previously occurred in technical
code C of schedule C3 of part C, but those occurrences have been updated under a separate rule
amendment.
2
461911-1
10