Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.

00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode
1
2
3
4

Task Name

Duration

Start

Finish

Sat 19-07-14
Mon 04-08-14
Mon 04-08-14
Mon 04-08-14

Thu 29-01-15
Fri 09-01-15
Sat 08-11-14
Sun 24-08-14

31 Mar '14

PROGRAMME FOR SECTION CH. 45+000 TO CH.67+000 - 194


22 KM
days
Highway Works
158 days
CH. 45+000 TO 54+100 - 9.10 KM
96 days
C&G
20 days

EMBANKMENT CONSTRUCTION

66 days

Thu 07-08-14

Sun 12-10-14

SG FILLING

75 days

Thu 14-08-14

Tue 28-10-14

GSB

70 days

Thu 21-08-14

Thu 30-10-14

WMM

70 days

Mon 25-08-14

Mon 03-11-14

DBM

48 days

Fri 19-09-14

Thu 06-11-14

10

BC

45 days

Wed 24-09-14

Sat 08-11-14

Mon 04-08-14

Sun 16-11-14

Mon 04-08-14

Thu 14-08-14

11
12

CH. 54+100 TO 58+500 - MOHANA BYPASS - 4.40 104 days


KM
C&G
10 days

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

1 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

13

EMBANKMENT CONSTRUCTION

90 days

Thu 07-08-14

Wed 05-11-14

14

SG FILLING

85 days

Thu 14-08-14

Fri 07-11-14

15

GSB

80 days

Thu 21-08-14

Sun 09-11-14

16

WMM

78 days

Mon 25-08-14

Tue 11-11-14

17

DBM

50 days

Wed 24-09-14

Thu 13-11-14

18

BC

48 days

Mon 29-09-14

Sun 16-11-14

89 days
20 days

Mon 04-08-14
Mon 04-08-14

Sat 01-11-14
Sun 24-08-14

19
20

CH.58+500 TO 67+000 - 8.50 KM


C&G

21

EMBANKMENT CONSTRUCTION

60 days

Thu 07-08-14

Mon 06-10-14

22

SG FILLING

70 days

Thu 14-08-14

Thu 23-10-14

23

GSB

65 days

Thu 21-08-14

Sat 25-10-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

2 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

24

WMM

63 days

Mon 25-08-14

Mon 27-10-14

25

DBM

40 days

Fri 19-09-14

Wed 29-10-14

26

BC

38 days

Wed 24-09-14

Sat 01-11-14

98 days

Fri 03-10-14

Fri 09-01-15

27

OTHER WORKS

28

DRAIN WORKS

60 days

Fri 03-10-14

Tue 02-12-14

29

METALLIC CRASH BARRIER

60 days

Thu 06-11-14

Mon 05-01-15

30

ROAD MARKINGS, SIGN BOARDS, KILOMETERS,


TURFFING, EARTHEN DRAINS & STADS

60 days

Mon 10-11-14

Fri 09-01-15

194 days
194 days

Sat 19-07-14
Sat 19-07-14

Thu 29-01-15
Thu 29-01-15

108 days

Sat 19-07-14

Tue 04-11-14

31
32
33

STRUCTURES
MAJOR BRIDGE - 61+785
PIERS - 11 NOS

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

3 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

34

EXCAVATION

12 days

Sat 19-07-14

Thu 31-07-14

35

PCC

5 days

Tue 05-08-14

Sun 10-08-14

36

REINFORCEMENT FOR FOOTING

28 days

Thu 07-08-14

Thu 04-09-14

37

SHUTTERING FOR FOOTING

28 days

Sat 09-08-14

Sat 06-09-14

38

CONCRETE FOR FOOTING

28 days

Sun 10-08-14

Sun 07-09-14

39

REINFORCEMENT FOR PIERS

28 days

Tue 12-08-14

Tue 09-09-14

40

STAGING FOR PIER WORKS

30 days

Sat 16-08-14

Mon 15-09-14

41

FABRICATION OF PIER SHUTTERING

45 days

Fri 08-08-14

Mon 22-09-14

42

ERRECTION OF PIER SHUTTERING

40 days

Mon 18-08-14

Sat 27-09-14

43

CASTING OF PIERS

42 days

Tue 19-08-14

Tue 30-09-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

4 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

44

DE SHUTTERING OF PIERS

7 days

Thu 25-09-14

Thu 02-10-14

45

PIER CAP REINFORCEMENT

10 days

Fri 03-10-14

Mon 13-10-14

46

PIER CAP SHUTTERING

7 days

Tue 14-10-14

Tue 21-10-14

47

PIER CAP CONCRETE

7 days

Wed 22-10-14

Wed 29-10-14

48

CASTING OF PEDSAL

7 days

Thu 23-10-14

Thu 30-10-14

49

FIXING OF BEARING

4 days

Fri 31-10-14

Tue 04-11-14

50

FINISHING WORKS

4 days

Wed 29-10-14

Sun 02-11-14

51

ABUTMENTS - 2 NOS

42 days

Mon 04-08-14

Mon 15-09-14

52

EXCAVATION

4 days

Mon 04-08-14

Fri 08-08-14

53

PCC

4 days

Tue 05-08-14

Sat 09-08-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

5 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

54

FOOTING

10 days

Thu 07-08-14

Sun 17-08-14

55

I ST LIFT

9 days

Sun 10-08-14

Tue 19-08-14

56

II ST LIFT

3 days

Tue 19-08-14

Fri 22-08-14

57

III ST LIFT

3 days

Fri 22-08-14

Mon 25-08-14

58

IV ST LIFT

3 days

Mon 25-08-14

Thu 28-08-14

59

V ST LIFT

3 days

Thu 28-08-14

Sun 31-08-14

60

ABUTMENT CAP

7 days

Thu 04-09-14

Thu 11-09-14

61

CASTING OF PEDSAL

6 days

Sun 07-09-14

Sat 13-09-14

62

FIXING OF BEARING

1 day

Sat 13-09-14

Sun 14-09-14

63

FINISHING WORKS

4 days

Thu 11-09-14

Mon 15-09-14

32 days

Thu 07-08-14

Mon 08-09-14

64

RETAINING WALL & RETURN WALL

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

6 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

65

EXCAVATION

4 days

Thu 07-08-14

Mon 11-08-14

66

PCC

3 days

Sun 10-08-14

Wed 13-08-14

67

I ST LIFT

7 days

Wed 13-08-14

Wed 20-08-14

68

II ST LIFT

3 days

Wed 20-08-14

Sat 23-08-14

69

III ST LIFT

3 days

Sat 23-08-14

Tue 26-08-14

70

IV ST LIFT

3 days

Tue 26-08-14

Fri 29-08-14

71

V ST LIFT

3 days

Fri 29-08-14

Mon 01-09-14

72

VI ST LIFT

3 days

Mon 01-09-14

Thu 04-09-14

73

VII ST LIFT

3 days

Thu 04-09-14

Sun 07-09-14

74

FINISHING WORKS

3 days

Fri 05-09-14

Mon 08-09-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

7 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode
75

Task Name

Duration

Start

Finish

156 days

Tue 05-08-14

Thu 08-01-15

31 Mar '14

GIRDERS

76

PREPARATION OF YARD INCLUDING BEDS

60 days

Tue 05-08-14

Sat 04-10-14

77

CASTING OF 48 GIRDERS

75 days

Fri 19-09-14

Wed 03-12-14

78

PRESTRESSING OF GIRDERS

60 days

Fri 10-10-14

Tue 09-12-14

79

GROUTING & SEALING

75 days

Fri 17-10-14

Wed 31-12-14

80

TRANSPORTATION TO SITE

75 days

Wed 22-10-14

Mon 05-01-15

81

ERECTION AT SITE

62 days

Thu 06-11-14

Wed 07-01-15

82

CROSS GIRDERS

60 days

Sun 09-11-14

Thu 08-01-15

64 days
60 days

Tue 11-11-14
Tue 11-11-14

Wed 14-01-15
Sat 10-01-15

60 days

Thu 13-11-14

Mon 12-01-15

83
84

SLAB
SHUTTERING

85

Project: Final Construction Prog

REINFORCEMENT

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

8 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

86

CONCRETE

60 days

Sat 15-11-14

Wed 14-01-15

87

OTHER WORKS

149 days

Tue 02-09-14

Thu 29-01-15

88

CRASH BARRIER

7 days

Sat 17-01-15

Sat 24-01-15

89

BACKFILLING

52 days

Tue 02-09-14

Fri 24-10-14

90

APPROCH SLAB

13 days

Fri 16-01-15

Thu 29-01-15

91

WEARING COAT

6 days

Sun 18-01-15

Sat 24-01-15

92

STONE PITCHING

60 days

Sun 07-09-14

Thu 06-11-14

93

FINISHING AND OVERALL COMPLETION

3 days

Sun 18-01-15

Wed 21-01-15

162 days
83 days
12 days

Sat 16-08-14
Sat 16-08-14
Sat 16-08-14

Sun 25-01-15
Fri 07-11-14
Thu 28-08-14

94
95
96

MAJOR BRIDGE - 57+875


PIERS - 06 NOS
EXCAVATION

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

9 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

97

PCC

5 days

Tue 02-09-14

Sun 07-09-14

98

REINFORCEMENT FOR FOOTING

28 days

Thu 04-09-14

Thu 02-10-14

99

SHUTTERING FOR FOOTING

28 days

Sat 06-09-14

Sat 04-10-14

100

CONCRETE FOR FOOTING

28 days

Sun 07-09-14

Sun 05-10-14

101

REINFORCEMENT FOR PIERS

28 days

Tue 09-09-14

Tue 07-10-14

102

STAGING FOR PIER WORKS

25 days

Sat 13-09-14

Wed 08-10-14

103

FABRICATION OF PIER SHUTTERING

15 days

Sun 07-09-14

Mon 22-09-14

104

ERRECTION OF PIER SHUTTERING

25 days

Wed 17-09-14

Sun 12-10-14

105

CASTING OF PIERS

25 days

Thu 18-09-14

Mon 13-10-14

106

DE SHUTTERING OF PIERS

25 days

Sat 20-09-14

Wed 15-10-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

10 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

107

PIER CAP REINFORCEMENT

10 days

Mon 06-10-14

Thu 16-10-14

108

PIER CAP SHUTTERING

7 days

Fri 17-10-14

Fri 24-10-14

109

PIER CAP CONCRETE

7 days

Sat 25-10-14

Sat 01-11-14

110

CASTING OF PEDSAL

7 days

Sun 26-10-14

Sun 02-11-14

111

FIXING OF BEARING

4 days

Mon 03-11-14

Fri 07-11-14

112

FINISHING WORKS

4 days

Sat 01-11-14

Wed 05-11-14

113

ABUTMENTS - 2 NOS
EXCAVATION

36 days
4 days

Sat 16-08-14
Sat 16-08-14

Sun 21-09-14
Wed 20-08-14

114
115

PCC

4 days

Sun 17-08-14

Thu 21-08-14

116

FOOTING

10 days

Tue 19-08-14

Fri 29-08-14

117

I ST LIFT

9 days

Fri 22-08-14

Sun 31-08-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

11 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

118

II ST LIFT

3 days

Sun 31-08-14

Wed 03-09-14

119

III ST LIFT

3 days

Wed 03-09-14

Sat 06-09-14

120

ABUTMENT CAP

7 days

Sun 07-09-14

Sun 14-09-14

121

CASTING OF PEDSAL

6 days

Wed 10-09-14

Tue 16-09-14

122

FIXING OF BEARING

1 day

Tue 16-09-14

Wed 17-09-14

123

FINISHING WORKS

4 days

Wed 17-09-14

Sun 21-09-14

26 days
4 days

Mon 18-08-14
Mon 18-08-14

Sat 13-09-14
Fri 22-08-14

124
125

RETAINING WALL & RETURN WALL


EXCAVATION

126

PCC

3 days

Thu 21-08-14

Sun 24-08-14

127

I ST LIFT

7 days

Sun 24-08-14

Sun 31-08-14

128

II ST LIFT

3 days

Sun 31-08-14

Wed 03-09-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

12 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

129

III ST LIFT

3 days

Wed 03-09-14

Sat 06-09-14

130

IV ST LIFT

3 days

Sat 06-09-14

Tue 09-09-14

131

V ST LIFT

3 days

Tue 09-09-14

Fri 12-09-14

132

FINISHING WORKS

3 days

Wed 10-09-14

Sat 13-09-14

109 days
75 days

Sat 04-10-14
Sat 04-10-14

Wed 21-01-15
Thu 18-12-14

133
134

GIRDERS
CASTING OF 56 GIRDERS

135

PRESTRESSING OF GIRDERS

56 days

Sat 25-10-14

Sat 20-12-14

136

GROUTING & SEALING

68 days

Fri 17-10-14

Wed 24-12-14

137

TRANSPORTATION TO SITE

65 days

Wed 22-10-14

Fri 26-12-14

138

ERECTION AT SITE

65 days

Sun 09-11-14

Tue 13-01-15

139

CROSS GIRDERS

69 days

Thu 13-11-14

Wed 21-01-15

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

13 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID
140
141

Task
Mode

Task Name

Duration

Start

Finish

59 days
52 days

Tue 18-11-14
Tue 18-11-14

Fri 16-01-15
Fri 09-01-15

31 Mar '14

SLAB
SHUTTERING

142

REINFORCEMENT

55 days

Thu 20-11-14

Wed 14-01-15

143

CONCRETE

55 days

Sat 22-11-14

Fri 16-01-15

144
145

OTHER WORKS
CRASH BARRIER

144 days
50 days

Wed 03-09-14
Sat 29-11-14

Sun 25-01-15
Sun 18-01-15

146

BACKFILLING

52 days

Wed 03-09-14

Sat 25-10-14

147

APPROCH SLAB

14 days

Mon 05-01-15

Mon 19-01-15

148

WEARING COAT

6 days

Fri 16-01-15

Thu 22-01-15

149

STONE PITCHING

60 days

Sun 07-09-14

Thu 06-11-14

150

FINISHING AND OVERALL COMPLETION

3 days

Thu 22-01-15

Sun 25-01-15

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

14 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID
151

Task
Mode

Task Name

Duration

Start

Finish

115 days

Wed 20-08-14

Sat 13-12-14

65 days

Wed 20-08-14

Fri 24-10-14

31 Mar '14

MAJOR BRIDGE - 53+725

152

PIERS - 02 NOS

153

EXCAVATION

4 days

Wed 20-08-14

Sun 24-08-14

154

PCC

2 days

Sat 23-08-14

Mon 25-08-14

155

REINFORCEMENT FOR FOOTING

7 days

Sun 24-08-14

Sun 31-08-14

156

SHUTTERING FOR FOOTING

14 days

Mon 25-08-14

Mon 08-09-14

157

CONCRETE FOR FOOTING

14 days

Wed 27-08-14

Wed 10-09-14

158

REINFORCEMENT FOR PIERS

14 days

Sat 30-08-14

Sat 13-09-14

159

STAGING FOR PIER WORKS

16 days

Fri 29-08-14

Sun 14-09-14

160

FABRICATION OF PIER SHUTTERING

14 days

Mon 25-08-14

Mon 08-09-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

15 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

161

ERRECTION OF PIER SHUTTERING

12 days

Sun 14-09-14

Fri 26-09-14

162

CASTING OF PIERS

7 days

Fri 26-09-14

Fri 03-10-14

163

DE SHUTTERING OF PIERS

7 days

Fri 03-10-14

Fri 10-10-14

164

PIER CAP REINFORCEMENT

4 days

Fri 10-10-14

Tue 14-10-14

165

PIER CAP SHUTTERING

2 days

Tue 14-10-14

Thu 16-10-14

166

PIER CAP CONCRETE

2 days

Thu 16-10-14

Sat 18-10-14

167

CASTING OF PEDSAL

2 days

Sat 18-10-14

Mon 20-10-14

168

FIXING OF BEARING

2 days

Mon 20-10-14

Wed 22-10-14

169

FINISHING WORKS

2 days

Wed 22-10-14

Fri 24-10-14

170

ABUTMENTS - 2 NOS

28 days

Thu 21-08-14

Thu 18-09-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

16 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

171

EXCAVATION

4 days

Thu 21-08-14

Mon 25-08-14

172

PCC

4 days

Sun 24-08-14

Thu 28-08-14

173

FOOTING

7 days

Tue 26-08-14

Tue 02-09-14

174

I ST LIFT

7 days

Thu 28-08-14

Thu 04-09-14

175

II ST LIFT

7 days

Sat 30-08-14

Sat 06-09-14

176

III ST LIFT

7 days

Mon 01-09-14

Mon 08-09-14

177

IV ST LIFT

7 days

Wed 03-09-14

Wed 10-09-14

178

ABUTMENT CAP

7 days

Fri 05-09-14

Fri 12-09-14

179

CASTING OF PEDSAL

7 days

Sun 07-09-14

Sun 14-09-14

180

FIXING OF BEARING

7 days

Tue 09-09-14

Tue 16-09-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

17 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Start

Finish

7 days

Thu 11-09-14

Thu 18-09-14

23 days

Fri 22-08-14

Sun 14-09-14

31 Mar '14

181
182

Duration

FINISHING WORKS
RETAINING WALL & RETURN WALL

183

EXCAVATION

4 days

Fri 22-08-14

Tue 26-08-14

184

PCC

3 days

Sun 24-08-14

Wed 27-08-14

185

I ST LIFT

7 days

Tue 26-08-14

Tue 02-09-14

186

II ST LIFT

7 days

Thu 28-08-14

Thu 04-09-14

187

III ST LIFT

7 days

Sat 30-08-14

Sat 06-09-14

188

IV ST LIFT

7 days

Mon 01-09-14

Mon 08-09-14

189

V ST LIFT

7 days

Wed 03-09-14

Wed 10-09-14

190

VI ST LIFT

7 days

Fri 05-09-14

Fri 12-09-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

18 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Start

Finish

7 days

Sun 07-09-14

Sun 14-09-14

100 days

Thu 04-09-14

Sat 13-12-14

31 Mar '14

191
192

Duration

FINISHING WORKS
GIRDERS

193

CASTING OF 12 GIRDERS

75 days

Thu 04-09-14

Tue 18-11-14

194

PRESTRESSING OF GIRDERS

60 days

Fri 10-10-14

Tue 09-12-14

195

GROUTING & SEALING

55 days

Fri 17-10-14

Thu 11-12-14

196

TRANSPORTATION TO SITE

52 days

Wed 22-10-14

Sat 13-12-14

197

ERECTION AT SITE

45 days

Thu 18-09-14

Sun 02-11-14

198

CROSS GIRDERS

45 days

Mon 22-09-14

Thu 06-11-14

64 days

Thu 25-09-14

Fri 28-11-14

60 days

Thu 25-09-14

Mon 24-11-14

199

SLAB

200

Project: Final Construction Prog

SHUTTERING

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

19 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

201

REINFORCEMENT

60 days

Sat 27-09-14

Wed 26-11-14

202

CONCRETE

60 days

Mon 29-09-14

Fri 28-11-14

204

OTHER WORKS
CRASH BARRIER

93 days
7 days

Wed 03-09-14
Fri 28-11-14

Fri 05-12-14
Fri 05-12-14

205

BACKFILLING

52 days

Wed 03-09-14

Sat 25-10-14

206

APPROCH SLAB

14 days

Mon 17-11-14

Mon 01-12-14

207

WEARING COAT

6 days

Thu 27-11-14

Wed 03-12-14

208

STONE PITCHING

60 days

Wed 10-09-14

Sun 09-11-14

209

FINISHING AND OVERALL COMPLETION

3 days

Sun 09-11-14

Wed 12-11-14

73 days
20 days

Wed 20-08-14
Wed 20-08-14

Sat 01-11-14
Tue 09-09-14

203

210
211

BOX CULVERTS - 10 Nos


EXCAVATION & PCC LAYING

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

20 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

212

FOUNDATION

45 days

Fri 22-08-14

Mon 06-10-14

213

SUBSTRUCTURE

60 days

Sun 24-08-14

Thu 23-10-14

214

SUPERSTRUCTURE

60 days

Wed 27-08-14

Sun 26-10-14

215

RETURN WALLS

60 days

Sun 24-08-14

Thu 23-10-14

216

CRASH BARRIER

14 days

Wed 15-10-14

Wed 29-10-14

217

FINISHING WORKS

14 days

Sat 18-10-14

Sat 01-11-14

28 days
14 days

Sat 19-07-14
Sat 19-07-14

Sat 16-08-14
Sat 02-08-14

218
219

PIPE CULVERTS - 12 Nos


EXCAVATION & PCC LAYING

220

HEAD WALL FIRST LIFT

14 days

Mon 21-07-14

Mon 04-08-14

221

GRANULAR BED LAYING

7 days

Thu 31-07-14

Thu 07-08-14

222

LAYING OF NP4 PIPES

10 days

Sat 02-08-14

Tue 12-08-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

21 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

223

HEAD WALL II LIFT

14 days

Thu 31-07-14

Thu 14-08-14

224

FINSHING WORKS

3 days

Wed 13-08-14

Sat 16-08-14

72 days
20 days

Thu 14-08-14
Thu 14-08-14

Sat 25-10-14
Wed 03-09-14

225
226

MINOR BRIDGE - 10 Nos


EXCAVATION & PCC LAYING

227

FOUNDATION

45 days

Sat 16-08-14

Tue 30-09-14

228

SUBSTRUCTURE

60 days

Mon 18-08-14

Fri 17-10-14

229

SUPERSTRUCTURE

60 days

Wed 20-08-14

Sun 19-10-14

230

RETURN WALLS

60 days

Fri 22-08-14

Tue 21-10-14

231

CRASHBARRIER

14 days

Thu 09-10-14

Thu 23-10-14

232

FINISHING WORKS

14 days

Sat 11-10-14

Sat 25-10-14

55 days

Sat 19-07-14

Fri 12-09-14

233

PUP'S - 2 Nos

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

22 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km
ID

Task
Mode

Task Name

Duration

Start

Finish
31 Mar '14

234

EXCAVATION & PCC LAYING

7 days

Sat 19-07-14

Sat 26-07-14

235

PUP FOUNDATION

14 days

Mon 21-07-14

Mon 04-08-14

236

PUP SUBSTRUCTURE

45 days

Wed 23-07-14

Sat 06-09-14

237

PUP SUPERSTRUCTURE

45 days

Fri 25-07-14

Mon 08-09-14

238

CRASHBARRIER

7 days

Wed 03-09-14

Wed 10-09-14

239

FINISHING WORKS

3 days

Tue 09-09-14

Fri 12-09-14

Project: Final Construction Prog

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

12 May '14

23 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

24 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

25 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

26 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

27 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

28 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

29 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

30 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

31 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

32 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

33 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

34 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

35 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

36 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

37 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

38 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

39 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

40 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

41 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

42 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

43 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

44 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

19 Jan '15

02 Mar '15

45 of 46

Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh - Construction Programme from Ch.45+000 km to Ch.67+000 km

12 May '14

23 Jun '14

Project: Final Construction Prog

04 Aug '14

15 Sep '14

27 Oct '14

08 Dec '14

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only