SITE INSPECTION AND TEST RECORD

Description:

Order no.:

Record no.:

TRIP SUPERVISION RELAY


TYPE: XR350
Customer:SEC

End Client:SEC

Sheet:

Site: RIYADH 7037- 3313.8 KV substation

Panel / Designation / Location no.:

Project no.:

1 of 3

1.GENERAL DATA AND INFORMATION:


Bay No
:
Bay Name
:
Manufacture
:
Order No
:
Draw & Sheet No:

Serial No
:
Aux Voltage
:
Rated Voltage
:
No Of Contacts
:
Conn Diagram No
:

2.MECHANICAL CHECKS AND VISUAL INSPECTION


ITEM

DESCRIPTION

CHECKE
D
ok
Ok
Ok
Ok
ok

1
Inspect for physical damage / defects.
2
Verify connections as per approved drawings.
3
Check tightness of all connections.
4
Check Ferrules.
5
Check apparatus lists.
3.ELECTRICAL TEST:
A) FUNCTION TEST:
ITEM
1
2
3

DESCRIPTION
All contacts checked.
All output contacts resistance measured.
Flag operation checked.

CHECKED

B) COIL RESISTANCE/EXTERNAL RESISTANCE CHECKED:


ITE
M
1
2
3
4
5

DESCRIPTION

MEASURED
VALUE

Resistance of coil A/B


Resistance of coil C
External resistance AR1
External resistance AR2

C) MEASURE AUX SUPPLY VOLTAGE & CURRENT:


TERMINALS
28(+) &
29(-)

VOLTAGE
MEASURED
35.5V

CURRENT
MEASURED
1.555A

Make short circuit between two terminals 13&22 across R2 (R1=R2=3.3K)


Tested by:
Name
Signature & Date:

338429233.doc

Witnessed by:
Name
Signature & Date:

SITE INSPECTION AND TEST RECORD


Description:

Order no.:

Record no.:

TRIP SUPERVISION RELAY


TYPE: XR350
Customer:SEC

End Client:SEC

Sheet:

Site: RIYADH 7037- 3313.8 KV substation

Panel / Designation / Location no.:

Project no.:

2 of 3

connect (R3=2K)to terminal 27.


the limit of supply voltage should be 80-120% from rated voltage
The drain power is 4w
While testing the drain current; keep the supply voltage at terminal 21(+) and 14(-) at 125
v dc
D)PICKUP AND DROP-OFF TEST:
TERMINALS
21(+) &
22(-)

VOLTAGE
MEASURE
8.832V

PICKUP
CURRENT
MEASURE
1.541A

VOLTAGE
MEASURE
1.069V

DROP-OFF
CURRENT
MEASURE
1.131A

NOTE:
for testing purpose the dc supply for the terminal 21,14 and dc supply for the terminal
27,28 must be different.
the pickup and drop off test should be done at the relay terminal 21(+) and 14(-)
during the pickup and drop off test do not disturb the aux supply at terminal 28(+) and27(-)
E) RELAY BURDEN TEST:
TERMINAL
13(+)&14(-)
21(+)&22(-)

VOLTAGE APPLAYED
50V DC
50V DC

CURRENT MEASURED
1.679A
1.680 A

C.B STATUS
COILA+B (CB OPEN)
COIL A(CB CLOSED)

power through the circuit21(+) & 14(-) at voltage 125 dc should be 1W while CB open and
2w while CB closed
F) OPERATE AND RESET TIME TEST (AT RATED VOLTAGE):
OPERATE TIME (m sec)
89

RESET TIME (m sec)


0.219

CONTACT
5-7

NOTE:
the timing test should be done at relay terminal 21(+),14(-)
during the timing test do not distrub the aux supply at terminal 28(+) &27(-)
CONTACT RESISTANCE:
SL NO
1
2
Tested by:
Name
Signature & Date:

338429233.doc

TERMINALS
1,3 NC
2,4NC

CONTACT RESISTANCE
0.1
0.1
Witnessed by:
Name
Signature & Date:

SITE INSPECTION AND TEST RECORD


Description:

Order no.:

Record no.:

TRIP SUPERVISION RELAY


TYPE: XR350
Customer:SEC

End Client:SEC

Sheet:

Site: RIYADH 7037- 3313.8 KV substation

Panel / Designation / Location no.:

Project no.:

3
4
5

Tested by:
Name
Signature & Date:

338429233.doc

6,8NC
5,7NO
10,12NO

3 of 3

0.1
0.1
0.1

Witnessed by:
Name
Signature & Date: