CPMQUESTION

The Activities information on a particular project is shown in the


table ..

Table .. Logic table for project activities A through F.


(i) Draw a Network Diagram showing the various logical activity
relationships from this information.
(ii) Perform a forward and backward pass to complete activity boxes. Arrange
data within activity boxes as outlined in Figure below.
EARLY
START
FLOAT
LATE
START

EARLY
FINISH
ACTIVITY
NO.

DURATION
LATE
FINISH

Figure . Layout of Activity Box information.


(iii)
b)

Highlight the critical path on your diagram.


It is suggested that the duration of the whole project could be shortened by 4
days by completing Activity B in 4 days rather than 8 days. Rework the Network
Diagram and comment on whether this strategy would succeed. State the reasons for

your
Answer.