Main Control Valve - Assemble


SMCS - 5051-016

Assembly Procedure
Table 1
Required Tools
Tool

Part Number

Part Description

1U-6396

O-Ring Assembly Compound

138-7575

Link Brackets

155-0695

Thread Lock Compound

1P-2420

Transmission Repair Stand

Qty

Note: Cleanliness is an important factor. Before assembly, all parts should be thoroughly cleaned in cleaning
fluid. Allow the parts to air dry. Wiping cloths or rags should not be used to dry parts. Lint may be deposited
on the parts which may cause later trouble. Inspect all parts. If any parts are worn or damaged, use new parts
for replacement. All disassembly and all assembly procedures must be performed on a clean work surface and
in a clean hydraulic area. Keep cleaned parts covered and protected at all times.
Note: O-ring seals, gaskets, and seals should always be replaced. A used O-ring seal may not have the same
sealing properties as a new O-ring. Use Tooling (A) during the assembly procedure.
Note: Apply a light film of hydraulic oil to all components before assembly.

Variable Swing Priority Valve

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
1 de 49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 1

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00708438

1. Install O-ring seals (241) on the valve body.

Illustration 2

g00708437

2. Attach Tooling (B) and a suitable lifting device to the upper valve body. Position the valve bodies and
install bolts (240) .

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
2 de 49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 3

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00708436

3. Install covers (239) on the valve body.

Illustration 4

g00708419

4. Install O-ring seals on the plug and fitting. Install plug (237) and fitting (238) in the valve body. Tighten
the plug to a torque of 35 3 Nm (26 2 lb ft).

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
3 de 49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

Illustration 5

g00708384

5. Assemble valve assembly (226), as follows: Install valve (231) and spring (228) in stem (235). Position
rod (232) in stem (235). Install pin (233). Install stem (235) in sleeve (227). Install spring (236) and
sleeve (230) in sleeve (227). Install two O-ring seals (229) and two O-ring seals (234) .

Illustration 6

g00708902

6. Install valve assembly (226) in the valve housing.

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
4 de 49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 7

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00708418

7. Install O-ring seals (224) and (225) .

Illustration 8

g00708417

8. Install the O-ring seals. Install plugs (223). Tighten plug (223) to a torque of 5 2 Nm (4 1 lb ft).

Illustration 9

g00708416

9. Install the O-ring seals. Install plugs (220) and (221) and fittings (222) in the variable swing priority
Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
5 de 49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

valve. Tighten plug (221) to a torque of 5 2 Nm (4 1 lb ft).

Illustration 10

g00708383

10. Position variable swing priority valve (219). Install four bolts (218) .

Control Valve (Boom II)

Illustration 11

g00708376

1. Install O-ring seal (215) on plug (214). Install spring (216) in valve (217) .

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
6 de 49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 12

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707975

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
2. Install check valve (213) in the valve housing. Tighten check valve (213) to a torque of 175 15 Nm
(129 11 lb ft).

Illustration 13

g00707863

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
7 de 49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

and wear protective equipment.


3. Assemble the control valve spool. Apply Tooling (C) to bolt (170). Install bolt (170), retainers (169),
and spring (171) to stem (168). Tighten bolt (72) to 50 + 10 - 0 Nm (37 + 7 - 0 lb ft).
4. Install control valve spool (212) in the valve housing.

Illustration 14

g00707972

5. Install spring (210) and valve (211) in plug (208). Install O-ring seal (209) on plug (208) .
6. Install the O-ring seals and fittings in cover (204) and housing (206).

Illustration 15

g00707968

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
8 de 49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

and wear protective equipment.


7. Position housing (206) and install bolts (205). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).
8. Install check valve (207). Tighten check valve (207) to a torque of 200 25 Nm (148 18 lb ft).

Illustration 16

g00707966

9. Install cover (204) and bolts (203). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Stick Regeneration Valve

Illustration 17

g00707939

1. Install valve spool (202) .

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
9 de 49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 18

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707938

2. Install connector (201) and fitting (200). Tighten connector (200) to a torque of 105 10 Nm (77 7
lb ft).

Illustration 19

g00707937

3. Install guide (199) and spring (198) into the valve body housing.

Illustration 20

g00707936

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


10 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
4. Install the O-ring seal on the plug. Install plug (197) into the valve housing. Tighten plug (197) to a
torque of 285 30 Nm (210 22 lb ft).

Line Relief Valve

Illustration 21

g00708071

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Install O-ring seals (191), (192), (193), (195), and (196). Install backup rings (190) and (194) .

Control Valve (Stick I)


PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
11 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 22

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707863

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Assemble the control valve (stick I) spool assembly. Apply Tooling (C) to bolt (170). Install bolt (170),
two retainers (169), and spring (171) to stem (168). Tighten bolt (72) to 50 + 10 - 0 Nm (37 + 7 - 0 lb
ft).

Illustration 23

g00707922

2. Install control valve spool (189) into the valve housing.


3. Install the O-ring seals and fittings on cover (185) and housing (187) .

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


12 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 24

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707970

4. Install line relief valve (188). Tighten line relief valve (188) to a torque of 95 14 Nm (70 10 lb ft).
5. Position housing (187) and install bolts (186). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Illustration 25

g00707920

6. Position cover (185) and install bolts (184). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Stick Unloading Valve

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


13 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 26

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707919

1. Install backup seal (183) and O-ring seal (182) on the valve assembly. Install guide (180) on valve
assembly (181).

Illustration 27

g00707918

2. Install spool (179) in guide (180). Install valve assembly (181). Install spring (178) .

Illustration 28

g00707917

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


14 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
3. Install the O-ring seal on plug (177). Install plug (177). Tighten plug (177) to a torque of 285 30 Nm
(210 22 lb ft).

Control Valve (Swing)

Illustration 29

g00707863

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Assemble the control valve spool. Apply Tooling (C) to bolt (170). Install bolt (170), retainers (169),
and spring (171) to stem (168). Tighten bolt (170) to 50 + 10 - 0 Nm (37 + 7 - 0 lb ft).

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


15 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 30

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707915

2. Install control valve spool (176) into the valve housing.


3. Install the O-ring seals and fitting on cover (155) and housing (157) .

Illustration 31

g00707914

4. Position housing (175) and install bolts (174). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Illustration 32

g00707913

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


16 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

5. Position cover (173) and install bolts (172). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Control Valve (Travel Left)

Illustration 33

g00707863

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Assemble the control valve spool. Apply Tooling (C) to bolt (170). Install bolt (170), two retainers
(169), and spring (171) to stem (168). Tighten bolt (72) to 50 + 10 - 0 Nm (37 + 7 - 0 lb ft).

Illustration 34

g00707862

2. Install control valve spool (167) into the valve housing.


PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
17 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 35

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707861

3. Install O-ring seal (165) on fitting (164). Install fitting (164). Install O-ring seal (166) in housing (163).

Illustration 36

g00707859

4. Position housing (163) and install two bolts (162). Tighten the bolts to a torque of 49 5 Nm (36 4 lb
ft).

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


18 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 37

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707858

5. Install O-ring seal (160) on fitting (159). Install fitting (159). Install O-ring seal (161) in cover (158) .

Illustration 38

g00707856

6. Position cover (158) and install bolts (157). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Main Relief Valve

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


19 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 39

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707731

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Install backup seal (149). Install O-ring seals (147), (148), (150), (151), (152) and (153).
2. Install filter (156), collar (155), and ring (154) into valve assembly (139) .
3. Assemble the main relief valve. Install spring (140) and seat (141) into the valve assembly. Install valve
(142) and spring (143) into holder (144). Install holder (144) into valve assembly (139). Install adjuster
(146) and nut (145) into holder (144).

Control Valve (Straight Travel)

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


20 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 40

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707769

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Install valve (135) and spring (136) in the valve stem. Install O-ring seal (137) on guide (138). Install
guide (138) in valve stem (134) .

Illustration 41

g00707694

2. Install straight travel spool assembly (133) in the valve housing.

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


21 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 42

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707693

3. Install O-ring seals (132) on solenoid (131) .

Illustration 43

g00707692

4. Install the O-ring seals on the fittings. Install fittings (129) in housing (127). Install O-ring seal (130) on
the housing. Position solenoid (131) and install bolts.

Illustration 44

g00707691

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


22 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

5. Position housing (127) and install bolts (126). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).
Install main relief valve (128). Tighten main relief valve (128) to a torque of 135 10 Nm (100 7 lb
ft).

Illustration 45

g00707689

6. Install piston (125) and spring (124) in the valve housing.

Illustration 46

g00707561

7. Install O-ring seal (121) on fitting (120). Install fitting (120) in cover (119). Install stopper (123) and
O-ring seal (122) on the cover.

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


23 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 47

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707560

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
8. Position cover (119) and install bolts (118). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Check Valves

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


24 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 48

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707559

1. Install spring (116), valve (117), and O-ring seal (115) on the load check valve (106) .

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.

Illustration 49

g00707558

2. Install spring (113), valve (114), and O-ring seal (112) on load check valve (105) .

Illustration 50

g00707557

3. Install O-ring seal (111) on plug (104) for the travel control valve.

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


25 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 51

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707266

4. Install backup seal (107), O-ring seal (108), spring (109), and valve (110) into the check valves.

Illustration 52

g00707265

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
5. Install check valves (103) into the straight travel control valve. Tighten check valves (103) to a torque
of 200 25 Nm (148 18 lb ft). Install plug (104) into the travel control valve. Tighten plug (104) to a
torque of 200 25 Nm (148 18 lb ft). Install load check valve (105) into the swing control valve.
Tighten load check valve (105) to a torque of 200 25 Nm (148 18 lb ft). Install load check valve
(106) into the stick control valve. Tighten load check valve (105) to a torque of 285 30 Nm (210
22 lb ft).

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


26 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 53

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707264

6. Install covers (102) on the valve housing.

Control Valve (Travel Right)

Illustration 54

g00885900

1. Install the O-ring seals on fittings (99), (100), and (101) .

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


27 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 55

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707262

2. Install fittings (99), (100), and (101) in the valve housing.

Illustration 56

g00707863

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
3. Assemble the control valve spool. Apply Tooling (C) to bolt (170). Install bolt (170), two retainers
(169), and spring (171) to stem (168). Tighten bolt (72) to 50 + 10 - 0 Nm (37 + 7 - 0 lb ft).

Illustration 57

g00707253

4. Install control valve spool (98) in the valve housing.


PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
28 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

5. Install the O-ring seals and fittings in cover (95) and housing (97) .

Illustration 58

g00707252

6. Position housing (97) and install bolts (96). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Illustration 59

g00707251

7. Position cover (95) and install bolts (96). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Control Valve (Attachment)

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


29 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 60

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707248

1. Install O-ring seal (90), backup ring (91), and O-ring seal (92) on the plug.

Illustration 61

g00707250

2. Install plug assembly (93) in the valve housing. Tighten plug assembly (93) to a torque of 95 14 Nm
(70 10 lb ft).

Illustration 62

g00707248

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


30 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

3. Install O-ring seal (90), backup ring (91) and O-ring seal (92) on the plug.

Illustration 63

g00707246

4. Install plug assembly (89) to the valve housing. Tighten plug assembly (89) to a torque of 95 14 Nm
(70 10 lb ft).

Illustration 64

g00707863

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
5. Assemble the control valve spool. Apply Tooling (C) to bolt (170). Install bolt (170), retainers (169),
and spring (171) to stem (168). Tighten bolt (72) to 50 + 10 - 0 Nm (37 + 7 - 0 lb ft).

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


31 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 65

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707245

6. Install control valve spool (88) in the valve housing.

Illustration 66

g00707242

7. Install the O-ring seals on the fittings, the nipple, and the plug. Install fittings (84) and (87), nipple (85)
and plug (86) in housing (80).
8. Install the O-ring seals on solenoid (83). Refer to Step 12.

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


32 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 67

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707237

9. Install solenoid (83) and bolts (82) on housing (80). Install O-ring seal (81) in housing (80) .

Illustration 68

g00707236

10. Position housing (80) and install bolts (81). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Illustration 69

g00707235

11. Install the O-ring seals. Install fittings (75) and (76), nipple (79), and plugs (77) and (78) on housing
(70).

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


33 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 70

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00885897

12. Install O-ring seals (74) on solenoid (73) .

Illustration 71

g00707158

13. Install solenoid (73) and bolts (72). Install O-ring seal (71) in housing (70).

Illustration 72

g00707154

14. Position housing (70) and install bolts (69). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).
PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
34 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

Line Relief Valves (Bucket Cylinder Rod and Head End)

Illustration 73

g00706937

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Install O-ring seals (52), (53), (54), (56), and (57). Install backup rings (51) and (55) .
2. Replace the O-ring seals in the line relief valves (67) and (68). Refer to Step 1.

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


35 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 74

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00707025

3. Install line relief valve (bucket cylinder head end) (68) to the valve housing. Tighten relief valve (68) to
a torque of 95 14 Nm (70 10 lb ft).

Illustration 75

g00707024

4. Install line relief valve (bucket cylinder rod end) (67) to the valve housing. Tighten relief valve (68) to a
torque of 95 14 Nm (70 10 lb ft).

Control Valve (Bucket)

Illustration 76

g00707863

Improper assembly of parts that are spring loaded can cause bodily
injury.

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


36 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

To prevent possible injury, follow the established assembly procedure


and wear protective equipment.
1. Assemble the control valve (bucket) spool assembly. Apply Tooling (C) to bolt (170). Install bolt (170),
retainers (169), and spring (171) to stem (168). Tighten bolt (170) to 50 + 10 - 0 Nm (37 + 7 - 0 lb ft).

Illustration 77

g00707017

2. Install control valve (bucket) spool assembly (66) in the valve housing.
3. Install the O-ring seals and fittings in cover (63) and housing (65).

Illustration 78

g00706999

4. Position housing (65) and install bolts (64). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


37 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 79

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00706996

5. Position cover (63) and install bolts (62). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Check Valve

Illustration 80

g00885896

1. Install O-ring seal (59) on plug (58). Install valve (61) and spring (60) into the valve housing.

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


38 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 81

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00706973

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
2. Install plug (58) in the valve housing. Tighten plug (58) to a torque of 175 15 Nm (129 11 lb ft).

Line Relief Valve (Boom Cylinder Rod End)

Illustration 82

g00706937

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Install O-ring seals (52), (53), (54), (56), and (57). Install backup rings (51) and (55) .

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


39 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 83

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00706897

2. Install line relief valve (50) to the valve housing. Tighten relief valve (50) to a torque of 95 14 Nm
(70 10 lb ft).

Regeneration Valve

Illustration 84

g00706893

1. Install O-ring seal (48) on connector (47). Install valve (49) into the valve housing.

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


40 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 85

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00706892

2. Install connector (47) in the valve housing. Tighten connector (47) to a torque of 105 10 Nm (77 7
lb ft).

Illustration 86

g00706814

3. Install O-ring seal (44) on plug (43). Install guide (46) and spring (45) into the valve housing.

Illustration 87

g00706685

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


41 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
4. Install plug (43) in the valve housing. Tighten plug (43) to a torque of 285 30 Nm (210 22 lb ft).

Control Valve (Boom I)

Illustration 88

g00707863

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Assemble the control valve spool. Apply Tooling (C) to bolt (170). Install bolt (170), two retainers
(169), and spring (171) to stem (168). Tighten bolt (72) to 50 + 10 - 0 Nm (37 + 7 - 0 lb ft).

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


42 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 89

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00706665

2. Install control valve spool (42) into valve housing (4) .


3. Install the O-ring seals and fittings on cover (39) and housing (41).

Illustration 90

g00706650

4. Position housing (41) and install bolts (40). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Illustration 91

g00706573

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


43 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

5. Position cover (39) and install bolts (38). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Control Valve (Stick II)

Illustration 92

g00706552

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Assemble the control valve spool. Position two retainers (35) and spring (37) on stem (34). Apply
Tooling (C) to bolt (36). Install bolt (36). Tighten bolt (36) to 50 + 10 - 0 Nm (37 + 7 - 0 lb ft).

Illustration 93

g00706500

2. Install control valve spool (33) in valve housing (4) .


PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)
44 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 94

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00706482

3. Install O-ring seal (31) on fitting (32). Install fitting (32). Install O-ring seal (30) in housing (29).

Illustration 95

g00706476

4. Position housing (29) and install bolts (28). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


45 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 96

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00706454

5. Install O-ring seal (26) on fitting (27). Install fitting (27). Install O-ring seal (25) on cover (24).

Illustration 97

g00706429

6. Position cover (24) and install bolts (23). Tighten the bolts to a torque of 49 5 Nm (36 4 lb ft).

Negative Control Relief Valve

Illustration 98

g00706395

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


46 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
1. Install shims (20), spring (21) and valve (22) in plug (15). Install O-ring seal (16) on plug (15). Install
plug (15) in relief valve body (18). Install O-ring seals (17) and (19) in relief valve body (18) .

Illustration 99

g00706213

2. Install relief valve (14) in the valve housing. Tighten relief valve (14) to a torque of 145 15 Nm (107
11 lb ft).

Load Check Valves

Illustration 100

g00706113

1. Assemble the stick valve or the second load check valve. Install spring (11), valve (10), and O-ring seal
(12) on plug (13) .

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


47 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

2. Repeat the preceding step for the assembly of the remainder of the load check valves.

Illustration 101

g00706100

3. Assemble the top plug assembly. Install spring (7), valve (6), and O-ring seal (8) on plug (9) .

Illustration 102

g00706056

Improper assembly of parts that are spring loaded can cause bodily
injury.
To prevent possible injury, follow the established assembly procedure
and wear protective equipment.
4. Install five load check valves (5) in the valve housing. Tighten load check valves (5) to a torque of 200
25 Nm (148 18 lb ft).

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


48 deCreate
49

20/10/2010 06:57 p.m.

330C L & 330C LN Excavators CGZ00001-UP (MACHINE) POWERED...

Illustration 103

https://sis.cat.com/sisweb/sisweb/techdoc/techdoc_print_page.jsp?returnu...

g00705884

1. Position covers (3) and install bolts (2) on valve housing (4) .

Illustration 104

g00705874

2. Remove main control valve (1) from Tooling (D). The weight of the main control valve is
approximately 181 kg (400 lb).
End By: Install the main control valve. Refer to Disassembly and Assembly, "Main Control Valve - Install".
Copyright 1993 - 2010 Caterpillar Inc.
Todos los derechos reservados.
Red privada para licenciados del SIS.

Wed Oct 20 2010 18:56:48 GMT-0300

PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)


49 deCreate
49

20/10/2010 06:57 p.m.

Das könnte Ihnen auch gefallen