PROJECT CHARTER

CASE 7 : EDUCATION INDUSTRY


UniKL MIIT Online Technoproneurship Assessment System
Project Role And Deliverables

Name
Idham bin zulkifli
Maryam Mardhiah
binti Mohd Amin
Juliana binti
mohamed sharif
Hidayatul Husna
binti Mohd Salleh
Nurfathiah Farhani
binti yahawa
Muhammad
Hafizuddin bin
Mohamad Suhaini

Role
Project Manager

Project Team
Members

Deliverables
Project Estimation
& Budget
Project Charter
Overall proposed
system architecture
Proposal
Project Prioritize
Risk list
Project Timeline

PROJECT CHARTER
Project Title:

UniKL MIIT Online Technoproneurship Assessment System

Project Sponsor: UniKL MIIT


Project Manager: Idham bin zulkifli

Date Prepared: 25/11/2016


Project Customer: UniKL MIIT

Project Purpose or Justification:


To develop a web application system named UniKL MIIT Online Technoproneurship Assessment
System . The project purpose it to provide student and teacher handy tools to conduct teaching and
learning activity , so teacher and student can interact with each other through a website and provide
easy access anytime and anywhere.

Project Description:
Every course require student to complete series of lecture, assignment,quiz ,test and examination for
them to pass the course. Unfortunately, these all required a wasting a lot of paper and lecturer need to
mark the paper manually .Lecturer job of teaching the student have been distracted with them need to
manually key in each students mark . Developing a web application for Online Assessment system might
solved the problem that have been on going since past time.

Project and Product Requirements:


1. The system should have login feature that will authenticate between student and lecturer.
2.The system should have online quiz/test and allow student to answer the quiz/test .
3.The system should have timing system for student to answer the quiz/test.
4.The system should automatically calculate the marks and submit it to the management.
5. The system should have forum section where lecturer and student can interact with each other.

Acceptance Criteria:
1. A user that have student account only can access student page .
2. Only Lecturer can create quiz/test and set their answering method.
3. Only Lecturer can set the desired time for conduction online quiz/test.
4. Only lecturer can edit the marks calculated.
5. Only Lecturer can upload notes on the forum section , student can only download it .

Initial Risks:
1. There is a risk of network failure we need experts to handle such errors.
2. For data bases we need strong tool to avoid loss of data. We need to have backup server to avoid
this situation.

Project Objectives

Success Criteria

Person Approving

PROJECT CHARTER
Scope:
Deliver a quality online
assessment site within the time,
cost, and project requirements
defined by our Project Team

The project will achieve its


success criteria when it is finish
within the time ,cost and project
requirement given.

Time:
To complete project in less than
6 month.

Project finish in less and equal 6


month

Cost:
To complete the project with
budget of RM 150 000.00

Total cost of developing is not


more than RM 150 000.00

Quality:
To deliver a system that will
satisfy customer.

System should be usable,


secure, reliable, efficient enough
to support the operation in an
effective manner.

Other:

Summary Milestones
Project Management plan
- Project Management plan completed

Due Date
24 - 31 December 2016

Requirement and Specification


- Software requirement specification finalized
- System requirement specification finalized
- User Manual
- Helping material finalized

1 - 15 January 2017

Design
- completed Detail Design done
- Database of the system Finalized System

16 - 31 January 2017

Development
Front end developed
User Interface finalized
Testing
- Testing done
- All the testing including unit integration and system level testing
completed
Project closing
Project completed
- Website Publish

1 February - 15 May 2017

Estimated Budget:

16 May 10 Jun 2017

10 Jun 16 Jun 2017

PROJECT CHARTER
RM 150 , 000.00

Project Manager Authority Level


Staffing Decisions:
Project Manager will have the decision to hire, fire and take all necessary action which are needed.

Budget Management and Variance:


No variance has been found till project end

Technical Decisions:
Project manager can take all Technical decision regarding hardware problem by consulting with hardware
engineer and can take necessary action

Conflict Resolution:
Conflict resolution is very challenging job hence project manager will address conflicts in accordance
with the supervisor of team.

Escalation Path for Authority Limitations:


Any problem which occurs outside the authority of project manager in this case project manager will
refer problem to line manager

Approvals:
Project Manager Signature

Sponsor or Originator Signature

Idham bin zulkifli


Project Manager Name

Sponsor or Originator Name

25 November 2016
Date

Date