Beruflich Dokumente
Kultur Dokumente
Technical Report
EPRI 3412 Hillview Avenue, Palo Alto, California 94304 PO Box 10412, Palo Alto, California 94303 USA
800.313.3774 650.855.2121 askepri@epri.com www.epri.com
ORDERING INFORMATION
Requests for copies of this report should be directed to EPRI Orders and Conferences, 1355 Willow
Way, Suite 278, Concord, CA 94520, (800) 313-3774, press 2 or internally x5379, (925) 609-9169,
(925) 609-1310 (fax).
Electric Power Research Institute and EPRI are registered service marks of the Electric Power
Research Institute, Inc. EPRI. ELECTRIFY THE WORLD is a service mark of the Electric Power
Research Institute, Inc.
Copyright 2003 Electric Power Research Institute, Inc. All rights reserved.
CITATIONS
This report was prepared by
Framatome ANP
400 South Tryon St.
Charlotte, NC 28285
Principal Investigators
J. Hamlen
P. Clay
This report describes research sponsored by EPRI.
The report is a corporate document that should be cited in the literature in the following manner:
Life Cycle Management SourcebooksVolume 10: Feedwater Heaters, EPRI, Palo Alto, CA:
2003. 1009073.
iii
PRODUCT DESCRIPTION
EPRI is producing a series of Life Cycle Management Planning Sourcebooks, each containing a
compilation of industry experience and data on aging degradation and historical performance for
a specific type of system, structure, or component (SSC). This sourcebook provides information
and guidance for implementing cost-effective life cycle management (LCM) planning for
feedwater heaters.
Background
Industrys cost for producing LCM plans for the many important SSCs in operating nuclear
plants can be reduced if LCM planners have an LCM sourcebook of generic industry
performance data for each SSC they intend to addresssee Life Cycle Management Planning
SourcebooksOverview Report (EPRI 1003058). The general objective of EPRIs LCM
sourcebook effort is to provide system engineers with generic information, data, and guidance
they can use to generate a long-term equipment reliability plan for plant SSCs. These consist of
aging and obsolescence management plans that are optimized for plant performance and
economics. The long-term equipment reliability plan or LCM plan for the plant SSC combines
industry experience and plant-specific performance data to provide an optimum maintenance
plan, schedule, and expense profile throughout the plants remaining operational life.
Objectives
To provide plant engineers or their expert support with a compilation of generic information,
data, and guidance needed to create a plant-specific LCM plan for the mechanically passive
components of nuclear power plant feedwater heaters.
Approach
Experts in the maintenance and aging management of feedwater heaters followed the Life Cycle
Management Planning SourcebooksOverview Report. They defined the scope of the physical
system (the boundary) and the scope of the components to be included in the study. They then
compiled information and data on historical industry performance of selected feedwater heaters
within the scope and presented technical guidance for preparing plant-specific LCM plans. Prior
to publication, the sourcebook was reviewed by EPRI LCM utility advisors.
Results
This sourcebook contains information on typical boiling water reactor (BWR) and pressurized
water reactor (PWR) feedwater heaters. Information includes performance issues, reliability
information, failure rate determination, component aging mechanisms, aging management
maintenance activities, equipment upgrades, and replacements. Typical alternative plans for life
cycle management are delineated. The sourcebook includes an extensive list of references.
EPRI Perspective
This reporttogether with the LCM process defined in the EPRI LCM Implementation
Demonstration Project (EPRI 1000806)should enable the preparation of plant-specific LCM
plans for feedwater heaters with substantially less effort and cost than if planners/engineers had
to gather all the generic information themselves. This sourcebook captures both industry
experience and the expertise of the authors related to feedwater heaters. Using this sourcebook,
planners and engineers need only to add plant-specific data and information to complete an
economic evaluation and overall LCM plan for feedwater heaters.
EPRI plans to sponsor additional LCM sourcebooks for other plant SSC types. The process of
using sourcebooks as an aid in preparing LCM plans will improve as the industry gains
experience in this area. EPRI welcomes constructive feedback from users. As EPRI integrates
LCM analysis with development of equipment reliability technology starting in 2004, it also
plans to incorporate lessons learned in future LCM sourcebook revisions.
Keywords
Life cycle management
Aging management
Nuclear asset management
Feedwater heater
Heat exchanger
Tube
System reliability
Component reliability
vi
ACKNOWLEDGMENTS
The technical contributions, review, and comment by the following individuals greatly enhanced
this document and are appreciated:
Patrick Clay, Framatome ANP
Bert Mayer, Framatome ANP
Cliff Munns, Framatome ANP
Mitch McFarland, Framatome ANP
EPRI Expert Reviewers
Alan Grunsky, EPRI
Sharon Parker, EPRI
George Sliter, EPRI
Gary Toman, EPRI
vii
CONTENTS
2.2
2.3
Basis for Selection of Feedwater Heaters for an LCM Sourcebook ........................... 2-1
3.2
3.3
3.4
4.1.1
4.1.2
4.1.3
Maintenance Rule............................................................................................4-12
4.1.4
4.2
4.2.1
4.2.2
4.2.3
4.2.4
4.3
4.4
4.5
ix
5.1.1 Feedwater Heater Condition Reviews (Work Orders, Failures Trends, Lost
Power Generation, Trips, Preventive Repairs, Replacements, Refurbishments) ............ 5-2
5.1.2
5.2
5.3
5.4
5.4.1
5.2.4
5.5
5.6
5.6.1
5.6.2
Tube Repair.....................................................................................................5-20
5.6.3
5.6.4
5.6.5
5.6.6
5.6.7
5.7
Heater Access..........................................................................................................5-24
6.2
6.3
6.4
Plant Operating Strategies and Types of LCM Planning Alternatives ........................ 7-1
7.1.1
Plant Strategy 1: Operate plant for currently licensed period of 40 years......... 7-1
7.1.2
Plant Strategy 2: Operate plant for 60 years with license renewal.................... 7-2
7.2
7.3
7.3.1
7.3.2
7.3.3
7.3.4
7.3.5
7.4
xi
LIST OF FIGURES
Figure 2-1 (a) LCM Planning Flowchart SSC Categorization and Selection ......................... 2-3
Figure 2-1 (b) LCM Planning Flowchart Technical and Economic Evaluation ....................... 2-4
Figure 2-1 (c) LCM Planning Flowchart Implementation....................................................... 2-5
Figure 3-1 Basic Outline of Plant Feedwater Heater Arrangement (items 1 through 6 are
the feedwater heaters)..................................................................................................... 3-2
Figure 3-2 Cutaway View of a Typical Feedwater Heater (double-zone) ................................. 3-3
Figure 3-3 Single Zone Feedwater Heater .............................................................................. 3-4
Figure 3-4 Double Zone Feedwater Heater ............................................................................. 3-4
Figure 3-5 Long and Short Drains Cooler Outline.................................................................... 3-6
Figure 3-6 Vertical Channel-Down Feedwater Heater (showing condensing and subcooling zones) ................................................................................................................. 3-8
Figure 3-7 Vertical Channel-Up Feedwater Heater.................................................................. 3-9
Figure 3-8 Bolted Pass Partition.............................................................................................3-11
Figure 3-9 Welded Pass Partition...........................................................................................3-12
Figure 4-1 SYSMON Access Screen System 18 Extraction Steam, Feedwater
Heaters & Drains ............................................................................................................4-12
Figure 4-2 SYSMON Outline Plan ..........................................................................................4-13
Figure 5-1 Eddy Current Flowchart (from EPRI 1003470) ....................................................... 5-8
Figure 5-2 Summary of FW Heater Problems and Possible Causes (from EPRI 1003470) ....5-16
xiii
LIST OF TABLES
Table 4-1 Frequency of Initiating Events for Plant Faults ........................................................ 4-3
Table 4-2 Summary of Industry Database Search Results for FW Heaters (Operating
Experience) ....................................................................................................................4-11
Table 4-3 Feedwater Heater PM Basis Template...................................................................4-15
Table 4-4 Failure Locations, Degradation Mechanisms, and PM Strategies...........................4-16
Table 4-5 LER Evaluation (from INPO SEE-IN database) ......................................................4-21
Table 4-6 NPRDS Feedwater Heater Search Results - Summary ..........................................4-23
Table 4-7 NPRDS Feedwater Heater Search Results Specific Components and
Consequences ...............................................................................................................4-24
Table 4-8 EPIX System/Component Search Results for Feedwater Heaters..........................4-25
Table 4-9 EPIX Word Search Results for Feedwater Heaters (unique items).........................4-26
Table 4-10 Damage Incidence for FW Heaters (Fossil) From Survey (EPRI 7417) .............4-27
Table 4-11 Operating Experience Data for FW Heater Failure Rate Determination................4-31
Table 5-1 Feedwater Heater Responses (to plant changes) from EPRI TR-107422-V1 ......5-14
Table 5-2 Troubleshooting Feedwater Heater Problems (from EPRI 1003470) ......................5-15
Table 5-3 Recommended Spart Parts for FW Heaters (from EPRI 1003470) .........................5-23
Table 6-1 FW Heater Summary Aging Mechanisms & Effects.............................................. 6-2
Table 6-2 Application of Obsolescence Evaluation Criteria ..................................................... 6-7
Table 7-1 FW Heater Composite Evaluation for LCM Planning (generic) ................................ 7-6
xv
1
EXECUTIVE SUMMARY
This Life Cycle Management (LCM) Planning Sourcebook for feedwater heaters will help plant
engineers and/or expert consultants in preparing a life cycle management plan (a long-term
reliability plan) for the feedwater heaters at their plant. The generic information and guidance
presented in this document are expected to help plant engineers focus on areas where there may
be significant opportunities for cost-effective improvements in long-term plans. Use of this
sourcebook will help reduce the cost of preparing a plant-specific LCM plan for feedwater
heaters.
Guidance consists mainly of generic industry information, data, and references on feedwater
heaters. This sourcebook identifies component aging mechanisms together with the maintenance
activities to manage them, as well as any applicable obsolescence issues and available
management options. Guidance is provided on how to build alternative LCM plans that can be
considered for long-term planning for the critical components in the system. This sourcebook
provides sample generic LCM plan alternatives to serve as starting points for plant-specific
applications. Depending upon the level of detail desired for the plant-specific LCM plan, the
generic data in this sourcebook may allow plant engineers to identify areas where significant
cost-effective improvements or reductions in maintenance activity can be realized and where
long-term planning for emerging obsolescence issues can be developed.
This sourcebook also contains lessons learned from the LCM Planning Demonstration Project by
providing guidance in the evaluation of plant-specific data, selection of plant operating
strategies, and feasible alternative LCM plans. A comprehensive reference listing is included to
give the utility engineer additional resources for consultation.
In a companion document, the LCM Planning Sourcebook Overview Report (EPRI 1003058)
[Ref. 1], LCM planning process-oriented information is presented as well as additional generic
guidance for the preparation of plant-specific LCM plans. The sourcebook and overview report
are meant to be used in conjunction, with the sourcebook addressing what to evaluate and the
overview report addressing how to evaluate.
The Feedwater Heater reliability issues identified and addressed by this study are :
Executive Summary
The most sensitive components are the tubes, and their expected reliability and lifetime are based
on the material involved. Sections 5 and 6 address these issues. Internals problems are often
identified when the tubes are being inspected, and their failures (erosion, cracking) will often
cause vibration problems leading to tube failure. Problems with FW heater shells (minor cracks
and small areas of thinning) are relatively simple to repair via standard welding techniques if
identified early, but a shell that has lost much of its thickness over a large area is a major
corrective maintenance problem.
The potential candidate approaches for formulating feedwater heater LCM plans as alternatives
are identified in Section 7. These alternatives are options for consideration beyond the plant
current base case for SSC inspection and maintenance. They include the following cases:
Increasing the scope of NDE (more tubes, shell welds, major portions of the shell etc.)
The potential for license renewal will also drive plants to consider when to replace feedwater
heaters, depending upon refurbishment budgets and current heater reliability. The expected
lifetime of stainless steel tubes is approximately 20 years (see Section 6.4 of this sourcebook),
and engineers will need to plan accordingly as they perform LCM planning.
1-2
2
LCM SOURCEBOOK INTRODUCTION
2.1
As indicated in the Life Cycle Management (LCM) Sourcebook Overview Report [Ref. 1], an
LCM sourcebook is a compilation of generic information, data, and guidance an engineer
typically needs to produce a plant-specific LCM plan for a system, structure, or component. The
sourcebook will enable plant engineers or outside experts to develop an LCM plan with
substantially less effort than if starting from scratch. The engineer need only compile and then
add plant-specific data and information to complete an economic evaluation and LCM plan for
the feedwater heaters (the subject of this report).
It must be recognized that not all generic information in a sourcebook applies to every plant.
Designs, layouts, and operational conditions are different from plant to plant. Some of the data
can assist in the establishment of a benchmark when performing plant-specific LCM planning.
The data may also show indicators or precursors to problems not yet experienced at a given unit.
Caution and guidance is therefore provided in the plant-specific guidance sections of this report
(Sections 5, 7, and 8) for the application and use of the generic feedwater heater information.
These sections also contain useful tips and lessons learned from the EPRI LCM Plant
Implementation Demonstration Program [Ref. 2] and various plant-specific LCM plans.
2.2
The process steps for LCM planning are detailed in the EPRI LCM Sourcebook Project
Overview Report [Ref. 1]. The LCM Planning flowcharts in Figures 2-1 through 2-3 of this
feedwater heater sourcebook are the same as Figure 1-1 of the LCM Sourcebook Overview
Report. The chart is segmented into the four elements of the LCM planning process: 1) SSC
categorization/selection, 2) technical evaluation, 3) economic evaluation, and 4) implementation.
Process step numbering has been maintained consistent with the LCM Sourcebook Overview
Report.
2.3
The feedwater heaters were selected for the preparation of an LCM sourcebook by EPRImember utility advisors for the following reasons:
Their technical data are available in a number of previous EPRI technical reports
Improvements in feedwater heater operation directly affect the plant thermal cycle.
Section 3.4 contains further information on the nature of components and their scope with
respect to reliability and LCM planning.
2-2
Figure 2-1
(a) LCM Planning Flowchart SSC Categorization and Selection
2-3
Figure 2-1
(b) LCM Planning Flowchart Technical and Economic Evaluation
2-4
Figure 2-1
(c) LCM Planning Flowchart Implementation
2-5
3
BASIC INFORMATION ON FEEDWATER HEATERS
3.1
Though feedwater heaters are non-safety related, they are important to power generation because
they serve to help optimize plant thermal efficiency. Loss of feedwater heating may impose
severe stress on the plant in terms of increased heat flux in the fuel and increased stress (as well
as associated fatigue) on equipment such as feedwater nozzles, headers, and piping. Loss of
feedwater heating will impact plant thermal performance. Most repairs can be performed online, but do require power reductions and heater isolations. If a Low-Pressure (LP) feedwater
heater must be removed from service, an entire string must be isolated. The remaining string(s)
will then be required to supply the entire feedwater flow requirements. Depending upon the
plant design, the unit may need to be derated to approximately 80% of the rated power. If a
High-Pressure (HP) feedwater heater string is removed from service, the unit may have to be
derated to approximately 50% of rated power to make the necessary repairs. In addition, the
repairs are often conducted in high temperature environments, under cramped conditions and
with high humidity, making working conditions difficult. In terms of power generation and
maintaining capacity factor, feedwater heater operation is very important to nuclear plants, both
financially and with respect to thermal efficiency. Changes in power plant output cause changes
in feedwater heating. The volume of feedwater flow (and the velocity) directly affects the
amount of heat transfer taking place in the feedwater heaters.
The primary references for this section are EPRI 1003470 (Feedwater Heater Maintenance
Guide) [Ref. 11], EPRI NP-4057, Volume 3 (Nuclear Plant Feedwater Heater Handbook) [Ref.
23], and the Heat Exchanger Institute (HEI) Standards for Closed Feedwater Heaters [Ref. 30].
There are a variety of materials used in feedwater heater components. EPRI 1003470 [Ref. 11]
provides a detailed description of these materials and their technical properties, particularly in
Section 8. Typical materials are discussed later in this section. Unless specifically noted, the
information in this sourcebook applies to both PWRs and BWRs equally.
3.2
This Section addresses Step 7 of Figure 2-1a, and provides a brief description of feedwater
heaters and basic information on the feedwater heating systems in typical BWR and PWR
nuclear power plants.
An outline of basic feedwater heater arrangement in a typical plant is shown in Figure 3-1.
3-1
Figure 3-1
Basic Outline of Plant Feedwater Heater Arrangement (items 1 through 6 are the feedwater
heaters)
The purpose of the feedwater heating system is to increase plant thermal efficiency by preheating
the condensate/feedwater prior to its entering the reactor vessel (BWR) or steam generator
(PWR). The system is comprised of various components and controls, which provide the
following functions:
Maintain proper water levels in the feedwater heaters and drains to provide maximum
efficiency of the system.
Provide a flow path for the return of the condensed extraction steam drains to the feedwater
and condensate systems.
Nuclear units require very large feedwater flows. There are generally five or six low-pressure
and one high-pressure heater in each string of feedwater heaters. There may be two or three
complete or partial strings of feedwater heaters. For example, there may be three low-pressure
strings and two high-pressure heater strings for each unit. The numbering of each feedwater
heater varies according to specific plant nomenclature. Some plants use the turbine extraction
th
stage (the steam supply for the heater), such as the 14 stage, etc. Some plants number the
3-2
heaters in numeric order for each string. For the purposes of this sourcebook, nuclear units are
assumed to have between 12 and 21 FW heaters, depending upon design and vintage.
A basic cutaway outline of a typical feedwater heater is shown below.
Figure 3-2
Cutaway View of a Typical Feedwater Heater (double-zone)
The feedwater heaters themselves are simply shell-and-tube heat exchangers, whereby the
extraction steam (shell side) is used to heat the feedwater (tube side). The system consists of low
pressure (LP) and high pressure (HP) feedwater heaters. The LP heaters are located on the
suction side of the feedwater pumps and are used to heat condensate from the condenser hotwell
before the water enters the feedwater pumps. The HP heaters are located on the discharge side of
the feedwater pumps and are used to further heat the feedwater before it enters the reactor vessel
(BWR) or the steam generators (PWR). The extraction steam system removes steam from
various points on the HP and LP turbines for use in preheating the condensate and feedwater to
improve overall thermal cycle efficiency. The condensate drained from the HP heaters is used
along with the extraction steam from the LP turbine to heat the feedwater in the LP heaters.
Some LP feedwater heaters are actually located in the condenser neck. Most BWRs are arranged
to cascade all heater drains back to the condenser, allowing the condensate to be demineralized
prior to being returned to the reactor vessel (as feedwater). Conversely, PWRs typically pump
part of the higher-stage heater drains flow forward to the next higher stage heater (see Fig. 3-1).
Nuclear plant high pressure feedwater heaters are generally of the two-zone design (condensing
and drains subcooling zones). Nuclear plant low pressure feedwater heaters are generally either
two-zone or single-zone (condensing only). Most feedwater heaters are oriented horizontally,
but some plants use vertically-oriented heaters, especially in plants with limited floor space.
BWRs are more likely to have vertically-oriented feedwater heaters.
The main portions of a typical feedwater heater are as follows: the channel, the condensing
zone, and the drains subcooling zone. The channel portion provides for the feedwater inlet and
outlet nozzles. There are two types of channel design configurations: full access and manway
3-3
access designs. The elliptical head and hemispherical head are manway access designs, and the
bolted removable cover and removable cover with a full opening are full access designs.
Channels are designed to minimize the effects of erosion on the tubesheet and to provide
convenient access for tubesheet plugging and other related maintenance. Channels also provide
a surge chamber that allows the feedwater flow to achieve a more uniform flow distribution
before entering the tubes. These portions of a feedwater heater are shown (as outlines) in
Figures 3-3 and 3-4, below.
Figure 3-3
Single Zone Feedwater Heater
Figure 3-4
Double Zone Feedwater Heater
3-4
The condensing zone is the largest zone in the feedwater heater. Steam is condensed as it
traverses through the condensing zone and passes over the tubes carrying the feedwater. Drains
from higher-pressure feedwater heaters flow into the condensing zone from the drains inlet
nozzle (the drains cascade to the upstream heater, which is a lower pressure heater). An
impingement plate is installed just inside this nozzle to protect the tubes from these flashing
drains. The vent system typically consists of one or more perforated vent pipes installed along
the length of the tube bundle. Many other designs are also used to accomplish this function.
Non-condensible gases collect in these pipes and then pass through shell vent connections to the
dearator of the main condenser, and are vented. BWR unit feedwater heater vent capacity is
usually higher due to the radioactive hydrogen and oxygen produced in the reactor.
The most common method of subcooling nuclear power plant feedwater heater drains is to
provide the feedwater heater with a full-pass partial-length drain subcooling zone (see Figure 3-5
for a view of the short and long drains cooler designs). This zone is designed to achieve crossflow of the drains on the outside of the tubes (which carry the feedwater). The cross-flow design
maximizes the heat transfer rate because the film coefficient is reduced by the perpendicular
flow.
In the horizontal heater, the full-pass short-end design requires the use of a siphon between the
nominal level in the heater in the condensing zone and the flooded level of the drain cooler zone.
This siphon results in a pressure lower than the shell pressure all around the inside of the drain
cooler zone shroud. In addition, it requires that a minimum pressure drop exist across the
entrance to the drain cooler zone to avoid flashing. The velocities through the shell side of the
drain cooler zone must be minimized to keep the pressure drop low in order to avoid tube
vibration.
In the long drain cooler design (Figure 3-5), the entire drain cooler shroud is flooded and there is
no pressure differential. In addition, a siphon is not required to reduce the possibility of flashing.
The long and short drain designs are shown in the following figures.
3-5
Long Drains
Short Drains
Figure 3-5
Long and Short Drains Cooler Outline
The pressure drop through the full-length drains cooler zone, for the same given fluid velocity, is
greater than the pressure drop through the short-end cooler zone (due to the greater length).
Feedwater heaters can be classified based on orientation: horizontal, vertical channel-up, or
vertical channel-down (see Figures 3-6 and 3-7 for the vertical orientation). The majority of
nuclear plant heaters are horizontal, while the majority of fossil heaters are vertical [Ref. 11]. A
vertical feedwater heater has considerably less fluid capacitance (volume of liquid contained in a
unit level change) than a horizontal feedwater heater. In some cases, for channel-down
applications, the shell of the heat exchanger is enlarged to increase the capacitance (sometimes
called a belly band). This design change has also been made to original equipment at some
plants. Considerations for vertical FW heaters involve proper distribution of steam and
condensate within the shell.
A vertical channel-up feedwater heater that includes drains cooling is subject to difficulties with
flashing during varying flow conditions (i.e., changes in plant load). In this design, the drains
cooler shrouding encloses several rows of tubes, and water level is maintained at the U-bend end
3-6
of the shell. These drains must be lifted to the top of the unit, and the potential for flashing is
high.
A horizontal heater provides more drains storage capacity, is easier to maintain, and requires
more floor space (and supports). A vertical channel-up heater uses less floor space, has
problems in the drains cooler zone design, is difficult to maintain, and is unable to have water
drained from the tubes. A vertical channel-down heater uses less floor space, has problems with
the drains cooler zone design, and is the most difficult heater to maintain. Appendix B of the
Heat Exchange Institute (HEI) Closed Feedwater Heater Standards [Ref. 30] provides a detailed
description of vertical feedwater heater issues.
The feedwater heaters are controlled by a series of level controllers and other instrumentation
controlling the vents, drains, and pumps. Feedwater heater controls have been addressed in a
separate EPRI LCM sourcebook, EPRI 1007425 [Ref. 6]. It is important to note that the level
within a feedwater heater is not the same at all locations along the tube length. The level can
vary, depending upon the position of the steam inlet (or inlets), the design of the internals, and
the flow through the unit. The level can vary significantly from the tubesheet to the U-tube end
of the heater, especially if the drain cooler velocities are high. Maintaining a suitable level at the
drain cooling zone inlet on short-end designs (operating under a siphon) is essential, in order to
prevent flashing and subsequent erosion/damage. It is especially important to maintain the level
well above the entrance at all times. The short-end drains cooler is capable of satisfactory
performance if properly designed and operated, but it does offer more of a challenge than the
long drains cooling design (due to the smaller space and therefore more sensitive parameter
control). Accurate knowledge of the liquid level is very important in the drains cooling zone of
any applicable feedwater heater.
The following figures show the vertical channel-down and the vertical channel-up configuration
for feedwater heaters. Further discussion about the unique difficulties associated with vertical
feedwater heaters is also found in EPRI 1003470, Appendix B (which addresses heaters in fossil
plants).
3-7
Figure 3-6
Vertical Channel-Down Feedwater Heater (showing condensing and sub-cooling zones)
3-8
Figure 3-7
Vertical Channel-Up Feedwater Heater
3-9
The feedwater heaters contain a number of sub-components (which are addressed in this report),
including tubes, tubesheets, baffles, shield plates (or impingement plates), tube tie rods and
spacers, tube supports, the drain nozzles, and the steam inlet and outlet nozzles. The heat
exchanger shell is an ASME pressure vessel and houses all the internals. The channel head is
removable so that access to the tubes and tubesheet can be provided. The tubes are typically Utubes which allow a double-pass for the feedwater through the shell. The components (and subcomponents) detailed in this report are as follows:
Shell
Tubesheet
Tubes
Vents
Nozzles
The shell is a pressure vessel that provides support for the feedwater heater internal components
and allows for the distribution of the extraction steam with a negligible pressure loss. The shell
is a level control reservoir for the heater drains system. The shell also acts as a cooler for the
condensed steam.
The channel serves as the inlet plenum for the feedwater/condensate into the heat exchanger.
The channel acts to redirect the flow from one tube pass to the next. The shape of the channel is
dictated by the feedwater pressure and by tube end accessibility considerations.
The pass partition divides the channel into feedwater inlet and outlet passes. There are three
types of pass partitions: welded, bolted, and floating. The pass partition cover can be welded or
bolted, depending upon maintenance access concerns. During plant operation, one half of the
channel is hotter than the other half. The radial growth of the hotter side is greater than the
colder side due to thermal expansion. This effect results in bending stresses at the pass partition
weld junction. Over time, cyclical pressure and thermal stress may lead to cracking around the
perimeter of the pass partition. A floating pass partition is welded only to the tubesheet face and
to the feedwater outlet nozzle. This is the most flexible design, and is used to reduce stresses in
the channel and the channel-to-tubesheet connection. Figures 3-8 and 3-9 show bolted and
welded pass partitions.
3-10
Figure 3-8
Bolted Pass Partition
3-11
Figure 3-9
Welded Pass Partition
The tubesheet is a plate with holes drilled in it for the tubes. Some tubesheet holes have tube
hole grooves that increase the holding force of the expanded tubes. Low-pressure feedwater
heaters tubesheets are generally composed of carbon steel plate, while high-pressure heater
tubesheets are generally composed of forged carbon steel. The tubesheets of nuclear highpressure heaters are typically 10-15 inches thick. Low-pressure tubesheets are typically 6-10
inches thick. Nuclear plant high-pressure heater tubes are always seal welded and roller
expanded to the tubesheet. Low-pressure heater tubes for PWRs are typically roller expanded to
a sufficient depth to meet ASME requirements, while the low-pressure tubes for BWRs are
generally welded due to access limits associated with the anticipated high radioactivity levels.
The tube design pressure is required by ASME and other governing codes to be equal to or
greater than the maximum normal pressure that will be experienced during operation. The
design minimum tube wall thickness for U-tube stainless steel is 0.035 inches and 0.028 inches
for straight stainless steel tubes. The minimum radius of the U-bends should be 1.5 times the
tube diameter.
3-12
Baffles and tube support plates are pinned supports for the tubes (in the shell). When properly
designed, the support plates can prevent damage to the tubes from excessive vibration. The
baffles direct the flow through the bundle. Baffles are used in the drains cooler zone to increase
the rate of single-phase heat transfer.
The shell relief valve is designed to protect the shell when the tube design pressure is greater
than the shell design pressure. The relief valve protects the shell in the case of tube or tubesheet
failure. BWRs must have a design to prevent a general discharge to the plant. The relief valve
should be sized to take the flow of one clean heater tube rupture (two open ends discharging
feedwater).
The vents on a feedwater heater remove non-condensible gases from the shell and tube side of
the heater during start-up and normal operation.
There are inlet and outlet nozzles on feedwater heaters for the connections to the feedwater
piping, the heater drains piping, the extraction steam piping, vent lines, and relief valves. There
are also instrument taps (as necessary). In addition, there are other appurtenances to the shell,
such as manways, flanges, hand-holds, lifting lugs, etc., but except for leakage events, these are
not addressed in this report.
These individual items are discussed in detail in EPRI 1003470 (Feedwater Heater Maintenance
Guide) [Ref. 11] and in EPRI NP-4057, Volumes 1-3 (Nuclear Plant Feedwater Heater
Handbook) [23]. Much of the information and most of the figures in this LCM Planning
Sourcebook were taken from these two references.
The normal flow path for the feedwater in a nuclear power plant is typically described in the
following steps:
Condensate flows from the condensate demineralizers through the tubes of the fifth and
fourth point drain coolers.
The condensate flows through the tubes of the sixth through the second point heaters (in that
order).
The feedwater flows through the first point heater through to the reactor (BWR) or steam
generators (PWR).
Both the first- and second-point feedwater heaters (high-pressure heaters) typically have inlet
and outlet motor-operated isolation valves. Each of these two feedwater heaters has a bypass
line with a motor-operated isolation valve.
The feedwater is successively heated by extraction steam, starting with low pressure saturated
steam from the LP turbine to the sixth-point feedwater heater. Higher pressure saturated
extraction steam is used for subsequent feedwater heaters. The first-point feedwater heater
receives high pressure saturated extraction steam from one of the stages of the HP turbine.
Different plants use different numbering systems when classifying their feedwater heaters, such
3-13
that heater #1 is the first heater after the condensate pumps and heater #6 (for example) is the
closest to the steam generators (or the reactor vessel).
As outlined in Figure 3-1, extraction steam from the HP and LP turbines is sent to the shell side
of the feedwater heaters. As heat energy from the extraction steam is transferred to the
feedwater (which flows in the tubes), the steam is condensed and is collected in the drain
receiver (at the bottom of the feedwater heater). The energy given up to the feedwater causes the
steam to condense and collect. The drain path depends upon the location of the heater or drain
receiver in the heater string. The typical drain paths are shown in Figure 3-1. As previously
mentioned, for BWRs, the drain path for all the FW heaters is typically directly back to the
condenser, while for PWRs, the drain path is often forward to next higher-stage heater.
Drain flow paths, water levels, FW heater controls, and interlocks are discussed in further detail
in EPRI 1007425 (LCM Planning Sourcebook, Vol.6: Feedwater Heater Controls) [Ref. 6].
3.3
Considering the flowpath to be condensate to feedwater, the feedwater heaters are bounded on
the upstream side by the condensate system and also the extraction steam (sub-)system. The
downstream boundary is the feedwater system itself - prior to the FW isolation valves to the
reactor [BWR] or the steam generators [PWR]. The heater drains system also forms part of the
downstream boundary (for the drain flow back into the condenser). The low-pressure heaters are
typically part of the condensate system and the high-pressure heaters are typically part of the
feedwater system. Differences from one plant to the next may exist with respect to the actual
piping boundaries and system titles. Differences also exist between BWR and PWR plants,
although with respect to the feedwater heaters themselves, the shell and tube design is the same.
Figure 3-1 shows the typical outline for the feedwater heater arrangement.
3.4
Per the guidance contained in INPO document AP-913, Equipment Reliability Process
[Ref.32], if a failure of a component or its structural supports defeats or degrades an important
function or a function that is redundant to an important function, then it is considered a critical
component. As discussed in Section 3.1, feedwater heaters are not safety-related, so the critical
nature of the feedwater heater components is related to their importance for plant productivity.
The scope of this report includes only the passive mechanical components and sub-components
of nuclear plant feedwater heaters. The scope covers the most common mechanical components
contained in feedwater heaters found in both BWRs and PWRs. These include:
Shell
Tubes
Tubesheet
Tube-to-Tubesheet Joints
3-14
Tube Supports
Baffles
Impingement Plates
Nozzles
Vents
Active components such as instrumentation, controls, and valves, are excluded. Feedwater
heater controls are addressed separately in EPRI report 1007425 [Ref. 6]. Non-metallic
materials, such as insulation and gaskets, are not addressed by this sourcebook. In addition, FW
heater supports are considered to be structural components, and are not addressed by this
sourcebook.
The tubes are the most vulnerable component with respect to damage and are of the highest
concern with respect to surveillance and maintenance, so they are considered the most critical
components. As discussed in Section 4, erosion and wall thinning in FW heater shells has also
been observed, and one event (in 1999) involved the catastrophic rupture of a FW heater shell
due to erosion. Other heater damage has been noted due to cracked or broken impingement
plates or baffles (or end supports). Most of the surveillance and maintenance focus is on the
tubes, but the other components will be addressed as well (see Section 5 for a review of
condition monitoring and repair techniques).
3-15
4
HISTORICAL PERFORMANCE DATA FROM INDUSTRY
OPERATING EXPERIENCE
This section addresses Step 9 in the LCM planning flowchart (Figure 2-1b). The information
compiled in this section is to be used for a comparison or benchmark of plant-specific conditions
and operating experience. The qualitative data is intended as a checklist of potential conditions
affecting plant-specific performance, while the quantitative failure data may provide insight into
the potential for plant-specific enhancements and may help identify where improvements can be
made. For example, if the plant-specific component failures are much lower (e.g., by a factor of
3) than the generic data indicates, then one might conclude that the existing maintenance plan is
effective and that further improvements will be difficult to achieve. On the other hand, the
discrepancy between realized and industry typical failure rates might suggest that the current
maintenance on the equipment could be relaxed if high reliability is viewed as the result of
excessive maintenance practices that are not cost-effective.
Similarly, if the plant-specific component failure rates are substantially higher than the generic
industry failure rates presented in this section, or if the contribution of feedwater heaters to lost
power production significantly exceeds the generic values (for BWRs and PWRs), then
equipment replacement or major changes to current maintenance practices might be needed.
Also, if the reliability of an SSC falls below a certain level, replacement or other major
maintenance efforts will be required to satisfy Maintenance Rule performance criteria.
It should be noted that this section addresses failures and failure data rather than repair practices
and data. Some repair (and maintenance) techniques will be mentioned, but, in general, repair
times will be available from specific plant records and will depend upon plant-specific
maintenance practices. Monitoring techniques are addressed in Section 5. The Mean-Time-ToRepair (MTTR) will have an impact on system availability (with respect to the Maintenance
Rule). A further discussion of specific maintenance (preventive or repair) and troubleshooting is
found in Section 5.
Computing (or estimating) failure rates for components is not an exact science. Hundreds,
sometimes thousands, of event reports must be reviewed to determine which items are to be
directly characterized as failures for the components under review. In addition, for a subject like
feedwater heaters, the term failure will not mean the same thing among different utilities. Unlike
electronic components (instrumentation), which are replaced when they fail (and are relatively
easy to benchmark), many instances of feedwater heater failure are repaired without direct
component replacement. A catastrophic failure of a shell is obviously a failure. However, the
plugging of a single tube (possibly including adjacent tubes as insurance) may not be considered
a failure, but just good preventive maintenance.
4-1
Because these events are characterized differently by different plants, any failure rate which is
estimated from INPO failure data (i.e., EPIX) is going to be lower than a true failure rate
experienced in the field. Likewise, some FW heaters may be inspected and/or repaired when the
plant is shut down for other reasons, and items identified during such work may not be classified
as failures, even though corrective maintenance is needed. Also, there are significant differences
between EPIX and NPRDS reports these differences are discussed in Sections 4.1.2 and 4.2.3.
There is a large amount of data from various sources related to industry experience presented in
Section 4 of this sourcebook; this data is tabulated and evaluated in the appropriate sub-sections,
and is summarized in Section 4.5, where the generic industry failure rate for FW heaters is
addressed. Section 4.5 presents the failure rate values necessary for unit-specific LCM planning.
4.1
This section contains information on failure data and the associated failure mechanisms for
nuclear power plant feedwater heaters. The information is presented in two forms: qualitative
and quantitative. The qualitative information describes the degradation mechanisms and effects
that apply to nuclear plant feedwater heaters, while the quantitative information identifies
industry failures and failure mechanisms (by listing specific events). The quantitative
information may be used to determine a generic industry failure rate, although subject to
uncertainty. The listing of the failures may be used to provide an understanding of the industry
experience as system and component engineers at specific plants evaluate LCM planning for
feedwater heaters at their units. The listing of events is detailed for each source where the
information was found, and is presented to highlight the applicable feedwater heater subcomponent involved (shell, tubes, baffles, shield plates, etc.). EPRI 1007425 (Life Cycle
Management Planning Sourcebooks, Volume 6: Feedwater Heater Controls) [Ref. 6] presents
this information for feedwater heater controls, so any problems with instrumentation and control
schemes will be listed there.
A comprehensive review of the available industry operating experience has been done to extract
the salient information and to present the data that the plant system or component engineer may
utilize in assessing the plant-specific performance of a feedwater heater. A variety of industry
databases were reviewed to identify problems that have been reported with feedwater heaters at
nuclear power plants. The industry sources used in this review include EPRI (previous technical
reports), INPO (EPIX/NPRDS), and NRC. The primary EPRI technical report referenced in this
Section is EPRI 1003470 (Feedwater Heater Maintenance Guide) [Ref. 11]. To begin the
operating experience review, the proper place is to consider system failure contributions to plant
events. This information is available in NUREG/CR-5750 [Ref. 41], with the understanding that
this reference uses the words fault, failure, transient, and initiating event in generally the
same sense (in conflict with the typical safety analysis usage of these terms).
To provide an industry benchmark for generic historical SSC performance used in nuclear plant
PRA analysis, the NRC conducted a review of industry-wide plant initiating events for the period
1987-1995 (from NUREG/CR-5750) [Ref. 41]. The relevant data for the initial plant faults from
this report are tabulated separately for BWRs and PWRs in Table 4-1. Assuming that each fault
contributes equally to plant shutdowns (i.e., all plant trips are considered equivalent fault or
failure events with respect to consideration as data points), an estimate of the percentage of total
plant failures contributed by a specific SSC may be estimated. The table shows this system
contribution factor, on such a percentage basis.
4-2
This average generic SSC contribution can be used as an initial generic benchmark for the SSCspecific sourcebook (as a first step in the determination of an industry failure rate). These
factors, after comparison with plant-specific SSC failure rates, can be used in economic analysis
calculations to determine the impact on lost power generation attributed to the SSC under
review. For SSCs not represented in Table 4-1, it may be assumed that the generic industry
failure rate is negligible with respect to lost power generation. For feedwater heaters, the data
must be evaluated carefully because they are not specifically mentioned as a separate component,
but (as the table shows) feedwater problems are one of the leading items causing plant faults.
The following table presents data from NUREG/CR-5750 [Ref. 41], which compiled information
on the rates of initiating events for US nuclear units from 1987-1995. The data is based
primarily on operating experience derived from Licensee Event Reports. While the table does
not explicitly address feedwater heaters, it is clear that feedwater problems represent a significant
contribution factor (approximately 19% in BWRs and approximately 27% in PWRs) towards
plant faults (transients). If the loss of condensate flow is also considered, the percentages rise
almost another 3%.
Table 4-1
Frequency of Initiating Events for Plant Faults
SYSTEM-CATEGORY
ALL EVENTS
LOSS OF OFFSITE POWER
Contribution %
Factor
BWR 658
PWR 1327
BWR 100
PWR 100
13
0.607
0.980
1.060
0.226
LOSS OF IAS
13
13
1.976
0.980
FIRE
10
21
1.520
1.583
16
2.432
0.377
27
13
4.103
0.980
24
62
3.647
4.672
20
0.760
1.507
12
19
1.824
1.432
16
34
2.432
2.562
11
36
1.672
2.713
45
240
6.839
18.086
PARTIAL/TOTAL LOSS OF
CONDENSATE FLOW
18
36
2.736
2.713
EXCESSIVE FEEDWATER
49
61
7.447
4.597
64
132
9.726
9.947
REACTIVITY IMBALANCE
88
0.912
6.631
TURBINE TRIPS
173
284
26.292
21.402
55
48
8.359
3.617
SPURIOUS SSAs
14
22
2.128
1.658
OTHER TRIPS
89
177
13.523
13.338
4-3
Note that the word fault in this table does not automatically refer to an accident event, but
rather to an initial plant transient (see Table 2-1 of NUREG/CR-5750 for an outline of all faults
evaluated in the report). Some of them are accident events and some are just general transients.
NUREG/CR-5750 evaluates both.
As noted in the discussion on LERs, probably only a small number of these events (or faults) are
directly related to feedwater heaters. Other issues (valve problems, drain problems, feedwater
pump and feedwater recirculation problems) predominate, but some of these events are related to
feedwater heaters. When considering feedwater heater failure rates and the impact to overall
plant operation, it should be remembered that the greatest negative impact that feedwater heater
performance can have on the plant is the cost of replacement power (for a sudden component
failure). Feedwater heater repairs involve detailed and often difficult maintenance evolutions,
and replacement of a feedwater heater tube bundle or of the heater itself is considered only as a
last resort, once other options have been exhausted (tube plugging, sleeving, etc.).
With respect to this data for LCM planning, one step would be to take the overall FW system
initiating event rate (19% for BWRs and 27% for PWRs), review the plant-specific data to
remove contributions from FW heater controls problems, and then multiply the remaining value
by the number of trips, transients, and power reductions in a given period to determine a rate
specific to feedwater heaters. In order to remove the I&C portion of the FW event data, one
could use the data in Table 4-2, where (with the exception of the NPRDS information), only
about 10% of the failures linked to FW heaters are specific to the heaters themselves.
In summary, the NUREG/CR-5750 data confirms that FW systems and components contribute
significantly to industry productivity losses and warrant the preparation of formal LCM plans.
However, it would be difficult to determine a specific failure rate for feedwater heaters from the
data, and any estimates would have a large uncertainty range. Other information has been
reviewed to develop an estimated industry generic failure rate for feedwater heaters, as discussed
later in this section.
4.1.1 Qualitative Data
Qualitative data indicate several different failure modes from different aging/degradation
mechanisms for feedwater heaters. The qualitative data typically list and describe aging
mechanisms and/or effects, and may also describe various types of degradation. In the
terminology of aging management, life cycle management, and license renewal (see, for
example, SAND96-0344, NUREG-1800, or NUREG 1801), an aging mechanism results from
exposure to a stressor, usually an environmental or cyclical condition, and the mechanism causes
an aging effect in the SSC, which leads to degradation and ultimately to failure, in a specific
mode.
In SAND93-7070 [Ref. 7], The Aging Management Guideline for Commercial Nuclear Power
Plants Heat Exchangers, the stressors applicable to heat exchangers in nuclear power plants
are summarized as:
Mechanical
Hydraulic
4-4
Chemical
Electrical
Mechanical stresses primarily involve fabrication issues and piping connection loads. Vibration
and thermal expansion are also considered mechanical issues.
Hydraulic stressors are loads imposed on heat exchanger components as a result of the pressure
and flow of fluid through the heat exchanger. The magnitude of the hydraulic stress is dependent
upon the characteristics of the process fluid, the design parameters of the heat exchanger, and the
severity of operation or duty that the heat exchanger is expected to encounter over its service life.
The fluid pressures exert stress on the heat exchanger shell, nozzles, tubes, tubesheets, channel
heads, and partitions (including impingement plates). Erosion is considered a hydraulic issue.
Process fluids react with the heat exchanger materials (internal components) and, depending
upon the specific mechanical composition, can cause the components to become stressed. This
stress can be localized and/or uniformly distributed throughout the heat exchanger internal
surfaces. The water chemistry issues related to feedwater heaters are discussed in further detail
in Section 5 of this report.
The only electrical stressor for heat exchangers is galvanic corrosion resulting from a coupling of
materials remote from one another on the galvanic series chart (anode to cathode). Galvanic
corrosion is addressed in EPRI 1003470 [Ref. 11]. For the purposes of this report, it is not
considered to be a major degradation mechanism, because dissimilar metal couples are only
occasionally used in power plant functions (EPRI CS-3184) [Ref. 25]. Industry experience with
galvanic corrosion in feedwater heaters is limited.
The environmental stressors are detailed as follows: thermal stressors involve internal process
fluid temperature effects on heat exchanger components, moisture stressors involve external
humidity effects on the applicable heat exchanger components, and radiation stressors involve
the cumulative radiation effects on the applicable heat exchanger components. These stressors
are not considered as significant (particularly in comparison with the degradation mechanisms
and effects resulting from the mechanical, hydraulic, and chemical stressors). The aging
mechanisms and effects (i.e., the categories of problems) resulting from the important stressors
are summarized as follows (from Tables 1-5 and 2-2 of the Heat Exchanger AMG):
Fatigue
Corrosion
Erosion
Embrittlement
Wear
Stress Relaxation
4-5
Creep
Fouling
In the text of the report (SAND93-7070, also the Heat Exchanger AMG), some of these aging
mechanisms and their sub-types are dismissed as non-significant (thermal embrittlement, creep,
thermal fatigue, irradiation-assisted stress corrosion, and neutron embrittlement). The remaining
categories are included for evaluation in the AMG. It should be noted that the scope of the Heat
Exchanger AMG does not include feedwater heaters, and steam is not addressed as a shell-side
fluid. But the principal discussions related to shell-and-tube heat exchangers are the same for
feedwater heaters, and the evaluations in the Heat Exchanger AMG provide an introduction into
other industry technical reports on feedwater heater maintenance, operation, and problem/failure
review. Note that fouling, while an important subject in the Heat Exchanger AMG and in other
general heat exchanger technical reports (such as EPRI NP-7552 [Ref. 16]), is not a serious
concern for feedwater heaters because the feedwater is boiler-quality water with strict chemistry
controls (as opposed to raw or filtered water, which is used in many critical heat exchangers in a
nuclear plant). Fouling is not a significant degradation mechanism for feedwater heaters.
The Heat Exchanger AMG details the sub-components in the following groupings (from Table 32 of the report):
Tubes / Coils
Tube Sheets
The Heat Exchanger AMG details typical heat exchanger materials as follows (Table 3-3):
Tubes / Coils
Tube Sheets
Baffle Plates
Divider Plates
Fasteners
This breakdown compares well with previous EPRI analysis of feedwater heaters. For example,
EPRI CS-1776 (Failure Cause Analysis Feedwater Heaters) [Ref. 18] details feedwater heater
problems in the following categories (from Table 2-1):
4-6
Steam Impingement
Tube Vibration
Corrosion
Unknown
Internal Failure
Tube Defects
The focus of this EPRI report was on fossil units, but the issues are the same for nuclear units.
The primary difference between feedwater heaters in fossil units and those in nuclear units is that
the fossil units typically have superheated steam and the nuclear units do not. Therefore, the
fossil units must have a de-superheating zone, which is not addressed in this sourcebook.
In EPRI NP-4057, Vol. 3, (Nuclear Plant Feedwater Heater Handbook) [Ref. 23], the problems
with feedwater heaters are summarized as follows (from Section 3):
Problems in the Condensing Zone
High Velocity Wet Steam Causing Erosion of Shells and Support Plates
Erosion of Tubes and/or Baffle Plates Resulting from Inadequate Water Level and/or
Inadequate Anti-Vortexing Design
High Drain Cooler Velocity Causing Vibration Damage, Baffle Plate Erosion
High Drain Cooler Velocity Resulting from Excessive Duty (i.e., a lower pressure FW heater
being isolated)
Carbon Steel
Admiralty Brass
Copper-Nickel Alloys
Titanium
In EPRI 1003470 (Feedwater Heater Maintenance Guide) [Ref. 11], the feedwater heater
problems are categorized as follows:
Vibration
Vibration is further broken down to address two flow-induced excitation mechanisms which
affect feedwater heater tubes: vortex shedding and fluidelastic whirling. The common tube
damage from vibration is labeled as follows: fretting, collision, and cracking.
In summary, it is clear that the environments and operating conditions in which feedwater
heaters operate can cause significant problems such as fatigue, erosion, corrosion, cracking, and
vibration. If not properly monitored, inspected, and maintained, the feedwater heaters will incur
damage over time, causing a negative impact to plant efficiency. The following section of this
report outlines specific numerical industry data on feedwater heater problems and failures.
4.1.2 Quantitative Data (EPRI, INPO EPIX/NPRDS, NRC)
Quantitative failure data is available for feedwater heaters, their structures, and their components
from a number of sources such as EPRI, INPO (EPIX/NPRDS, Plant Events database, O&MR,
SEE-IN, and LER), and NRC (LER and Generic Communications). It should be recognized that
such quantitative data has often been gathered for risk assessment or other safety-related
evaluations. As such, the data tends to reflect functional failures rather than degradation failures
(or discoveries), even though the degradation may reflect chronic problems and should be the
primary focus of maintenance activities. It should also be noted that not all component failures
at all plants are going to be listed in generic industry databases (i.e., this search cannot be
considered exhaustive). The NPRDS database covers events/items from approximately late 1976
to late 1996 and the EPIX database (the successor to NPRDS) covers items from 1997 to the
4-8
present. The INPO Plant Events Database contains summaries of events since 1991. Significant
events are further described in the INPO SEE-IN process (under SER, SEN, and SOER). The
NRC ADAMS search covers a period from late 1998 to 2003, with more documents being added
as the database is developed.
As described in the following paragraphs, a refining process is needed to conduct a useful search
of these industry databases. Extraneous items must be removed and actual SSC events must be
addressed.
Searches of the INPO databases (NPRDS, EPIX, and Plant Events) identified many items not
directly associated with feedwater heater components, such as condenser problems, valve
problems, secondary side I&C problems, secondary side piping problems, etc. For example, the
INPO NPRDS search by system (checking the Feedwater, Condensate, and Extraction Steam
systems) and component (checking Heat Exchanger, Condenser, Steam Generator) returned
924 failure records, while the NPRDS word search on feedwater AND heater returned 2076
records. Obviously, many of the word search results involved other equipment (with only a
tangential mention of or connection to feedwater heaters). A review of the first 450 records (out
of the 2076 items) showed that only 157 of these 450 records (~35%) were related to the
component grouping of Heat Exchanger, Condenser, Steam Generator.
The EPIX search results showed a similar pattern: the detailed system/component search listed
38 failure records, while the word search on feedwater AND heater listed 276 records. Most
of these 276 failures did not involve feedwater heaters directly, but the feedwater heaters were
mentioned in the abstract as being affected by or included in the event. One purpose of the
quantitative review is to cull through all this information to present only the data specific to
feedwater heaters. It should be noted that searches of failure data for all Life Cycle Management
studies, no matter what system or component is being reviewed, must employ the same refining
process.
Searches of INPO records for LERs (Licensee Event Reports) show the same pattern, as do
searches of the NRC databases (such as an ADAMS search). With respect to the feedwater
heaters, the search of the INPO LER database (by system - feedwater & condensate, and by
component -heat exchanger) identified 5 LERs for a period covering 1984 to 2003, while the
NRC ADAMS search (a word search keyed to feedwater heater and covering 1999 to 2003)
identified 35 LERs. A search of the INPO SEE-IN records, looking specifically for LERs with
the keywords feedwater heater, identified 281 records from 1984 to 2002. Not all of these
items are actually LERs and not all of them directly relate to the feedwater heaters. So a more
detailed evaluation of the records is necessary to accurately identify items directly related to
feedwater heaters and their sub-components.
In addition, EPRI report 1003470 (Feedwater Heater Maintenance Guide) [Ref. 11] contains a
summary of feedwater heater operating experience. The report states that there were 166 records
found in the NPRDS database for failure items involving feedwater heater shells and internal
components (from 1977 to 1996). The EPIX search described in the report lists 5 items (related
to tube leaks) that were identified (for 1997 to 2001). Although EPRI 1003470 does not
explicitly state it, this total of 171 failure-related items can be characterized as a generic industry
failure rate of 0.0632 feedwater heater failures per plant per year, assuming that there are 104
operating reactors in the US and using a 26-year period (171 divided by 104 divided by 26).
4-9
This value is a general estimate, but it provides a starting point, using applicable industry
information.
Also, EPRI 1003470 [Ref. 11] identified 29 items pertaining directly to feedwater heaters in the
INPO Plant Events database. The breakdown of these items is as follows:
17 events involved inspection and discovery of shell thinning (near the nozzle inlet area)
4-10
Source (Database)
Records Found
in Initial Search
Items Applicable to
FW Heaters
35
281
23
209
47
2076
N/A
924
850
276
27
38
20
32
18
18
Note that the NPRDS items from the keyword search were not reviewed, due to the large amount
of compiled material. The total number is listed here for completeness. Those items found from
the system/component search were reviewed in detail. From the table above, it is clear that the
vast majority of items identified through database searches do not impact the feedwater heaters
and their mechanical components. Only the NPRDS review (for the system/component search)
accurately focused in on the FW heaters themselves. It should be noted that the NPRDS
system/component search was the most comprehensive and detailed search conducted, and it
provided the most useful results. EPIX (the successor to NPRDS) is based more on Maintenance
Rule (10CFR50.65) requirements than NPRDS, meaning that events (failures) in non-safety
systems were not listed as often as in NPRDS. In addition, EPIX items are typically not
identified unless there is a change in plant status (trip, power reduction, etc.). The NPRDS and
EPIX items are addressed in Section 4.2.3.
After a review of these items, those related to feedwater heater mechanical components are
included in the industry generic failure rate estimation. In order to execute successful LCM
planning on feedwater heaters, the items culled from the totals above need to be included as the
operating experience history. Plant-specific operating experience augments this data to estimate
failure rates used in LCM economic evaluations.
4-11
Figure 4-1
SYSMON Access Screen System 18 Extraction Steam, Feedwater Heaters & Drains
4-12
Figure 4-2
SYSMON Outline Plan
4-13
Performance Monitoring
NDE Inspection
Internal Inspection
Operator Rounds
Each task has its own frequency, depending upon criticality, duty cycle, and the severity of the
service conditions. In addition, cleaning and leak testing were also included as separate items
(see Table 4-3).
The template also contains a listing of potential failure locations for the feedwater heaters,
including degradation mechanism and influence (cause). There are 24 separate listings, which
cover the tube joint, the tubesheet, the tubes, the nozzles, the closure devices, and the internal
hardware (plates, supports, etc.). Each of the separate listings is coded for the four tasks detailed
above, in terms of importance.
4-14
The template defines the boundary of the feedwater heater as comprising all components from
nozzle to nozzle, including the shell and internal components, and excluding the control systems
and devices, the relief valves, and the insulation, along with the main steam reheaters (MSR).
The PM template helps to build and/or evaluate the maintenance performed on the feedwater
heaters at any given plant. It provides a quick overview to the system or maintenance engineer
of the minimum recommended maintenance for feedwater heaters. The overall PM Basis
template for tube-type heat exchangers is as follows, with the feedwater heater information
shown. Columns 1 through 8 refer to the different heat exchangers considered in the EPRI
program column 1 represents the high-pressure feedwater heaters and column 3 represents the
low-pressure feedwater heaters. Other heat exchangers addressed by the template include the
Service Water heat exchangers, the Safety Injection oil coolers, the Diesel Generator Jacket
Water heat exchangers and lube oil coolers, the RHR heat exchangers, and various plant area
coolers (including control room A/C).
Table 4-3
Feedwater Heater PM Basis Template
Equipment Description
Critical:
Duty Cycle:
PM Task
Service
Conditions:
Yes
1
(HP)
X
2
X
3
(LP)
X
Low
Severe
X
X
Mild
X
X
No
High
X
X
Performance
Monitoring
Task Interval
1M
1M
NDE Inspection
Task Interval
5Y
5Y
Internal
Inspection
Task Interval
5Y
5Y
Task Interval
2Y
AR
Task Interval
2Y
4Y
External
Inspections
(air-cool only)
Cleaning
Leak Testing
The indicated frequencies are 1 Month, 5 Years, 2 Years, 4 Years, and As Required.
4-15
EPRI TR-106857-V32 [Ref. 19] contains a discussion of each PM task, including information
about possible failure locations for consideration, the progression of the observed degradation,
fault discovery, and the tools and equipment needed for the task. The report also provides
definitions for the terms used in the template (critical, duty cycle, service conditions, etc.). There
is also a detailed discussion about degradation mechanisms for the various sub-components and
possible PM strategies for each item.
The PM strategy to address degradation is outlined in the following table, which lists failure
locations, degradation mechanisms, and the PM strategy for tube-type heat exchangers. Items
related to MIC and fouling are not addressed because they are not as applicable to FW heaters as
other heat exchangers.
Table 4-4
Failure Locations, Degradation Mechanisms, and PM Strategies
Failure
Location
Tubes
Degrad.
Mechanism
Erosion
(internal)
Degrad.
Influence
High flow velocity
Degrad.
Progression
Continuous
Failure
Timing
1
Random
Random
Random
Internal
Inspections
Continuous
Random
Cleaning
Continuous
Random
Continuous or
Random
Continuous
Random
Random
Continuous
Random
2
Random
Foreign Material
Suspended
Solids
Discovery /
Prevention
Eddy Current
Inspection
Cleaning
PM
Strategy
NDE
FAC
Non-uniform
scale deposits
Erosion
(external)
Fluid
impingement
Corrosion:
Foreign Material
Water Chemistry
and Fluid Quality
MIC
Galvanic
Chemical
Tube Materials
Defects
Eddy Current
NDE
Inspection
Perform.
Monitoring
Eddy Current
NDE
P, T
*(these are not
as applicable for
FW Heaters as
other HX)
Manufacturing
Installation
4-16
Random
Random
Random
Cleaning
Internal
Inspections
Inspection
Cleaning
NDE
Eddy Current
Degrad.
Mechanism
Cracking
Degrad.
Influence
Vibration
Degrad.
Progression
Continuous or
Random
Failure
Timing
Random
Fatigue
Discovery /
Prevention
Eddy Current
PM
Strategy
NDE
Inspection
Perform.
Monitoring
Monitoring
Leak Test
Vibration
Inspection
Audible
Noise
Tube Joint
(welded)
Tube Joint
(rolled)
Defect
Defect
Galvanic
Attack
Internals:
Looseness
Baffles,
Supports,
Tie Rods,
Spacers,
Diffusers,
Impingem.
Plates
Tubesheet
Failed
Welds
Improper
Installation
Random
Leak Test
Pressure
Testing
Random
Abusive
Transient
Ultrasonic
Testing
Plugging
Chemistry
Monitoring
Pressure
Testing
Improper
Installation
Random
Random
Abusive
Transient
Ultrasonic
Testing
Plugging
Chemistry
Monitoring
Inspection
Continuous or
Random
Random
Materials
Water Hammer
Random
Random
Vibration
Continuous
Random
Water Chemistry
Audible
Noise
1
Thermal Stress
Continuous
Random
Impingement
(Tube Failure)
Random
Random
Corrosion
Water Chemistry
Random
Random
Cracking
Materials
Plugging
Random
Random
Leak Test
Leak Test
Internal
Inspections
Inspection
Video Insp.
Operator
Rounds
Cathodic
Protection
Internal
Inspections
Inspection
Leak Test
Pressure
Test
Internal
Inspection
Erosion
4-17
Degrad.
Mechanism
FAC
Degrad.
Influence
Flow Rates
Inlet and
Outlet
Nozzles
Corrosion
Water Quality
Failure
Timing
3
Random
Discovery /
Prevention
Inspection
PM
Strategy
Internal
Inspections
UT Thick.
NDE
MIC
*(not as
applicable
for FWH)
Gasket and
O-ring leaks
Closure
Devices
Channel,
Partitions,
Manways,
Flanges
Notes:
1)
2)
3)
Degrad.
Progression
Continuous
Eddy Current
Improper
Installation
Random
Random
Materials
Random
Age
Continuous
(should be
failure free
for 7 yrs.)
Inspection
Thermal
Performance
Perform.
Monitoring
Operator
Rounds
This table should also be used with the consideration of various PM, PdM, and CM schemes
(discussed in Section 5).
4.2
The NRC issues several hundred documents to the public each day. Many of these are specific
to one licensee, but some are intended for the entire industry (or a portion thereof). Generic
Communications are NRC-issued documents which address industry operating experience and
are transmitted to one or more class of licensee. The most typical types of generic
communications include Information Notices, Generic Letters, Information Bulletins, and
Regulatory Issue Summaries. This report details the review of Information Notices, Information
Bulletins, and Generic Letters with respect to feedwater heaters.
Information Notices are issued to provide significant recently identified information about safety,
safeguards, or environmental issues. They do not require a response. Information Bulletins
provide notice of recently identified issues in more detail, and typically they do require a
response. Generic Letters request that addressees: (1) perform analyses or submit descriptions
of proposed corrective actions regarding matters of safety, safeguards, or the environment and
submit in writing that they have complied with the requests with or without prior NRC approval
of the action; (2) submit technical information that the NRC needs to perform its regulatory
function; or (3) submit proposed changes to technical specifications. By a generic letter, the
NRC may also provide licensees with staff technical or policy positions not previously
transmitted or not broadly understood.
The NRC website provides two methods for searching Generic Communications a word search
of the Generic Communications or an ADAMS search.
4-18
As previously listed, a review of NRC generic communications indicated the following items
(with respect to feedwater heaters):
4-19
The INPO SEE-IN LER word search (keyed on feedwater heater) identified 281 items,
covering a period from 1984 to 2003. Of these 281 items, a review indicates that 23 were related
to feedwater heater mechanical components or subcomponents. These items are listed in the
following table.
4-20
Date
Plant
Type
Description
5/14/99
PWR
Steam leak from the rupture of the shellside of the feedwater heater
(combination of steam impingement & flow-accelerated corrosion).
6/18/95
PWR
1/5/95
BWR
11/8/93
BWR
9/22/93
PWR
During the secondary plant response, the piping welds on the inlet of the
feedwater heater relief valves failed.
7/27/93
PWR
During the secondary plant response after the reactor trip, the tube side
relief valve for the feedwater heater ruptured and an upstream small bore
pipe failed at an elbow upstream of the valve.
3/1/93
PWR
10/16/91
BWR
9/12/91
PWR
Reactor at 93% for repair of tube leaks in the low pressure feedwater
heater.
12/15/90
BWR
11/21/90
PWR
One feedwater heater developed a gasket leak due to slight water hammer
resulting from the unit trip. The feedwater heater head bolts were
retorqued to eliminate the leakage.
4/10/90
BWR
Weld failure on the relief valve line on the north feedwater heater.
5/30/89
PWR
9/1/88
PWR
Design deficiency in the feedwater heater which caused it to become "airbound" (originally intended to have a continuous operating vent, but the
vent was never installed).
4/30/88
PWR
Sludge-lancing and crevice flushing were done to reduce the sludge and
remove to contaminants from the tubesheet crevice.
To reduce the caustic environment in the tube crevice and prevent tube
support plate denting, a secondary system boric acid addition program has
been implemented.
4-21
Date
Plant
Type
Description
2/4/87
PWR
12/30/86
BWR
7/2/86
PWR
A cracked weld on the high pressure feedwater heater relief valve piping
that resulted from overpressurization.
4/24/86
BWR
Through-wall failure in the 6th stage feedwater heater extraction steam line
at the downstream reducer leading to the 6th stage feedwater heater. The
failure was caused by wet steam erosion.
5/31/85
PWR
12/11/84
PWR
11/28/84
PWR
5/5/84
PWR
Feedwater heater was later determined to have leaking tubes which were
plugged.
4/18/84
PWR
Feedwater heater was inspected and found to have one (1) leaking tube
and thirty-one (31) leaking tube plugs.
Most of the remaining items dealt with feedwater heater controls and other secondary side
problems (pipe failures, turbine and condenser problems, etc.). The 23 items identified in the
LER database can be used to compute a failure rate. Using a base of 104 operating reactors for
the period from 1984 to 2003, and covering a period of 20 years, the failure rate would be 0.0111
failures per unit per year (23 divided by 104 divided by 20). This value is smaller than the other
values previously estimated from the NPRDS/EPIX databases (0.0632), and the INPO Plant
Events database (0.0377). This is not unexpected because LERs do not have to be submitted if a
failure impacts production, but does not affect plant safety. Many issues will not be categorized
as LERs. Therefore, the failure rate determined from review of LERs on FW heaters (0.0111) is
not useful for the purposes of this sourcebook, and will not influence the generic industry failure
rate determination (see Section 4.5 for further detail).
The search of SERs, SENs, and O&MRs identified the following items:
There were 7 items identified under SEN (significant event notification) via a word search for
feedwater heater. Of these, two addressed the same event: the feedwater heater shell rupture at
a PWR in May 1999. One of the items involved a steam line rupture, one involved a condenser
tube rupture, and on involved the rupture of a drain line from a moisture separator reheater. One
4-22
item involved isolation of extraction steam with an unrecognized loss of FW heating, and one
item involved a scram due to excessive power oscillations.
There were 32 items identified under SER (significant event report) via a word search for
feedwater heater. A review indicated that only 4 items are related to feedwater heaters, and
none of these involved specific feedwater heater mechanical component failures.
There were 18 items identified in the INPO O&MR database via a word search for feedwater
heater. Of these, only one item was related to feedwater heaters mechanical components,
O&MR 431, Secondary Plant Pressure Vessel Wall Thinning. This item involves the FW heater
shell rupture previously addressed during the LER and SEN review.
4.2.3
As previously described, there were four searches done of the INPO NPRDS/EPIX databases.
NPRDS was investigated using a word search (for feedwater AND heater) and using a
system/component search (focused on the condensate, feedwater, heater drains, and extraction
steam systems and on heat exchanger as the component), and EPIX was searched in the same
manner. The word searches yielded significantly more items than the system/component
searches, but this almost certainly reflects the occurrence of the words feedwater heater in the
text of items which do not directly involve feedwater heaters. The review and evaluation of
these items is addressed in this sub-section.
The numbers of items identified are listed in Table 4-2. The NPRDS items identified via a word
search on feedwater heater were not individually reviewed due to the amount. The NPRDS
items identified through a system/component search were individually reviewed (924 total
items). The EPIX responses were reviewed individually, for both the word search and the
system/component search, with 38 items listed for the system/component search and 276 items
for the word search.
The NPRDS data is tabulated in Tables 4-6 and 4-7. Note that the items are considered for the
years 1983 through 1996 the previous years were dropped because only 11 items were
identified (too few data points for 1976-1982). Note also that the data do not show how much
lost power generation was experienced, only whether the event caused a power reduction or a
plant shutdown (the records do not identify lost megawatt hours). The average number of plants
(95) was chosen based upon plant start-up dates.
Table 4-6
NPRDS Feedwater Heater Search Results - Summary
Total Items
HP / LP
Applicable
Items
Time Span
Avg. Number
of Plants
Failure Rate
924
292 / 632
839
14 years
95
0.631
These results are an order of magnitude greater than those found for the INPO Plant Events
database, the LER data, and the INPO EPIX database. This is not unexpected, because the
4-23
NPRDS failure criteria were different than the other databases, and included many failures the
others do not identify. These results are discussed further in Section 4.5, where the failure rates
for FW heaters are evaluated in more detail.
The following list details the NPRDS feedwater heater records by year.
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
19
44
62
51
64
90
105
101
79
72
74
30
59
35
Table 4-7
NPRDS Feedwater Heater Search Results Specific Components and Consequences
Tube Leak /
Tube Thinning
Manway /
Flange Leak
Shell Leak
505 (60.2%)
204 (24.3%)
33 (3.9%)
Nozzle
Leak
19 (2.3%)
Plug Leak
54 (6.4%)
FWH
Internals
Damage
49 (5.8%)
Power
Reduction
123 (14.7%)
Note that the total is greater than 100% because many items involved more than one finding.
Also, the items with power reductions are an estimate only because often the NPRDS field for
plant impact often conflicted with the text of the record. The percentage of failures involving
power reductions and shutdowns will be used in Section 4.5 in the determination of the generic
industry estimated failure rate. For the manway/flange leaks, the records were primarily for
worn, damaged, or misapplied gaskets, with a small percentage (about 10%) involving weld
cracks, seal leaks, or improper bolt tightness.
For the 38 EPIX system/component search items, 18 involved relief valves, vent valves, or
controls and are not included in the final total. The 20 EPIX items involve one shell failure
(already identified), four other cases of external leakage (shell leakage), one problem with a
manway flange, one problem with a divider plate, and 13 items involving tube leakage or
unavailability (due to surveillance test results). It should be noted that 7 of the 20 items were
submitted by the same multi-unit site, which supports the previous statement that not all utilities
report failures to the same degree or with the same frequency (for one site to submit more than
1/3 of the total is quite unusual, given that there are 104 operating plants of varying age in the
overall data field).
4-24
The EPIX results are presented in tabular form in Table 4-8, showing the impact on power
generation from the various failures.
Table 4-8
EPIX System/Component Search Results for Feedwater Heaters
Date
BWR/
PWR
Type
(LP / HP)
Description
LP FWH tube leakage attributed
to design limitations
LP FWH tube leakage attributed
to design limitations
LP FWH tube leakage attributed
to design limitations
LP FWH tube leakage attributed
to design limitations
LP FWH tube leakage attributed
to design limitations
LP FWH tube leakage attributed
to design limitations
Lost
Megawatt
Hours
3/24/97
PWR
LP
6/08/97
PWR
LP
6/24/97
PWR
LP
8/01/97
PWR
LP
10/26/97
PWR
LP
2/24/98
PWR
LP
10/06/98
BWR
HP
1/15/99
PWR
LP
2/08/99
PWR
LP
2/20/99
PWR
LP
4/02/99
PWR
LP
Tube Leak
29,285
5/14/99
PWR
LP
Shell Rupture
78,029
7/10/99
BWR
HP
Tube Leakage
14,552
7/15/99
PWR
LP
Tube Leakage
21,049
10/07/99
PWR
LP
Shell Thinning
None
12/06/00
PWR
HP
None
1/25/01
PWR
HP
Tube Leakage
4/30/01
BWR
LP
None
5/01/01
BWR
LP
None
4/11/03
BWR
LP
Tube Failures
Tube Leakage
Tube leakage due to inadequate
design of drain cooler endplate
Tube leakage due to inadequate
design of drain cooler endplate
Tube leakage due to inadequate
design of drain cooler endplate
15,433.2
11,345.3
23,215.6
13,970
10,896.6
None
19,927
17,028
4212
4363
12,341
72,243
347,889.7
17,394.5
A review of the 276 EPIX word search (on feedwater AND heater) results indicates the
following: 27 items which are directly related to the passive mechanical components of FW
heaters. The remainder of the items address controls or other secondary side equipment. If these
27 items are used to estimate a failure rate for FW heaters, then 27 is divided by 104 (assumed
4-25
number of operating reactors) divided by 6 years, which gives a result of 0.0433 FW heater
failures per unit per year.
A more detailed review of these 27 items shows that only 7 were not previously identified in the
EPIX system/component search. These 7 items are listed in tabular form below (note that the
word search items often did not specify whether a LP FWH or a HP FWH was involved, so that
tag is left out).
Table 4-9
EPIX Word Search Results for Feedwater Heaters (unique items)
Lost
Megawatt
Hours
Date
BWR/PWR
Description
7/20/97
PWR
Tube Leakage
43,392
10/16/98
PWR
Tube Leakage
4896
12/27/98
PWR
1/18/99
BWR
Shell Thinning/Leakage
73,081
6/16/99
BWR
Tube Leakage
19,993
10/10/00
BWR
Tube Leakage
55,923
6/21/01
BWR
Shell/Weld Leakage
197,285
28,184
Of the 27 items listed in Tables 4-8 and 4-9, 19 (or 70%) are attributed to tube leakage, while 5
(or 18.5%) are attributed to shell thinning or shell damage. The remaining items involve plug
problems and inlet FAC.
4.2.4 Experience in Fossil Power Generation and Industrial Facilities
EPRI CS-1776 (Failure Cause Analysis Feedwater Heaters) [Ref. 18] was developed as part of
the EPRI Fossil Plant Performance and Reliability Program. Data from the Edison Electric
Institute (EEI) was used, along with data from a special survey conducted by EPRI and EEI to
gather information on feedwater heater problems. After the data was received and reviewed, a
study team visited several utilities to gather additional information and to clarify the data. In
addition, three major FWH vendors and a major A/E firm were visited to obtain their views on
feedwater heater failures. CS-1776 provides a summary of the survey results and also discusses
the problem areas for feedwater heaters. The most serious areas identified were the following:
Tube vibration
Tube plugging
4-26
Corrosion
Steam impingement
The report addressed each of these areas in a separate section. Channel head-to-shell leakage
was also identified as a serious problem, although it was found that other problems usually
caused this damage. Feedwater heater failures for unknown reasons comprised a large problem
area, reflecting the difficulty in diagnosing failures in a closed feedwater heater.
EPRI sponsored a feedwater heater survey in 1991 (EPRI GS-7417, Feedwater Heater Survey)
[Ref. 24] to ensure that the state of the art knowledge was collected, to extend current technical
knowledge and experience, and to meet the higher demands of future power plants. This survey
was part of the development project, Feedwater Heaters for Improved Coal-Fired Power
Plants. An initial step in the project was to review the problems associated with HP Feedwater
Heaters. A detailed questionnaire was prepared and distributed. The survey was distributed to
35 power plants in the USA and 16 power plants in Europe. The units were all fossil-fired. A
brief summary of the survey results are as follows:
Table 4-10
Damage Incidence for FW Heaters (Fossil) From Survey (EPRI 7417)
Defective Component
United States
Europe
Hxch Tubes
83%
25%
Tube-to-Tubesheet Joint
23%
12%
23%
6%
Other Components
37%
6%
Replaced FW Heaters
8%
6%
Table 4-10 shows that 83% of US fossil plants (from the survey) have experienced tube
problems at some time or another.
EPRI has also issued a number of documents associated with improving the heat rate for fossil
power plants (some of this information would be applicable to nuclear plants as well). Those
reports include EPRI TR-109546 [Ref. 26]. In addition, there is a two-volume EPRI set
available on plant thermal performance, EPRI TR-107422 (Thermal Performance Engineers
Handbook) [Refs. 13 & 14].
4.3
The following codes and standards are applicable to feedwater heaters, and are regularly used in
the design, specification, operation, inspection, maintenance, repair, and modification of
feedwater heaters:
4-27
HEI (Heat Exchange Institute) Standards for Closed Feedwater Heaters, Sixth Edition, 1998
ASME Codes/Standards (Boiler & Pressure Vessel Code, Section VIII, Div. 1)
Feedwater heaters are pressure vessels and their design and construction must meet the
requirements of the ASME Boiler & Pressure Vessel Code, Section VIII, Division 1, including
applicable addenda and case rulings. All feedwater heater units are to be stamped with the
ASME Code symbol. Both the HEI and TEMA standards reference the ASME Code (as they
describe code requirements for the heat exchanger equipment).
The HEI Standards for Closed Feedwater Heaters combines present industry standards, typical
purchaser requirements, and manufacturers experience to provide an overall view of design
criteria for closed feedwater heaters. The standards outline practical information on equipment
nomenclature, dimensions, testing, and performance. Use of the standards enables effective
communication between the purchaser and the manufacturer. The standards represent the
collective experience of the section members (manufacturers) and they provide a guide in the
preparation of feedwater heater specifications and selection. The standards are organized to
provide definition of technical terms, a discussion on feedwater heater performance, a listing of
mechanical design standards for sub-components (including code requirements), material design
standards, guidance on replacement specifications, a discussion of feedwater heater protection, a
discussion of typical installations, an overview of feedwater heater channel types, and an outline
of typical feedwater heater internals. Appendices address various issues such as feedwater heater
operation, maintenance, and the various zones within a feedwater heater.
The TEMA Standards are presented in three classes, for R, C, and B, each reflecting
acceptable designs for various service applications (power plant heat exchangers fall into the C
category). The standards are compiled by the Technical Committee of the Association. The
standards present information on the nomenclature for heat exchangers, data on fabrication
tolerances, general fabrication and performance information, a discussion on installation,
operation, and maintenance, mechanical standards for the three different classes described,
materials specifications, thermal standards, data on physical properties of fluids, general
technical information, and recommended good practices for heat exchangers. The standards also
address topics such as tube orientation, thermal expansion, heat exchangers supports,
impingement protection, and heat exchanger testing. TEMA is comprised of manufacturers of
various types of shell and tube heat exchanger equipment.
ASME PTC 12.1 provides procedures, direction, and guidance for determining the performance
of a closed feedwater heater with respect to the following:
1. Terminal Temperature Difference (TTD), which is the difference between the saturation
temperature (corresponding to the steam inlet pressure and the feedwater outlet temperature)
2. Drain Cooler Approach (DCA), which is the difference between the drain outlet temperature
and the feedwater inlet temperature
4-28
ANSI (American National Standards Institute) standards for dimensional requirements for
materials such as piping, tubing, flanges, etc.
AWS (American Welding Society) procedures for welding and post-weld heat treatment
that are not already covered by ASME or HEI
SSPS (Steel Structures Painting Council) standards for removal of mill scale, blasting,
surface preparation, and the application of coatings or paint
ASTM (American Society of Testing and Materials) standards for the physical and
chemical properties of heat exchanger materials, fabrication tolerances, and materials testing
that is not addressed by ASME
In addition, there are requirements associated with pressure vessels and nuclear insurance which
must be part of the overall feedwater heater maintenance and engineering file at each power
plant. The system or component engineer is normally responsible for this area. Feedwater
heaters are addressed in the NEIL (Nuclear Electric Insurance Limited) Loss Control Standards
[Ref. 44] in two places: first, as part of the condensate/feedwater systems, where credit is given
under the boiler & machinery loss control program for high integrity tubing observation, testing,
inspection, and surveillance; and second, where partial credit is applied for original tubing that
has been replaced with non-copper bearing tubing (i.e., stainless steel).
4-29
4.4
EPRI maintains a Plant Performance Enhancement Program (P2EP) technical library which
contains a variety of documents on feedwater heaters. The documents range from evaluations of
drain cooler problems at specific plants to overall descriptions of feedwater heater replacements
(at specific plants) to test program reviews and evaluations. These files are available to EPRI
members via the EPRI website or by contacting EPRI directly. EPRI TR-107422-V2 (Thermal
Performance Engineering Handbook, Volume 2) [Ref. 14] lists over 100 separate files applicable
to feedwater heaters.
4.5
The review of plant operating experience to determine a failure rate for FW heaters has shown
that the data have a wide disparity, and any estimation of a generic industry failure rate is highly
dependent upon how the data are evaluated and which sets are the most credible for the purposes
of LCM planning.
The following table summarizes the wide range of values determined from the operating
experience review. The number of failures are those found in the search that are directly related
to FW heater mechanical components, and the failure rate is the value determined by dividing the
number of events by the applicable number of operating nuclear units, and then dividing again by
the number of years (inclusive) that the database covers.
4-30
Source
NPRDS/EPIX
data from
EPRI report
1003470
No.
Failures
171
Time
Span
1976
2002
Failure
Rate
Observations
0.0632
0.0377
0.0111
0.0433
0.631
INPO Plant
Events
47
INPO LER
database
INPO EPIX
review
INPO NPRDS
review
23
20
839
1991
2003
1984
2003
1997
2003
1983
1996
4-31
The reasons for the broad range of failure rates have been explained in the specific sub-sections
that address the sources of the data. In order to determine or select a meaningful value for a
generic industry failure estimate for FW heaters, these differences need to be considered.
In view of the wide range of failure rates in Table 4-11, it is appropriate to estimate a range,
rather than a single value, for a generic industry failure rate. This allows for the consideration of
all the data sources, without ignoring or relying too heavily on any single one. In this manner,
all events are considered (to the appropriate degree) both the events that actually impact the
plants power production and the events discovered during surveillance but do not impact plant
operation. For this LCM sourcebook, the balance is struck by estimating a generic industry
failure rate of between 0.05 and 0.1 failures per unit per year.
The lower value of 0.05 is chosen as being representative of the EPRI 1003470 NPRDS/EPIX
data, the INPO Plant Events data reviewed for this sourcebook, and the EPIX data reviewed for
this sourcebook. The value chosen is higher than the individual failure rates found for the last
two sources because they do not include all failures impacting production. The upper value of
0.1 was chosen based on the percentage of NPRDS failures (about 15% from Table 4-7) that
involved power reductions (from Table 4-11, 0.631 times 0.15 equals 0.095),
This estimated failure range addresses the uncertainty involved in reviewing the disparate
industry failure data. The range allows for the differences in failure definition, differences in
failure reporting, and differences in how failures are categorized with respect to maintenance.
The range also accounts for differences in FW heater age and service, because older FW heaters
are expected to have a higher failure rate and will require additional surveillance and more
maintenance.
The experience information analyzed above is available only on a per-plant basis and not on a
per-heater basis. Because plant-specific LCM planning is normally done on a component basis,
the extent to which available information can provide an estimate of failure rate for an individual
FW heater is explored in the following paragraphs.
One way to estimate a per-heater failure rate is to simply divide a generic per-unit rate estimated
in this report by the plant-specific number of heaters. Although this would be an improved
generic estimate (because it would appropriately give higher or lower per-unit rates depending
on the number of plant-specific heaters), it would contain an element of inaccuracy because the
per-unit generic estimate does not account for the per-unit number of heaters on which the failure
count is based.
To improve the accuracy of the generic estimate for LCM planning purposes we need to know
the total population of heaters covered by the data sources. The average number of heaters per
unit would then be divided into the per-unit failure rates to give the average per-heater failure
rate.
A way to obtain the exact population of heaters and the average per-unit number of heaters is to
research documents such as Safety Analysis Reports for all plants. This activity was beyond the
scope of this project. It could, of course, be performed by any future plant-specific LCM
planner.
4-32
For our purposes, an estimate of the average number of heaters per unit was obtained by
interviewing several plant experts familiar with US plants. They came up with a range of perunit heaters of from 12 to 21, with the average of 16.5, assuming a uniform distribution of
values, which is only approximately true. (An estimate of the total is then 16.5 x 104 = 1716 FW
heaters in US plants). The average divided into the per-unit range of 0.05 to 0.1 leads to the perheater range of 0.003 to 0.006 failures per year. This would be the range of values to be used by
a FW heater LCM planner regardless of the number of heaters in his or her plant. Note that
these estimates still include the uncertainty caused by not knowing the exact number of FW
heaters in the population.
A point-value evaluation of the net present value of various alternative plant-specific LCM plans
would use a value between 0.003 to 0.006 as generic information to be combined with plantspecific failure data to give the value or values of failure rate to be used in the calculations with a
point-value LCM tool such as EPRIs LcmVALUE or LcmPLATO. This could be done using
either a single value (such as the average, 0.0045) or a higher/lower value within the range to
account for judgments of how well the industry average applies to the plant under evaluation.
For example, if the plant currently has a preventive maintenance program or a tube/shell material
type superior to the average plant, then a lower value in the range would be used to combine
with the plant-specific failure rate. Another approach might be to use the upper and lower values
of the range (i.e. a sensitivity study) and see if this changes the choice of the optimum LCM
alternative.
This studys finding that there is a significant range of industry experience-based failure rates (so
that forecasts of future failure rates would be even more uncertain) is the same finding as in most
of the nine other LCM sourcebooks produced to date. For this reason, the fidelity of LCM
planning efforts can be improved (over that provided by the point value approach) by going to
the next level of analytical technology and treating uncertainty explicitly using the probabilistic
approach embedded in decision analysis. In this approach, the single values used in
deterministic evaluations are replaced by probability density functions (PDFs) as inputs. It has
been shown (e.g., in the LCM uncertainty analysis performed for the South Texas main generator
[Ref. 46]) that failure rates are among the most important drivers of LCM decisions. As a first
order approximation to a FW heater PDF, one might use a uniform distribution between 0.003
and 0.006 failures per year (perhaps adjusted to account for plant-specific data). An improved
distribution could be obtained by conventional methods for combining statistical data with expert
judgment (for a FW heater, the judgment would be elicited from a few experts such as the plant
FW heater component engineer, a secondary-side system engineer, a manufacturer technical
representative, or an expert consultant). EPRI is exploring various existing tools for performing
plant-level LCM with uncertainty and will use the findings to guide future work in this area [Ref.
47].
4-33
5
GUIDANCE FOR PLANT-SPECIFIC SSC CONDITION &
PERFORMANCE ASSESSMENT
This section addresses Steps 8, 10, and 11A in the LCM planning flowchart (Figure 2-2) and
provides guidance for the plant-specific LCM planning for feedwater heaters. Also included in
this section is a compilation and description of available and useful condition or performance
monitoring programs, along with a brief overview of the most common repair techniques used in
the industry for feedwater heaters. This information is useful for LCM planning when
maintenance strategies are being evaluated and alternative LCM plans are being developed.
Individual plants may also discover that their program can be enhanced by including some of
these techniques (if they are not currently utilized).
Step 10 comprises a compilation and review of the plant-specific maintenance program for
feedwater heaters (see Section 5.2) leading to the establishment of a complete inventory of
the current maintenance tasks and providing a basis for determining if enhancements or
changes are desirable (or necessary).
In Step 11A, the intent is to characterize the present plant-specific physical condition and
performance of the feedwater heaters and the implementation of effective preventive
maintenance procedures, diagnostics, and component condition monitoring. The assessment
of the maintenance tasks should pay close attention to whether and how the tasks address any
deviations identified in the SSC performance assessment and SSC condition review. The
deviations may be positive in that plant-specific SSC performance and conditions are
superior to the industry average, which may indicate that unnecessary or too frequent PM is
being performed, or the deviations may be negative, which indicate a need or opportunity for
improvement. Details of the condition and performance assessment are discussed in Section
5.3.
5.1
The operating/performance history and the age of the FW heaters at any given plant have a major
bearing on the LCM planning evaluation and the choices made for the future, and they provide
the basis for the condition and performance assessment. In conjunction with the performance
review, a thorough assessment of the existing equipment is of paramount importance in making
realistic decisions with respect to the feasibility of maintenance options and strategies. To make
the optimal decisions, the history must be known and correctly evaluated. The following are the
recommended steps in assembling the operating and performance history for the FW heaters:
5-1
Assembling the maintenance history for the FW heaters, particularly for the past 10-15 years.
This includes maintenance on the shell (if any), the tubes, the tubesheets, the tube supports,
the baffles and shield plates, the drains and vents, and the inlet/outlet nozzles. The
maintenance history includes preventive maintenance, predictive maintenance, corrective
maintenance, and a listing of work orders.
Trending the historic failure rates to identify the specific components that exhibit unusual
performance challenges (either design or operational problems). This will primarily involve
the tubes and the baffle and shield plates.
Compiling and reviewing performance test results, surveillance test results, etc., to determine
if trends exist in the FW heaters. This includes a review of available data on thermal
performance.
Reviewing the Maintenance Rule performance parameters and trends, the system &
component health reports, the monitoring status, the goals, and the discussions of specific
failures, along with the effectiveness of corrective action.
Reviewing the plant trip and power reduction history to determine and list the events caused
by the FW heaters and sub-components. For those events, the lost power generation, the
extended outages, the power reductions, the corrective actions, etc. provide the input into the
historical cost of FW heater failure. These results provide a basis for projecting future
performance in the LCM planning. The results will be negative if the performance is
declining and additional corrective action is not implemented and positive if new PM or PdM
tools are applied, or if equipment replacement is begun.
Review of design changes and technology upgrades (in maintenance or operation) that have
been instituted.
Review to establish the feasibility of obtaining major component replacement in the most
efficient manner possible (particularly for older equipment).
The following sections/paragraphs detail specific areas for review and provide specific guidance
on industry methodology to determine the current condition of the feedwater heaters. Also
included is a review of current repair techniques for feedwater heater components.
5.1.1 Feedwater Heater Condition Reviews (Work Orders, Failures Trends, Lost
Power Generation, Trips, Preventive Repairs, Replacements, Refurbishments)
To develop a clear picture of past feedwater heater performance from which projections can be
made, a thorough review of the maintenance history is needed. The maintenance history is
captured at most plants in Work Orders, usually located within a database (most plants typically
have electronic records from the mid-1980s to the present). Work Orders are written to
implement preventive, predictive, and corrective maintenance and also to implement other
activities, such as surveillance tests, overhauls, inspections, design changes, and replacements.
5-2
With respect to feedwater heater LCM, the most important Work Orders are those which
implement corrective actions as a result of problems or failures (including work from design
changes due to problems or enhancements). These Work Orders often contain information
concerning the root cause, whether repetitive problems were involved, the cost and man-hours
spent in the corrective action, and the reason why the problem was not detected in an early stage.
This information is used to identify additional preventive maintenance (PM) or predictive
maintenance (PdM) activities, potential enhancements to the current maintenance program,
and/or the need for upgrades, replacement, or new design. The basic premise is that performance
can only be improved by preventing problems (the ability to detect degradation and failure
before loss of function occurs) and by determining the actions which could prevent future
problems.
The Work Order review also provides detailed information as to the annual frequency of
occurrence of problems and failures presently experienced by the feedwater heaters. The
problem occurrence rate is one of the most important inputs for calculating the costs of
corrective maintenance and failure (due to lost power production, new equipment, regulatory
risk, EPIX reporting, MR monitoring, etc.) when performing economic modeling of LCM
alternatives.
The Work Order review can also be used to trend the annual corrective and preventive
maintenance activities over the past several years to determine if the rate of problem occurrence
is increasing or decreasing, and if the ratio of corrective to preventive Work Orders (and their
implementation costs) are changing. An effective PM program should show a gradual decrease
in corrective Work Orders and associated costs. This data can lead to the identification of
additional corrective and/or preventive actions that may be justified to improve the feedwater
heater programs. These actions would then be part of the alternative LCM plans for the
feedwater heaters (to be evaluated on a plant-by-plant basis).
In the Work Order review, consideration must be given to the impact of FW heater maintenance
on plant reliability, with respect to the different types of heaters involved (high-pressure or lowpressure), with respect to plant lost power generation (if an entire heater string is taken out of
service), and any overall maintenance strategy for doing work on-line versus off-line.
5.1.2 Review of Diagnostic Tests and Monitoring Devices/Data
There are a number of applicable EPRI reports that address feedwater heater testing and
performance monitoring. They are briefly described (with applicable information) in the
following paragraphs.
EPRI 1003470 (Feedwater Heater Maintenance Guide) [Ref. 11] provides an overview of
general maintenance activities, preventive maintenance tasks, non-destructive examination
testing, and destructive testing and analysis (see Section 6 of the reference for details). The
report also addresses performance monitoring (and inspections). Performance monitoring looks
at the overall integral performance of the feedwater heater. Performance deterioration that is
detectable is likely to be caused by vibration, corrosion, erosion, scaling or other deposits, or
control system problems (addressed in EPRI 1007425) [Ref. 6].
5-3
Shell-side pressure
Feedwater flow
As previously detailed in Section 4.3, this data can be used to determine the uncorrected terminal
temperature difference (TTD) and the drains cooling approach (DCA) for comparison with
design values. Note that there is a difference between the uncorrected TTD (which is the
saturated temperature for the actual shell-side steam pressure minus the actual feedwater outlet
temperature) and the corrected TTD (developed in PTC 12.1), which is the saturated temperature
for design steam pressure minus the feedwater outlet temperature corrected to design conditions.
The TTD is essentially a measure of the heat transfer capability of the feedwater heater. The
higher the TTD above the design value, the poorer the performance of the heater. The actual
measurements can only be compared with the values obtained during performance testing to
determine if significant changes are taking place. If for the same conditions, the TTD is
substantially higher, then the feedwater heater has problems. In general, a TTD that is
significantly higher than design (even if conditions are not identical) is cause for concern. A
tabular representation of FW heater performance monitoring is shown in Table 5-1.
NP-4057 points to ASME PTC 12.1 [Ref. 39] for detailed, comprehensive, and accurate
performance testing.
The DCA (drains cooling approach) is the difference between the drains outlet temperature and
the feedwater inlet temperature. A DCA that is significantly higher than the design value is
cause for concern. For proper analysis of the data, it is desirable to know the water level within
the shell and to know how it was determined (and where the instrument taps are).
5-4
EPRI GS-6935 (Feedwater Heaters Maintenance and Repair Technology: Reducing Outage
Cost) [Ref. 17] contains a detailed outline of maintenance tasks, on-line monitoring, maintenance
accessibility, inspection and testing, corrective maintenance and repairs, and post-maintenance /
pre-operational testing. This reference also addresses recording maintenance data, and has a
section devoted to heater venting maintenance. The purposes of the report are:
To develop feedwater heater procurement specifications and guidelines based upon the best
sample specifications and experience available
To develop additional recommendations for EPRI and the Utility Advisory Group for future
projects to improve the maintenance of feedwater heaters
The report was written based on material collected from numerous sources, principally an
industry literature search (conducted from 1982 1988), which reviewed technical reports,
articles, symposia, and other data specifically related to feedwater heater maintenance. Also
included in the source review were the study teams own records and experience, a utility
maintenance and engineering records search (related to feedwater heaters), interviews with
power plant personnel, expert interviews, and comments from EPRI and the Utility Advisory
Group. The report strongly concluded that feedwater heater maintenance plans must be
effectively established and implemented in order to obtain the optimum performance. The report
challenged utilities to apply strong forward-looking programs to maintain the feedwater heaters
in their plants. The details of such maintenance (and performance monitoring) are presented in
the following paragraphs.
The report highlighted the following on-line monitoring techniques:
The report highlighted the following inspection and test techniques (for easily accessible areas):
Visual Inspection - internal (channel interior surface, pass partition plate, tubesheet face,
tube-to-tubesheet joints, and tube interiors)
Inaccessible areas of the feedwater heater (such as the shell interior) should be performed with
boroscopes, fiberscopes, and video boroscopes. Erosion on the shell and/or baffle/impact plates
and tube damage should be considered and investigated when conducting these types of
inspections.
Acoustic leak detection is most valuable when monitored on-line. Early leak detection is based
on the fact that even the smallest leak creates discrete noises from the turbulence of the leak jet.
The sensors are piezoelectric pressure transducers installed near the feedwater inlets and
5-5
mounted so that the water-borne noise is acoustically coupled to the transducers. EPRI has
sponsored a number of programs to demonstrate the various configurations of test equipment,
and several plants (nuclear and fossil) have identified tube leaks, baffle erosion, and shell cracks
well before scheduled outages and before the damage became severe enough to impact plant
operation [Ref.17].
The leak testing of tubes can be accomplished from either the tube or the shell side using several
different testing methods. All leaking tube and/or tube-to-tubesheet joints should be identified
both on the tubesheet (with an oil-based marking pen) and on a tubesheet layout drawing.
The most widely used methods for leak detection from the shell-side are as follows:
Pressurized Air
Water
Vacuum
Halogen Gas
Though less frequently utilized for general leak testing, the following tube-side techniques are
effective:
Pressurized Air
Vacuum
Hydrotest
Sonic Pulse
As with leak testing, the determination of the tube leak location within the tube span may be
accomplished from either the shell side or the tube side via several different methods, such as
vacuum testing, pressurized air, water, and sonic pulse testing. In some cases, the orientation of
the feedwater heater will feature a specific type of test. Individual tube hydrotesting has also
been useful in examining tubes that have presented indications of problems through other
observation (i.e., eddy current testing). An individual hydrotest will show tubes that are near
failure. An individual hydrotest can be used to verify eddy current results, although tubes may
be damaged by the test. In that case, the tube will need to be stabilized with rods (and plugged).
Sonic pulse testing involves the transmission of an audible sound wave down the inside of an
empty tube under inspection. Echoes from this sound wave are returned from any anomalies in
the tubes inner wall and the echo characteristics provide information about the locations and
types of the anomalies. This method detects anomalies on the inner tube wall.
Electromagnetic testing (ET) is the technique used most often to examine feedwater heater tubes.
It can be performed rapidly with a high confidence in the test results, and the data is repeatable
(and can be stored and retrieved easily). Selection of the appropriate ET technique is dictated by
the magnetic properties of the tubing material. For non-magnetic alloys (304 SS), eddy current
testing (ECT) is widely used. For shell thickness determination and verification, pulsed eddy
current testing is used (and is described later in this section).
5-6
The most commonly used NDE technique for determining the condition of feedwater heater
tubes is eddy current testing (ECT). Eddy current testing is extremely fast, repeatable, good for
baseline screening, and accurate in sizing known defects. However, ECT is very operatordependent. Quantification of certain types of defects is sometimes difficult, and other NDE
methods must be used in conjunction with ECT to obtain optimum results. Eddy current testing
is described in detail in EPRI 1003470 (Feedwater Heater Maintenance Guide) [Ref. 11].
Eddy current testing utilizes an internal probe specifically designed for the tube diameter and
material being tested. The probe consists of an alternating current coil which establishes an
electric field that produces a field of eddy currents in the tube. This field is interrupted by tube
wall flaws such as wall thinning, cracking, and pitting, and these interruptions cause an
impedance change in the coil. This impedance change is reflected as a Lissajous signal and is
measured in terms of signal magnitude and/or signal phase. In-place tube bundles are inspected
from the tube inside diameter by pulling the test probe through the tube at a constant speed.
Tubing can be inspected at rates greater than 1 foot per second. During this process, the data can
be saved to a magnetic disk for review by a qualified analyst. The defect type, size, depth, and
wall thickness can be determined by comparison to a known calibration standard.
Figure 5-1 shows a flowchart rendition of the eddy current process.
5-7
Figure 5-1
Eddy Current Flowchart (from EPRI 1003470)
5-8
The tubes are scanned through the absolute and/or differential test modes to achieve full
volumetric inspection along the entire tube length. This is accomplished by fully inserting the
probe and pulling the probe back along the tube length at specified test speeds.
The inspection objective is to detect and analyze all potential tube flaws. Eddy current testing
offers the following advantages:
It is relatively fast (high digital sample rates allow for test speeds up to 260 in. per sec.
The test equipment is easily configured and applied for automatic examinations.
Eddy currents are influenced by the presence of material flaws and material property
variations such as conductivity, permeability, geometry, etc.
Eddy currents are influenced by flaw orientations that make the testing direction-dependent.
Eddy current testing is mainly used for testing thin materials (i.e., tubes).
The sensitivity level for flaw detection is not uniform throughout the test piece. Optimum
detection occurs at the test surface closest to the test coil and decreases exponentially below
the surface.
Good eddy current signal interpretation requires a high level of operator training and
awareness.
Because conventional eddy current testing cannot be performed on magnetic tubing material,
several alternative eddy current schemes need to be considered:
Full-Saturation ET: This procedure uses a magnetic saturation technique which renders
ferromagnetic tubing non-magnetic. This technique is applicable for tubes made of 439
stainless steel, Seacure, Monel, and Al29-4C with a wall thickness of up to 0.035 inches
(0.9mm).
Partial-Saturation ET: This technique uses an ET probe with equipped with permanent
magnets to partially saturate the tube wall. This technique is applicable to carbon steel tubes
and thick-walled ferritic stainless steel tube materials.
Flux Leakage: A pair of induction coils are used to detect tube flaws, one for inside and
outside diameter flaws, and one for just inside diameter flaws. By positioning on
5-9
differentially connected induction coil between the magnetic poles, differences in flux
leakage along the wall are monitored. Changes in the total flux caused by gradual wall
thinning are easily noted.
The most important considerations in planning ECT examinations are to prepare a
comprehensive tube sampling scheme to adequately assess the current feedwater heater
conditions, to perform the necessary corrective measures, including tube pulls, to mitigate any
existing problems, and to calculate the remaining life once the test results are complete. In order
to have a successful ECT examination, the following tasks should be considered:
Prepare for repair and remedial measures (i.e., tube cleaning) if necessary
EPRI 1003470 [Ref. 11] contains a detailed section that addresses each of these items and
provides data on tube plugging criteria. Please refer to Section 6.3.4 for further detail on ECT.
EPRI GS-6935 also contains detailed information on eddy current testing [Ref. 17].
EPRI 1003470 also contains a discussion of pulsed eddy current testing, which is used to
evaluate the thickness of FW heater shells. Pulsed eddy current testing senses the presence of
defects by inducing eddy currents in the insulation jacket and outside surface of the shell. The
change in the magnetic field is monitored as the currents diffuse and permeate the shell and the
wall of the insulation jacket. The shell thickness is measured by recording the time it takes for
the currents to diffuse and permeate.
Pulsed eddy current testing has been increasingly used in FW heater applications because of the
following features:
The methodology measures wall thickness through the insulation, eliminating the cost of
insulation removal
The probe can penetrate a carbon steel shell up to several inches thick
The probe requires no direct contact with the shell and can be applied on-line
The testing is not affected by the geometry of the shell, any coatings, or the type of insulation
The probe is not sensitive to the users skill (unlike tube testing)
The technique focuses on a relatively large area which limits its application (or usefulness) to the
identification of widespread corrosion/erosion. But this is the case with flow-accelerated
corrosion (FAC). The limitations of pulsed eddy current testing include the need to assess a
broad area of the shell, possible underestimation of wall loss, the possibility that localized
damage could be overlooked, the need to re-calibrate the equipment at various locations around
the shell, and the difficult working conditions (when used on-line) due to heat and noise.
5-10
The results of pulsed eddy current testing indicate that the technology will show damage after
wall loss exceeds about 20%.
5.2
Once the plant-specific maintenance history has been compiled, the current maintenance
activities need to be identified. When using the word maintenance in LCM planning, it must be
noted that this includes preventive, predictive, and corrective actions, whether required by
regulations (testing, inspection, surveillance, monitoring, sampling, EQ, etc.), or by applicable
codes/standards (IEEE, NFPA, ASME, etc.) or by insurance requirements, or by state/local
government requirements, or by plant procedures, programs, or policies. Collecting the
associated activity parameters (frequency, affected components, labor hours, material costs, etc.)
will provide key input to developing a base case for LCM planning. This base case will not only
create an inventory of the current activities but will provide a benchmark for comparison to
industry practice and a basis from which the need for additional activity, enhancements, or even
task reductions can be considered. One way to assemble this information is shown in Table 7-1,
where the LCM alternatives can be compared. Further detail will be included in plant-specific
LCM tables because actual estimated costs can be developed, based upon known factors (labor
rates and material costs) and supported by yearly budgets, estimates, and future projections.
Section 3.3 of EPRI 1003058 (Life Cycle Management Planning Sourcebooks Overview
Report) [Ref. 1] provides guidance on collecting plant-specific information about the current
maintenance plan, both in terms of technical scope and economics. The guidance for system
engineer interviews and the data detailed in Table 3-7 (Listing of Typical Plant Programs) and
Table 3-8 (Inventory of SSC Maintenance Tasks and Parameters) will be particularly helpful in
the review. Section 3.8 of EPRI 1003058 details the collection of data for economic evaluations,
which is the fulcrum of any plant-specific LCM plan. Often, the most difficult data to quantify
are the costs associated with various plant maintenance activities.
5.3
The generic performance data and information presented in the preceding sections can be used
for plant-specific LCM planning in several ways. In particular, for plants without a large basis of
experience, the generic data provides a basis for a sound component-specific PM program. The
data may also be used for comparison trending or performance projection when attempting longterm LCM planning. The data may also be used to evaluate future degradation and/or failure
estimations. The steps involved in plant-specific performance and condition assessment
(including benchmarking) can be summarized as follows:
At the system level, benchmark the feedwater heater contribution to the total plant lost power
generation against the BWR/PWR specific average (Table 4-1). This will provide a
preliminary assessment as to the current and past plant system and component health and will
indicate if the plant feedwater heaters perform at, above, or below the present industry
standards with respect to lost power generation (and any associated impact to plant safety).
The results of this benchmarking provide a basis for projecting future trends (negative or
positive) in the LCM planning for the feedwater heaters. This step also allows for the
5-11
establishment of a plant-specific failure rate (which may be used in future LCM planning
documents).
At the component level (for an individual feedwater heater and its sub-components), a review
should be conducted of all the plant transients, power reductions, and reactor scrams since
plant operation began. This review should focus on the cause of the event, the principal
systems or components involved, and whether the feedwater heaters were a direct or indirect
contributor to the event. In many transients, the feedwater heaters are affected even if they
are not involved in the root cause, and their response to the event should be noted and
understood.
At the component level, compare the plant-specific failure rates with those discussed in
Section 4.1 of this sourcebook. If this is not possible, review in detail the previous 10 years
of feedwater heater corrective action work orders to develop the plant-specific failure history.
Compare the EPRI SYSMON data for feedwater heaters (discussed in Section 4.1.3 of this
sourcebook) with the plant-specific parameters established under the Maintenance Rule to
verify that the plant parameters are reasonable and representative and appropriate for the
feedwater heaters. The SYSMON goal is no more than 3% unplanned capacity loss or no
more than three (3) unplanned capacity loss events with greater than or equal to a 20% power
reduction over a 24-month period, and also no common cause unplanned scrams and no more
than two (2) scrams over a 24-month period [Ref. 38].
Evaluate any design-related deficiencies (such as shield plate geometry problems leading to
erosion) causing plant-specific issues with the feedwater heaters.
Compare plant-specific failures (i.e., their causes) to the generic failures and causes
discussed in Section 4 to identify problems not yet experienced at the plant.
EPRI has issued a number of technical reports that address feedwater heater assessment. These
reports provide guidance in performing maintenance, and also in evaluating component
conditions. For example, EPRI 1003470 (Feedwater Heater Maintenance Guide) outlines
feedwater heater performance, troubleshooting, failure modes, condition-based maintenance,
repairs, and replacements. EPRI NP-7552 (Heat Exchanger Performance Monitoring
Guidelines) provides discussions of heat exchanger selection criteria, a description of the effects
of fouling, a description of performance monitoring methods, and an analysis of the results of
heat exchanger performance monitoring. EPRI NP-4057 (Nuclear Plant Feedwater Heater
Handbook) provides 3 volumes which address feedwater heater design & operation, feedwater
heater specifications, and feedwater heater maintenance. EPRI TR-106741 (Heat Exchangers:
An Overview of Maintenance and Operations) provides an overview of heat exchanger
performance, monitoring, and repair. Finally, EPRI GS-6913 (Feedwater Heaters: Replacement
5-12
Specification Guidelines) provides improved guidance for the development of specifications for
the procurement of replacement feedwater heaters.
5.4
Condition monitoring for individual components and performance monitoring for the FW heaters
as a whole are critical processes to maintain heater reliability at the highest levels. Performance
monitoring will include an overview of the FW heaters as a whole and also is part of the plants
thermal performance monitoring program.
5.4.1 System Condition Monitoring
System condition monitoring consists of observing the system parameters and trends during
operation and comparing this to typical operation to determine if any degradation of performance
is occurring. Levels, pressures, and temperatures are monitored continuously for the feedwater
heaters and alarms are experienced during process excursions. In digital control systems,
operating parameters can be trended using statistical process control techniques and system
performance can be predicted. In older analog systems, external recording devices are used to
record the system parameter values (responses) and to develop baselines for comparing
performance trends. These methods can be used to predict future performance and system
degradation, allowing corrective maintenance to be performed prior to critical situations.
The FW heaters play an important role in the overall thermal performance of the plant. The
methods mentioned earlier (in Sections 4.3 and 5.1.2) for FW heater performance monitoring
include the TTD (terminal temperature difference) and the DCA (drain cooler approach). Also
of importance is the TR (temperature rise) across the FW heater. To reiterate, the terms are
defined as follows:
The TTD of a FW heater is the difference between the temperature of the extraction steam
o
and the temperature of the FW outlet. The design TTD for most plants varies from 5 F to
o
8 F. A high TTD indicates that the FW heater thermal performance is deficient.
The DCA of a FW heater is the difference between the temperature of the subcooled
condensate leaving the heater and the temperature of the feedwater entering the heater. It can
be a direct measure of the heat transfer capability of the heater. For most plants, the design
o
DCA is typically about 15 F.
Also, the TR across the FW heater (the difference between the feedwater inlet and outlet
temperatures) gives an indication of how well the heater is operating.
The data can be assembled in tabular form to provide the FW heater response to changes in these
parameters. Compared to the design values for the FW heater, increases in TTD, decreases in
TR, and changes in DCA are indications of one or more problems.
5-13
TTD
DCA
Power Increase
Increase
Increase
Increase
Power Decrease
Decrease
Decrease
Decrease
TTD
DCA
Inadequate Venting
Decrease
Increase
Decrease
Level Increase
Decrease
Increase
Decrease
Level Decrease
Increase
Decrease
Increase
Tube Fouling
Decrease
Increase
Increase
Tube Leak
Decrease
Increase
Decrease
High FW Flow
Decrease
Increase
Increase
Plugged Tubes
Decrease
Increase
Increase
Trending of these variables allows for the development of a historical health report for each
FW heater, and is an important part of a successful preventive maintenance program. EPRI has
developed a model to assist with evaluation of overall thermal performance, the Nuclear Thermal
Performance Advisor (NTPA). The NTPA is a PC-based program based on expert system
technology and on the EPRI Thermal Performance Diagnostic Manual. The NTPA is an
interactive heat rate diagnostic system that includes nine plant diagnostic areas:
Condenser
High-Pressure FW Heaters
High-Pressure Turbine
Low-Pressure FW Heaters
Low-Pressure Turbine
5-14
Area of Investigation
Possible Solutions
Air-binding non-condensable
gases are accumulating in the
steam space of the FW heater.
The gland seals at the lowpressure end of the turbine may
be operating incorrectly.
Avoid contamination.
Check the vents.
Check the gland seals.
For heaters operating at vacuum,
check all joints.
FW flow is bypassing.
5-15
Once a problem has been identified and checked, then the cause(s) need to be determined. This
involves a review and a comparison of the specific problem event to known failure modes, which
would include the previously identified aging mechanisms (and effects).
A summary of FW heater problems and a flowchart of possible causes are listed in the following
figure.
Figure 5-2
Summary of FW Heater Problems and Possible Causes (from EPRI 1003470)
5-16
EPRI NP-7552 [Ref. 16] provides a detailed summary of heat exchanger performance
monitoring methods.
5.5
EPRI NP-4057 [Ref. 23] contains a discussion on water chemistry for feedwater heaters. The
discussion references EPRI CS-3184 (Corrosion-Related Failure in Feedwater Heaters) [Ref.
25] for additional technical information.
In conventional nuclear plants, the fluid under consideration is demineralized water in various
o
o
phases from liquid to slightly superheated steam with a temperature range of 100 F to 550 F
o
o
(38 C to 288 C). The pressure range is from almost full vacuum to 2000 psig (13,993 kPa).
Some of the impurities present in feedwater are calcium and magnesium salts, totally dissolved
and suspended solids, as well as corrosion products and contaminants. Silica, aluminum, iron,
and copper deposits are commonly found, as we as residuals of oxygen, hydrazine, ammonia,
and hydroxide. For BWRs, ammonia, hydrazine, and hydroxide are not likely to be present, but
oxygen levels are likely to be substantially higher than in PWRs, and free hydrogen is also
present. There are two basic treatments used to control feedwater chemistry. PWRs now use allvolatile treatement while BWRs rely upon high purity, demineralized water.
The water chemistry factors which influence feedwater heater tube corrosion are steam
contaminants (e.g., chloride ions, halide salts, and dissolved oxygen). Other critical factors are
fluid temperature and pH achieved by adjustment with ammonia. Systems with all-steel and
stainless steel components generally run with a pH between 9.2 and 9.8 to minimize carbon steel
corrosion, thereby limiting the entrainment of corrosion products in the condensate. Problems
are encountered with mixed metal systems containing both copper and carbon steel alloys.
These systems are generally run at a pH of between 8.8 and 9.2 which is not optimum for the
control of corrosion in either material, but represents a useful compromise.
Oxygen contributes to uniform corrosion, stress corrosion cracking, intergranular corrosion
(particularly exfoliation), and inlet-end erosion in PWR units. Steam surface condensers reduce
oxygen levels to 7 ppb or less, but steam surface condensers are only designed to maintain this
oxygen removal at full load and with minimal air in-leakage. High concentrations of oxygen can
occur at low loads and during outages. Temperature levels are critical to various tube materials
because of their inherent material properties.
There are many problems and inadequacies with the metals used in feedwater heaters and none
of the materials is totally immune to corrosion. The nature and aggressiveness of the
environment determines the degree and type of corrosion. All of the following major categories
of corrosion have been experienced in feedwater heater systems:
Crevice corrosion
Pitting
Intergranular corrosion
5-17
Erosion-corrosion
It is important to recognize that the water chemistry can vary considerably throughout the
feedwater system. Variations in pH from 7.2 to 10.4 have been noted. For this reason, the whole
system should be monitored as necessary to protect the feedwater heaters.
For further information, a much more complete evaluation of water chemistry issues is found in
EPRI TR-102134-R5 (PWR Secondary Water Chemistry Guidelines) [Ref. 12].
Also, as previously mentioned, additional detail about corrosion problems in feedwater heaters
may be found in EPRI CS-3184 (Corrosion-Related Failures in Feedwater Heaters) [Ref. 25].
This report evaluates feedwater heater corrosion problems on a materials basis, with separate
sections for carbon steel, admiralty brass, copper-nickel alloys, Monel alloy 400, type 304
stainless steel, and titanium. There is also a detailed discussion of water chemistry in power
plants. In developing LCM plans for feedwater heaters, it is recommended that the system or
component engineer be familiar with the specific plant specifications with respect to secondaryside water chemistry. A past history of corrosion problems in the feedwater heaters (and in the
secondary-side piping, valves, etc.) may indicate a weakness in the plant chemistry program.
5.6
Making timely and appropriate repairs to feedwater heaters is very important because
components cannot always be replaced (and should not be) when problems are first identified.
Part of a successful surveillance and maintenance program is the implementation of proper
repairs to damaged or degraded equipment. Feedwater heaters operate in stressful environments
and will show evidence of this stress as the plant ages, even if all the sub-components function
properly. EPRI 1003470 [Ref. 11] contains a section that addresses feedwater heater repair
(Section 7). The items addressed include the following:
Tube Repairs
Tube-to-Tubesheet Repairs
Miscellaneous Repairs
Spare Parts
Each of these items (and also shell repair) is briefly discussed in the following paragraphs. For
detailed information, refer to EPRI 1003470 [Ref. 11], and also EPRI TR-106741 [Ref. 15],
which addresses general heat exchanger repair.
5-18
The use of detailed operational indications involves marking the stem positions of the normal
drain valve during each shift. This method can be enhanced by developing a valve flow vs. stem
position calibration curve. Indications of leakage in the feedwater heater can also be found from
an increased water level in the heater (which should be checked frequently), an increasing
terminal temperature difference (TTD), the actuation of a high-level alarm, the opening of the
high-level dump valve to the condenser, a discrepancy between the condensate and feedwater
flow indicators, an increasing air demand signal for the air-operated control valves, and an
excessive pressure drop across the integral drains cooler.
Acoustic leak detection is possible because when a leak develops in a pressurized heater tube, the
turbulence associated with the water escaping from the leak generates pressure disturbances in
the surrounding medium (i.e., the shell). These disturbances (or sound waves) are propagated
through the shell-side medium and may be detected by the use of accelerometers or piezoelectric
equipment (or by pressure transducers). Both low-frequency (2-20 kHz) and high-frequency
(20-175 kHz) detection monitoring is used, with the high-frequency equipment being more
effective and reliable. Manufacturers have developed dual-frequency sensors because the lowfrequency data is also helpful.
Shell pressurization is widely used in leak detection, and is discussed in detail in Section 5.1.2.
Identifying the exact location of a tube leak within the tube can be difficult; however, the
location is important in determining the probable cause of the failure. In U-tube feedwater
heaters, the following details should be determined and documented: the pass in which the
failure occurred, the distance from the failure location to the tubesheet, and the overall length of
the failure (if possible).
5-19
Elastomeric plug
Mechanical-type plug
Welded-type plug
The hammer-in taper plugs are relatively easy to install, are inexpensive, and can be removed
with a pipe wrench or by drilling them out. The plug material must be compatible with the tube
to be plugged and should be softer than the tube material. The design allows for only limited
contact between the plug and the tube wall. Hammer-in plugs are typically limited to use on LP
FW heaters.
Mechanical seal plugs typically contain jaw segments and an O-ring which allow for greater
sealing capability. The plugs are driven into the tube with a driving nut and an Allen wrench.
They can be installed fairly easily and give reliable performance in both LP and HP applications.
They are more expensive than hammer-type plugs.
Welded plugs can be either seal-welded in the tube or explosively expanded into the tube. Seal
welding involves a mechanical plug (tapered or hollow) that is inserted into the tube like the
hammer-in method and is then welded to the tubesheet for a permanent seal. Seal welding is
difficult at times due to the heater orientation and because the surfaces need to be very clean to
build a good weld. Explosive welding involves the insertion of a thimble plug (with a small
detonator) into the tube. The plug then explodes against the tube, forming a seal across the entire
length of the plug. Explosive welding has matured as a plugging technique, so that safe and
reliable bonds can now be made without damage to the tubesheet ligaments. Explosive plugging
offers greater integrity and better long-term reliability than other techniques, it is relatively easy
to perform (even in awkward orientations), it can be less expensive than regular seal welding,
and minimum preparation is needed. Its limitations include the need for licensed personnel to
perform the work and the permanency of the plugs (they are typically pure nickel and are
difficult to drill out).
Each plugging technique has its limitations and special considerations for where it might be
used. If permanent repairs cannot be decided upon and made in a timely fashion, it is better to
use a high integrity temporary plug instead.
5-20
Complete detail on the various tube plug schemes, along with an outline for making the decisions
and proper planning necessary to successfully plug tubes, may be found in EPRI 1003470,
Section 7 [Ref. 11]. In addition to plugging, the section also discusses tube stabilizing (to
prevent any future damage to adjacent tubes. The section also addresses tube failure reporting
and the maintenance of tube plugging records. EPRI GS-6935, Section 9 [Ref. 17] also
addresses tube plugging in detail, with an emphasis on excellent procedural control and a good
description of the plugging techniques and their selection criteria.
As a part of license renewal programs (and refurbishments), some utilities are reviewing their
maintenance histories and considering feedwater heater restoration by decreasing the number of
tubes that have been plugged. For example, non-defective tubes that were plugged for insurance
purposes can be examined and then returned to service if undamaged. Also, some leaks at the
tube-to-tubesheet joint can be sleeved and the tube returned to service. Comprehensive testing
(i.e., a hydrotest) is needed to verify that restoration is a viable option, with a post-maintenance
test to certify the work.
5.6.3 Tube Sleeving
Tube sleeves can be used to cover damaged inlet tube ends and to seal a tube leak at almost any
point along the tube. Often, permanent repairs can be made without losing the use of the tube.
Tube sleeving involves the following considerations:
Tube sleeving can be the optimum repair for inlet end erosion
Tube sleeving can strengthen tubes at the supports (where vibration and thinning occur)
Tube sleeving requires detailed advance planning for the vendor and the tools needed
probable that there is wire-drawing damage to the ligament. This possibility is one reason for the
full-depth expansion of tubes into the tubesheet holes.
Eroded tube-to-tubesheet welds should always be examined to determine if cracks or any
porosity has been exposed. The metal surface should be removed to the bottom of the crack or
the porosity, and then the space can be repaired via welding.
If the wormholing has progressed into the ligaments, then the damaged areas need to be ground
out. Most of tube should be removed from the tubesheet (leaving enough to anchor the tube in
place). Weld metal is then applied to the tubesheet until the original thickness is restored.
In the course of performing eddy current or visual examinations of feedwater heaters, it is
sometimes necessary to pull a tube from a tube bundle for further examination. EPRI 1003470
provides a description of how tubes are pulled from heaters.
There are two types of tube-to-tubesheet joints used for feedwater heaters: expanded-only, and
welded and expanded. Expanded-only tube joints are used for low-pressure feedwater heaters.
An alloy weld overlay is generally not required for an expanded-only joint. High pressure
feedwater heaters generally use a welded and expanded tube joint with an overlay on the face of
the tubesheet to match the tubing material. Again, EPRI 1003470 presents a detailed overview
of tube-to-tubesheet joint repairs (in Section 7.3). Repairs to the diaphragm, the pass partition,
the channel covers, and other gasketed covers are detailed in Section 7.4 of EPRI 1003470
(Feedwater Heater Maintenance Guide).
5.6.5 Shell Repairs
Shell repairs are made as the result of erosion or cracking or other problems discovered through
non-destructive examination of the FW heater shell (or through visual inspection). Typical
repairs include weld build-ups of wasted areas, repairs on major shell welds, and welding repairs
made to expansion joints (if applicable). Weld repairs are also made for problems identified on
nozzles, manways, and other shell connections (vents, etc.). Cracks in the shell (at the tubesheet
joint, for example) may be ground out prior to welding repairs.
Shell repairs are addressed in detail in EPRI 1003286 (Repair Technology for Degraded
Pressure Vessels and Heat Exchanger Shells: Repair and Replacement Applications Center
Task 91) [Ref. 45]. This report assists plant personnel in making informed repair or replacement
decisions that take into account the continued operation of the vessel, the consequences of
possible outage time and loss of production, and the satisfaction of all applicable ASME Boiler
& Pressure Vessel Code requirements.
Heads, channels, and gasket joints need to be replaced in the same orientation in which they were
removed. The gasket should be aligned just as it was prior to removal and the manufacturers
directions need to be followed with respect to bolting torque, torque pattern, and the number of
torque passes. The head (or flange) ought to seat the gasket, not crush it. A large amount of
gasket material protruding from the edge of a flange joint indicates over-tightening. Lubricant
must be applied to bolts prior to tightening. The bolts are then tightened at the specified torque
and in a staggered pattern consistent with the manufacturers direction, with the proper number
5-22
of passes being used. EPRI TR-106741 [Ref. 15] addresses shell repairs and issues related to
flanges and other shell features.
5.6.6 FW Heater Cleaning
Cleaning is a corrective maintenance activity that is employed after significant degradation has
been observed. It is not a preventive maintenance activity for FW heaters. Cleaning will not
extend the life of the tubes directly, but will remove deposits from the internal surface. Cleaning
should involve the following tasks: an evaluation of the type of degradation that has occurred, a
determination of the appropriate cleaning method (providing the best results and limiting any
potential damage to the heater), and a consideration of chemical cleaning as an option.
Industry literature (see EPRI GS-6935, Appendix A) [Ref. 17] indicates that mechanical cleaning
of heat exchanger tubes does not appreciably cause thinning of the tube wall.
5.6.7 Spare Parts
The recommended spare parts for feedwater heaters are listed below.
Table 5-3
Recommended Spart Parts for FW Heaters (from EPRI 1003470)
Parts
Tube Plugs
Quantity
Comments
2% - 3% of tubes depending
upon heater condition
Two sets
One set
Bolting:
------
As recommended by the
manufacturer
The decision to replace a feedwater heater (or to re-tube or rebundle the heater) is explored in
Section 8 of EPRI 1003470. A materials list is also presented that details material specifications
and plant environment. It is noted that, in general, feedwater heaters are designed with
approximately 5% excess heat transfer surface area. Historically, a feedwater heater is
5-23
approaching a replacement or major overhaul decision point when 10% of the tubes are plugged
[Ref. 23]. Decisions for run/repair/replacement and remaining life assessment are detailed in
Section 8 of EPRI 1003470 [Ref. 11]. The run/repair/replacement decision is also addressed in
Sections 7 and 8 of this LCM Sourcebook.
5.7
Heater Access
It is normal practice in the industry to obtain detailed design instructions from the manufacturer
for the disassembly and reassembly of each heater. As detailed in EPRI 1003470 [Ref. 11], the
typical information provided includes the following:
Torque values and tightening pattern sequence, type of gasket material, gasket surface
preparation, and the alignment of mating components for bolted designs
Special care needed in removal and re-installation instructions for welded diaphragm
configurations
Most heaters a U-tube configurations and have both tube ends in the same channel separated by a
partition plate. Many older heaters, particularly high-pressure hemi-head designs, provide
inadequate clearances for maintenance in the channel area. In addition, some partitions were
fully welded, which requires cutting and re-welding to gain access to both passes. Overall, the
industry has moved away from such designs. Utilities should consider how much working
clearances and accessibility impact the maintenance and testing for their feedwater heaters.
Modifications which improve access and working clearances should be considered in
conjunction with LCM planning, and accessibility should definitely be factored into any heater
replacement decisions in the future. One possibility to consider is the installation of neck flange
and bolted cover arrangements, to allow full access with easily removable manways.
An additional recommendation (from EPRI NP-4057-V3 [Ref. 23]) is to substitute flanged fullaccess covers for the elliptical heads.
5-24
6
GENERIC AGING AND OBSOLESCENCE
ASSESSMENT
This section addresses steps numbered 11B and 11C in the LCM planning flowchart (see Figure
2-1b). The intent is to help characterize the aging of passive SSCs, the wear-out of active
components, and the obsolescence of SSCs. This discussion will serve both to help address the
need for and the timing of any replacement of FW heaters in the LCM planning process, and to
identify potential environmental or service conditions that affect the rate of degradation or that
may require special plant-specific attention. It is noted that obsolescence is not considered for
FW heaters because obsolescence is normally related to electronic components, instruments,
analog equipment, and piece parts that are no longer commercially available. However, the
aging mechanisms and effects for the FW heaters are tabulated and evaluated (but obsolescence
is not listed). FW heaters and obsolescence are addressed in Section 6.3.
6.1
Table 6-1 presents a brief overview of the aging mechanisms and effects (and the common plant
programs for aging management) for FW heaters and their various materials. This table is not
comprehensive, because it does not mention plant-specific programs or frequencies, but it is
detailed enough to begin to develop an understanding of aging management for FW heaters. A
plant-specific LCM plan will contain the details of each plant program.
In terms of license renewal, FW heaters are usually excluded from the LR scope and are
therefore not typically listed in aging management matrices (for various heat exchangers).
However, an aging matrix for a FW heater will be similar to an aging matrix for other plant heat
exchangers that are included in license renewal. Table 6-1 follows the format and information
given in GALL report (NUREG-1801) [Ref. 29] for heat exchangers.
6-1
6-2
Tubes
Tubes
Component / Part
Stainless Steel
(high alloy)
Material
(typical)
Carbon Steel
(low-alloy)
(same as above)
Performance Testing
Surveillance Testing
Plant/Heater Specific
Chemistry Control Program,
Preventive Maintenance,
Functional Testing,
Surveillance Testing,
Performance Testing
(same as above)
Performance Testing
Surveillance Testing
Surveillance Testing
Loss of Material
Loss of Material
Fouling
Cumulative Damage
Cumulative Damage
Loss of Material
Loss of Material
Fouling
Cracking
Cumulative Damage
General Corrosion
Galvanic Corrosion
Crevice / Pitting Corrosion
MIC
Erosion & Erosion/Corrosion
(FAC)
Wear
Particulates, Precipitation
Flow-Induced Vibration
Mechanical / Thermal Fatigue
Crevice / Pitting Corrosion
MIC
Erosion & Erosion/Corrosion
(FAC)
Wear
Particulates, Precipitation
Stress Corrosion Cracking (SCC)
Flow-Induced Vibration
Typical Aging
Management Program
Plant/Heater Specific
Cumulative Damage
Aging Effect(s)
Aging Mechanism(s)
Table 6-1
FW Heater Summary Aging Mechanisms & Effects
Tubesheet
Tubes
Component / Part
Carbon Steel
(low alloy)
Material
(typical)
Copper Alloys
Chemistry Control Program,
Preventive Maintenance,
Functional Testing,
Surveillance Testing,
Performance Testing
(same as above)
Surveillance Testing
Hardness Test
Surveillance Testing
Plant/Heater Specific
Chemistry Control Program,
Preventive Maintenance,
Functional Testing,
Surveillance Testing,
Performance Testing
(same as above)
Surveillance Testing
Surveillance Testing
Loss of Material
Loss of Material
Fouling
Cracking
Change in Material
Properties
Cumulative Damage
Cumulative Damage
Loss of Material
Loss of Material
Fouling
Cracking
Galvanic Corrosion
Crevice / Pitting Corrosion
MIC
Erosion & Erosion/Corrosion
(FAC)
Wear
Particulates, Precipitation
Stress Corrosion Cracking (SCC)
Selective Leaching
Flow-Induced Vibration
Mechanical / Thermal Fatigue
General Corrosion
Galvanic Corrosion
Crevice / Pitting Corrosion
MIC
Erosion & Erosion/Corrosion
(FAC) and Wormholing
Wear
Particulates, Precipitation
Stress Corrosion Cracking
Typical Aging
Management Program
Plant/Heater Specific
Cumulative Damage
Aging Effect(s)
Aging Mechanism(s)
6-3
Carbon Steel
6-4
Carbon Steel
(low alloy)
Material
(typical)
Stainless Steel
(high alloy)
Shell/Nozzles/Internals
Tubesheet
Component / Part
Loss of Material
Loss of Material
General Corrosion
Galvanic Corrosion
Crevice / Pitting Corrosion
MIC
Erosion & Erosion/Corrosion
(FAC)
General Corrosion
Galvanic Corrosion
Crevice / Pitting Corrosion
Erosion & Erosion/Corrosion
(FAC)
Surveillance Testing
Plant/Heater Specific
Cracking
Cumulative Damage
Cumulative Damage
Surveillance Testing
Fouling
Particulates, Precipitation
(same as above)
Loss of Material
Wear
Loss of Material
General Corrosion
Crevice / Pitting Corrosion
MIC
Erosion & Erosion/Corrosion
(FAC) and Wormholing
Typical Aging
Management Program
Plant/Heater Specific
Cumulative Damage
Aging Effect(s)
Aging Mechanism(s)
7) The threshold temperature for stress-corrosion cracking in stainless steel is 140 F in the presence
o
of bulk fluid halides or sulfates and 200 F in the presence of O2
8) Copper alloys that have less than 15% zinc or 8% aluminum (aluminum bronze) are susceptible
to crevice/pitting corrosion as well as selective leaching (if not inhibited, such as admiralty brass
containing >1% tin)
Table 6-1 is typical for aging mechanism evaluation performed for license renewal. Table 4-4,
while similar, is more directed towards degradation and failure.
An aging mechanism review is at the heart of LCM maintenance planning. There are five (5)
documents pertinent to such a review for feedwater heaters: The Aging Management Guideline
for Commercial Nuclear Power Plants Heat Exchangers (SAND93-7070) [Ref. 7], Standard
Review Plan for the Review of License Renewal Applications for Nuclear Power Plants
(NUREG-1800) [Ref. 28], The Generic Aging Lessons Learned (GALL) report (NUREG-1801)
[Ref. 29], Nuclear Energy Institute (NEI) Guidance Document NEI 95-10 [Ref. 42], and EPRI
1003056 (Non-Class 1 Mechanical Implementation Guideline and Mechanical Tools, Revision 3)
[Ref. 43]. This last reference was developed to provide guidance on implementing the
requirements of license renewal for applicable mechanical SSCs.
With respect to License Renewal, feedwater heaters are passive but they do not require aging
management evaluation because they are typically scoped out of consideration. Heat exchangers
that are within the scope of license renewal are evaluated for their pressure boundaries in the
tubes and shells. The aging mechanisms and effects for these heat exchangers are monitored and
controlled by existing plant programs, as detailed in the License Renewal Application and the
technical aging management review document.
The NEI guidance document can be used as a starting point in the aging management review of
the feedwater heaters (by reviewing the heat exchanger group with plant-specific data). The
GALL report (NUREG-1801) [Ref. 29] outlines the required aging management programs for
heat exchangers. Passive SSCs susceptible to aging are identified together with typical
materials, environments, and aging mechanisms and effects. The active components of the heat
6-5
exchangers are excluded from aging management review (they are addressed under the
performance monitoring required by the Maintenance Rule under 10CFR50.65). EPRI 1003056
[Ref. 43] provides details on how to implement license renewal programs (surveillance,
maintenance, procedures, inspections) for in-scope mechanical equipment.
6.2
A new feedwater heater today would be expected to last 20 years or more (the lifetime of the
materials in the tubes); however, that has not been the case in the past (due to age-related
degradation, specific design problems, material problems, etc.). Section 4 of this document
provides an overview of FW heater failures and problems as identified in various industry
databases.
The expected lifetime is based upon the expected lifetimes of the various materials in the FW
heater. The tubes are the most sensitive sub-components and will usually be the limiting factor
in overall heater lifetime. Shell thinning due to erosion is also a factor, although good
surveillance programs should identify shell thinning before the problem is serious (see Section
5.1.2). But it is worth noting that 38% of the items involving feedwater heaters from the INPO
Plant Events database were discoveries of shell thinning. From NPRDS, the percentage of items
involving the shell was about 4%; however catastrophic shell failures can impact a plant for
months, due to FW heater isolation, possible power reductions, potential damage and personnel
injury, and root cause investigations.
As noted in Section 5.6, a FW heater is approaching time for retubing, rebundling, or complete
replacement when approximately 10% of the tubes have been plugged [Refs. 11 and 23].
6.3
Technical Obsolescence
Many systems in nuclear power plants (particularly those with electronic instrumentation) are
susceptible to technical obsolescence. For LCM maintenance planning, these systems or
components may have to be replaced or modified to account for the unavailability of spare parts.
In these cases, the likelihood and timing of the need for replacement will be determined by the
failure (or degradation) rate of the equipment. The feasibility and cost of reverse engineering the
obsolete components also needs to be considered.
For feedwater heaters, obsolescence is not a concern because they are strictly mechanical
components which can be repaired over long periods of time and replacements can be fabricated
(if necessary), and although they are subject to aging, they are not expected to cause any
operational vulnerabilities based on the unavailability of replacement components. The
obsolescence of the feedwater heater controls (which is an important issue) is addressed in EPRI
1007425 [Ref. 6]. To ascertain whether a given system or component is susceptible to technical
obsolescence, the evaluation methodology provided in the EPRI LCM Sourcebook Overview
[Ref. 1] is utilized (as a first step). Table 6-2 provides for the weighting of the various issues
with obsolescence. The ranking guidance for the table is presented below, along with a short
evaluation of the scoring for feedwater heaters.
6-6
Score
1.
5.0
2.
Is there more than one supplier for the SSC for the
foreseeable future?
3.0
3.
3.0
4.
3.0
3.0
6.
3.0
7.
1.0
8.
3.0
3.0
5.
9.
Yes
5
3
3
17
If the total score is < 6 (RED), then the SSC obsolescence is serious and will have an
immediate impact on LCM planning. Potential options to address obsolescence and
contingency planning should be identified.
If the total score is between 6 and 10 (YELLOW), the SSC may have long-term concerns
with obsolescence.
If the total score is >10 (GREEN), then obsolescence is not of concern for the SSC.
The estimated score (on a generic industry basis) for feedwater heaters is greater than 10, with
firm YES answers for questions 1, 2, 4, 6 (for smaller sub-components), and 9. Question 5 is
not really applicable because plants do not keep spare feedwater heaters in stock (although repair
parts for sub-components are stocked). Therefore, obsolescence is not an issue for feedwater
heaters. Some plants may need to address issues with procurement and test equipment
6-7
availability on a going-forward basis, especially with respect to the potential for license renewal
(an extended 20 years of plant operation). For the feedwater heater controls, EPRI 1007425
estimated that for most instrumentation, the total score will probably be below 6.
6.4
EPRI 1003470 [Ref. 11] addresses component lifetimes on a material basis in Section 8. Early
heater tubing materials (the tubes are the most sensitive component) were admiralty brass,
copper, and copper-nickel alloys. These materials have high thermal conductivity and some
corrosion resistance. In the 1960s, as fossil units grew in size and supercritical units were built,
carbon steel and Monel (70/30 nickel copper) became popular for high-pressure heater
applications. The emergence of copper deposits in boilers and on turbine blades forced the
industry to move towards stainless steel and carbon steel materials. In the nuclear industry,
stainless steel tubes began to replace all copper alloys in feedwater heaters. The most common
types of tube materials are 304-SS (TP304N), ASME SA286-TP349, AL-6XN, and Seacure.
The most recent tubing material introduced is ASME SA213 T-22. Type 439 SS (ferritic) is also
being selected more for FW heater tubes. EPRI 1003470 provides a comparison for these
materials and feedwater heater lifetimes.
The average life expectancy for a carbon steel tubed heater is approximately 12 years. The
average life expectancy for a T-22 tubed heater is 15 to 20 years. The average life expectancy
for a 304-SS tubed heater is 20 years. The expected lifetimes of other heater components (shell,
impingement plates, supports, etc.) is dependent on the maintenance and surveillance performed
on the heater (and sometimes on the design). For example, impingement plates which are
installed as completely perpendicular to the direction of steam flow will not last as long as plates
which are curved or are installed at an angle. The lifetime of the tubes is also dependent upon
the quality and the spacing of the tube supports (vibration problems from poor support design are
a common issue). Likewise, design problems which cause flashing in the drains cooler zone will
lead to rapid tube damage and also erosion of supports and the shell itself. Detailed material
evaluations and comparisons may also be found in EPRI GS-6913 [Ref. 20].
The values given are indicative and are for planning purposes only. Depending upon the
effectiveness of each plants maintenance and condition monitoring programs (along with the
water chemistry program), these values could vary widely.
6-8
7
GENERIC ALTERNATIVE LCM PLANS
This section addresses Steps 12 to 17 in the LCM planning flowchart (Figure 2-2). The EPRI
LCM Demonstration Project Report [Ref. 2] summarizes alternative LCM plans as follows:
Following the assessment of aging and reliability, potential alternative LCM plans
should be identified. The objective here should be to explore whether there are
potentially better ways of addressing the aging management of the SSC. These inputs
can come from plant staff, but input should also be solicited from outside experts and
industry benchmarking projects.
The following guidance for these steps includes the identification of possible plant operating life
strategies and the development of alternative LCM plans that are compatible with or integral to
the strategies identified. Also provided is a hypothetical illustration of alternative plans for
feedwater heaters, with the attendant discussions of the logic used to build the alternatives along
with the derivatives of the assumptions.
With an expected FW lifetime of approximately 20 years (less than the overall plant lifetime),
utilities will need to plan for several FW heater replacements for the duration of plant operation.
7.1
The determination of LCM planning alternatives will be driven to a large extent by the plant
operating strategies that (implicitly or explicitly) are being followed or evaluated, and by the
current reliability of the FW heaters. Accordingly, the set of LCM planning alternatives to be
evaluated is quite plant-specific. Typical plant operating strategies and standard approaches to
LCM planning alternatives are presented and discussed below.
7.1.1 Plant Strategy 1: Operate plant for currently licensed period of 40 years
This strategy requires minimizing risk during the remaining operating period until the plants
license expires, and identifying the limiting SSCs which could result in premature power
reduction or equipment replacements possibly forcing an economic decision regarding early
decommissioning. Feedwater heaters would certainly qualify as a limiting component, given
their importance to power production and their influence on the plants overall heat rate. LCM
plan alternatives under this strategy include:
LCM Plan Alternative 1A: A base case to determine the cost of the activities performed
under the current maintenance plan, assuming that the activities will continue as-is until the
7-1
end of the licensed plant life. This case also assumes the continuation of the existing
maintenance program without any major capital investments, unless absolutely necessary.
LCM Plan Alternative 1B: An alternative plan in which the current maintenance plan is
optimized and low-cost activities are added to provide improvements in reliability.
LCM Plan Alternative 1C: An alternative plan in which the current maintenance plan is
optimized and an aggressive PM program is implemented to reduce equipment failures, lost
power production, and regulatory risk.
LCM Plan Alternative 1D: An alternative plan in which the current maintenance plan is
optimized and older components are replaced with more reliable equipment. For the
feedwater heaters, this could include new tubes, new shield plates, and other internal subcomponent replacements. In the most extreme situation, it would involve an entirely new
feedwater heater.
7.1.2 Plant Strategy 2: Operate plant for 60 years with license renewal
This strategy recognizes the potential for license renewal and extended operation of the plant.
Major investments will be required to achieve extended operation. These investments can only
be justified by the additional revenue generated in the period of extended operation (20 years).
LCM planning alternatives considered for feedwater heaters under this strategy should include
the following:
LCM Plan Alternative 2A: A rigorous preparation for license renewal with an aggressive
aging management program, system/component performance enhancements, and timely
component replacements and/or upgrades. This LCM plan includes replacement of
feedwater heater components in a timely manner. This can even include replacement of the
entire FW heater.
LCM Plan Alternative 2B: Preparing for license renewal with an aggressive PM and PdM
program, but delaying plans for major capital improvements until the actual extended license
is implemented (i.e., year 39 of plant life). This alternative involves the position that the
expected lifetime for a feedwater heater is at least 20 years (with proper maintenance and
surveillance). This plan could include consideration of cleaning the FW heater tubes.
Every plant should prepare a base case for 60 years of operation (to address the remaining
lifetime). This will include actions to reach the limit of 60 years, which will probably include
the replacement of several FW heaters on some sort of prioritization (rolling) schedule.
7.1.3 Other Plant Strategies: (Power Uprate, Early Decommissioning, >60 Years)
Many plants have pursued various types of power uprate programs to increase the megawatts
thermal and megawatts electric output. With respect to feedwater heaters, this has caused some
unique difficulties because power uprate programs often involve increased feedwater flow
(leading to higher velocities in the FW heater tubes, and the potential for subsequent tube
vibration and erosion). Heat transfer rates are also affected, putting more demands on FW heater
operation. This alternative must be reviewed carefully with respect to the FW heaters in order to
obtain the maximum benefit to the plant. INPO issued SER (Significant Event Report) 5-02
7-2
[Ref. 40] in August 2002 to address problems with power uprates at nuclear units involving
inadequate analysis, design, or implementation which caused over 40 plant events between 1997
and 2002. Many of these events involved secondary-side equipment like feedwater heaters. In
terms of license renewal and power uprate and implementation projects, the impact on the
feedwater heaters needs to be carefully considered to avoid any problems or any acceleration of
degradation.
With respect to early decommissioning, this alternative would probably lead to the continuation
of the current maintenance plan for the FW heaters. Future equipment replacements would
probably be considered only if the failure rate was so high that overall unit operation was
strongly impacted (frequent shutdowns, large drops in power production, a large drop in overall
plant heat rate). The input of the plant Thermal Performance Engineer is critical in evaluating
how the feedwater heaters fit into the overall maintenance and operation of the plant. Section 8
of EPRI 1003470 [Ref. 11] gives guidance on major repair and replacement decisions.
7.2
For each alternative LCM plan proposed, detailed maintenance activities and schedules need to
be identified. Each plan will involve some mixture of the LCM approaches shown in steps 13 to
17 of Figure 2-2. The plans might involve the following:
Addressing tasks that facilitate or enable operating changes which minimize or equalize
component wear.
Adding preventive and predictive maintenance activities that may enhance the reliability of
the feedwater heaters. A number of these activities are discussed in Sections 5.1 and 5.2;
other suggestions may be sought from other power plants or industry working groups. If
improvements in heat transfer capability are needed, FW heater cleaning could be
considered.
One alternative that will almost certainly be considered, if only as a base case for comparison
with actual changes, is the option of continuing the current scheme for the feedwater heaters.
This case is presented with the presumption that existing maintenance practices will continue and
that present failure rates will apply. However, in characterizing this base case, the wear-out of
the major components (and the need for replacement) and the acceleration of the failure rates as
components reach their end-of-life condition must be considered.
7-3
Another option to be considered for FW heaters involves the cleaning of the tubes, particularly if
performance monitoring has shown that thermal performance of a given heater has declined.
This can be done during an outage with no impact on plant operation. The improvement in heat
transfer capability can be determined via a comparison of data from before and after the tube
cleaning.
In developing and reviewing each alternative task for LCM planning, all costs and benefits
should be considered and utilized in the analysis. This includes the cost of labor and materials,
the cost of planning itself, the costs associated with lost generation (declining thermal efficiency,
heater derating, and plant trips) and replacement power, and any potential regulatory costs (due
to NRC involvement or financial oversight from state regulators).
The base case for the feedwater heaters includes all the current surveillance and maintenance
done on the feedwater heaters at any given plant. For the purposes of LCM planning, these costs
will include engineering and craft labor, equipment costs, and vendor costs for surveillance
testing and inspections. For some plants, a certain number of FW heaters are inspected each
outage, for other plants, problems heaters are already identified, and the outage work involves
checking the condition of the current degradation. Other plants (plants which have recently
replaced FW heaters) may not require such detailed inspections, and their average costs may be
lower. It should be noted that over the life of the plant, the predictive and preventive
maintenance costs may be able to be controlled and remain fairly constant, but corrective
maintenance costs will increase with time.
It should be noted that an engineering evaluation needs to be performed on FW heaters for any
decision involving power uprate or FW heater upgrades. Due to increased flow requirements,
some existing heaters may not be acceptable under such plans, and additional changes may be
necessary.
7.3
A simple hypothetical case outline is evaluated to illustrate the process of developing LCM
Planning Alternatives for the feedwater heaters. The various alternatives mentioned above are
evaluated here.
7.3.1 Alternative A Base Case
Alternative A (the base case) is to continue the current maintenance program and to enhance or
upgrade the program only if absolutely necessary. Major efforts, such as tube rebundling or FW
heater replacement, are considered only if required.
This alternative would be selected if a plant already has a successful FW heater maintenance and
surveillance program, as verified by the LCM economic analysis showing no benefit from
increased PM and/or PdM activities. The cost would be (approximately) the same as the plants
current program, with minor adjustments in the future for possible tube plugging, and additional
7-4
NDE as the FW heaters age. For plants with above industry average problems or failure rates,
this option is clearly not recommended (although plant-specific data will reveal the situation).
7.3.2 Alternative B Step Increase in NDE Examinations of the FW Heaters
This alternative considers a step increase in the NDE examination of the FW Heaters, which
means an increase in eddy current testing (of the tubes and the shell), and additional
examinations of the tubesheet, the impingement plates, the channel head, and the inlet/outlet
nozzles. The purpose of this alternative is to offer increased surveillance so that costly surprises
(i.e., tube failures) can be avoided. As a rough estimate, this alternative involves an increase in
the overall maintenance spending for the FW Heaters, due to more frequent (and more detailed)
inspection. Part of the increase will involve engineering time to develop more detailed
documents to track the condition of the FW Heaters (drawings, evaluation reports for NDE data,
etc.). There may also be increased engineering costs as the component engineer and possibly the
thermal performance engineer (and even system engineers) educate themselves further about
feedwater heaters. There may also be additional costs related to tube plugging, sleeving, and
other maintenance actions (arising from better surveillance data).
7.3.3 Alternative C Major Maintenance (Tube Rebundle, etc.)
This alternative considers a major repair effort on a damaged FW Heater. This effort will
involve a large outlay to correct problems that may have been known for some time, but have not
been completely addressed. This effort may involve re-tubing or rebundling. Re-tubing a heater
involves replacing only the tubes. Rebundling a heater involves replacing the tubes, the
tubesheet, the tube supports, and the baffle plates. Retubing is typically an option for lowpressure, straight tube heaters only. Rebundling is usually an option for just low-pressure heaters
as well. Individual tubes can be replaced in high-pressure heaters, although this is not typical.
It should be noted that the difference in cost between a rebundle and a complete FW Heater
replacement is usually only about 5% or less. This factor should be considered when a heater is
experiencing repeated degradation problems.
7.3.4 Alternative D FW Heater Replacement
This alternative involves the complete replacement of a FW Heater. Such a determination is
made when the present heater is at its limit with respect to tube plugging, and further degradation
is expected. Complete replacement is also a consideration if the shell is damaged (eroded or
cracked) beyond a reasonable repair (i.e., a localized weld repair or patch).
As a rough estimate, when 10% of the tubes in a FW heater are plugged, the heater is
approaching its end of life. Further plugging would only increase the negative economic impact
on the plant.
Section 8 of EPRI 1003470 [Ref. 11] contains detailed information on how to plan for the
procurement of a new FW Heater, including a detailed list of materials for all the sub7-5
components involved. The technical and commercial properties (cost) are also presented. EPRI
GS-6913 [Ref. 20] also addresses FW heater replacement in detail.
7.3.5 Composite Evaluation
A composite evaluation of the alternatives is listed in Table 7-1. This composite shows the
attributes for consideration and provides a summary which can be used as a starting point for
plant-specific evaluations (with plant-specific technical data and economic analysis).
As discussed in Section 4 of this LCM Sourcebook, as estimated industry generic failure rate for
feedwater heaters has been determined to be approximately 0.05 to 0.1 failures per plant per
year. This value reflects the fact that nuclear plants typically have 12 or more feedwater heaters.
See Section 4.5 for an explanation of the generic industry failure rate estimation.
Table 7-1 presents a comparison of the various hypothetical alternatives.
Table 7-1
FW Heater Composite Evaluation for LCM Planning (generic)
Attribute
Plant Impact
(Lost Generation)
Initial Cost
Future Work Needed
Composite
Alternative B
Alternative C
Alternative D
Higher Impact
Highest Impact
+20% of Alternative A
$700,000*
$800,000*
Minimal Impact
Yes
Better than Base Case
Not Expected
Needed if Heater is
Degrading Beyond Repair
*Note that these values are the cost of the tubes and the replacement heater only. The design and
modification costs, construction costs, and testing costs are not included. These can often be
significant (depending upon heater accessibility, location, and orientation), and may cost much
more than the new tubes or replacement heater itself. Also, there will be a difference between
the cost of a low-pressure FW heater and a high-pressure FW heater, and this difference can be
significant (due to higher pressures and temperatures and more stringent ASME Section VIII
construction criteria). In general, it takes about 1 to 2 months to prepare a new FW heater
specification (longer if more time is needed to assemble data or if the engineering data is not
readily available). The lead time for ordering a tube rebundle is approximately 6 months, and the
lead time for an entirely new heater is approximately 8-10 months. Depending upon FW heater
accessibility and orientation, the actual rebundle or replacement time (schedule) may vary from 2
to 6 weeks.
7-6
The values for a heater rebundle cost and a full heater replacement were taken from
communication with mechanical component engineers in the industry who have specified new
FW heaters and other heater repairs. These values are indicative and are given as general
estimates only. Actual cost is highly dependent upon FW heater location, accessibility, and
orientation.
The expectation for LCM planning is that a FW heater maintenance scheme will be based upon
an evaluation of the current status of the plant equipment, rather than a complete change in
direction with respect to plant maintenance and surveillance. For a plant with FW heater
degradation problems, Alternatives C and D will very likely be selected if the current equipment
is negatively affecting operation. For plants with good equipment and a well-developed
maintenance and surveillance program (and a pro-active repair program), a choice in line with
Alternative B will likely be considered, even if the base case is working well (for future
successful heater operation and possible consideration of license renewal). The potential for
license renewal will also drive plants to consider FW heater replacements in a controlled manner,
in order to achieve the 60-year lifetime.
As mentioned in Section 6, the average expectancy for carbon steel tubed heaters is about 12
years. The average life expectancy for T-22 tubed heaters is 15 to 20 years, and the average life
expectancy of a type 304-SS tubed heater is about 20 years. This data will figure into any major
repair/replacement decisions.
7.4
In assessing the most economical approaches to major FW heater maintenance decisions, the age
of the FW heater, the design performance, and the impact on outage time for a heater
replacement must be evaluated.
First, the age is important because any heater older than 15 years will be facing increasing
difficulties going forward. Even a FW heater with 15 years of satisfactory performance will
show aging degradation at an increasing rate.
Second, the performance of the specific heater design will require evaluation to determine if
reliable performance can continue. Some heaters have design problems with poor tube supports
(or supports placed too far apart), problems with undersized or poorly oriented impingement
plates, problems with poor separation for the drains cooler zone (leading to steam entry and/or
flashing), and problems with pass partition plates. These problems can be repaired (to varying
degrees), but any new heater specification should avoid the problems of the past.
Third, the impact on outage duration for a FW heater replacement can be significant depending
upon the amount of work necessary for installation (as previously mentioned). It is also
important to consider how much of the total labor will be from the fabrication shop, and how
much will be performed at the site.
7-7
EPRI NP-4507-V3 [Ref. 23] contains a detailed discussion of cost evaluation, which considers
shop labor, field labor, replacement power cost, and material costs for heater rebundles and
heater replacements. All of these factors need to be addressed in plant-specific LCM planning.
7-8
8
GUIDANCE FOR ESTIMATING FUTURE FAILURE
RATES
This section addresses a part of step number 18 of Figure 2-2. It must be recognized that failure
rates are a main driver of the LCM planning process, and knowledge about estimating future
failure rates will directly impact decisions about component maintenance and replacement. In
addition, as components age, their vulnerability to the applicable aging mechanisms increases.
General guidance for estimating SSC future failure rates can be found in Section 2.6 of the LCM
Planning Sourcebook Overview Report (EPRI 1003058) [Ref. 1]. Below are some useful ideas
for estimating failure rates in FW heater LCM planning studies.
Sections 6.1 and 6.2 provide a discussion on the estimated life of FW heaters. This data is
not conclusive, because there is no set figure for the duration of a FW heater lifetime, but it is
a beginning point in estimating the expected remaining life of a FW heater (based upon
operating experience gained to date). If in-kind replacements are made, existing failure
rates may be applied for the future (and possibly extended, given improvements in
technology and maintenance). Specific communications with equipment manufacturers is
key in developing this information (with respect to LCM planning). The generic industry
failure rate discussed in Section 4 may be used in conjunction with plant-specific data to
establish a plant-specific failure rate for feedwater heaters.
Plants with FW heater trending programs can extract failure data (for tubes and other subcomponents) and compute failure rates directly. Data can be plotted to determine if the aging
effects previously identified are being exhibited and/or if the current PM programs are
effective. A sufficient duration of time for data collection is necessary (at least 10-15 years).
A review of Corrective Work Orders (WOs) can provide a means of following the FW heater
problems and may be used to compute failure rates. The criterion of failure must be clearly
defined. This WO review should encompass a long enough span of time to generate
meaningful results (for FW heaters, more than 10-15 years, in order to observe the aging
effects and to evaluate the effectiveness of plant maintenance). Repetitive problems must be
identified and categorized as such in LCM planning.
The data presented in Section 4 provides a background for understanding how FW heater
problems can impact plant operation.
The feedwater heaters are installed with strings of heaters in the plant (for LP and HP
applications). A single string out of service would rarely cause the loss of the entire system
function (and plant shutdown), but it would require some degree of power reduction. While
component failure (and the repair/replacement impact) must be addressed in LCM planning,
the consideration of lost power generation may be limited to just power reductions (small or
large) rather than complete shutdown.
Maintenance Rule programs and PRA evaluations emphasize functional failures rather than
degraded performance. Feedwater heater LCM plans should consider both.
PRA models may assume that the probability of catastrophic failures of passive heat
exchangers is insignificant compared to the probability of other component failures.
However, these passive failures (as discussed in Section 4) are of considerable concern in
LCM planning (due to the impact of lost power production and the cost of replacement
power). The complete failure of a feedwater heater shell must be addressed in LCM
planning, especially if plant data shows evidence of wall thinning.
The effects of any power uprate on a nuclear unit must be considered when evaluating future
failure rates. INPO SER 5-02 addresses the fact that over 40 plant events have occurred from
1997 to 2002 as a result of inadequate analysis, design, or implementation of nuclear plant
power uprates. Many of these events involved feedwater heaters and related secondary-side
equipment. The effects of power uprate on the feedwater heaters (increased FW flow,
increased heat transfer demand, etc.) must be reviewed and considered on a going-forward
basis.
The potential for license renewal (with an extended 20 years of plant operation) will
introduce new considerations in LCM planning, particularly for components that normally
experience age-degradation at a slow rate, but can experience damage to vulnerable
components in just one cycle (like feedwater heaters). LCM planning for the period of
extended operation must account for possible feedwater heater replacement if the plant
undergoes a general refurbishment prior to (or at the beginning of) the 20 year period.
In summary, failure rate predictions for feedwater heaters are made using the guidance of the
LCM Sourcebook Overview Report [Ref. 1]. The generic industry failure rate is discussed in
Section 4 of this document and in Section 5 of EPRI 1003470 [Ref. 11]. This rate is based upon
available data and is uncertain. The plant-specific PRA and Maintenance Rule records will be an
important source of information in determining a plant-specific failure rate (along with all the
maintenance records, of course). The LCM planning process should be fairly complete with
carefully defined activities for each of the LCM alternative plans (as they are developed). In this
way, the influence of new or additional PM activities, implementation of component
replacements, and plant modifications (power uprate, license renewal, etc.) can be appropriately
considered in estimating future failure rates for input into LCM economic evaluations.
8-2
9
INFORMATION SOURCES AND REFERENCES
9-1
9-2
9-3
10
ACRONYMS
ABB
AE
Acoustic Emission
AMG
AMR
ANSI
ASME
ASNT
ASTM
AVT
All-Volatile Treatment
AWS
B&PV
B&W
BOP
Balance-of-Plant
BWR
Btu
CS
Carbon Steel
CE
Combustion Engineering
DCA
ECP
Electrochemical Potential
ECT
EEI
EPIX
EPRI
ET
Electromagnetic Testing
FAC
Flow-Accelerated Corrosion
FMAC
FFT
Acronyms
FIV
Flow-Induced Vibration
FW
Feedwater
FWH
Feedwater Heater
GADS
GARS
GE
General Electric
GL
Generic Letter
HEI
HP
High Pressure
ID
Inner Diameter
IGA
Inter-Granular Attack
IGSCC
INPO
IRIS
IRT
Infrared Technology
ITHT
LCM
LER
LP
Low Pressure
LR
License Renewal
MIC
Microbiologically-Influenced Corrosion
MPFF
MR
Maintenance Rule
MSR
MT
MTTR
Mean-Time-to-Repair
NEIL
NERC
NDE
Non-Destructive Examination
NMAC
NPAR
NPRDS
NPV
10-2
Acronyms
NRC
O&MR
OD
Outer Diameter
OE
Operating Experience
OPEC
pH
Percent Hydrogen
PM
Preventive Maintenance
PdM
Predictive Maintenance
ppm
PT
PTC
PWR
RCM
Reliability-Centered Maintenance
RFEC
RVT
SCC
SEE-IN
SEN
SER
SOER
SS
Stainless Steel
SSC
SYSMON
TGSCC
TEMA
TR
Temperature Rise
TTD
UCLF
UT
Ultrasonic Testing
VT
Westinghouse
10-3
Program:
Nuclear Power
About EPRI
EPRI creates science and technology solutions for
the global energy and energy services industry. U.S.
electric utilities established the Electric Power
Research Institute in 1973 as a nonprofit research
consortium for the benefit of utility members, their
customers, and society. Now known simply as EPRI,
the company provides a wide range of innovative
products and services to more than 1000 energyrelated organizations in 40 countries. EPRIs
multidisciplinary team of scientists and engineers
draws on a worldwide network of technical and
business expertise to help solve todays toughest
energy and environmental problems.
EPRI. Electrify the World
EPRI 3412 Hillview Avenue, Palo Alto, California 94304 PO Box 10412, Palo Alto, California 94303 USA
800.313.3774 650.855.2121 askepri@epri.com www.epri.com